CN204491324U - The interim twilight orbit structure of operation line steel sleeper in a kind of subway tunnel - Google Patents

The interim twilight orbit structure of operation line steel sleeper in a kind of subway tunnel Download PDF

Info

Publication number
CN204491324U
CN204491324U CN201520002024.0U CN201520002024U CN204491324U CN 204491324 U CN204491324 U CN 204491324U CN 201520002024 U CN201520002024 U CN 201520002024U CN 204491324 U CN204491324 U CN 204491324U
Authority
CN
China
Prior art keywords
steel sleeper
interim
operation line
bearing
subway tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520002024.0U
Other languages
Chinese (zh)
Inventor
周登辉
贾炳义
殷业锁
周卫国
龚元
李琦
沈韫
卫海津
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201520002024.0U priority Critical patent/CN204491324U/en
Application granted granted Critical
Publication of CN204491324U publication Critical patent/CN204491324U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses the interim transition of operation line steel sleeper in a kind of subway tunnel and open track structure, comprise steel sleeper, bearing and connecting rod, employing steel sleeper designs, between steel sleeper is longitudinal, connecting rod connects, form overall track structure, be convenient to install, dismounting, can realize bias, superelevation adjustment, stressed through safety inspection calculation meet operation security condition.

Description

The interim twilight orbit structure of operation line steel sleeper in a kind of subway tunnel
Technical field
The utility model relates to interim twilight orbit construction applications, specifically after existing ballast bed structure is removed, meet Operational requirements and the interim transition steel sleeper track structure installing, set up.
Background technology
After operation line operational railway structure is abolished in subway tunnel, the Operational requirements of circuit be met, and train operation safety will be ensured.Therefore design have developed the interim transition steel sleeper track structure of one, substitutes existing railway roadbed, can realize bias, superelevation adjustment, and is convenient to install, dismantle, and ensures train safe operation.
Utility model content
The purpose of this utility model is to provide the interim twilight orbit structure of operation line steel sleeper in a kind of subway tunnel, recover temporary line and guarantee the requirement of circuit operation security, bias, superelevation adjustment can be realized while guarantee recovers circuit and circuit operation security, and be convenient to install, dismantle, effectively ensure that efficiency of construction and train operation safety.
The technical solution adopted in the utility model is as follows:
The interim twilight orbit structure of operation line steel sleeper in subway tunnel, include the hard-wired bearing of tunnel tube wall with both sides, between the bearing of both sides, erection has steel sleeper, adjustable link is connected with between two adjacent steel sleepers, described adjustable link includes the swivel nut be fixedly connected with both sides steel sleeper, and the double threaded screw matched with swivel nut.
Described tunnel tube wall is fixedly connected with by 4 setscrews with bearing.
Leave enough adjustment spaces between steel sleeper of the present utility model and bearing, be connected with connecting rod between steel sleeper with steel sleeper and ensure that steel sleeper track structure globality, it is characterized in that adopt steel sleeper design, stressed through safety inspection calculation meet safe operation condition; Bias, superelevation adjustment can be realized, and be convenient to install, dismantle, ensure train operation safety.
The utility model has the advantages that:
1, steel sleeper track structure is made up of three parts and comprises steel sleeper, bearing and connecting rod, and combining structure is convenient to substep and is installed, and meeting the short time sets up requirement;
2, steel sleeper track structure can realize track circuit bias, superelevation adjustment, connect with connecting rod between steel sleeper, ensure that the globality of steel sleeper track structure, stressed through safety inspection calculation meet safe operation condition, effectively raise operating efficiency and ensure that train operation safety.
Accompanying drawing explanation
Fig. 1 is steel sleeper cross-sectional drawing of the present utility model;
Fig. 2 is that steel sleeper of the present utility model connects plan view.
concrete implementation step
See accompanying drawing, the interim twilight orbit structure of operation line steel sleeper in subway tunnel, include bearing 2 hard-wired with the tunnel tube wall 1 of both sides, tunnel tube wall 1 is fixedly connected with by 4 setscrews with bearing 2, between the bearing of both sides, erection has steel sleeper 3, be connected with adjustable link 4 between two adjacent steel sleepers 3, adjustable link 4 includes the swivel nut be fixedly connected with both sides steel sleeper, and the double threaded screw matched with swivel nut.
Steel sleeper connected mode is described in detail below in conjunction with accompanying drawing:
In subway tunnel operation line rest the head on interim twilight orbit structure by steel sleeper, bearing and connecting rod three part form: 1) measurement and positioning steel sleeper support position; 2) by 4 setscrews, bearing is fixed on tube wall on tunnel tube wall; 3) steel sleeper is erected at itself and bearing are fixed with bolt by the bearing that fixes; 4) between two steel sleepers, an entirety is connected into connecting rod; 5) by steel rail laying on the track of steel sleeper, reach track after accurate adjustment and open requirement.

Claims (2)

1. the interim twilight orbit structure of operation line steel sleeper in subway tunnel, it is characterized in that, include the hard-wired bearing of tunnel tube wall with both sides, between the bearing of both sides, erection has steel sleeper, adjustable link is connected with between two adjacent steel sleepers, described adjustable link includes the swivel nut be fixedly connected with both sides steel sleeper, and the double threaded screw matched with swivel nut.
2. the interim twilight orbit structure of operation line steel sleeper in subway tunnel according to claim 1, it is characterized in that, described tunnel tube wall is fixedly connected with by 4 setscrews with bearing.
CN201520002024.0U 2015-01-04 2015-01-04 The interim twilight orbit structure of operation line steel sleeper in a kind of subway tunnel Active CN204491324U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520002024.0U CN204491324U (en) 2015-01-04 2015-01-04 The interim twilight orbit structure of operation line steel sleeper in a kind of subway tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520002024.0U CN204491324U (en) 2015-01-04 2015-01-04 The interim twilight orbit structure of operation line steel sleeper in a kind of subway tunnel

Publications (1)

Publication Number Publication Date
CN204491324U true CN204491324U (en) 2015-07-22

Family

ID=53570622

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520002024.0U Active CN204491324U (en) 2015-01-04 2015-01-04 The interim twilight orbit structure of operation line steel sleeper in a kind of subway tunnel

Country Status (1)

Country Link
CN (1) CN204491324U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499384A (en) * 2015-01-04 2015-04-08 中铁四局集团有限公司 Steel sleeper type temporary transition track structure for inner operating railway of subway tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499384A (en) * 2015-01-04 2015-04-08 中铁四局集团有限公司 Steel sleeper type temporary transition track structure for inner operating railway of subway tunnel

Similar Documents

Publication Publication Date Title
CN203947375U (en) A kind of shield machine chassis and battery truck composite sleeper
CN103452018B (en) Track gauge correction method for double-block type ballastless track construction
CN207363606U (en) A kind of drilling machine sliding system
CN204491324U (en) The interim twilight orbit structure of operation line steel sleeper in a kind of subway tunnel
CN104499384A (en) Steel sleeper type temporary transition track structure for inner operating railway of subway tunnel
CN204283451U (en) Cold district railway tunnel winterization system
CN204753350U (en) Combination bridge
CN208088195U (en) A kind of municipal administration security protection warning rail
CN203212952U (en) Docking device of train rail
CN104088297B (en) A kind of bellows installing rack for culvert construction and application thereof
CN202359511U (en) Subway tunnel ditch and track bed one-time pouring formwork structure
CN202687787U (en) Gantry crane rail transfer device for heavy haul railway beam yard
CN206591374U (en) The portable disanchoring device of railroad sleeper
CN204941564U (en) Subway tunnel narrow spacing leaves the right or normal track row gate-type lining cutting bench frame apparatus
CN204139577U (en) Embedment means formula wall-connecting piece after a kind of
CN201671029U (en) Ballastless track bed turnout assembling platform
CN203050727U (en) Lining formwork trolley horizontally-moving upper longitudinal beam structure
CN203701282U (en) Pre-buried channel and support structure matched with same
CN203213308U (en) Prefabricated concrete column connection node structure
CN203668779U (en) Double-block type ballastless track sleeper interval adjusting device
CN202055122U (en) Steel rail with seamless connection
CN205116012U (en) Bolt - steel casing pipe - connection finned plate's hookup
CN206015434U (en) A kind of railroad bridge guard rail
CN205077341U (en) Clearance adjustment device of magnetic levitation track section of track
CN105155368B (en) A kind of lash adjusting device of the magnetic-levitation section of track

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant