CN204516500U - A kind of two suspended compound insulator string - Google Patents
A kind of two suspended compound insulator string Download PDFInfo
- Publication number
- CN204516500U CN204516500U CN201520083034.1U CN201520083034U CN204516500U CN 204516500 U CN204516500 U CN 204516500U CN 201520083034 U CN201520083034 U CN 201520083034U CN 204516500 U CN204516500 U CN 204516500U
- Authority
- CN
- China
- Prior art keywords
- insulator string
- suspension
- pair
- eye
- suspended
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Insulators (AREA)
Abstract
本实用新型公开了一种双悬式复合绝缘子串,包括联板,所述联板上悬挂有若干承担导线的悬垂线夹,与所述联板顶部相连设有连接输电塔的第一绝缘子串和第二绝缘子串,各所述悬垂线夹上均设有防风偏装置。本双悬式复合绝缘子串,在联板上设置与输电塔连接的第一绝缘子串和第二绝缘子串,联板则通过悬垂线夹连接导线,如此本实用新型通过上述结构的改进增加了连接导线的机械强度的同时,保证了整体结构的简便性,降低制作成本,节约线路投资,也方便线路安装和维修。此外,在各悬垂线夹上设置的防风偏装置则能够改善整个绝缘子串的防风偏能力,避免发生风偏放电事故。
The utility model discloses a double-suspended composite insulator string, which comprises a connecting plate, on which a plurality of suspension clamps for conducting wires are hung on the connecting plate, and a first insulator string connected to the transmission tower is arranged on the top of the connecting plate. and the second insulator string, each of the suspension clamps is provided with a wind deflection device. In this double-suspension composite insulator string, the first insulator string and the second insulator string connected to the transmission tower are arranged on the connecting plate, and the connecting plate is connected to the wire through the suspension clamp, so that the utility model increases the connection through the improvement of the above structure. While the mechanical strength of the wire is guaranteed, the simplicity of the overall structure is ensured, the production cost is reduced, the line investment is saved, and the line installation and maintenance are also convenient. In addition, the wind deflection device installed on each suspension clamp can improve the wind deflection capability of the entire insulator string and avoid wind deflection discharge accidents.
Description
技术领域 technical field
本实用新型用于输电线路领域,特别是涉及一种双悬式复合绝缘子串。 The utility model is used in the field of power transmission lines, in particular to a double-suspended composite insulator string.
背景技术 Background technique
随着工业发展,用户对电能的需求越来越高,输电线路的容量正向更大的方向发展,线路的容量增大,则导线的截面增加,同时导向重量增加,目前在输变电线路中,塔与线路之间主要依靠各类连接金具进行连接,因此对导线与杆塔之间连接的金具要求也越来越高,金具的机械强度要求必须加大,而大强度的金具不但制作成本高,且体积庞大、结构复杂,造成线路投资高,也给线路安装和维修带来不便。 With the development of industry, the user's demand for electric energy is getting higher and higher, and the capacity of the transmission line is developing in a larger direction. As the capacity of the line increases, the cross-section of the wire increases, and the weight of the guide increases. Among them, the connection between the tower and the line mainly depends on various connecting fittings, so the requirements for the fittings connecting the wire and the tower are getting higher and higher, the mechanical strength requirements of the fittings must be increased, and the high-strength fittings not only cost more High, bulky and complex structure, resulting in high line investment and inconvenience to line installation and maintenance.
近年来,由于气候变化,大风天气逐渐增多,对电力线路安全运行带来了严重威胁,由大风引起的输电线路风偏放电事故多有发生,其原因是线路防污闪改造中大量调爬,增加了瓷质或玻璃绝缘子串的长度,使间隙圆半径增大,抗风偏放电能力降低;再就是复合绝缘子的大量应用,因复合绝缘子重量轻,防风偏能力差,容易发生风偏放电事故。 In recent years, due to climate change, windy weather has gradually increased, which has brought serious threats to the safe operation of power lines. Wind deflection discharge accidents on transmission lines caused by strong winds have occurred frequently. The length of the porcelain or glass insulator string is increased, the radius of the gap circle is increased, and the ability to resist wind deflection discharge is reduced; then there are a large number of applications of composite insulators, because composite insulators are light in weight and poor in wind deflection resistance, prone to wind deflection discharge accidents .
实用新型内容 Utility model content
为解决上述问题,本实用新型提供一种结构简单、安装方便、机械强度高,同时改善防风偏能力的双悬式复合绝缘子串。 In order to solve the above problems, the utility model provides a double-suspended composite insulator string with simple structure, convenient installation, high mechanical strength, and improved ability to prevent wind deflection.
本实用新型解决其技术问题所采用的技术方案是:一种双悬式复合绝缘子串,包括联板,所述联板上悬挂有若干承担导线的悬垂线夹,与所述联板顶部相连设有连接输电塔的第一绝缘子串和第二绝缘子串,各所述悬垂线夹上均设有防风偏装置。 The technical solution adopted by the utility model to solve the technical problem is: a double-suspended composite insulator string, including a connecting plate, on which a number of suspension clamps for conducting wires are suspended on the connecting plate, and are connected to the top of the connecting plate to set There are a first insulator string and a second insulator string connected to the transmission tower, and a wind deflection device is provided on each of the suspension clamps.
进一步作为本实用新型技术方案的改进,所述第一绝缘子串和第二绝缘子串的前端均连接球头挂环,所述球头挂环上装有可与输电塔连接的U型螺栓,所述第一绝缘子串和第二绝缘子串的末端均通过碗头挂板与联板相连。 As a further improvement of the technical solution of the present utility model, the front ends of the first insulator string and the second insulator string are connected to a ball-joint hanging ring, and the ball-joint hanging ring is equipped with U-shaped bolts that can be connected to the transmission tower. Both ends of the first insulator string and the second insulator string are connected to the connecting plate through the bowl hanging plate.
进一步作为本实用新型技术方案的改进,所述球头挂环和碗头挂板上均装有电弧环。 As a further improvement of the technical solution of the utility model, arc rings are installed on the ball hanging ring and the bowl hanging plate.
进一步作为本实用新型技术方案的改进,所述第一绝缘子串和第二绝缘子串均采用复合绝缘子。 As a further improvement of the technical solution of the utility model, both the first insulator string and the second insulator string use composite insulators.
进一步作为本实用新型技术方案的改进,所述联板为悬挂有三个悬垂线夹的三分裂联板,各所述悬垂线夹均通过U型夹悬挂在所述三分裂联板上。 As a further improvement of the technical solution of the present utility model, the connecting plate is a three-split connecting plate suspended with three suspension clips, and each of the suspension clips is suspended on the three-split connecting plate through a U-shaped clip.
进一步作为本实用新型技术方案的改进,所述防风偏装置包括扣装在所述悬垂线夹外侧的U型环,所述悬垂线夹的顶端设有正对的第一连接孔,所述U型环的顶端设有正对的第二连接孔,所述U型环通过穿过所述第一连接孔和第二连接孔的螺栓与悬垂线夹连接,U型环的弧顶部分在悬垂线夹的下方形成球头挂环,与所述球头挂环连接设有可安装若干重锤片的配重机构。 As a further improvement of the technical solution of the utility model, the wind deflection device includes a U-shaped ring fastened on the outside of the suspension wire clamp, and the top end of the suspension wire clamp is provided with a first connecting hole facing to it. The top of the type ring is provided with a second connecting hole opposite, and the U-shaped ring is connected with the suspension clamp through the bolts passing through the first connecting hole and the second connecting hole, and the arc top part of the U-shaped ring is suspended A ball-end hanging ring is formed below the wire clip, and a counterweight mechanism that can install several heavy hammers is connected with the ball-end hanging ring.
进一步作为本实用新型技术方案的改进,所述配重机构包括跨过所述球头挂环的U型螺丝,所述重锤片穿入所述U型螺丝并通过U型螺丝底端的螺母锁紧。 As a further improvement of the technical solution of the present invention, the counterweight mechanism includes a U-shaped screw that straddles the ball-head hanging ring, and the weight piece penetrates the U-shaped screw and locks it through the nut at the bottom of the U-shaped screw. tight.
进一步作为本实用新型技术方案的改进,各所述悬垂线夹内均装有护线套。 As a further improvement of the technical solution of the utility model, each of the suspension wire clamps is equipped with a wire protection sleeve.
本实用新型的有益效果:本双悬式复合绝缘子串,在联板上设置与输电塔连接的第一绝缘子串和第二绝缘子串,联板则通过悬垂线夹连接导线,如此本实用新型通过上述结构的改进增加了连接导线的机械强度的同时,保证了整体结构的简便性,降低制作成本,节约线路投资,也方便线路安装和维修。此外,在各悬垂线夹上设置的防风偏装置则能够改善整个绝缘子串的防风偏能力,避免发生风偏放电事故。 Beneficial effects of the utility model: the double-suspension composite insulator strings are provided with the first insulator string and the second insulator string connected to the transmission tower on the connecting plate, and the connecting plate is connected to the wire through the suspension clamp, so that the utility model can pass The improvement of the above structure not only increases the mechanical strength of the connecting wire, but also ensures the simplicity of the overall structure, reduces the production cost, saves the line investment, and facilitates the line installation and maintenance. In addition, the wind deflection device installed on each suspension clamp can improve the wind deflection capability of the entire insulator string and avoid wind deflection discharge accidents.
附图说明 Description of drawings
下面结合附图对本实用新型作进一步说明: Below in conjunction with accompanying drawing, the utility model is further described:
图1是本实用新型实施例结构主视图; Fig. 1 is a front view of the utility model embodiment structure;
图2是本实用新型实施例结构侧视图; Fig. 2 is a side view of the structure of the utility model embodiment;
图3是本实用新型实施例垂线夹上均防风偏装置结构示意图。 Fig. 3 is a schematic diagram of the structure of the wind deflection prevention device on the vertical wire clip according to the embodiment of the utility model.
具体实施方式 Detailed ways
参照图1至图3,本实用新型提供了一种双悬式复合绝缘子串,包括联板1,所述联板1上悬挂有承担导线的悬垂线夹2,所述联板1为悬挂有三个悬垂线夹2的三分裂联板,各所述悬垂线夹2均通过U型夹3悬挂在所述三分裂联板上。各所述悬垂线夹2内均装有护线套4。与所述联板1顶部相连设有连接输电塔的第一绝缘子串5和第二绝缘子串6,所述第一绝缘子串5和第二绝缘子串6均采用复合绝缘子。所述第一绝缘子串5和第二绝缘子串6的前端均连接球头挂环7,所述球头挂环7上装有可与输电塔连接的U型螺栓8,所述第一绝缘子串5和第二绝缘子串6的末端均通过碗头挂板9与联板1相连。所述球头挂环7和碗头挂板9上均装有电弧环10。 Referring to Fig. 1 to Fig. 3, the utility model provides a double-suspended composite insulator string, which includes a connecting plate 1, on which a hanging clamp 2 for conducting wires is suspended, and the connecting plate 1 is suspended with three A three-split joint plate of a suspension line clamp 2, each of the suspension line clamps 2 is suspended on the three-split joint plate by a U-shaped clamp 3. A grommet 4 is housed in each of the suspension clamps 2 . The first insulator string 5 and the second insulator string 6 connected to the transmission tower are connected to the top of the connecting plate 1, and both the first insulator string 5 and the second insulator string 6 use composite insulators. The front ends of the first string of insulators 5 and the second string of insulators 6 are connected to a ball joint ring 7, and the ball joint ring 7 is equipped with a U-shaped bolt 8 that can be connected to a transmission tower. The first string of insulators 5 and the ends of the second insulator string 6 are connected to the connecting plate 1 through the bowl hanging plate 9 . The arc ring 10 is all housed on the described ball hanging ring 7 and the bowl hanging plate 9 .
各所述悬垂线夹2上均设有防风偏装置。所述防风偏装置包括扣装在所述悬垂线夹2外侧的U型环11,所述悬垂线夹2的顶端设有正对的第一连接孔,所述U型环11的顶端设有正对的第二连接孔,所述U型环11通过穿过所述第一连接孔和第二连接孔的螺栓12与悬垂线夹2连接,U型环11的弧顶部分在悬垂线夹2的下方形成球头挂环,与所述球头挂环连接设有可安装若干重锤片13的配重机构。所述配重机构包括跨过所述球头挂环的U型螺丝14,所述重锤片13穿入所述U型螺丝14并通过U型螺丝14底端的螺母15锁紧。U型环11直接安装在悬垂线夹2的第一连接孔上,使用时可通过一个螺栓12实现整个装置在上部联板1上的安装,同时通过U型环11的弧顶部分直接形成连接下方配重机构的球头挂环,结构简洁,从而在节约制作成本的同时,简化安装、拆卸工作。 Each of the suspension clamps 2 is provided with a wind deflection device. The wind deflection device includes a U-shaped ring 11 fastened on the outside of the suspension wire clamp 2, the top end of the suspension wire clamp 2 is provided with a first connecting hole directly opposite, and the top end of the U-shaped ring 11 is provided with The second connection hole facing the U-shaped ring 11 is connected with the suspension clamp 2 through the bolt 12 passing through the first connection hole and the second connection hole. The bottom of 2 forms a ball joint link, is connected with described ball joint link and is provided with the counterweight mechanism that can install some heavy hammer plates 13. The counterweight mechanism includes a U-shaped screw 14 straddling the ball hanging ring, and the weight piece 13 penetrates the U-shaped screw 14 and is locked by a nut 15 at the bottom of the U-shaped screw 14 . The U-shaped ring 11 is directly installed on the first connection hole of the suspension clamp 2. When in use, the entire device can be installed on the upper connecting plate 1 through a bolt 12, and at the same time, the arc top part of the U-shaped ring 11 is directly connected. The ball head hanging ring of the lower counterweight mechanism has a simple structure, which simplifies installation and disassembly while saving production costs.
本双悬式复合绝缘子串,在联板1上设置与输电塔连接的第一绝缘子串5和第二绝缘子串6,联板1则通过悬垂线夹2连接导线,如此本实用新型通过上述结构的改进增加了连接导线的机械强度的同时,保证了整体结构的简便性,降低制作成本,节约线路投资,也方便线路安装和维修。此外,在各悬垂线夹2上设置的防风偏装置则能够改善整个绝缘子串的防风偏能力,避免发生风偏放电事故。 In this double-suspension composite insulator string, the first insulator string 5 and the second insulator string 6 connected to the transmission tower are arranged on the connecting plate 1, and the connecting plate 1 is connected to the wire through the suspension clamp 2, so that the utility model adopts the above structure The improvement of the invention not only increases the mechanical strength of the connecting wire, but also ensures the simplicity of the overall structure, reduces the production cost, saves line investment, and facilitates line installation and maintenance. In addition, the windage-deflection device provided on each suspension clamp 2 can improve the windage-deflection capability of the entire insulator string and avoid windy-deflection discharge accidents.
当然,本发明创造并不局限于上述实施方式,熟悉本领域的技术人员在不违背本实用新型精神的前提下还可作出等同变形或替换,这些等同的变型或替换均包含在本申请权利要求所限定的范围内。 Of course, the present invention is not limited to the above-mentioned embodiments. Those skilled in the art can also make equivalent modifications or replacements without violating the spirit of the present utility model. These equivalent modifications or replacements are all included in the claims of this application. within the limited range.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520083034.1U CN204516500U (en) | 2015-02-05 | 2015-02-05 | A kind of two suspended compound insulator string |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520083034.1U CN204516500U (en) | 2015-02-05 | 2015-02-05 | A kind of two suspended compound insulator string |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204516500U true CN204516500U (en) | 2015-07-29 |
Family
ID=53714448
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520083034.1U Expired - Lifetime CN204516500U (en) | 2015-02-05 | 2015-02-05 | A kind of two suspended compound insulator string |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204516500U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106099812A (en) * | 2016-07-01 | 2016-11-09 | 国家电网公司 | A kind of wire equilateral triangle arrangement yoke plate mechanism |
| CN109065290A (en) * | 2018-09-06 | 2018-12-21 | 国家电网有限公司 | The high altitude localities alternating current circuit 500kV duplex I type band parallel connection gaps suspension insulator |
| CN110364316A (en) * | 2019-08-14 | 2019-10-22 | 国网青海省电力公司西宁供电公司 | A transmission line support insulator fitting end |
| CN114389221A (en) * | 2021-12-30 | 2022-04-22 | 国网河南省电力公司经济技术研究院 | Windage yaw prevention fixing device for double split conductors of power transmission line |
-
2015
- 2015-02-05 CN CN201520083034.1U patent/CN204516500U/en not_active Expired - Lifetime
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106099812A (en) * | 2016-07-01 | 2016-11-09 | 国家电网公司 | A kind of wire equilateral triangle arrangement yoke plate mechanism |
| CN109065290A (en) * | 2018-09-06 | 2018-12-21 | 国家电网有限公司 | The high altitude localities alternating current circuit 500kV duplex I type band parallel connection gaps suspension insulator |
| CN110364316A (en) * | 2019-08-14 | 2019-10-22 | 国网青海省电力公司西宁供电公司 | A transmission line support insulator fitting end |
| CN114389221A (en) * | 2021-12-30 | 2022-04-22 | 国网河南省电力公司经济技术研究院 | Windage yaw prevention fixing device for double split conductors of power transmission line |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110011249A (en) | Windbreaker and power transmission tower | |
| CN204516500U (en) | A kind of two suspended compound insulator string | |
| CN204497696U (en) | A kind of power line tension shaft tower wind-deviation insulator string holding clamp | |
| CN103422699A (en) | Electric transmission line tower made of composite materials | |
| CN206673533U (en) | A kind of novel high-pressure transmission line of electricity angle pole mounting structure | |
| CN204516503U (en) | A kind of wind-deviation suspension insulator | |
| CN201191541Y (en) | Synthetic insulator preventing wind drift | |
| CN207069526U (en) | A kind of aerial cable stockbridge damper device for preventing positioning | |
| CN210490398U (en) | Prevent wind inclined to one side and use handbag formula suspension clamp | |
| CN105337236A (en) | Windproof line drawing device for high-voltage transmission line | |
| CN205212386U (en) | Insulator chain that dangles prevents waving device | |
| CN110768194B (en) | Windage yaw prevention suspension insulator string and installation method | |
| CN204516502U (en) | A kind of double sheet power multiple division electricity transmission line insulator string | |
| CN203039319U (en) | Anti-corona aluminium pipe interval rod | |
| CN206818948U (en) | A force unloading device for installing ADSS optical cables on iron towers | |
| CN207053143U (en) | Female link fitting of pipe | |
| CN2914433Y (en) | Duplex hanging string of extra high voltage transmission line | |
| CN210536240U (en) | Wall bushing mounting structure | |
| CN204858403U (en) | A temporary hanging point fixing device for live replacement of V-shaped insulators on transmission lines | |
| CN203243003U (en) | Anti-windage suspension clamp | |
| CN103311863B (en) | A kind of bolt type adjusting elbow | |
| CN209001541U (en) | Suspension clip for insulator string with good tensile performance | |
| CN204516499U (en) | The two suspended compound insulator string of a kind of lightning protection | |
| CN207250732U (en) | 1000kV strain tower of transmission line hard wire jumper is grounded Special wire-clip | |
| CN105977860A (en) | Composite cross-arm insulator device and method for replacing overhead transmission line |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: Two suspension type composite insulator clusters Effective date of registration: 20161222 Granted publication date: 20150729 Pledgee: FOGANG RURAL CREDIT COOPERATIVE ASSOCIATION Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: 2016990001166 |
|
| PLDC | Enforcement, change and cancellation of contracts on pledge of patent right or utility model | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Date of cancellation: 20181123 Granted publication date: 20150729 Pledgee: FOGANG RURAL CREDIT COOPERATIVE ASSOCIATION Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: 2016990001166 |
|
| PC01 | Cancellation of the registration of the contract for pledge of patent right | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: Two suspension type composite insulator clusters Effective date of registration: 20181203 Granted publication date: 20150729 Pledgee: FOGANG RURAL CREDIT COOPERATIVE ASSOCIATION Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: 2018440000345 |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Date of cancellation: 20191129 Granted publication date: 20150729 Pledgee: FOGANG RURAL CREDIT COOPERATIVE ASSOCIATION Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: 2018440000345 |
|
| PC01 | Cancellation of the registration of the contract for pledge of patent right | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: Two suspension type composite insulator clusters Effective date of registration: 20191205 Granted publication date: 20150729 Pledgee: Guangdong Fogang Rural Commercial Bank Co.,Ltd. Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: Y2019440020032 |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Date of cancellation: 20210309 Granted publication date: 20150729 Pledgee: Guangdong Fogang Rural Commercial Bank Co.,Ltd. Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: Y2019440020032 |
|
| PC01 | Cancellation of the registration of the contract for pledge of patent right | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: A double suspension composite insulator string Effective date of registration: 20210330 Granted publication date: 20150729 Pledgee: Guangdong Fogang Rural Commercial Bank Co.,Ltd. Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: Y2021440000110 |
|
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Date of cancellation: 20230327 Granted publication date: 20150729 Pledgee: Guangdong Fogang Rural Commercial Bank Co.,Ltd. Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: Y2021440000110 |
|
| PC01 | Cancellation of the registration of the contract for pledge of patent right | ||
| PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: A Double Suspension Composite Insulator String Effective date of registration: 20230330 Granted publication date: 20150729 Pledgee: Guangdong Fogang Rural Commercial Bank Co.,Ltd. Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: Y2023980036988 |
|
| PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
| CX01 | Expiry of patent term |
Granted publication date: 20150729 |
|
| CX01 | Expiry of patent term | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right | ||
| PC01 | Cancellation of the registration of the contract for pledge of patent right |
Granted publication date: 20150729 Pledgee: Guangdong Fogang Rural Commercial Bank Co.,Ltd. Pledgor: GUANGZHOU XINYUAN HENGYE POWER TRANSMISSION DEVICE Co.,Ltd. Registration number: Y2023980036988 |