CN204456846U - For building the template system of body of wall - Google Patents

For building the template system of body of wall Download PDF

Info

Publication number
CN204456846U
CN204456846U CN201520021675.4U CN201520021675U CN204456846U CN 204456846 U CN204456846 U CN 204456846U CN 201520021675 U CN201520021675 U CN 201520021675U CN 204456846 U CN204456846 U CN 204456846U
Authority
CN
China
Prior art keywords
template
mold board
board wall
groove
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520021675.4U
Other languages
Chinese (zh)
Inventor
李震
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201520021675.4U priority Critical patent/CN204456846U/en
Application granted granted Critical
Publication of CN204456846U publication Critical patent/CN204456846U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a kind of template system for building body of wall, comprise internal mold board wall, external mold board wall and Screw arbor with nut at both-ends, internal mold board wall, external mold board wall offers the installing hole for wearing Screw arbor with nut at both-ends, described Screw arbor with nut at both-ends penetrates internal mold board wall, installing hole on external mold board wall, thus connect internal mold board wall and external mold board wall, described internal mold board wall and external mold board wall form by some pieces of template splicings, it is characterized in that: the vertical two ends of template arrange the first grafting block respectively, the vertical two ends of the first inserting groove or template all arrange the first grafting block and the first inserting groove, the horizontal two ends of template arrange the first grafting block respectively, the horizontal two ends of the first inserting groove or template all arrange the first grafting block and the first inserting groove.The utility model can manually realize quick splicing, and without the need to adopting support to reinforce, decrease installation, dismounting man-hour, improve operating efficiency, template can repeated disassembled and assembled, reuses, improves product utilization rate.

Description

For building the template system of body of wall
Technical field
The utility model relates to a kind of template system for building body of wall.
Background technology
In current construction work, in order to realize accelerating construction progress and reduce the object of engineering cost, a large amount of use utilizes construction formwork and adopts the mode of building to be shaped the mode of construction of body of wall.The working template system of Cast-in-situ Concrete Structural Engineering, primarily of template and Screw arbor with nut at both-ends two parts composition.Template is the force bearing plate directly contacting newly placed concrete, forms internal mold board wall and external mold board wall by template splicing, thus is formed between internal mold board wall and external mold board wall for concrete perfusion and the body of wall space of the body of wall that is shaped; Screw arbor with nut at both-ends is used for internal mold board wall to be connected with external mold board wall, thus keeps the spacing of internal mold board wall and external mold board wall and bear concrete lateral pressure and load.Also need between form walls and external mold board wall to arrange the sleeve pipe for controlling distance between internal mold board wall and external mold board wall, described sleeve pipe is generally set on Screw arbor with nut at both-ends.
Existing template system, mounting means is as follows, template splicing is become internal mold board wall and external mold board wall, wherein internal mold board wall and external mold board wall are provided with the installing hole for wearing Screw arbor with nut at both-ends, operator is by hand-held sleeve pipe, sleeve pipe is sent between internal mold board wall and external mold board wall, and Screw arbor with nut at both-ends is penetrated space between internal mold board wall and external mold board wall and threading from installing hole, Screw arbor with nut at both-ends passes from another corresponding installing hole, now operator can decontrol sleeve pipe, Screw arbor with nut at both-ends to be locked top nut, thus sleeve pipe is fixed between internal mold board wall and exterior sheathing.
Existing template system, the internal mold board wall become by template splicing and external mold board wall, template often needs to be achieved a fixed connection by the support be fixed on outside template, cause whole template system not only to need that a large amount of supports is installed and also need removal bracket after having built, cause whole man-hour very long, efficiency is not high.
Utility model content
The purpose of this utility model is to overcome above shortcomings in prior art, and provides a kind of reasonable in design, without the need to the template system for building body of wall being undertaken reinforcing by support.
The technical scheme in the invention for solving the above technical problem is:
A kind of template system for building body of wall, comprise internal mold board wall, external mold board wall and Screw arbor with nut at both-ends, internal mold board wall, external mold board wall offers the installing hole for wearing Screw arbor with nut at both-ends, described Screw arbor with nut at both-ends penetrates internal mold board wall, installing hole on external mold board wall, thus connect internal mold board wall and external mold board wall, described internal mold board wall and external mold board wall form by some pieces of template splicings, it is characterized in that: the vertical two ends of template arrange the first grafting block respectively, the vertical two ends of the first inserting groove or template all arrange the first grafting block and the first inserting groove, the horizontal two ends of template arrange the first grafting block respectively, the horizontal two ends of the first inserting groove or template all arrange the first grafting block and the first inserting groove, wherein, first grafting block and the first inserting groove match, make all to realize splicing mutually by the first grafting block and the first inserting groove between two templates between two templates adjacent on vertical direction and adjacent in horizontal direction, thus become internal mold board wall by template splicing, external mold board wall.By said structure, can manually realize quick splicing, without the need to adopting support to reinforce, decrease installation, dismounting man-hour, improve operating efficiency, template can repeated disassembled and assembled, reuses, improves product utilization rate.
As preferably, the vertical two ends of template are respectively arranged with two the first grafting blocks, first inserting groove of two, the horizontal two ends of template are respectively arranged with two the first grafting blocks, first inserting groove of two, the vertical two ends of template and horizontal two ends are provided with semi-cylindrical first groove, first groove is between two the first grafting blocks or between first inserting groove of two, first groove of two templates adjacent on vertical direction is spliced into installing hole, and the first groove of two templates adjacent in horizontal direction is spliced into installing hole.Thus make on internal mold board wall, external mold board wall, except being positioned at the template at edge, all the other each templates can be provided with four Screw arbor with nut at both-ends, improving overall intensity.
As preferably, the medial surface of template is plane structure, the medial surface of template is easy to and mixes earth to depart from.
As preferably, Screw arbor with nut at both-ends is provided with sleeve pipe, the two ends of sleeve pipe are provided with holder, described holder is formed by the inserting paragraph for inserting installing hole and for the blind end be against outside template, described holder offers the spliced eye for inserted joint casing, the inwall of spliced eye is provided with the limiting section (limiting section can be the annular projection of the inwall of protrusion spliced eye or spaced casting lug thereon) for propping up sleeve pipe, sleeve pipe penetrates installing hole, enter internal mold board wall, behind body of wall space between external mold board wall, holder is plugged at the two ends of sleeve pipe, Screw arbor with nut at both-ends penetrates the spliced eye on one of them holder successively, sleeve pipe, lock Screw arbor with nut at both-ends after spliced eye on another holder, the two ends of sleeve pipe are against on the limiting section of two holders respectively, the inward at both ends of Screw arbor with nut at both-ends compresses two holders, the external diameter of sleeve pipe and the diameter compatible of spliced eye close, the external diameter of inserting paragraph and the diameter compatible of installing hole close.Thus can in casting process, prevent mixed earth from being leaked by spliced eye, installing hole, the distance between two holders is controlled by Screw arbor with nut at both-ends and sleeve pipe, and after the body of wall space between internal mold board wall, external mold board wall pours into mixed earth, mixed earth expands, extrude internal mold board wall, external mold board wall laterally, the outside of internal mold board wall, the outside of external mold board wall are against on the blind end on holder, thus can control the thickness of building body of wall.Adopt this kind of structure, maximum improvement is, can insert sleeve pipe from installing hole, realizes the installation of sleeve pipe, owing to putting between internal mold board wall and external mold board wall without the need to hand-held sleeve pipe, therefore greatly facilitates operation, improves efficiency of assembling.
As preferably, the end of internal mold board wall and the end of external mold board wall are provided with end panel, the side of end panel is provided with for coordinating the second inserting groove of the first grafting block or for coordinating the second grafting block of the first inserting groove or arrange the second inserting groove, the second grafting block simultaneously, thus end panel is fixed in template, adjacent end panel plane-plane contact, thus realize, the sealing of template system, prevent mixed earth from being leaked by the gap of adjacent end panel, the medial surface of end panel is set to plane structure.
As preferably, the side of end panel is provided with two the second inserting grooves or two the second grafting blocks, being provided with between two the second inserting grooves for being spliced into the second groove of installing hole or the sealing for closing the first groove with the first groove, being provided with between two the second grafting blocks for being spliced into the second groove of installing hole or the sealing for closing the first groove with the first groove.
As preferably, template adopts integrated injection forming, and the outside of template is latticed first reinforcing rib.Adopt this kind of structure, greatly reducing injection moulding materials, while reducing manufacturing cost, ensure that overall intensity, make product more durable, improve repeat usage, and in installation process, hand-held first reinforcing rib also can be facilitated to carry out model sheetinstallat, improve the convenience of operation.
As preferably, spliced eye is provided with the second reinforcing rib that some extend to limiting section, described second reinforcing rib is arranged along the axis of spliced eye, adopt this kind of structure, greatly reducing injection moulding materials, while reducing manufacturing cost, the intensity of limiting section is improve by the second reinforcing rib arranged along the axis of spliced eye, make holder can bear the pressure of larger Screw arbor with nut at both-ends, make in casting process, the intensity of template system is more firm.
As preferably, the first inserting groove, the second slot adopt oat tail groove structure.Adopt this structure, structure is simple, and after splicing, the structure of internal mold board wall, external mold board wall is comparatively firm.
As preferably, the end of inserting paragraph is pyramidal structure, thus conveniently extracts out from building body of wall.
As preferably, the length of template is 20cm-50cm, and the width of template is 20cm-50cm, and the thickness of template is 2cm-10cm.
The utility model compared with prior art, has the following advantages and effect: can manually realizing quick splicing, reinforcing without the need to adopting support, decrease installation, dismounting man-hour, improve operating efficiency, template can repeated disassembled and assembled, reuse, improve product utilization rate.
Accompanying drawing explanation
Fig. 1 is the structural representation of the utility model embodiment one.
Fig. 2 is the structural representation of template connecting structure in the utility model embodiment one.
Fig. 3 is the mounting structure schematic diagram of wherein a kind of end panel in the utility model embodiment one.
Fig. 4 is the mounting structure schematic diagram of alternative end panel in the utility model embodiment one.
Fig. 5 is the mounting structure schematic diagram of split bolt in the utility model embodiment one.
Fig. 6 is the perspective view of template in the utility model embodiment one.
Fig. 7 is the perspective view of wherein a kind of end panel in the utility model embodiment one.
Fig. 8 is the perspective view of alternative end panel in the utility model embodiment one.
Fig. 9 is the perspective view on another visual angle of wherein a kind of end panel in the utility model embodiment one.
Figure 10 is the perspective view on another visual angle of alternative end panel in the utility model embodiment one.
Figure 11 is the sectional structure schematic diagram of template in the utility model embodiment one.
Figure 12 is the sectional structure schematic diagram of wherein a kind of end panel in the utility model embodiment one.
Figure 13 is the sectional structure schematic diagram of alternative end panel in the utility model embodiment one.
Figure 14 is the structural representation of holder in the utility model embodiment one.
Figure 15 is the structural representation of the utility model embodiment two.
Figure 16 is the structural representation of template connecting structure in the utility model embodiment two.
Figure 17 is the mounting structure schematic diagram of wherein a kind of end panel in the utility model embodiment two.
Figure 18 is the mounting structure schematic diagram of alternative end panel in the utility model embodiment two.
Figure 19 is the mounting structure schematic diagram of split bolt in the utility model embodiment two.
Figure 20 is the sectional structure schematic diagram of template in the utility model embodiment two.
Figure 21 is the sectional structure schematic diagram of wherein a kind of end panel in the utility model embodiment two.
Figure 22 is the sectional structure schematic diagram of alternative end panel in the utility model embodiment two.
Figure 23 is the structural representation of holder in the utility model embodiment two.
Figure 24 is the sectional structure schematic diagram of wherein a kind of end panel in the utility model embodiment three.
Figure 25 is the sectional structure schematic diagram of alternative end panel in the utility model embodiment three.
Figure 26 is the sectional structure schematic diagram of wherein a kind of end panel in the utility model embodiment three.
Figure 27 is the sectional structure schematic diagram of alternative end panel in the utility model embodiment three.
Detailed description of the invention
Below in conjunction with accompanying drawing, also by embodiment, the utility model is described in further detail, and following examples are that the utility model is not limited to following examples to explanation of the present utility model.
Embodiment one
See Fig. 1-Figure 14, the present embodiment is for building the template system of body of wall, comprise internal mold board wall 1, external mold board wall 2 and Screw arbor with nut at both-ends 3, internal mold board wall 1, external mold board wall 2 offer the installing hole 4 for wearing Screw arbor with nut at both-ends 3, described Screw arbor with nut at both-ends 3 penetrates the installing hole 4 on internal mold board wall 1, external mold board wall 2, thus connect internal mold board wall 1 and external mold board wall 2, described internal mold board wall 1 and external mold board wall 2 are spliced by some pieces of templates 5, the medial surface of template 5 is plane structure, the medial surface of template is easy to and mixes earth to depart from.The vertical two ends of template 5 are respectively arranged with the first inserting groove 52 of two the first grafting blocks 51, two, the horizontal two ends of template 5 are respectively arranged with the first inserting groove 52 of two the first grafting blocks 51, two, wherein, first grafting block 51 and the first inserting groove 52 match, make all to realize mutual splicing by the first grafting block 51 and the first inserting groove 52 between two templates 5 between two templates 5 adjacent on vertical direction and adjacent in horizontal direction, thus be spliced into internal mold board wall 1, external mold board wall 2 by template 5.The vertical two ends of template 5 and horizontal two ends are provided with semi-cylindrical first groove 53, first groove 53 is between two the first grafting blocks 51 or between first inserting groove 52 of two, first groove 53 of two templates 5 adjacent on vertical direction is spliced into installing hole 4, and the first groove 53 of two templates 5 adjacent in horizontal direction is spliced into installing hole 4.Screw arbor with nut at both-ends 3 is provided with sleeve pipe 6, the two ends of sleeve pipe 6 are provided with holder 7, described holder 7 is formed by the inserting paragraph 71 for inserting installing hole 4 and for the blind end 72 be against outside template 5, described holder 7 offers the spliced eye 711 for inserted joint casing 6, the inwall of spliced eye 711 is provided with the limiting section 712 for propping up sleeve pipe 6, sleeve pipe 6 penetrates installing hole 4, enter internal mold board wall 1, behind body of wall space between external mold board wall 2, holder 7 is plugged at the two ends of sleeve pipe 6, Screw arbor with nut at both-ends 3 penetrates the spliced eye 711 on one of them holder 7 successively, sleeve pipe 6, lock Screw arbor with nut at both-ends 3 after spliced eye 711 on another holder 7, the two ends of sleeve pipe 6 are against on the limiting section 712 of two holders 7 respectively, the inward at both ends of Screw arbor with nut at both-ends 3 compresses two holders 7, the external diameter of sleeve pipe 6 and the diameter compatible of spliced eye 711 close, the external diameter of inserting paragraph 71 and the diameter compatible of installing hole 4 close.The end of internal mold board wall 1 and the end of external mold board wall 2 are provided with end panel, the structure of end panel divides two kinds, wherein a kind of side of end panel 81 is provided with two the second inserting grooves 811 (as shown in figure 12) for coordinating the first grafting block 51, the side of alternative end panel 82 is provided with two the second grafting blocks 821 (as shown in figure 13) for coordinating the first inserting groove 52, thus end panel is fixed in template 5, adjacent end panel plane-plane contact.Being provided with between two the second inserting grooves 811 wherein in a kind of end panel 81 for being spliced into the second groove 812 of installing hole 4 with the first groove 53, between two the second grafting blocks 821 of alternative end panel 82, being provided with the sealing 822 for closing the first groove 53.Template 5 adopts integrated injection forming, and the outside of template 5 is latticed first reinforcing rib 54.Spliced eye 711 is provided with the second reinforcing rib 713 that some extend to limiting section 712, described second reinforcing rib 713 is arranged along the axis of spliced eye 711.First inserting groove 52, second slot adopts oat tail groove structure.The end of inserting paragraph 71 is pyramidal structure.The length of template 5 is 20cm-50cm, and the width of template 5 is 20cm-50cm, and the thickness of template 5 is 2cm-10cm.
Embodiment two
See Figure 14-Figure 23, the present embodiment is for building the template system of body of wall, comprise internal mold board wall 1, external mold board wall 2 and Screw arbor with nut at both-ends 3, internal mold board wall 1, external mold board wall 2 offers the installing hole 4 for wearing Screw arbor with nut at both-ends 3, described Screw arbor with nut at both-ends 3 penetrates internal mold board wall 1, installing hole 4 on external mold board wall 2, thus connect internal mold board wall 1 and external mold board wall 2, described internal mold board wall 1 and external mold board wall 2 are spliced by some pieces of templates 5, the vertical two ends of template 5 are provided with a first grafting block 51, first inserting groove 52 of one, the horizontal two ends of template 5 are provided with a first grafting block 51, first inserting groove 52 of one, wherein, first grafting block 51 and the first inserting groove 52 match, make all to realize mutual splicing by the first grafting block 51 and the first inserting groove 52 between two templates 5 between two templates 5 adjacent on vertical direction and adjacent in horizontal direction, thus be spliced into internal mold board wall 1 by template 5, external mold board wall 2.The vertical two ends of template 5 and horizontal two ends are provided with semi-cylindrical first groove 53, first groove 53 is between the first grafting block 51, first inserting groove 52 of template 5 end, first groove 53 of two templates 5 adjacent on vertical direction is spliced into installing hole 4, and the first groove 53 of two templates 5 adjacent in horizontal direction is spliced into installing hole 4.Screw arbor with nut at both-ends 3 is provided with sleeve pipe 6, the two ends of sleeve pipe 6 are provided with holder 7, described holder 7 is formed by the inserting paragraph 71 for inserting installing hole 4 and for the blind end 72 be against outside template 5, described holder 7 offers the spliced eye 711 for inserted joint casing 6, the inwall of spliced eye 711 is provided with the limiting section 712 for propping up sleeve pipe 6, sleeve pipe 6 penetrates installing hole 4, enter internal mold board wall 1, behind body of wall space between external mold board wall 2, holder 7 is plugged at the two ends of sleeve pipe 6, Screw arbor with nut at both-ends 3 penetrates the spliced eye 711 on one of them holder 7 successively, sleeve pipe 6, lock Screw arbor with nut at both-ends 3 after spliced eye 711 on another holder 7, the two ends of sleeve pipe 6 are against on the limiting section 712 of two holders 7 respectively, the inward at both ends of Screw arbor with nut at both-ends 3 compresses two holders 7, the external diameter of sleeve pipe 6 and the diameter compatible of spliced eye 711 close, the external diameter of inserting paragraph 71 and the diameter compatible of installing hole 4 close.The end of internal mold board wall 1 and the end of external mold board wall 2 are provided with end panel, the side of end panel is provided with for coordinating the second inserting groove 811 of the first grafting block 51 and for coordinating the second grafting block 821 of the first inserting groove 52, thus end panel is fixed in template 5, adjacent end panel plane-plane contact.The structure of end panel divides two kinds, being provided with between the second inserting groove 811, second grafting block 821 wherein in a kind of end panel 81 for being spliced into the second groove 812 of installing hole 4 with the first groove 53, between the second inserting groove 811, second grafting block 821 of alternative end panel 82, being provided with the sealing 822 for closing the first groove 53.Template 5 adopts integrated injection forming, and the outside of template 5 is latticed first reinforcing rib 54.Spliced eye 711 is provided with the second reinforcing rib 713 that some extend to limiting section 712, described second reinforcing rib 713 is arranged along the axis of spliced eye 711.First inserting groove 52, second slot adopts oat tail groove structure.The end of inserting paragraph 71 is pyramidal structure.The length of template 5 is 20cm-50cm, and the width of template 5 is 20cm-50cm, and the thickness of template 5 is 2cm-10cm.
Embodiment one
See Figure 24-27, the present embodiment is for building the template system of body of wall, substantially identical in its domain embodiment one, its difference is: be provided with the sealing 822 for closing the first groove 53 between two the second inserting grooves 811 wherein in a kind of end panel 81.Be provided with between two the second grafting blocks 821 of alternative end panel 82 for being spliced into the second groove 812 of installing hole 4 with the first groove 53.
Above content described in this manual is only to the explanation of the utility model example.The utility model person of ordinary skill in the field can make various amendment or supplements or adopt similar mode to substitute to described specific embodiment; only otherwise depart from the content of the utility model manual or surmount this scope as defined in the claims, protection domain of the present utility model all should be belonged to.

Claims (10)

1. one kind for building the template system of body of wall, comprise internal mold board wall, external mold board wall and Screw arbor with nut at both-ends, internal mold board wall, external mold board wall offers the installing hole for wearing Screw arbor with nut at both-ends, described Screw arbor with nut at both-ends penetrates internal mold board wall, installing hole on external mold board wall, thus connect internal mold board wall and external mold board wall, described internal mold board wall and external mold board wall form by some pieces of template splicings, it is characterized in that: the vertical two ends of template arrange the first grafting block respectively, the vertical two ends of the first inserting groove or template all arrange the first grafting block and the first inserting groove, the horizontal two ends of template arrange the first grafting block respectively, the horizontal two ends of the first inserting groove or template all arrange the first grafting block and the first inserting groove, wherein, first grafting block and the first inserting groove match, make all to realize splicing mutually by the first grafting block and the first inserting groove between two templates between two templates adjacent on vertical direction and adjacent in horizontal direction, thus become internal mold board wall by template splicing, external mold board wall.
2. the template system for building body of wall according to claim 1, it is characterized in that: the vertical two ends of template are respectively arranged with two the first grafting blocks, first inserting groove of two, the horizontal two ends of template are respectively arranged with two the first grafting blocks, first inserting groove of two, the vertical two ends of template and horizontal two ends are provided with semi-cylindrical first groove, first groove is between two the first grafting blocks or between first inserting groove of two, first groove of two templates adjacent on vertical direction is spliced into installing hole, first groove of two templates adjacent in horizontal direction is spliced into installing hole.
3. the template system for building body of wall according to claim 1, it is characterized in that: Screw arbor with nut at both-ends is provided with sleeve pipe, the two ends of sleeve pipe are provided with holder, described holder is formed by the inserting paragraph for inserting installing hole and for the blind end be against outside template, described holder offers the spliced eye for inserted joint casing, the inwall of spliced eye is provided with the limiting section for propping up sleeve pipe, sleeve pipe penetrates installing hole, enter internal mold board wall, behind body of wall space between external mold board wall, holder is plugged at the two ends of sleeve pipe, Screw arbor with nut at both-ends penetrates the spliced eye on one of them holder successively, sleeve pipe, lock Screw arbor with nut at both-ends after spliced eye on another holder, the two ends of sleeve pipe are against on the limiting section of two holders respectively, the inward at both ends of Screw arbor with nut at both-ends compresses two holders, the external diameter of sleeve pipe and the diameter compatible of spliced eye close, the external diameter of inserting paragraph and the diameter compatible of installing hole close.
4. the template system for building body of wall according to claim 1, it is characterized in that: the end of internal mold board wall and the end of external mold board wall are provided with end panel, the side of end panel is provided with for coordinating the second inserting groove of the first grafting block or for coordinating the second grafting block of the first inserting groove or arrange the second inserting groove, the second grafting block simultaneously, thus end panel is fixed in template, adjacent end panel plane-plane contact.
5. the template system for building body of wall according to claim 4, it is characterized in that: the side of end panel is provided with two the second inserting grooves or two the second grafting blocks, being provided with between two the second inserting grooves for being spliced into the second groove of installing hole or the sealing for closing the first groove with the first groove, being provided with between two the second grafting blocks for being spliced into the second groove of installing hole or the sealing for closing the first groove with the first groove.
6. the template system for building body of wall according to claim 1, is characterized in that: template adopts integrated injection forming, and the outside of template is latticed first reinforcing rib.
7. the template system for building body of wall according to claim 3, is characterized in that: spliced eye is provided with the second reinforcing rib that some extend to limiting section, described second reinforcing rib is arranged along the axis of spliced eye.
8. the template system for building body of wall according to claim 4, is characterized in that: the first inserting groove, the second slot adopt oat tail groove structure.
9. the template system for building body of wall according to claim 3, is characterized in that: the end of inserting paragraph is pyramidal structure.
10. the template system for building body of wall according to claim 1, is characterized in that: the length of template is 20cm-50cm, and the width of template is 20cm-50cm, and the thickness of template is 2cm-10cm.
CN201520021675.4U 2015-01-13 2015-01-13 For building the template system of body of wall Expired - Fee Related CN204456846U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520021675.4U CN204456846U (en) 2015-01-13 2015-01-13 For building the template system of body of wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520021675.4U CN204456846U (en) 2015-01-13 2015-01-13 For building the template system of body of wall

Publications (1)

Publication Number Publication Date
CN204456846U true CN204456846U (en) 2015-07-08

Family

ID=53663753

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520021675.4U Expired - Fee Related CN204456846U (en) 2015-01-13 2015-01-13 For building the template system of body of wall

Country Status (1)

Country Link
CN (1) CN204456846U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106032706A (en) * 2015-11-06 2016-10-19 广州容联建筑科技有限公司 Integrated casting molding construction method of reinforced concrete shear wall
CN111021735A (en) * 2019-12-17 2020-04-17 中冶天工集团有限公司 Novel ground height difference accurate positioner and construction method thereof
CN111910921A (en) * 2020-07-09 2020-11-10 河南五方合创建筑设计有限公司 Building template pull rod, building template and building template tie fixing system

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106032706A (en) * 2015-11-06 2016-10-19 广州容联建筑科技有限公司 Integrated casting molding construction method of reinforced concrete shear wall
CN106032706B (en) * 2015-11-06 2018-01-09 广州容联建筑科技有限公司 A kind of integral type pouring molding construction method of reinforced concrete shear wall
CN111021735A (en) * 2019-12-17 2020-04-17 中冶天工集团有限公司 Novel ground height difference accurate positioner and construction method thereof
CN111021735B (en) * 2019-12-17 2024-03-26 中冶天工集团有限公司 Construction method adopting ground height difference accurate positioner
CN111910921A (en) * 2020-07-09 2020-11-10 河南五方合创建筑设计有限公司 Building template pull rod, building template and building template tie fixing system
CN111910921B (en) * 2020-07-09 2022-05-03 河南五方合创建筑设计有限公司 Building template drawknot fixing system

Similar Documents

Publication Publication Date Title
CN204456877U (en) For the split bolt syndeton of construction formwork
CN103982199B (en) Tunnel Second Lining formwork jumbo locking plug template, plug node and method for blocking
CN208009692U (en) A kind of assembled architecture wall
CN204585497U (en) A kind of Cast-in-situ Beam mould
CN204456846U (en) For building the template system of body of wall
CN206801028U (en) A kind of building template supporting construction
CN204456866U (en) Construction formwork syndeton
CN204001745U (en) The assembly structure of a kind of construction formwork and pulling-on piece assembly
CN204663543U (en) A kind of concrete lining mould of assembled arcuated stalk tunnel
CN102979183B (en) Embedded cylindrical nut anchor bed and use method thereof
CN112942671B (en) Assembled component and connection structure thereof
CN204456844U (en) Construction formwork
CN210177707U (en) Precast concrete wallboard construction connection structure
CN205355726U (en) Pre -buried subassembly of wiring magazine
CN204456842U (en) Build body of wall end connecting
CN103132691A (en) Large steel formwork corner reinforcing device
CN204456873U (en) For building the holder of body of wall
CN204456843U (en) For building the end junction plate of body of wall
CN213597225U (en) Prefabricated formula heat preservation composite wall
CN204531420U (en) Concreting plate device
CN212153394U (en) Recoverable scalable device that props that trades of subway station deep basal pit
CN204326533U (en) A kind of formwork reinforcement fixture
CN202706529U (en) Modular wall top plastic formwork system
CN107060332B (en) Unilateral Screw arbor with nut at both-ends system
CN204691258U (en) A kind of latch of concrete blinding jockey and jockey

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150708

CF01 Termination of patent right due to non-payment of annual fee