CN204546800U - A kind of processing of stone workshop - Google Patents

A kind of processing of stone workshop Download PDF

Info

Publication number
CN204546800U
CN204546800U CN201520241240.0U CN201520241240U CN204546800U CN 204546800 U CN204546800 U CN 204546800U CN 201520241240 U CN201520241240 U CN 201520241240U CN 204546800 U CN204546800 U CN 204546800U
Authority
CN
China
Prior art keywords
rail road
hanger rail
row
row hanger
streamline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520241240.0U
Other languages
Chinese (zh)
Inventor
赵应文
张奉伟
陈愚宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shidian County Lian Yuan Celestial Stone Co Ltd
Original Assignee
Shidian County Lian Yuan Celestial Stone Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shidian County Lian Yuan Celestial Stone Co Ltd filed Critical Shidian County Lian Yuan Celestial Stone Co Ltd
Priority to CN201520241240.0U priority Critical patent/CN204546800U/en
Application granted granted Critical
Publication of CN204546800U publication Critical patent/CN204546800U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of processing of stone workshop, parallelly be provided with the first row hanger rail road and the second row hanger rail road, between the first row hanger rail road and the second row hanger rail road, vertical the first row hanger rail road and the second row hanger rail road are provided with stone material conveying track, between the first row hanger rail road and the second row hanger rail road, be parallel to stone material conveying track be provided with the first row and hang dolly and the second row hangs dolly, roughing streamline and fining-off streamline is provided with between the first row is hung and the second row hangs, rhone is provided with between roughing streamline and fining-off streamline, sedimentation basin is provided with in one end of rhone, of the present utility modelly be a little the occupation of land saving job shop, also reduce the input of manpower, save the time.

Description

A kind of processing of stone workshop
Technical field
The utility model relates to manufacture field, is specifically related to a kind of processing of stone workshop.
Background technology
The processing of stone workshop of prior art, be provided with row to hang, but between two row hang without any relation, also the track do not transported between row hangs is connected, think to carry out again after stone material carries out roughing operation fining-off just employ a large amount of manpower small handcarts to move stone material, also without any association between every one manufacturing procedure on fining-off streamline, carry out the mode that every one manufacturing procedure all adopts manpower transport's stone material, time and processing land used is wasted while waste of manpower, stone needs when cutting ceaselessly to water, one is cooling cutting machine, two is the health that the stone flour avoiding producing when cutting stone endangers staff, therefore the side of every platform cutting machine is all provided with rhone, many walkings being naturally also just unfavorable for small handcart that rhone is established, be prone to accidents because stone weight also compares when carrying out stone carrying greatly, produce hidden danger.
Utility model content
For above-mentioned prior art, the technical problem that the utility model solves be to provide a kind of two row hang between have transport stone material track to connect, also have the processing of stone workshop that stone material conveying track connects between per pass machining clearance.
Its technical scheme is:
A kind of processing of stone workshop, described processing of stone workshop is parallel is provided with the first row hanger rail road and the second row hanger rail road, between the first row hanger rail road and the second row hanger rail road, vertical the first row hanger rail road and the second row hanger rail road are provided with stone material conveying track, roughing streamline and fining-off streamline is provided with between the first row hanger rail road and the second row hanger rail road, some roughing stone material conveying tracks are provided with side by side perpendicular to the first row hanger rail road between the first row hanger rail road and the second row hanger rail road, one end of every bar roughing stone material conveying track is connected with row hanger rail road, the other end is then provided with cutting machine, fining-off stone material conveying track is connected with perpendicular to the second row hanger rail road between the first row hanger rail road and the second row hanger rail road, the side of fining-off stone material conveying track is provided with fining-off streamline, fining-off streamline comprises the transverse cutting unit be arranged on foremost, be arranged on the slitter after transverse cutting unit, be arranged on the resistance wire drying chamber after slitter, be arranged on the gluing room after drying chamber, be connected to the hurricane drier behind gluing room, be connected to the picture mosaic room after hurricane drier.
Due to the first row hang and the second row hang be arranged in parallel and between each machining clearance, have corresponding stone material conveying track to be connected, just do not need to employ a large amount of manpowers to move stone material man-hour adding stone material like this, processing machine concentrated setting is also reduced the floor space of job shop, saved the time that half uses stone material.
Further, between roughing streamline and fining-off streamline, be provided with rhone, be provided with sedimentation basin in one end of rhone.
The centre that setting due to roughing streamline and fining-off streamline concentrates on two process lines arranges a rhone and just the drainage of processing water can be gone out, and saves space.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model, wherein: 1-the first row hanger rail road, 2-the first row hang dolly, 3-second row hanger rail road, 4-roughing stone material conveying track, 5-cutting machine, 6-stone material conveying track, 7-rhone, 8-transverse cutting unit, 9-slitter, 10-resistance wire drying chamber, 11-gluing room, 12-hurricane drier, 13-fining-off stone material conveying track, 14-picture mosaic room, 15-sedimentation basin, 16-second row hang dolly.
Detailed description of the invention
As shown in the figure, a kind of processing of stone workshop, described processing of stone workshop is parallel is provided with the first row hanger rail road 1 and the second row hanger rail road 3, between the first row hanger rail road 1 and the second row hanger rail road 3, vertical the first row hanger rail road 1 and the second row hanger rail road 3 are provided with stone material conveying track 6, roughing streamline and fining-off streamline is provided with between the first row hanger rail road 1 and the second row hanger rail road 3, some roughing stone material conveying tracks 4 are provided with side by side between the first row hanger rail road 1 and the second row hanger rail road 3 perpendicular to the first row hanger rail road 1, one end of every bar roughing stone material conveying track 4 is connected with row hanger rail road, the other end is then provided with cutting machine 5, fining-off stone material conveying track 13 is connected with between the first row hanger rail road 1 and the second row hanger rail road 3 perpendicular to the second row hanger rail road 3, the side of fining-off stone material conveying track 13 is provided with fining-off streamline, fining-off streamline comprises the transverse cutting unit 8 be arranged on foremost, be arranged on the slitter 9 after transverse cutting unit 8, be arranged on the resistance wire drying chamber 10 after slitter 9, be arranged on the gluing room 11 after drying chamber, be connected to the hurricane drier 12 behind gluing room, be connected to the picture mosaic room 14 after hurricane drier, rhone 7 is provided with between roughing streamline and fining-off streamline, sedimentation basin 15 is provided with in one end of rhone 7.

Claims (2)

1. a processing of stone workshop, it is characterized in that, described processing of stone workshop is parallel is provided with the first row hanger rail road (1) and the second row hanger rail road (3), between the first row hanger rail road (1) and the second row hanger rail road (3), vertical the first row hanger rail road (1) and the second row hanger rail road (3) are provided with stone material conveying track (6), roughing streamline and fining-off streamline is provided with between the first row hanger rail road (1) and the second row hanger rail road (3), some roughing stone material conveying tracks (4) are provided with side by side perpendicular to the first row hanger rail road (1) between the first row hanger rail road (1) and the second row hanger rail road (3), one end of every bar roughing stone material conveying track (4) is connected with row hanger rail road, the other end is then provided with cutting machine (5), fining-off stone material conveying track (13) is connected with perpendicular to the second row hanger rail road (3) between the first row hanger rail road (1) and the second row hanger rail road (3), the side of fining-off stone material conveying track (13) is provided with fining-off streamline, fining-off streamline comprises the transverse cutting unit (8) be arranged on foremost, be arranged on the slitter (9) after transverse cutting unit (8), be arranged on the resistance wire drying chamber (10) after slitter (9), be arranged on the gluing room (11) after drying chamber, be connected to the hurricane drier (12) behind gluing room, be connected to the picture mosaic room (14) after hurricane drier.
2. a kind of processing of stone workshop according to claim 1, is characterized in that, is provided with rhone (7) between roughing streamline and fining-off streamline, is provided with sedimentation basin (15) in one end of rhone (7).
CN201520241240.0U 2015-04-21 2015-04-21 A kind of processing of stone workshop Expired - Fee Related CN204546800U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520241240.0U CN204546800U (en) 2015-04-21 2015-04-21 A kind of processing of stone workshop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520241240.0U CN204546800U (en) 2015-04-21 2015-04-21 A kind of processing of stone workshop

Publications (1)

Publication Number Publication Date
CN204546800U true CN204546800U (en) 2015-08-12

Family

ID=53821958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520241240.0U Expired - Fee Related CN204546800U (en) 2015-04-21 2015-04-21 A kind of processing of stone workshop

Country Status (1)

Country Link
CN (1) CN204546800U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106584686A (en) * 2016-12-25 2017-04-26 山东赫峰石材高端装备研究院有限公司 Intelligent deep processing production line for quartz stone
CN107187660A (en) * 2017-05-16 2017-09-22 刘晓富 A kind of brake block manufactory high efficiency packing device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106584686A (en) * 2016-12-25 2017-04-26 山东赫峰石材高端装备研究院有限公司 Intelligent deep processing production line for quartz stone
CN106584686B (en) * 2016-12-25 2018-05-15 山东赫峰石材高端装备研究院有限公司 Quartz intelligence deep processing and production line
CN107187660A (en) * 2017-05-16 2017-09-22 刘晓富 A kind of brake block manufactory high efficiency packing device
CN107187660B (en) * 2017-05-16 2019-04-23 龙口市隆昌汽车配件有限公司 A kind of brake block manufacture station-service packing device

Similar Documents

Publication Publication Date Title
CN204546800U (en) A kind of processing of stone workshop
CN204184411U (en) A kind of plate pusher of energy leaping over obstacles
CN104369757A (en) Special axle carrier vehicle for taking broken screw taps
CN206810996U (en) Mould changing device
CN204078414U (en) Tire barrow
CN203922049U (en) A kind of double-deck plate conveying arrangement that divides for wooden industry processing
CN205203065U (en) Workpiece transporating trolley
CN204818573U (en) Multi -functional high altitude construction car rear axle welding frock
CN204415462U (en) A kind of liftable spraying sheet material dries transfer car(buggy)
CN203184057U (en) Rice polishing emery roll
CN204038453U (en) Off-line chassis maintenance line-shifting machine
CN203854686U (en) Vegetable basket transfer trolley
CN204641809U (en) A kind of universal cushion frame transfer trolley
CN204397418U (en) A kind of frock fixture for the processing of exhaust seat multistation
CN205033011U (en) Cutter dolly
CN204775355U (en) Steel sheet transfer device
CN203512328U (en) Four shaft coupling transporter
CN204128353U (en) Pushing type heating furnace backing strap transshipment acitivity
CN205169801U (en) Brake disc is push -and -pull car for production line
CN203410224U (en) Knurl wheel
CN203332791U (en) Adjustable transition conveying structure
CN203805931U (en) Yarn steaming cart
CN201770133U (en) Door frame
CN207534972U (en) A kind of timber cutter device
CN204702089U (en) Utilize the conveyor line guide rail of gravity transfer material

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150812

Termination date: 20170421

CF01 Termination of patent right due to non-payment of annual fee