CN204386602U - Pressure regulating well pit shaft cavity collapse backfill auxiliary structure - Google Patents

Pressure regulating well pit shaft cavity collapse backfill auxiliary structure Download PDF

Info

Publication number
CN204386602U
CN204386602U CN201420800622.8U CN201420800622U CN204386602U CN 204386602 U CN204386602 U CN 204386602U CN 201420800622 U CN201420800622 U CN 201420800622U CN 204386602 U CN204386602 U CN 204386602U
Authority
CN
China
Prior art keywords
backfill
cavity
collapse
chamber
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420800622.8U
Other languages
Chinese (zh)
Inventor
李波
贺双喜
赵继勇
雷有栋
韩纯杰
向贤镜
祁伟强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201420800622.8U priority Critical patent/CN204386602U/en
Application granted granted Critical
Publication of CN204386602U publication Critical patent/CN204386602U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a collapse cavity backfill auxiliary structure of a pressure regulating well shaft, which is arranged in the pressure regulating well shaft with a collapse cavity; the construction method comprises backfill aggregate, a reinforcing mesh, a pipe shed, a full-space scaffold and backfill concrete, wherein the backfill aggregate is laid at the bottom of a shaft of the surge shaft, the reinforcing mesh is laid in a projection area of a collapsed cavity on the backfill aggregate, the pipe shed is buried on the reinforcing mesh and is deep into the wall of the collapsed cavity, the backfill concrete is buried on the pipe shed, the full-space scaffold is wrapped inside the backfill concrete, and the top of the collapsed cavity is tightly attached to the full-space scaffold. By adopting the technical scheme, the collapse cavity of the shaft can be safely and quickly treated, the risk of collapse treatment is greatly reduced, and the collapse treatment method can be popularized and applied to collapse treatment of the surge shaft or other vertical caverns in hydropower engineering.

Description

一种调压井井筒塌腔回填辅助结构An auxiliary structure for backfilling the collapsed cavity of a pressure regulating well

技术领域technical field

本实用新型属于水利工程施工技术领域,尤其涉及一种调压井井筒塌腔回填辅助结构。The utility model belongs to the technical field of water conservancy engineering construction, in particular to an auxiliary structure for backfilling the collapsed cavity of a surge well shaft.

背景技术Background technique

在调压井井筒开挖过程中,受到岩石破碎、裂隙发育、丰富地下水、爆破扰动等不利因素影响时,容易发生井筒内壁塌方。尤其是内径较大、深度较深的调压井,塌方后形成的空腔处理难度大,耗费时间更长。现有技术中,塌方空腔处理的方法通常为在空腔内回填混凝土等,但由于塌腔底部通常为倾向于井筒中心的斜面,若直接进行回填,则回填混凝土难以自稳,无法对塌腔顶部岩体起到支撑作用。在向下处理井筒内渣体时,塌方空腔回填混凝土存在二次塌方的可能性,从而威胁到整个井筒的稳定,给施工安全、工期进度带来了较大的隐患。因此,如何安全、快速的对塌腔进行处理,且保证塌腔回填混凝土的稳定,成为施工中亟待解决的问题,并决定调压井井筒塌方处修复的质量及工程施工期安全。During the excavation of the wellbore of the surge well, the inner wall of the wellbore will easily collapse when affected by unfavorable factors such as rock fragmentation, fracture development, abundant groundwater, and blasting disturbance. Especially for surge wells with larger inner diameters and deeper depths, it is difficult and time-consuming to treat the cavities formed after landslides. In the prior art, the method for dealing with the landslide cavity is usually to backfill the cavity with concrete, etc., but since the bottom of the collapse cavity is usually an inclined plane inclined to the center of the wellbore, if the backfilling is carried out directly, the backfilled concrete will be difficult to stabilize itself and cannot correct the collapse. The rock mass at the top of the cavity plays a supporting role. When the slag in the wellbore is processed downward, there is a possibility of secondary landslide in the backfill concrete of the collapsed cavity, which threatens the stability of the entire wellbore and brings great hidden dangers to construction safety and construction schedule. Therefore, how to safely and quickly deal with the collapsed cavity and ensure the stability of the backfilled concrete in the collapsed cavity has become an urgent problem to be solved in construction, and determines the quality of the repair of the surge shaft collapse and the safety of the project during the construction period.

实用新型内容Utility model content

为解决上述技术问题,本实用新型提供了一种调压井井筒塌腔回填辅助结构,达到了安全、快捷处理井筒塌腔并保证井筒稳定的效果。In order to solve the above-mentioned technical problems, the utility model provides an auxiliary structure for backfilling the collapsed cavity of a surge well, which can safely and quickly deal with the collapsed cavity of the wellbore and ensure the stability of the wellbore.

本实用新型通过以下技术方案得以实现。The utility model is realized through the following technical solutions.

本实用新型提供的一种调压井井筒塌腔回填辅助结构,该结构设置在塌腔的调压井井筒中;包括回填骨料、钢筋网、管棚、满堂脚手架和回填混凝土,其中回填骨料铺设在调压井井筒的底部,在回填骨料上塌腔的投影区域铺设钢筋网,钢筋网上埋设管棚,且管棚深入塌腔的壁中,管棚上填埋有回填混凝土,回填混凝土的内部包裹有满堂脚手架,满堂脚手架紧贴塌腔的顶部。The utility model provides an auxiliary structure for backfilling the collapsed cavity of a surge well shaft. The structure is arranged in the cavity of the surge well shaft; The material is laid at the bottom of the surge well shaft, and the reinforced mesh is laid on the projection area of the collapsed cavity on the backfilled aggregate. The pipe shed is buried on the reinforced mesh, and the pipe shed is deep into the wall of the collapsed cavity. The concrete interior is wrapped with a full-scale scaffolding that clings to the top of the collapse cavity.

所述的管棚至少深入塌腔的壁中5m。The pipe shed is at least 5m deep into the wall of the collapse cavity.

还包括锚索,所述的有多根,锚索的一端填埋在回填混凝土中,另一端深入塌腔壁中。It also includes anchor cables, which have multiple anchor cables, one end of the anchor cables is buried in the backfill concrete, and the other end goes deep into the wall of the collapsed cavity.

所述的锚索至少深入塌腔的壁中8mThe anchor cable is at least 8m deep into the wall of the collapsed cavity

本实用新型的有益效果在于:The beneficial effects of the utility model are:

1、通过在调压井井筒内回填骨料到某一高程,可快速找平塌腔底部;1. By backfilling the aggregate in the wellbore of the surge well to a certain elevation, the bottom of the collapsed cavity can be quickly leveled;

2、通过在找平层铺设钢筋网,可使回填混凝土均匀作用于找平层的回填骨料上;2. By laying steel mesh on the leveling layer, the backfill concrete can be evenly acted on the backfill aggregate of the leveling layer;

3、通过在钢筋网上埋设管棚,且管棚另一端深入塌腔内壁岩体内,不仅可使灌浆充填空隙、胶结塌腔底部回填骨料,且在管棚内植入钢筋和回填混凝土可提高管棚刚度,对上部回填物起到一定的支撑作用;3. By burying the pipe shed on the steel mesh, and the other end of the pipe shed goes deep into the rock body of the inner wall of the collapse cavity, not only can grouting fill the gap, cement the bottom of the collapse cavity and backfill the aggregate, but also implant steel bars and backfill concrete in the pipe shed. Improve the rigidity of the pipe shed and play a certain role in supporting the upper backfill;

4、在塌腔底部钢筋网上架设脚手架,或者其他钢材支撑物,之后填满混凝土,对塌腔顶部岩体支撑作用更加有效;4. Set up scaffolding or other steel supports on the steel mesh at the bottom of the collapse cavity, and then fill it with concrete, which will be more effective in supporting the rock mass at the top of the collapse cavity;

5、通过提前引出的锚索预留孔,可方便布置锚索,对塌腔回填混凝土起到加固作用。5. Through the reserved holes for the anchor cables led out in advance, the anchor cables can be conveniently arranged to reinforce the backfill concrete in the collapsed cavity.

采用本技术方案能安全、快捷的处理井筒塌腔,极大的降低了塌方处理的风险,可在水电工程调压井或其他竖向洞室塌方处理中推广应用。Adopting the technical scheme can safely and quickly deal with the wellbore collapse cavity, greatly reducing the risk of landslide treatment, and can be popularized and applied in the treatment of hydropower engineering surge shafts or other vertical caverns.

附图说明Description of drawings

图1是本实用新型的结构示意图。Fig. 1 is the structural representation of the utility model.

图中:1-调压井井筒,2-塌腔,3-塌方渣体,4-回填骨料,5-钢筋网,6-管棚,7-满堂脚手架,8-回填混凝土,9-锚索,10-模板。In the figure: 1-Surge well shaft, 2-Collapse cavity, 3-Collapse slag, 4-Backfill aggregate, 5-Reinforcing mesh, 6-Pipe shed, 7-Mantang scaffolding, 8-Backfill concrete, 9-Anchor cable, 10-template.

具体实施方式Detailed ways

下面进一步描述本实用新型的技术方案,但要求保护的范围并不局限于所述。The technical solution of the utility model is further described below, but the scope of protection is not limited to the description.

如图1所示的一种调压井井筒塌腔回填辅助结构,该结构设置在塌腔2的调压井井筒1中;包括回填骨料4、钢筋网5、管棚6、满堂脚手架7和回填混凝土8,其中回填骨料4铺设在调压井井筒1的底部,在回填骨料4上塌腔2的投影区域铺设钢筋网5,钢筋网5上埋设管棚6,且管棚6深入塌腔2的壁中,管棚6上填埋有回填混凝土8,回填混凝土8的内部包裹有满堂脚手架7,满堂脚手架7紧贴塌腔2的顶部;还包括锚索9,所述的有多根,锚索9的一端填埋在回填混凝土8中,另一端深入塌腔2壁中。As shown in Figure 1, an auxiliary structure for backfilling the cavity of a surge well shaft is set in the well shaft 1 of the surge well shaft of the collapse cavity 2; it includes backfilling aggregate 4, steel mesh 5, pipe shed 6, and scaffolding 7 And backfill concrete 8, wherein the backfill aggregate 4 is laid on the bottom of the surge well shaft 1, and the steel mesh 5 is laid on the projection area of the collapse cavity 2 on the backfill aggregate 4, and the pipe shed 6 is buried on the steel mesh 5, and the pipe shed 6 Going deep into the wall of the collapse cavity 2, the pipe shed 6 is filled with backfill concrete 8, and the inside of the backfill concrete 8 is wrapped with a full-scale scaffolding 7, which is close to the top of the collapse cavity 2; it also includes anchor cables 9, the There are many, and one end of the anchor cable 9 is buried in the backfill concrete 8, and the other end goes deep into the wall of the collapsed cavity 2.

调压井井筒1在开挖过程中井筒内发生塌方,形成塌腔2,塌方渣体3堆积于已经开挖的井筒内,形成倾斜面;通过井筒内回填骨料4,回填高程位于塌腔2中下部,可快速找平塌腔2底部,又不至于回填料太多,增加后期开挖量;喷混凝土封闭塌腔2,在塌腔2底部回填骨料4上铺设钢筋网5,在钢筋网5上埋设管棚6,所述的管棚6至少深入塌腔2的壁中5m,优选为5~10m;在钢筋网5上立设满堂脚手架7,脚手架7紧贴塌腔2顶部;在塌腔2的壁上有多跟深入的锚索9,锚索9深入塌腔2的壁的深度至少为8m,优选8~15m;在塌腔2外侧架设模板10,回填混凝土8充满整个塌腔;在管棚6内灌浆,可使回填骨料胶结成整体,灌浆完毕在管棚6内植入2根钢筋,并用浆液充满;回填混凝土8达到一定龄期,在提前引出的锚索孔位布设锚索9。管棚直径可选108mm,管棚内钢筋直径可选32mm。塌腔2处理完之后,可正向用履带吊或者导井竖向清除回填骨料4,进行下一步施工,如此可有效、快捷保障塌腔处理完成。During the excavation of the wellbore 1 of the surge well, a landslide occurs in the wellbore, forming a collapse cavity 2, and the collapsed slag body 3 accumulates in the excavated wellbore, forming an inclined surface; through backfilling the aggregate 4 in the wellbore, the backfill elevation is located in the collapse cavity The middle and lower part of 2 can quickly level the bottom of the collapsed cavity 2 without too much backfill, which increases the amount of later excavation; the shotcrete closes the collapsed cavity 2, and lays reinforcement mesh 5 on the backfill aggregate 4 at the bottom of the collapsed cavity 2. A pipe shed 6 is buried on the net 5, and the pipe shed 6 is at least 5m deep into the wall of the collapse cavity 2, preferably 5-10m; a full house scaffold 7 is erected on the steel mesh 5, and the scaffold 7 is close to the top of the collapse cavity 2; There are many deep anchor cables 9 on the wall of the collapse cavity 2, and the depth of the anchor cables 9 deep into the wall of the collapse cavity 2 is at least 8m, preferably 8-15m; a formwork 10 is erected outside the collapse cavity 2, and the backfill concrete 8 fills the entire cavity. Collapse cavity; grouting in the pipe shed 6 can cement the backfill aggregate into a whole. After grouting, implant 2 steel bars in the pipe shed 6 and fill it with grout; Anchor cable 9 is laid in cable hole position. The diameter of the pipe shed can be 108mm, and the diameter of the steel bar in the pipe shed can be 32mm. After the collapse cavity 2 is processed, the backfill aggregate 4 can be removed vertically with a crawler crane or a guide shaft, and the next step of construction can be carried out, which can effectively and quickly ensure the completion of the collapse cavity treatment.

Claims (4)

1. a surge shaft pit shaft collapses chamber backfill supplementary structure, this vibrational power flow is in the surge shaft pit shaft (1) of chamber of collapsing (2), it is characterized in that: comprise backfill aggregate (4), steel mesh reinforcement (5), pipe canopy (6), full hall scaffold (7) and fill concrete (8), wherein backfill the bottom that aggregate (4) is laid on surge shaft pit shaft (1), steel mesh reinforcement (5) is laid by backfill aggregate (4) the is collapsed view field in chamber (2), steel mesh reinforcement (5) is buried pipe canopy (6) underground, and pipe canopy (6) deeply collapses in the wall of chamber (2), the upper landfill of pipe canopy (6) has fill concrete (8), the internal package of fill concrete (8) has full hall scaffold (7), full hall scaffold (7) is close to the top of chamber of collapsing (2).
2. surge shaft pit shaft as claimed in claim 1 collapses chamber backfill supplementary structure, it is characterized in that: described pipe canopy (6) at least deeply collapse chamber (2) wall in 5m.
3. surge shaft pit shaft as claimed in claim 1 collapses chamber backfill supplementary structure, it is characterized in that: also comprise anchor cable (9), one end landfill of anchor cable (9) is in fill concrete (8), and the other end deeply collapses in chamber (2) wall.
4. surge shaft pit shaft as claimed in claim 3 collapses chamber backfill supplementary structure, it is characterized in that: described anchor cable (9) at least deeply collapse chamber (2) wall in 8m.
CN201420800622.8U 2014-12-16 2014-12-16 Pressure regulating well pit shaft cavity collapse backfill auxiliary structure Expired - Lifetime CN204386602U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420800622.8U CN204386602U (en) 2014-12-16 2014-12-16 Pressure regulating well pit shaft cavity collapse backfill auxiliary structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420800622.8U CN204386602U (en) 2014-12-16 2014-12-16 Pressure regulating well pit shaft cavity collapse backfill auxiliary structure

Publications (1)

Publication Number Publication Date
CN204386602U true CN204386602U (en) 2015-06-10

Family

ID=53359333

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420800622.8U Expired - Lifetime CN204386602U (en) 2014-12-16 2014-12-16 Pressure regulating well pit shaft cavity collapse backfill auxiliary structure

Country Status (1)

Country Link
CN (1) CN204386602U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104975861A (en) * 2015-07-21 2015-10-14 招商局重庆交通科研设计院有限公司 Non-disturbance type supporting structure used for tunnel vault collapsed cavity processing
CN105821818A (en) * 2016-03-24 2016-08-03 中水北方勘测设计研究有限责任公司 Soft rock area surge chamber intersecting tunnel section collapse rapid treatment method
CN106368709A (en) * 2016-09-30 2017-02-01 首钢总公司 Construction method of vertical shaft

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104975861A (en) * 2015-07-21 2015-10-14 招商局重庆交通科研设计院有限公司 Non-disturbance type supporting structure used for tunnel vault collapsed cavity processing
CN105821818A (en) * 2016-03-24 2016-08-03 中水北方勘测设计研究有限责任公司 Soft rock area surge chamber intersecting tunnel section collapse rapid treatment method
CN105821818B (en) * 2016-03-24 2017-11-17 中水北方勘测设计研究有限责任公司 A kind of Soft Rock Area surge-chamber intersects hole section landslide immediate processing method
CN106368709A (en) * 2016-09-30 2017-02-01 首钢总公司 Construction method of vertical shaft

Similar Documents

Publication Publication Date Title
CN102678134B (en) Collapse and sink intrusion limit construction method for treating wind accumulated sand loess tunnel through stride shed pipe
CN103898916B (en) Mini stake Composite Braced Retaining Structure and construction method
CN103758134A (en) Combined double-row pile supporting system and construction method thereof
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN104196014A (en) Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof
CN105297757A (en) Construction method for quicksand layer pile foundation
CN110284885A (en) Shield inspection-pit construction method
CN106894420B (en) Basement construction method for supporting
CN102704480A (en) Construction method of front-end vibrating steel casing for super-thick quicksand layer of pile foundation
CN106592605A (en) Construction method of foundation pit bracing with tri-axial stirring piles overlapped with reinforced concrete cast-in-place piles to be driven
CN204386602U (en) Pressure regulating well pit shaft cavity collapse backfill auxiliary structure
CN108386198A (en) A kind of novel tunnel inverted arch basement weak country rock processing method
CN206204972U (en) A kind of prefabricated tubular pile as well-points dewatering
CN107313437A (en) The shut-in well construction method of foundation ditch pressure-bearing dewatering well
CN102888847A (en) Construction method free from lowering water level for local deep foundation pit of elevator shaft
CN101793027A (en) Core-grouted static pressure anchor rod pile
CN115595979A (en) Construction method for treating karst cave by bridge pile foundation under geological condition of strong development of karst
CN110777775A (en) Foundation pit structure and construction method thereof
CN205712144U (en) A kind of karst talus anchor pole reinforcement retaining structure
CN108316288A (en) Half casing guncreting pile construction equipment and construction method
CN203755332U (en) Device for treating collapsible loess with lime-soil compaction piles and CFG rigid piles combined
CN106968252A (en) Pile pulling recharge method and pile pulling recharge system
CN206368375U (en) A kind of electric power pylon basis
CN104963332A (en) Construction method for pipe-following drilling micro pile of slewing drilling machine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20150610