CN204551161U - A kind of roadbed repair structure - Google Patents

A kind of roadbed repair structure Download PDF

Info

Publication number
CN204551161U
CN204551161U CN201520227930.0U CN201520227930U CN204551161U CN 204551161 U CN204551161 U CN 204551161U CN 201520227930 U CN201520227930 U CN 201520227930U CN 204551161 U CN204551161 U CN 204551161U
Authority
CN
China
Prior art keywords
roadbed
pile
preformed pile
described preformed
repair structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520227930.0U
Other languages
Chinese (zh)
Inventor
陈远川
李佳坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing University of Arts and Sciences
Original Assignee
Chongqing University of Arts and Sciences
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University of Arts and Sciences filed Critical Chongqing University of Arts and Sciences
Priority to CN201520227930.0U priority Critical patent/CN204551161U/en
Application granted granted Critical
Publication of CN204551161U publication Critical patent/CN204551161U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The utility model discloses a kind of roadbed repair structure, comprise the supercrust on top and the roadbed of bottom, roadbed subsidence region is positioned at the top of supercrust and roadbed, many preformed piles are provided with in described roadbed, described preformed pile is vertical with the length direction of roadbed and be horizontally disposed with, and described preformed pile is cylindric, and front end is provided with cone shape pile crown, described preformed pile surface is uniform has multiple hole, is perfused with chemical slurry in described preformed pile.The utility model provides a kind of roadbed repair structure, horizontal side is effectively combined to the soil compaction effect of driving piles and grouting and reinforcing, by the compacted roadbed filling of piling of the nearly horizontal direction of side direction, roadbed in the vertical direction is squeezed high, recovers sedimentation and deformation.By pre-reservation pressure grouting channel and hole in preformed pile, make grouting and reinforcing more convenient and effective.

Description

A kind of roadbed repair structure
Technical field
The utility model relates to road construction, is specifically related to a kind of roadbed repair structure.
Background technology
Roadbed is the banded structure thing as road surface or track foundation built according to highway or rail route position and certain technical requirements, and be the basis of highway and railway, roadbed is the linear structure thing with soil or building stones build.Roadbed should be built under good geology, the hydrology and weather conditions.From material point, roadbed can be divided into soil subgrade, rock subgrade, soil-stone embankment three kinds.
Due to the effect of the factors such as filler is uneven, filler is bad, filling compaction is insufficient, water content is too high, earthquake, Construction Vibration, vehicular load, penetration, deadweight, there is the FAQs that sedimentation and deformation is road foundation in road foundation.Subgrade settlement must cause the destruction of railroad track and highway pavement, endangers safe traffic.Therefore, the settlement issues of effective Subgrade, has important practical significance for guarantee traffic safety.
At present, Some Domestic scholar has carried out research Roadbed Soil being improved to the aspects such as its intensity by grouting, although there is certain effect, because the degree of compaction of Roadbed Soil body is once more than 80%, grouting is just difficult to effectively carry out, and easily forms local and leaks irrigated area.At present, reinforce Rock And Soil by the means of piling, be mainly used in the punishment of structure foundation, and mainly vertical direction piling.Road foundation deformation solution aspect, the method that less use piling is repaired, has no the engineering method that horizontal side is repaired to piling.
Utility model content
Technical problem to be solved in the utility model is that existing road roadbed repairing effect is bad, easily forms the problem that irrigated area is leaked in local.
In order to solve the problems of the technologies described above, the technical scheme that the utility model adopts is to provide a kind of roadbed repair structure, comprise the supercrust on top and the roadbed of bottom, roadbed subsidence region is positioned at the top of supercrust and roadbed, is provided with many preformed piles in described roadbed, and described preformed pile is vertical with the length direction of roadbed and be horizontally disposed with, described preformed pile is cylindric, front end is provided with cone shape pile crown, and described preformed pile surface is uniform has multiple hole, is perfused with chemical slurry in described preformed pile.
Further technical scheme, described preformed pile is steel pipe pile or reinforced concrete pile.
Further technical scheme, described preformed pile is horizontal through roadbed, and the opening of perfusion slurry is left in the one end squeezing into preformed pile.
Further technical scheme, in the vertical section of roadbed, described preformed pile forms horizontal multirow, is crisscross arranged, forms multiple triangular structure between adjacent upper and lower two row.
The utility model provides a kind of roadbed repair structure, horizontal side is effectively combined to the soil compaction effect of driving piles and grouting and reinforcing, by the compacted roadbed filling of piling of the nearly horizontal direction of side direction, roadbed in the vertical direction is squeezed high, recovers sedimentation and deformation.By pre-reservation pressure grouting channel and hole in preformed pile, make grouting and reinforcing more convenient and effective.
Accompanying drawing explanation
The overall schematic of the roadbed repair structure that Fig. 1 provides for the utility model;
The elevational schematic of the roadbed repair structure that Fig. 2 provides for the utility model;
The preformed pile structural representation that Fig. 3 provides for the utility model.
In figure: 1. roadbed, 2. supercrust, 3. preformed pile, 4. roadbed subsidence region, 5. hole, 6. pile crown.
Detailed description of the invention
Subgrade settlement refers to the phenomenon that the basis of road (highway, railway etc.) sinks owing to being subject to extraneous power (earthquake, Construction Vibration, vehicular load, penetration etc.) or the Action of Gravity Field of self.Roadbed because of degree of compaction inadequate, the immersion of water is softened, and after pavement usage a period of time, depression (sedimentation) also can occur roadbed, and settling amount Observable is out.
Roadbed reparation recovers the intensity of roadbed, rigidity and stability by engineering, recovers the physical dimension such as design elevation, width of roadbed.Make generation deterioration by recovery technique, state got well by the roadbed of pathology, reach the object that is unimpeded and guarantee road geological security that maintains traffic.The roadbed restorative procedure that the utility model provides effectively is combined to the soil compaction effect of driving piles and grouting and reinforcing horizontal side, by the compacted roadbed filling of piling of the nearly horizontal direction of side direction, roadbed in the vertical direction squeezed high, recover sedimentation and deformation.By pre-reservation pressure grouting channel and hole in preformed pile, make grouting and reinforcing more convenient and effective.
Below in conjunction with accompanying drawing, the utility model is described in detail.
As shown in Figure 1, a kind of roadbed repair structure that the utility model provides comprises the supercrust on top and the roadbed of bottom, roadbed subsidence region is positioned at the top of supercrust and roadbed, is provided with many preformed piles in roadbed, and in the utility model, preformed pile can be steel pipe pile or reinforced concrete pile.Preformed pile is vertical with the length direction of roadbed and be horizontally disposed with, than the better effects if of vertically piling.As shown in Figure 3, preformed pile is cylindric, and front end is provided with cone shape pile crown, makes to squeeze into preformed pile more quick, reduces resistance.Preformed pile surface is uniform has multiple hole, is perfused with chemical slurry in preformed pile.
Preformed pile is horizontal through roadbed, and the opening of perfusion slurry is left in the one end squeezing into preformed pile.As shown in Figure 2, in the vertical section of roadbed, preformed pile forms horizontal multirow, be crisscross arranged between adjacent upper and lower two row, form multiple triangular structure, this frame mode make grouting evenly, it is more firm that slurry solidifies the support of rear preformed pile to whole roadbed.
The roadbed restorative procedure that the utility model provides comprises the following steps:
The steel pipe pile of S1, prefabricated band slip casting passage and hole or reinforced concrete pile;
S2, squeeze into the preformed pile of level in roadbed side, the filler of compacted and crowded high sedimentation roadbed, repair sedimentation and deformation, the mode squeezing into preformed pile for from the bottom up line by line dislocation squeeze into, form multiple triangular structure;
Side direction piling refers to the preformed pile by squeezing into nearly horizontal direction in the side direction of Roadbed Soil body, driven pile is equivalent to the solid phase grogs volume that makes Roadbed Soil body and weight increases, and the side direction crowd in-out effects of stake must make that gas phase air in roadbed space or hole is relative with the ratio of liquid phase moisture to be reduced.Therefore, side direction piling is clamp-oned roadbed and is equivalent in mechanics effect at Roadbed Soil surface applying compacting load, can reach the basic goal of the strengthening roadbed of Effective Compaction Roadbed Soil body completely.
S3, pressure inject chemical slurry, and chemical slurry solidifies, and reinforce the filler of sedimentation roadbed further.
S4, complete above-mentioned steps after maintenance is carried out to roadbed, form the road structure of high strength.
The utility model provides a kind of roadbed repair structure and method, and soil compaction of first driving piles, squeezes into the preformed pile close to horizontal direction by roadbed side, compacted roadbed filling, reduces space or hole that in roadbed, air and moisture content occupy, improves the compaction rate of roadbed.Hitting the person preformed pile in side direction horizontal direction, can squeeze elevated formation level filler at vertical direction, reaches the object recovering subgrade settlement, the design elevation before making road foundation height mark reach sedimentation.By grouting pipe reserved in preformed pile and hole, for pressure grouting provides passage.The effect of comprehensive side direction piling soil compaction effect and slip casing by pressure, realizes the reparation of sedimentation subgrade strength and distortion, ensures the stability of roadbed.
The utility model is not limited to above-mentioned preferred forms, and anyone should learn the structure change made under enlightenment of the present utility model, and every have identical or close technical scheme with the utility model, all falls within protection domain of the present utility model.

Claims (4)

1. a roadbed repair structure, comprise the supercrust on top and the roadbed of bottom, roadbed subsidence region is positioned at the top of supercrust and roadbed, it is characterized in that, be provided with many preformed piles in described roadbed, described preformed pile is vertical with the length direction of roadbed and be horizontally disposed with, described preformed pile is cylindric, front end is provided with cone shape pile crown, and described preformed pile surface is uniform has multiple hole, is perfused with chemical slurry in described preformed pile.
2. a kind of roadbed repair structure according to claim 1, is characterized in that: described preformed pile is steel pipe pile or reinforced concrete pile.
3. a kind of roadbed repair structure according to claim 1, is characterized in that: described preformed pile is horizontal through roadbed, and the opening of perfusion slurry is left in the one end squeezing into preformed pile.
4. a kind of roadbed repair structure according to claim 1, it is characterized in that: in the vertical section of roadbed, described preformed pile forms horizontal multirow, is crisscross arranged, forms multiple triangular structure between adjacent upper and lower two row.
CN201520227930.0U 2015-04-16 2015-04-16 A kind of roadbed repair structure Expired - Fee Related CN204551161U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520227930.0U CN204551161U (en) 2015-04-16 2015-04-16 A kind of roadbed repair structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520227930.0U CN204551161U (en) 2015-04-16 2015-04-16 A kind of roadbed repair structure

Publications (1)

Publication Number Publication Date
CN204551161U true CN204551161U (en) 2015-08-12

Family

ID=53826297

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520227930.0U Expired - Fee Related CN204551161U (en) 2015-04-16 2015-04-16 A kind of roadbed repair structure

Country Status (1)

Country Link
CN (1) CN204551161U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350418A (en) * 2015-12-04 2016-02-24 中国铁道科学研究院铁道建筑研究所 Subgrade strengthening method
CN106320121A (en) * 2015-04-16 2017-01-11 重庆文理学院 Subgrade repair structure and subgrade repair method
CN108360352A (en) * 2018-01-31 2018-08-03 杨波 A kind of horizontal prestressing force slip casting restorative procedure of crack on road disease

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320121A (en) * 2015-04-16 2017-01-11 重庆文理学院 Subgrade repair structure and subgrade repair method
CN106320121B (en) * 2015-04-16 2018-08-07 重庆文理学院 A kind of roadbed repairs structure and method
CN105350418A (en) * 2015-12-04 2016-02-24 中国铁道科学研究院铁道建筑研究所 Subgrade strengthening method
CN108360352A (en) * 2018-01-31 2018-08-03 杨波 A kind of horizontal prestressing force slip casting restorative procedure of crack on road disease

Similar Documents

Publication Publication Date Title
CN203960700U (en) The closed road structure of stake holder U-lag
CN106320121B (en) A kind of roadbed repairs structure and method
CN206956742U (en) High precipitous rock roadbed side slope repair system
CN106835880A (en) Highway lateral support type peg board formula is without earth roadbed
CN103215863A (en) High polymer grouting method for lifting ballastless track of high speed railway
CN204551161U (en) A kind of roadbed repair structure
CN103452130A (en) Prestressing force reinforcing mesh ribbing earth pillar plate type retaining wall
CN105804101B (en) Reduce off-loading supporting and retaining system system and construction method and the application of retaining structure stress
CN109137872B (en) Reinforced structure bag and method for processing soft foundation by using reinforced structure bag
CN111172833A (en) Construction method of steep slope high embankment structure
CN210194361U (en) Splicing structure for widening new and old roadbeds on road
CN113403903B (en) Roadbed reinforcing structure for highway construction and construction process thereof
CN108487234B (en) Construction method of cast-in-situ pile plate type platform wall
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN219410355U (en) Flexible side-width structure of high-fill embankment of existing railway
CN102966109A (en) Method for constructing zonal deep foundation pit bottom sealing of soft soil foundation
CN104894935A (en) Existing expressway (railway) embankment lightening settlement control method
CN207672604U (en) A kind of pellet type retaining wall structure
CN206941324U (en) A kind of embankment of anti-settling formula
CN207552833U (en) A kind of elevated bridge basal perimeter ground road structure
CN203007761U (en) Grouting reinforcement structure for steel floral tube of existing railway roadbed under operation condition
CN206127866U (en) Retailing backwall capable of preventing high filling earthwork subgrade from bridge bump
CN115652717A (en) High-fill roadbed construction method
CN209555946U (en) A kind of reparation structure that high embankment collapses
CN205934936U (en) Utilization reduces road structure that a lotus fender system found that subtracts of retaining structure atress

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150812

Termination date: 20180416