CN204418107U - A kind of assembled moving flood protection wall - Google Patents

A kind of assembled moving flood protection wall Download PDF

Info

Publication number
CN204418107U
CN204418107U CN201520054921.6U CN201520054921U CN204418107U CN 204418107 U CN204418107 U CN 204418107U CN 201520054921 U CN201520054921 U CN 201520054921U CN 204418107 U CN204418107 U CN 204418107U
Authority
CN
China
Prior art keywords
central post
chute
group
baffle group
baffle plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520054921.6U
Other languages
Chinese (zh)
Inventor
黄伟祥
陈子鑫
李吉娃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HAIYAN YAWEI INDUSTRIAL MATERIAL Co Ltd
Original Assignee
HAIYAN YAWEI INDUSTRIAL MATERIAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=53468491&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN204418107(U) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by HAIYAN YAWEI INDUSTRIAL MATERIAL Co Ltd filed Critical HAIYAN YAWEI INDUSTRIAL MATERIAL Co Ltd
Priority to CN201520054921.6U priority Critical patent/CN204418107U/en
Application granted granted Critical
Publication of CN204418107U publication Critical patent/CN204418107U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of assembled moving flood protection wall, comprise the baffle group for stopping flood, be arranged on the edge column of baffle group both sides outermost end and the central post between being arranged in the middle part of described baffle group, the baffle plate stack combinations that baffle group is fitting to connection mutually by several piece forms, edge column and central post all offer and presses down chute, baffle group be fastened on adjacent edge column and central post press down between chute or be fastened on adjacent central post press down between chute, the top being positioned at baffle group is provided with one end of depress lever pressing down chute, the other end of depress lever is installed with column and presses down screw and be against and be installed on pressing down on screw support in baffle group.The utility model adapts to the flood control Height Adjustment demand of making at any time because of flood situation; Can according to field ground planeness situation, by turn central post tiltedly/stull group on the regulating nut height of diagonal brace supporting seat adjust the height of adjusting base, balance central post group with this and produce stronger lever impact resistance.

Description

A kind of assembled moving flood protection wall
Technical field
The utility model relates to a kind of flood control flood control emergency set, is specifically related to a kind of assembled moving flood protection wall.
Background technology
In recent years along with the change of global climate, various natural calamity takes place frequently, bring about great losses to people's lives and properties, as typhoon, flood etc., for preventing or lowering the harm of flood damage to the mankind, various flood gate application and give birth to, so this existing gate all because of structural strength not and more loaded down with trivial details on using, and this gate is mainly used in City Building key access place; And the place such as river dyke cannot be met require that impact resistance is comparatively strong and want to adjust at any time as required the flood control requirement such as highly.
By the understanding of the technical scheme to existing flood gate, there are following 4 distinct disadvantage: one is that the overall dimensions of flashboard group and lock post group is less than normal and cannot meet the places such as river dyke and require the requirement that impact resistance is stronger; Two be lock post group upper end arrange the Fastening device that presses down be fixed, cannot according to regimen in flood season adjust flexibly flood control height; Three be lock post group side arrange side pressure Fastening device be some screws, the requirement of a large amount of flood surge on river dyke cannot be met; Four is that existing flood gate gusseted group lower support position must can be fixed by ground embedded foundation, cannot adapt to river dyke supports arrange ground out-of-flatness situation.
Utility model content
The purpose of this utility model is solve the problems of the technologies described above and provide a kind of assembled moving flood protection wall.
For achieving the above object, the utility model adopts according to following technical scheme:
A kind of assembled moving flood protection wall, comprise the baffle group for stopping flood, be arranged on the edge column of described baffle group both sides outermost end and the central post between being arranged in the middle part of described baffle group, the baffle plate stack combinations that described baffle group is fitting to connection mutually by several piece forms, described edge column and central post all offer and presses down chute, described baffle group be fastened on adjacent edge column and central post press down between chute or be fastened on adjacent central post press down between chute, the top being positioned at described baffle group is provided with one end of depress lever pressing down chute, the other end of described depress lever is installed with column and presses down screw and be against and be installed on pressing down on screw support in baffle group.
Preferred as one, described edge column offers two symmetrical mutually places and press down chute, be respectively provided with side waterproof adhesive tape, to improve the seal degree of baffle group and edge column pressing down both sides, chute place; The upper end of described edge column is also provided with edge column upper end cover plate.
Preferred as one, described central post is a hollow structure framework, it offers be arranged symmetrically with mutually press down chute everywhere, the both sides, chute place that press down of central post described in each are also respectively provided with two side waterproof adhesive tapes, to improve the seal degree of baffle group and central post; The upper end of described central post is also provided with central post upper end cover plate, and described central post upper end cover plate is provided with central post upper end suspension ring.
Preferred as one, described central post is positioned at two sides pressing down chute to pass through to wearing screw, 2 central post upper bed-plates to be embraced on central post, the below of described central post upper bed-plate is also provided with a central post lower bottom base, is also provided with central post base water-proof slab between described central post upper bed-plate and central post lower bottom base.
Preferred as one, described central post is also provided with diagonal brace and stull, described diagonal brace and stull are arranged on adjusting base away from one end of central post, and described diagonal brace adjusting base is set in and is provided with on the diagonal brace supporting seat of threaded column, and the threaded column of described diagonal brace supporting seat is provided with regulating nut.
Preferred as one, described central post is provided with two connectors, two described connectors are separately installed with connector, and two described connectors are separately installed with diagonal brace and stull.
Preferred as one, described baffle plate is provided with projection and groove, the projection of adjacent described baffle plate and fit depressions, the groove both sides of described baffle plate are provided with the adhesive tape groove for wearing adhesive tape, baffle plate adhesive tape is provided with in the adhesive tape groove of adjacent described baffle plate cooperation place, projection on the baffle plate of the described baffle group the superiors is provided with and presses down screw support, is provided with adhesive tape bottom baffle plate in the adhesive tape groove of the blind recess both sides of the described baffle group bottom.
Preferred as one, described side waterproof adhesive tape is provided with the end of matching with edge column and central post, and described end is connected with towards baffle plate waterproof side, and described waterproof side is provided with bellows segment.
Preferred as one, described side waterproof adhesive tape is provided with the end of matching with edge column and central post gluing clamp bar slot, described end is connected with towards baffle plate waterproof side, and described waterproof side is provided with multiple dentate body, and the end being positioned at described waterproof side is also provided with empennage.
Preferred as one, described depress lever be provided with press down that chute matches press down inserted sheet and lever arm, described pressing down between inserted sheet and lever arm is connected by latch, and described lever arm offers screwed hole, and the screwed hole on described lever arm is twisted and is provided with column and presses down screw.
After the utility model baffle group inserts edge column group and central post group, arrange depress lever on it can along set press down chute up and down adjustment arbitrarily press down permanent position, to adapt to the flood control Height Adjustment demand of making at any time because of flood situation; Enter baffle interior at flood during baffle group work and compress completely with the side waterproof adhesive tape that arranges on edge column and central post under the effect of flood lateral thrust and reach air-tight state, improving integral waterproofing effect; Can according to field ground planeness situation, by turn central post tiltedly/stull group on the regulating nut height of diagonal brace supporting seat adjust the height of adjusting base, balance central post group with this and produce stronger lever impact resistance.
Accompanying drawing explanation
Figure 1 shows that the schematic perspective view of the utility model embodiment;
Fig. 2 is the exploded perspective view of edge column in Fig. 1;
Fig. 3 be in Fig. 1 central post and mounted thereto oblique/exploded perspective view of stull group;
Fig. 4 be central post and upper bed-plate to install join cut open sectional schematic diagram;
Fig. 5 is the generalized section of baffle group;
Fig. 6 is the exploded perspective view of baffle group;
Schematic perspective view when Fig. 7 a is the use of the utility model embodiment;
Schematic top plan view when Fig. 7 b is the use of the utility model embodiment;
Fig. 8 a is the schematic perspective view that the utility model embodiment uses according to design height;
Fig. 8 b is the schematic front view that the utility model embodiment uses according to design height;
Fig. 9 a is that the utility model embodiment uses the schematic perspective view of height according to flood situation;
Fig. 9 b is that the utility model embodiment uses the schematic perspective view of height according to flood situation;
Figure 10 a is the operating diagram of depress lever on the utility model embodiment edge column;
Figure 10 b is the operating diagram of depress lever on the utility model embodiment central post;
Figure 11 a is the utility model embodiment flood control state partial top view;
Figure 11 b is the utility model embodiment flood control state sectional view;
Figure 12 a is the cross sectional representation of a kind of side of the utility model embodiment waterproof adhesive tape structure;
Figure 12 b is the cross sectional representation of another side waterproof adhesive tape structure of the utility model embodiment.
Detailed description of the invention
Below, in conjunction with example, substantive distinguishing features of the present utility model and advantage are further described, but the utility model is not limited to listed embodiment.
Refer to Fig. 1-12b, a kind of assembled moving flood protection wall, comprise the baffle group for stopping flood, be arranged on the edge column 1 of described baffle group both sides outermost end and the central post 2 between being arranged in the middle part of described baffle group, baffle plate 11 stack combinations that described baffle group is fitting to connection mutually by several piece forms, described edge column 1 and central post 2 all offer and presses down chute 19, described baffle group be fastened on adjacent edge column 1 and central post 2 press down between chute 19 or be fastened on adjacent central post 2 press down between chute 19, the top being positioned at described baffle group is provided with one end of depress lever 8 pressing down chute 19, the other end of described depress lever 8 is installed with column and presses down screw 9 and be against and be installed on pressing down on screw support 10 in baffle group.
Described edge column 1 offers two mutually symmetrical places and press down chute 19, be respectively provided with side waterproof adhesive tape 3, to improve the seal degree of baffle group and edge column 1 pressing down both sides, chute 19 place; The upper end of described edge column 1 is also provided with edge column upper end cover plate 4.
Described central post 2 is a hollow structure framework, it offers be arranged symmetrically with mutually press down chute 19 everywhere, the both sides, chute 19 place that press down of central post 2 described in each are also respectively provided with two side waterproof adhesive tapes 3, to improve the seal degree of baffle group and central post 2; The upper end of described central post 2 is also provided with central post upper end cover plate 5, and described central post upper end cover plate 5 is provided with central post upper end suspension ring 7.
Described central post 2 is positioned at two sides pressing down chute 19 by wearing screw by 2 central post upper bed-plates 14 armfuls on central post 2, the below of described central post upper bed-plate 14 is also provided with a central post lower bottom base 16, is also provided with central post base water-proof slab 15 between described central post upper bed-plate 14 and central post lower bottom base 16.
Described central post 2 is also provided with diagonal brace 20 and stull 21, described diagonal brace 20 and stull 21 are arranged on adjusting base 24 away from one end of central post 2, described diagonal brace adjusting base 24 is set in and is provided with on the diagonal brace supporting seat 25 of threaded column, and the threaded column of described diagonal brace supporting seat 25 is provided with regulating nut 27.
Described central post 2 is provided with two connectors 22, two described connectors 22 are separately installed with connector 23, and two described connectors 23 are separately installed with diagonal brace 20 and stull 21.
Described baffle plate 11 is provided with projection and groove, the projection of adjacent described baffle plate 11 and fit depressions, the groove both sides of described baffle plate 11 are provided with the adhesive tape groove for wearing adhesive tape, baffle plate adhesive tape 13 is provided with in the adhesive tape groove of adjacent described baffle plate 11 cooperation place, projection on the baffle plate 11 of the described baffle group the superiors is provided with and presses down screw support 10, is provided with adhesive tape 12 bottom baffle plate in the adhesive tape groove of the baffle plate 11 groove both sides of the described baffle group bottom.
Described side waterproof adhesive tape 3 is provided with the end 31 of matching with edge column 1 and central post 2, and described end 31 is connected with towards baffle plate 11 waterproof side 32, and described waterproof side 32 is provided with bellows segment 33.
Described side waterproof adhesive tape 3 is provided with the end 31 of matching with edge column 1 and central post 2 gluing clamp bar slot, described end 31 is connected with towards baffle plate 11 waterproof side 32, described waterproof side 32 is provided with multiple dentate body 34, and the end being positioned at described waterproof side 32 is also provided with empennage 35.
Described depress lever 8 be provided with press down that chute 19 matches press down inserted sheet 81 and lever arm 82, described pressing down between inserted sheet 81 and lever arm 82 is connected by latch 83, described lever arm 82 offers screwed hole, and the screwed hole on described lever arm 82 is twisted and is provided with column and presses down screw 9.
Edge column upper end cover plate 4 is connected with edge column 1 by M10 outer-hexagonal lock screw 6, central post upper bed-plate 14 is connected with central post 2 by M22 outer-hexagonal lock bolt 17, and described diagonal brace 20 is connected with adjusting base 24 by M14 outer-hexagonal lock bolt 26 with stull 21.
Fig. 7 a combines the example be installed on large tunnel hole or river dyke, and require that on installation both sides, hole or river dyke, both ends need be concrete wall (pillars), ground must be the smooth base surface of concrete, its embodiment is: be first fixed on left and right, installation position concrete wall (pillar) by edge column 1 with expansion bolt, waterproof sealing process is done with sealing structure silica gel in joint portion, then central post 2 is connected locking by the pre-buried good central post lower bottom base 16 of M24 hex socket set screws 18 and equalization, the regulating nut 27 at central post 2 rear portion (backwater to) is regulated to make diagonal brace adjusting base 24 be in correct position according to ground actual conditions, thus make tiltedly/stull group be in stretching state, sequentially inserted along edge column 1 and central post 2 opening at baffle plate 11 two ends, the groove between baffle plate 11 and convex body are closely chimeric again, thus make baffle group stacked group formula flood protection wall in aggregates.
The explanation of the utility model embodiment work the waterproof principle, first with reference to diagram 7a, shown in 3, left and right edge column group 1 and concrete wall (pillar) fix with expansion bolt and the process of structure silica gel sealing must be done in joint portion, a central post base water-proof slab 15 is joined between the pre-buried central post lower bottom base 16 of central post group 2 and ground, connect locking by M24 hex socket set screws 18 and reach sealing, to be first insert along the opening of edge column 1 and central post 2 baffle group again bottom being embedded with adhesive tape 12 bottom baffle plate, then the baffle group that bottom is embedded with baffle plate adhesive tape 13 is sequentially inserted, until setting height(from bottom), the chute 19 that presses down again in edge column 1 and central post 2 embeds column depress lever 8 respectively, press down screw 9 through the column in column depress lever 8 to prop up the column being located at baffle plate 11 two ends and press down screw support 10 and tighten, facilitated by the lever stress location of articulated type column depress lever 8 generation and press down fastening force, thus reach between baffle plate 11 and the sealing of baffle plate 11 and the indirect synapsis in ground.
Refer again to shown in diagram 11a, 11b, the lateral pressure produced when flood is attacked promotes baffle plate 11 to be forced waterproof adhesive tape 3 packing of side in the same way on itself and edge column 1 and central post 2 and reaches sealing, and the side direction fastening force produced along with the rising of flood level can be larger, and then sealing is stronger, best waterproof effect so can be reached.
Again with reference to shown in diagram 8a, 8b, 9a, 9b, can make adjustment to flood control height random according to flood situation concrete condition, namely heavy rain early warning or other relevant informations whether is issued according to national authority meteorological department, increase and decrease is made to the sheet number of baffle plate 11, and edge column 1 and central post 2 press down column depress lever 8 that chute 19 place arranges and best can press down the adjustment of packing position along with the increase and decrease of baffle plate 11 is made fast, thus allow flood control flood control operation more flexibly and convenient.
Again with reference to shown in diagram 3,4, the framework of central post 2 adopts hollow design (for bolt group provides space through framework), a central post upper bed-plate 14 is respectively established in front and rear part, framework lower end (meet water to backwater to), connecting locking through the screw on central post upper bed-plate 14 to wearing central post 2 framework Vacancy by M22 outer-hexagonal lock bolt 17, reaching the objects such as quick and intensity convenient for production is high.
In sum, unitary construction of the present utility model and performance can reach on river dyke or place's impact resistance such as large tunnel mouth higher and the requirement of flood control height can be adjusted at any time with flood situation, easy to assembly quick and be convenient to store, there is preferably ease of use.
The above is only preferred embodiment of the present utility model; it should be pointed out that for those skilled in the art, under the prerequisite not departing from the utility model principle; can also make some improvements and modifications, these improvements and modifications also should be considered as protection domain of the present utility model.

Claims (10)

1. an assembled moving flood protection wall, it is characterized in that, comprise the baffle group for stopping flood, be arranged on the edge column (1) of described baffle group both sides outermost end and the central post (2) between being arranged in the middle part of described baffle group, baffle plate (11) stack combinations that described baffle group is fitting to connection mutually by several piece forms, described edge column (1) and central post (2) all offer and presses down chute (19), described baffle group be fastened on adjacent edge column (1) and central post (2) press down between chute (19) or be fastened on adjacent central post (2) press down between chute (19), the top being positioned at described baffle group is provided with one end of depress lever (8) pressing down chute (19), the other end of described depress lever (8) is installed with column and presses down screw (9) and be against and be installed on pressing down on screw support (10) in baffle group.
2. a kind of assembled moving flood protection wall according to claim 1, it is characterized in that, described edge column (1) offers two symmetrical mutually places and press down chute (19), respectively be provided with side waterproof adhesive tape (3), to improve the seal degree of baffle group and edge column (1) pressing down chute (19) both sides, place; The upper end of described edge column (1) is also provided with edge column upper end cover plate (4).
3. a kind of assembled moving flood protection wall according to claim 1, it is characterized in that, described central post (2) is a hollow structure framework, it offers be arranged symmetrically with mutually press down chute (19) everywhere, chute (19) both sides, place that press down of central post described in each (2) are also respectively provided with two side waterproof adhesive tapes (3), to improve the seal degree of baffle group and central post (2); The upper end of described central post (2) is also provided with central post upper end cover plate (5), and described central post upper end cover plate (5) is provided with central post upper end suspension ring (7).
4. a kind of assembled moving flood protection wall according to claim 1, it is characterized in that, described central post (2) is positioned at two sides pressing down chute (19) to pass through to wearing screw, 2 central post upper bed-plates (14) to be embraced on central post (2), the below of described central post upper bed-plate (14) is also provided with a central post lower bottom base (16), is also provided with central post base water-proof slab (15) between described central post upper bed-plate (14) and central post lower bottom base (16).
5. a kind of assembled moving flood protection wall according to claim 1, it is characterized in that, described central post (2) is also provided with diagonal brace (20) and stull (21), described diagonal brace (20) and stull (21) are arranged on adjusting base (24) away from one end of central post (2), described diagonal brace adjusting base (24) is set in and is provided with on the diagonal brace supporting seat (25) of threaded column, and the threaded column of described diagonal brace supporting seat (25) is provided with regulating nut (27).
6. a kind of assembled moving flood protection wall according to claim 5, it is characterized in that, described central post (2) is provided with two connectors (22), two described connectors (22) are separately installed with connector (23), two described connectors (23) are separately installed with diagonal brace (20) and stull (21).
7. a kind of assembled moving flood protection wall according to claim 1, it is characterized in that, described baffle plate (11) is provided with projection and groove, the projection of adjacent described baffle plate (11) and fit depressions, the groove both sides of described baffle plate (11) are provided with the adhesive tape groove for wearing adhesive tape, baffle plate adhesive tape (13) is provided with in the adhesive tape groove of adjacent described baffle plate (11) cooperation place, projection on the baffle plate (11) of the described baffle group the superiors is provided with and presses down screw support (10), adhesive tape bottom baffle plate (12) is provided with in the adhesive tape groove of baffle plate (11) the groove both sides of the described baffle group bottom.
8. a kind of assembled moving flood protection wall according to Claims 2 or 3, it is characterized in that, described side waterproof adhesive tape (3) is provided with the end (31) of matching with edge column (1) and central post (2), described end (31) is connected with towards baffle plate (11) waterproof side (32), and described waterproof side (32) is provided with bellows segment (33).
9. a kind of assembled moving flood protection wall according to Claims 2 or 3, it is characterized in that, described side waterproof adhesive tape (3) is provided with the end (31) of matching with edge column (1) and central post (2) gluing clamp bar slot, described end (31) is connected with towards baffle plate (11) waterproof side (32), described waterproof side (32) is provided with multiple dentate body (34), and the end being positioned at described waterproof side (32) is also provided with empennage (35).
10. a kind of assembled moving flood protection wall according to claim 1, it is characterized in that, described depress lever (8) be provided with press down that chute (19) matches press down inserted sheet (81) and lever arm (82), described pressing down between inserted sheet (81) and lever arm (82) is connected by latch (83), (82) offer screwed hole to described lever arm, and the screwed hole on described lever arm (82) is twisted and is provided with column and presses down screw (9).
CN201520054921.6U 2015-01-27 2015-01-27 A kind of assembled moving flood protection wall Expired - Fee Related CN204418107U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520054921.6U CN204418107U (en) 2015-01-27 2015-01-27 A kind of assembled moving flood protection wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520054921.6U CN204418107U (en) 2015-01-27 2015-01-27 A kind of assembled moving flood protection wall

Publications (1)

Publication Number Publication Date
CN204418107U true CN204418107U (en) 2015-06-24

Family

ID=53468491

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520054921.6U Expired - Fee Related CN204418107U (en) 2015-01-27 2015-01-27 A kind of assembled moving flood protection wall

Country Status (1)

Country Link
CN (1) CN204418107U (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049355A (en) * 2016-08-08 2016-10-26 贺立军 Hard foundation retention wall structure and construction method thereof
CN106049356A (en) * 2016-08-10 2016-10-26 南京工业大学 Flood-damage-prevention retaining wall construction system
CN106088145A (en) * 2016-08-08 2016-11-09 贺立军 Soft foundation waterwall structure and construction method
CN106150316A (en) * 2016-08-13 2016-11-23 广州金霸建材股份有限公司 Prevent flooding gate panel system
CN106368167A (en) * 2016-09-22 2017-02-01 杭州中车车辆有限公司 Anti-flood combined type baffle mechanism
CN107604876A (en) * 2017-09-12 2018-01-19 中铝南铝(福建)铝结构技术开发有限公司 A kind of flood control structure
CN107700936A (en) * 2017-11-16 2018-02-16 东莞市庆臻钢结构工程有限公司 A kind of hoarding and waterstop
CN108316238A (en) * 2018-03-14 2018-07-24 辽宁忠旺铝合金精深加工有限公司 A kind of flapper and its dam protecting equipment
CN109083094A (en) * 2018-08-17 2018-12-25 合肥五凡建筑工程有限公司 A kind of flood control water fender of excellent shock resistance
CN109667240A (en) * 2017-10-17 2019-04-23 约尔格-米夏埃尔·施泰因哈特 For in the device for blocking wall elements used in the device of water and for blocking water
CN110029625A (en) * 2019-05-23 2019-07-19 中建科技(福州)有限公司 Detachable easily memory-type flood protection device
CN111335255A (en) * 2020-03-17 2020-06-26 德尼尔科环境技术(苏州)有限公司 Flood control plate sealing strip
CN112813990A (en) * 2021-01-05 2021-05-18 深圳市天翊建设有限公司 Foundation pit structure and construction process
CN113356135A (en) * 2021-05-21 2021-09-07 华北水利水电大学 Slide clamping groove type flood control wall
CN113389429A (en) * 2021-05-12 2021-09-14 广船国际有限公司 Interim protector and interim rail guard, interim flood prevention device
CN107700936B (en) * 2017-11-16 2024-04-30 东莞市庆臻钢结构工程有限公司 Temporary enclosing wall and water stop

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049355B (en) * 2016-08-08 2018-08-07 贺立军 Hard ground water blocking wall construction and construction method
CN106088145A (en) * 2016-08-08 2016-11-09 贺立军 Soft foundation waterwall structure and construction method
CN106049355A (en) * 2016-08-08 2016-10-26 贺立军 Hard foundation retention wall structure and construction method thereof
CN106088145B (en) * 2016-08-08 2018-08-07 贺立军 Soft foundation water blocking wall construction and construction method
CN106049356A (en) * 2016-08-10 2016-10-26 南京工业大学 Flood-damage-prevention retaining wall construction system
CN106049356B (en) * 2016-08-10 2018-07-06 南京工业大学 A kind of flood control water disaster retaining wall building system
CN106150316A (en) * 2016-08-13 2016-11-23 广州金霸建材股份有限公司 Prevent flooding gate panel system
CN106368167A (en) * 2016-09-22 2017-02-01 杭州中车车辆有限公司 Anti-flood combined type baffle mechanism
CN106368167B (en) * 2016-09-22 2018-06-15 杭州中车车辆有限公司 A kind of flood control combined baffle mechanism
CN107604876A (en) * 2017-09-12 2018-01-19 中铝南铝(福建)铝结构技术开发有限公司 A kind of flood control structure
CN109667240A (en) * 2017-10-17 2019-04-23 约尔格-米夏埃尔·施泰因哈特 For in the device for blocking wall elements used in the device of water and for blocking water
CN107700936A (en) * 2017-11-16 2018-02-16 东莞市庆臻钢结构工程有限公司 A kind of hoarding and waterstop
CN107700936B (en) * 2017-11-16 2024-04-30 东莞市庆臻钢结构工程有限公司 Temporary enclosing wall and water stop
CN108316238A (en) * 2018-03-14 2018-07-24 辽宁忠旺铝合金精深加工有限公司 A kind of flapper and its dam protecting equipment
CN109083094A (en) * 2018-08-17 2018-12-25 合肥五凡建筑工程有限公司 A kind of flood control water fender of excellent shock resistance
CN110029625A (en) * 2019-05-23 2019-07-19 中建科技(福州)有限公司 Detachable easily memory-type flood protection device
CN111335255A (en) * 2020-03-17 2020-06-26 德尼尔科环境技术(苏州)有限公司 Flood control plate sealing strip
CN112813990A (en) * 2021-01-05 2021-05-18 深圳市天翊建设有限公司 Foundation pit structure and construction process
CN113389429A (en) * 2021-05-12 2021-09-14 广船国际有限公司 Interim protector and interim rail guard, interim flood prevention device
CN113356135A (en) * 2021-05-21 2021-09-07 华北水利水电大学 Slide clamping groove type flood control wall

Similar Documents

Publication Publication Date Title
CN204418107U (en) A kind of assembled moving flood protection wall
CN108547413A (en) A kind of structure of roof integral photovoltaic plate
CN109184759B (en) Mine tunnel supporting device
TWM576650U (en) Rainproof structure for solar energy canopy frame
CN212670614U (en) Waterproof open caisson segment unit and open caisson structure thereof
CN216689826U (en) Deformation joint structure for house building
CN217811976U (en) Photovoltaic engineering roof waterproof construction
CN211499679U (en) Scaffold for reservoir construction
TWM535904U (en) Improved structure of water-guide supporting rack for solar panel
CN211523688U (en) Adjustable connector for angle of transverse keel and vertical keel of curtain wall
CN104074288A (en) Curtain wall multi-degree-of-freedom support system
CN204715592U (en) Abnormity Curtainwall connector
CN112252656A (en) Lock catch plastic floor
CN207176622U (en) Portable anti-flood wall and its column agency
CN209194933U (en) A kind of glass wing mounting structure of adjustable angle
CN208563945U (en) Outer protective frame sets up tooling and outer protective frame system
CN202299031U (en) Cellular board curtain wall
CN105464263A (en) Curtain wall large decorative strip connection structure
CN202265762U (en) Connective component for blanket plate and support beam
CN207069970U (en) A kind of mounting structure for solar energy battery curtain wall
CN107313512B (en) Original bamboo joint point based on original bamboo built-in embedded part
CN111945763A (en) Waterproof open caisson segment unit and open caisson structure thereof
CN111395555A (en) Outer wall deformation joint structure and mounting method
CN206313708U (en) New type solar energy support and ground foundation attachment means
CN220301928U (en) Assembled enclosure structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150624