CN204510209U - Secondary grouting prestress anchorage cable - Google Patents

Secondary grouting prestress anchorage cable Download PDF

Info

Publication number
CN204510209U
CN204510209U CN201420661710.4U CN201420661710U CN204510209U CN 204510209 U CN204510209 U CN 204510209U CN 201420661710 U CN201420661710 U CN 201420661710U CN 204510209 U CN204510209 U CN 204510209U
Authority
CN
China
Prior art keywords
cable
anchorage cable
pressure slip
prestress anchorage
casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420661710.4U
Other languages
Chinese (zh)
Inventor
成永刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420661710.4U priority Critical patent/CN204510209U/en
Application granted granted Critical
Publication of CN204510209U publication Critical patent/CN204510209U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of prestress anchorage cable, is specifically related to a kind of secondary grouting prestress anchorage cable, belongs to slope body stabilization works instrument field.The utility model comprises prestress anchorage cable, and on anchor cable body, binding has a Grouting Pipe, and on prestressed anchor cable body, also binding has an other high-pressure slip-casting pipe, and the duct wall of the high-pressure slip-casting pipe in prestressed cable anchorage segment limit is provided with some injected holes; Injected hole is quincunx distribution, spacing 100mm, aperture 5mm.By some injected holes that newly-increased high-pressure slip-casting pipe and its duct wall in anchorage cable anchoring segment limit are arranged, secondary high-pressure slip-casting is carried out to anchorage cable anchoring section Rock And Soil, anchorage cable anchoring section Rock And Soil shear resistance is improved greatly, effectively can improve the prestressed stretch-draw of anchor cable stabilization works, and then effectively improve the stability on side slope or landslide.Safety factor is high, short construction period, cost are low, and prestress anchorage cable can extensively be used at the Rock And Soil that formation lithology is poor.

Description

Secondary grouting prestress anchorage cable
Technical field
The utility model relates to a kind of prestress anchorage cable, is specifically related to a kind of secondary grouting prestress anchorage cable, belongs to slope body stabilization works instrument field.
Background technology
In the body stabilization works construction process of slope, often can run into the poor Rock And Soil of formation lithology, as silty clay, coal seam, expansive soil or underground water grow Rock And Soil.Because these Rock And Soil shear strengths are low, make the anchored force of prestress anchorage cable reach designing requirement, cause prestress anchorage cable effectively cannot use in these Rock And Soils, thus limit the scope of application of anchor cable.
Therefore the shear resistance of the poor Rock And Soil of these formation lithologies need be increased, improve the anchored force of anchor cable, prestress anchorage cable can extensively be used at the Rock And Soil that formation lithology is poor.
Utility model content
The purpose of this utility model is just to provide a kind of secondary grouting prestress anchorage cable to solve the problem, by carrying out secondary high-pressure slip-casting to anchorage cable anchoring section Rock And Soil, increase the shear strength of anchorage cable anchoring section Rock And Soil, effectively can improve the anchored force of prestress anchorage cable, prestress anchorage cable can extensively be used at the Rock And Soil that formation lithology is poor.
The utility model is achieved through the following technical solutions above-mentioned purpose:
Secondary grouting prestress anchorage cable, comprise prestress anchorage cable, on anchor cable body, binding has a Grouting Pipe, it is characterized in that, on prestressed anchor cable body, also binding has an other high-pressure slip-casting pipe, and the duct wall of the high-pressure slip-casting pipe in prestressed cable anchorage segment limit is provided with some injected holes.
Further, the injected hole that the duct wall of the high-pressure slip-casting pipe in described prestressed cable anchorage segment limit is arranged is quincunx distribution, spacing 100mm, aperture 5mm.
Further, described high-pressure slip-casting pipe adopts coating steel pipe to make.
The beneficial effects of the utility model are:
The some injected holes of the utility model by newly-increased high-pressure slip-casting pipe and its duct wall within the scope of the anchoring section of anchor cable are arranged, secondary high-pressure slip-casting is carried out to anchorage cable anchoring section Rock And Soil, anchorage cable anchoring section Rock And Soil shear resistance is improved greatly, effectively improve the anchoring in rock and soil performance of anchorage cable anchoring section, effectively can improve the prestressed stretch-draw of anchor cable stabilization works, and then effectively improve the stability on side slope or landslide, there is safety factor high, short construction period, low cost and other advantages, prestress anchorage cable can extensively be used at the Rock And Soil that formation lithology is poor.
Accompanying drawing explanation
Accompanying drawing 1 is result schematic diagram of the present utility model;
Accompanying drawing 2 is the utility model high-pressure slip-casting pipe and injected hole distributed architecture close-up schematic view.
Detailed description of the invention
Below in conjunction with drawings and Examples, the utility model is further illustrated.
As shown in drawings: the utility model is by the high-pressure slip-casting pipe increased newly and the some injected holes arranged in the anchoring section scope inner duct wall of anchor cable, secondary high-pressure slip-casting is carried out to anchorage cable anchoring section Rock And Soil, anchorage cable anchoring section Rock And Soil shear resistance is improved greatly, effectively improve the anchoring in rock and soil performance of anchorage cable anchoring section, effectively can improve the prestressing force of anchor cable stabilization works, and then effectively improve the stability on side slope or landslide, there is safety factor high, short construction period, low cost and other advantages, prestress anchorage cable can extensively be used at the Rock And Soil that formation lithology is poor.
The utility model is specially adapted to the anchorage cable engineering of formation lithology difference (as the side slope etc. that silty clay, coal seam, expansive soil or underground water are grown).Anchor cable adopts 15.24mm, high strength, the common steel strand manufacturing of underrelaxation, and steel strand intensity is f pk=1860MPa; When making anchor cable, steel strand length comparatively should increase 1.5m anchor head stretch-draw section by design length, and spiral bar near being positioned over anchor pad bottom, must being forbidden to throw off and placing.
Need before slip casting to block at the bottom of all injected holes in anchorage cable anchoring segment limit inner duct wall and pipe with two layers of engineering adhesive plaster, prevent slurry during first time slip casting from entering, the high-pressure slip-casting pipe of blocking secondary high-pressure slip-casting and cause secondary grouting to implement.
First on the body of slope, after machine drilling, in hole, the anchor cable being banded with once common Grouting Pipe and secondary high-pressure slip-casting pipe is put into.
First time slip casting: first time slip casting is injected from common Grouting Pipe, common Grouting Pipe adopts 22PVC pipe to make, and only reserves slurry outlet at pipe end.Adopt at the bottom of hole and return slurry slip casting method, forbid to pull out Grouting Pipe, to play the effect for secondary high-pressure slip-casting sealing of hole.
Second time slip casting: second time slip casting is injected from high-pressure slip-casting pipe, high-pressure slip-casting pipe adopts 22 coating steel pipes to make, and the duct wall within the scope of the anchoring section of anchor cable is provided with some injected holes, aperture 5mm, spacing 100mm, in quincunx distribution.After first time slip casting 2 hours bleeding, adopt M30 neat slurry to carry out high-pressure slip-casting to anchoring section, grouting pressure should not be less than 1.5MPa.The two layer engineering adhesive plaster of shutoff on injected hole can be washed open by high pressure.
Twice slip casting is complete after slurries shrink, and benefit slurry should be carried out in aperture, mends slurry and adopts M30 cement mortar.
After anchor cable secondary grouting completes 28 days, can be used for normal prestressd anchor cable stretch-draw.
Above-mentioned detailed description of the invention is preferred embodiment of the present utility model; can not limit the utility model; other is any does not deviate from the technical solution of the utility model and the substitute mode of the change made or other equivalence, is included within protection domain of the present utility model.

Claims (3)

1. secondary grouting prestress anchorage cable, comprise prestress anchorage cable, on anchor cable body, binding has a Grouting Pipe, it is characterized in that, on prestressed anchor cable body (1), also binding has an other high-pressure slip-casting pipe (2), and the duct wall of the high-pressure slip-casting pipe (2) in prestressed cable anchorage segment limit is provided with some injected holes (3).
2. a kind of secondary grouting prestress anchorage cable according to claim 1, is characterized in that, described injected hole (3) distribute spacing 100mm, aperture 5mm.
3. a kind of secondary grouting prestress anchorage cable according to claim 1, is characterized in that, described high-pressure slip-casting pipe (2) adopts coating steel pipe to make.
CN201420661710.4U 2014-11-07 2014-11-07 Secondary grouting prestress anchorage cable Expired - Fee Related CN204510209U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420661710.4U CN204510209U (en) 2014-11-07 2014-11-07 Secondary grouting prestress anchorage cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420661710.4U CN204510209U (en) 2014-11-07 2014-11-07 Secondary grouting prestress anchorage cable

Publications (1)

Publication Number Publication Date
CN204510209U true CN204510209U (en) 2015-07-29

Family

ID=53708201

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420661710.4U Expired - Fee Related CN204510209U (en) 2014-11-07 2014-11-07 Secondary grouting prestress anchorage cable

Country Status (1)

Country Link
CN (1) CN204510209U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105973559A (en) * 2016-07-04 2016-09-28 青岛建集团有限公司 Motor train unit body colliding rigid wall test platform system
CN112326942A (en) * 2020-10-29 2021-02-05 中国核工业华兴建设有限公司 Device and method for testing bleeding and volume stability of cement slurry
WO2022007695A1 (en) * 2020-07-06 2022-01-13 青岛理工大学 Pre-stressed anchor cable expandable inner anchor head

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105973559A (en) * 2016-07-04 2016-09-28 青岛建集团有限公司 Motor train unit body colliding rigid wall test platform system
CN105973559B (en) * 2016-07-04 2018-11-20 青岛一建集团有限公司 Motor train unit body hits rigid wall testing platform system
WO2022007695A1 (en) * 2020-07-06 2022-01-13 青岛理工大学 Pre-stressed anchor cable expandable inner anchor head
CN112326942A (en) * 2020-10-29 2021-02-05 中国核工业华兴建设有限公司 Device and method for testing bleeding and volume stability of cement slurry
CN112326942B (en) * 2020-10-29 2022-12-09 中国核工业华兴建设有限公司 Device and method for testing bleeding and volume stability of cement slurry

Similar Documents

Publication Publication Date Title
CN203475429U (en) Combined type anchor rod suitable for loess side slope
CN103726498B (en) Grouting expanding pre-stressed anchor rod of fiber bag and using method thereof
CN103669346B (en) A kind of tuck inside the sleeve raft pipe and the application in landslide control
CN103603675A (en) Supporting method of permeable soft broken rock stratum roadway
CN104032737A (en) Construction method and structure of pressure dispersing type expansion head anchor rod
CN105422128A (en) Method for preventing goaf gas leakage in deep shaft gob-side entry driving
CN104074190A (en) Secondary high-pressure grouting expansion bit anchor rod and construction method thereof
CN204510209U (en) Secondary grouting prestress anchorage cable
CN103089276A (en) Deep-shallow hole and high-low pressure coupling grouting technology
CN102168419B (en) Method for compounding anchor rod by geotextile reinforcing
CN102877470A (en) Combined soil nailing construction method
CN203701105U (en) Fiber bag grouting expanding body prestressed anchor
CN103696787A (en) Deformed steel bar high-pressure grouting anchor rod and support method for reinforcing roadway by deformed steel bar high-pressure grouting anchor rod
CN205152965U (en) Utilize reinforced (rfd) environmental protection of plant roots to squeeze into slip casting type soil nail wall
CN102182481B (en) Anchor rope grouting-stop plug
CN205530282U (en) Prestressed anchorage cable
CN205154213U (en) Slip casting anchor rope that adapts to high -pressure slip casting
CN103911993A (en) PHA (preliminary hazard analysis) anchor rod and construction method thereof
CN204311454U (en) A kind of pile end concrete placing device for foundation construction
CN205089343U (en) Mining high -pressure slip casting stock
CN204125941U (en) Uplift pile structure
CN103924592B (en) A kind of pressure-type PHA anchor pole and construction method thereof
CN204343286U (en) A kind of steel pipe pile support
CN204899958U (en) Antiskid anchor rope
CN205012333U (en) Recoverable FRP stock with enlarged footing

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150729

Termination date: 20171107