CN204386152U - The sliding formwork system of large-diameter cylinder body structure - Google Patents
The sliding formwork system of large-diameter cylinder body structure Download PDFInfo
- Publication number
- CN204386152U CN204386152U CN201420807872.4U CN201420807872U CN204386152U CN 204386152 U CN204386152 U CN 204386152U CN 201420807872 U CN201420807872 U CN 201420807872U CN 204386152 U CN204386152 U CN 204386152U
- Authority
- CN
- China
- Prior art keywords
- sliding formwork
- sliding
- formwork
- sliding form
- ring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000009415 formwork Methods 0.000 title claims abstract description 55
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 48
- 239000010959 steel Substances 0.000 claims abstract description 48
- 238000000465 moulding Methods 0.000 claims 3
- 239000000725 suspension Substances 0.000 claims 2
- 238000010276 construction Methods 0.000 abstract description 18
- 238000005516 engineering process Methods 0.000 abstract description 2
- 230000005855 radiation Effects 0.000 abstract 1
- 239000004567 concrete Substances 0.000 description 9
- 238000003466 welding Methods 0.000 description 5
- 239000011150 reinforced concrete Substances 0.000 description 4
- 239000003921 oil Substances 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000010720 hydraulic oil Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本实用新型公开了一种大直径筒体构筑物的滑模体系,解决了现有施工技术中的筒壁滑模体系和顶盖模板支撑体系存在施工设施不衔接的问题。包括在已浇筑的筒壁(1)中预埋有支撑杆(2)和门型提升架(7),在已浇筑的筒壁的内、外侧面上设置有滑模内、外模模板,滑模内模围圈(6)、滑模外模围圈(5)分别与门型提升架的下端固定连接在一起,在结构中心筒(11)的外圆周上等间隔弧度地设置有辐射状轻型钢桁架(12),辐射状轻型钢桁架(12)的外端与环形钢梁(10)通过螺栓固定连接,环形钢梁(10)固定焊接在滑模内模围圈(6)上,在相邻的两榀辐射状轻型钢桁架(12)之间设置有支撑架(13)。本实用新型结构简单,人工和工具投入少。
The utility model discloses a sliding form system of a large-diameter cylinder structure, which solves the problem that construction facilities are not connected in the cylinder wall sliding form system and the roof formwork support system in the prior construction technology. Including pre-embedded support rods (2) and door-shaped lifting frames (7) in the poured cylinder wall (1), setting sliding formwork inner and outer formwork on the inner and outer surfaces of the poured cylinder wall, The inner ring (6) of the sliding form and the outer ring (5) of the sliding form are fixedly connected with the lower end of the door-shaped lifting frame respectively, and radiation holes are arranged at equal intervals on the outer circumference of the structural central cylinder (11). Shaped light steel truss (12), the outer end of the radial light steel truss (12) is fixedly connected with the ring steel beam (10) by bolts, and the ring steel beam (10) is fixedly welded on the sliding form inner mold enclosure (6) , a supporting frame (13) is arranged between two adjacent radial steel trusses (12). The utility model is simple in structure, and labor and tool input are few.
Description
技术领域 technical field
本发明涉及一种筒体构筑物的滑动模板施工体系,特别涉及一种大直径筒体构筑物的滑模施工体系。 The invention relates to a sliding formwork construction system for cylindrical structures, in particular to a sliding formwork construction system for large-diameter cylindrical structures.
背景技术 Background technique
在工业建筑中,经常要进行大直径筒体构筑物的施工,例如:钢筋混凝土筒仓、水塔等。钢筋混凝土筒体结构具有直径大,筒体高和施工难度大的特点。构筑钢筋混凝土筒体时,是先施工筒体基础,在筒体基础上再安装滑模体系,分阶段进行筒体模板的搭设和浇注的。现有的滑模体系是在浇筑的筒壁中预埋支撑杆,在支撑杆上安装提升架,提升架上分别设置有滑模内模板和滑模外模板,筒体中央设置有一个中心盘,在中心盘与内模板之间搭设辐射状拉杆形成对内模板的环状支撑,辐射状拉杆的外端穿过提升架内侧设置的螺栓孔通过螺栓连接在一起,当筒体上的各提升架顶升不同步时,通过放松螺栓调节拉杆的径向长度来实现纠偏。由于在中心盘与内模板之间搭设辐射状拉杆强度有限,不能兼做内操作平台,因此,需要在提升架内侧另设置悬挑的环形内操作平台,环形内操作平台一般存在作业面狭小,操作不便和安全隐患多的问题。在筒壁施工中,当现阶段筒体浇筑完成后,将提升架沿预埋支撑杆向上移动,构筑下一段筒壁的模板体系,然后进行下一段筒体混凝土浇筑,直至完成整个筒体的构筑工作。 In industrial buildings, it is often necessary to construct large-diameter cylindrical structures, such as reinforced concrete silos, water towers, etc. The reinforced concrete cylinder structure has the characteristics of large diameter, high cylinder and difficult construction. When constructing a reinforced concrete cylinder, the foundation of the cylinder is constructed first, then the sliding form system is installed on the foundation of the cylinder, and the formwork of the cylinder is erected and poured in stages. In the existing sliding form system, support rods are pre-embedded in the poured cylinder wall, and a lifting frame is installed on the supporting rods. The sliding formwork inner formwork and the sliding formwork outer formwork are respectively arranged on the lifting frame, and a center plate is arranged in the center of the cylinder body. , set up radial tie rods between the center plate and the inner formwork to form a ring-shaped support for the inner formwork, and the outer ends of the radial tie rods pass through the bolt holes set on the inner side of the lifting frame and are connected together by bolts. When the lifting of the frame is not synchronized, the radial length of the pull rod can be adjusted by loosening the bolt to achieve deviation correction. Due to the limited strength of the radial tie rods set up between the center plate and the inner formwork, they cannot also be used as the inner operating platform. Therefore, it is necessary to set up a cantilevered ring-shaped inner operating platform inside the lifting frame. The ring-shaped inner operating platform generally has a narrow working surface. Inconvenient operation and many potential safety hazards. In the construction of the cylinder wall, after the pouring of the cylinder is completed at this stage, the lifting frame is moved upward along the embedded support rod to construct the formwork system of the next section of the cylinder wall, and then the concrete pouring of the next section of the cylinder is carried out until the completion of the entire cylinder Build work.
由于一般筒体构筑物均设置有钢筋混凝土顶盖,按常规方法施工完筒壁后,需要拆除原滑模体系,另行搭设满堂脚手架,作为顶盖施工的支撑体系。但满堂脚手架支撑体系搭设高度太高,对地基承载力要求也大,脚手架的搭拆需投入大量的人力和三钢工具,且搭设周期较长。 Since the general cylinder structure is equipped with a reinforced concrete roof, after the cylinder wall is constructed according to the conventional method, the original sliding form system needs to be dismantled, and a full hall scaffolding is erected separately as a support system for the roof construction. However, the erection height of the Mantang scaffolding support system is too high, and the requirements for the bearing capacity of the foundation are also large. The erection and disassembly of the scaffold requires a lot of manpower and three-steel tools, and the erection period is long.
发明内容 Contents of the invention
本发明提供了一种大直径筒体构筑物的滑模体系,解决了现有施工技术中的筒壁滑模体系和顶盖模板支撑体系各自独立,存在施工设施不衔接,投入人力和设备成本高和施工周期长的技术问题。 The invention provides a sliding form system for a large-diameter cylinder structure, which solves the problem that the cylinder wall sliding form system and the roof formwork support system in the existing construction technology are independent, there are construction facilities that are not connected, and the cost of manpower and equipment is high. And technical problems with long construction period.
本发明是通过以下技术方案解决以上技术问题的: The present invention solves the above technical problems through the following technical solutions:
一种大直径筒体构筑物的滑模体系,包括已浇筑的筒壁,在已浇筑的筒壁中预埋有支撑杆,在支撑杆上设置有门型提升架,在已浇筑的筒壁的内侧面上设置有滑模内模模板,在已浇筑的筒壁的外侧面上设置有滑模外模模板,在滑模外模模板外侧设置有滑模外模围圈,在滑模内模模板内侧设置有滑模内模围圈,滑模内模围圈与门型提升架的内侧吊杆的下端固定连接,滑模外模围圈与门型提升架的外侧吊杆的下端固定连接,在结构中心筒的外圆周上等间隔弧度的设置有辐射状轻型钢桁架,辐射状轻型钢桁架的外端与环形钢梁通过螺栓固定连接在一起,在相邻的两榀辐射状轻型钢桁架之间设置有支撑架,在支撑架铺设有脚手架板,环形钢梁固定焊接在滑模内模围圈上。 A sliding form system for a large-diameter cylindrical structure, including a poured cylinder wall, a support rod is pre-embedded in the poured cylinder wall, a door-shaped lifting frame is arranged on the support rod, and a The inner surface of the sliding form is provided with a sliding form inner formwork, the outer surface of the poured cylinder wall is provided with a sliding form outer formwork, the outer surface of the sliding form outer formwork is provided with an outer ring of the sliding form, and the inner form of the sliding form The inside of the formwork is provided with an inner mold enclosure of the sliding form, which is fixedly connected to the lower end of the inner suspender of the door-shaped lifting frame, and the outer mold enclosure of the sliding form is fixedly connected to the lower end of the outer suspender of the door-shaped lifting frame , radial light steel trusses are arranged at equal intervals on the outer circumference of the central cylinder of the structure. A support frame is arranged between the trusses, a scaffold plate is laid on the support frame, and the ring-shaped steel beam is fixedly welded on the inner mold enclosure of the sliding form.
滑模内模模板上均设置有上、中、下三道滑模内模围圈。 The inner mold templates of the sliding mold are provided with upper, middle and lower inner mold enclosures of the sliding mold.
一种大直径筒体构筑物的滑模体系的施工方法,包括以下步骤: A construction method of a sliding form system for a large-diameter cylindrical structure, comprising the following steps:
第一步、在已浇筑的筒壁中预埋支撑杆,在支撑杆上安装门型提升架,在已浇筑的筒壁的内侧面上设置滑模内模模板,在已浇筑的筒壁的外侧面上设置滑模外模模板,在滑模外模模板外侧设置滑模外模围圈,在滑模内模模板内侧设置滑模内模围圈; The first step is to pre-embed support rods in the poured cylinder wall, install door-shaped lifting frames on the support rods, set the slip-form internal formwork on the inner side of the poured cylinder wall, and The outer surface of the sliding form is set on the outer surface of the sliding form, the outer surrounding of the sliding form is set on the outer side of the outer forming of the sliding form, and the inner surrounding of the sliding form is set on the inner side of the inner sliding form template;
第二步、将滑模内模围圈与门型提升架的内侧吊杆的下端固定连接在一起,将下圈的滑模外模围圈与门型提升架的外侧吊杆的下端固定连接在一起; The second step is to connect the inner ring of the sliding form with the lower end of the inner suspender of the door type lifting frame, and connect the outer ring of the sliding form of the lower ring to the lower end of the outer suspender of the door type lifting frame together;
第三步、在结构中心筒的外圆周上等间隔弧度的焊接辐射状轻型钢桁架,将辐射状轻型钢桁架的外端与环形钢梁通过螺栓连接在一起,组成了滑模体系内操作平台;将环形钢梁焊接到滑模内模围圈上; The third step is to weld radial light steel trusses at equal intervals on the outer circumference of the central cylinder of the structure, and connect the outer ends of the radial light steel trusses to the ring steel beams through bolts to form an operating platform in the sliding form system ; Weld the ring steel beam to the inner form ring of the slipform;
第四步、将提升架沿支撑杆向上移动构筑下一段筒壁的模板体系,然后进行下一段筒体混凝土浇筑,在最后一段筒体混凝土浇筑中沿筒体内壁等间隔的预埋牛腿焊接埋件,浇注完成整个筒体的混凝土; The fourth step is to move the lifting frame upward along the support rod to construct the formwork system of the next section of the cylinder wall, and then pour the concrete of the next section of the cylinder, and weld the pre-embedded corbels at equal intervals along the inner wall of the cylinder in the last section of the cylinder concrete pouring Embedded parts, pouring the concrete of the entire cylinder;
第五步、在预埋牛腿焊接埋件的内侧焊接钢牛腿; The fifth step is to weld the steel corbel on the inner side of the pre-embedded corbel welding embedded part;
第六步,将环形钢梁与滑模内模围圈脱离,将由结构中心筒、辐射状轻型钢桁架和环形钢梁组成的平台的外圈固定焊接在钢牛腿上,构成顶盖模板支撑体系。 The sixth step is to separate the ring steel beam from the inner mold enclosure of the sliding form, and weld the outer ring of the platform composed of the structural central tube, radial light steel truss and ring steel beam to the steel corbel to form the roof formwork support system.
本发明将筒壁滑模体系与顶盖模板支撑体系合二为一,在筒壁滑升阶段,操作平台主要承担自重及滑模施工荷载,筒壁滑升至顶部后,则做为上部模板支撑体系,承担顶盖结构自重、施工荷载及本身的重量。本发明结构简单,调整方便,人工和工具投入少,工期短。 The invention combines the cylinder wall sliding formwork system and the roof formwork support system into one. During the cylinder wall sliding up stage, the operating platform mainly bears its own weight and the sliding formwork construction load. After the cylinder wall slides up to the top, it is used as the upper formwork The supporting system bears the weight of the roof structure, construction load and its own weight. The invention has the advantages of simple structure, convenient adjustment, less labor and tool investment, and short construction period.
附图说明 Description of drawings
图1是本发明的结构示意图; Fig. 1 is a structural representation of the present invention;
图2是本发明在俯视方向上的结构示意图; Fig. 2 is a schematic structural view of the present invention in a top view direction;
图3是本发明的牛腿焊接埋件15、钢牛腿16与环形钢梁10之间的配合关系图。 Fig. 3 is a diagram of the cooperation between the corbel welding embedded part 15, the steel corbel 16 and the ring steel beam 10 of the present invention.
具体实施方式 Detailed ways
下面结合附图对本发明进行详细说明: The present invention is described in detail below in conjunction with accompanying drawing:
一种大直径筒体构筑物的滑模体系,包括已浇筑的筒壁1,在已浇筑的筒壁1中预埋有支撑杆2,在支撑杆2上设置有门型提升架7,在已浇筑的筒壁1的内侧面上设置有滑模内模模板4,在已浇筑的筒壁1的外侧面上设置有滑模外模模板3,在滑模外模模板3外侧设置有滑模外模围圈5,在滑模内模模板4内侧设置有滑模内模围圈6,滑模内模围圈6与门型提升架7的内侧吊杆9的下端固定连接,滑模外模围圈5与门型提升架7的外侧吊杆8的下端固定连接,在结构中心筒11的外圆周上等间隔弧度的设置有辐射状轻型钢桁架12,辐射状轻型钢桁架12的外端与环形钢梁10通过螺栓固定连接在一起,在相邻的两榀辐射状轻型钢桁架12之间设置有支撑架13,在支撑架13 铺设有脚手架板14,环形钢梁10固定焊接在滑模内模围圈6上。 A sliding form system for a large-diameter cylindrical structure, including a poured cylinder wall 1, a support rod 2 is pre-embedded in the poured cylinder wall 1, and a door-shaped lifting frame 7 is arranged on the support rod 2. The inner surface of the poured cylinder wall 1 is provided with a sliding formwork inner formwork 4, the outer surface of the poured cylinder wall 1 is provided with a sliding formwork outer formwork 3, and the outer surface of the sliding formwork 3 is provided with a sliding formwork The outer mold surrounding ring 5 is provided with the sliding mold inner mold surrounding circle 6 inside the sliding mold inner mold template 4, and the sliding mold inner mold surrounding circle 6 is fixedly connected with the lower end of the inner suspender 9 of the door type lifting frame 7, and the sliding mold outer The mold enclosure 5 is fixedly connected to the lower end of the outer suspender 8 of the door-shaped lifting frame 7, and radial light steel trusses 12 are arranged at equal intervals on the outer circumference of the structural central cylinder 11. The end and the ring-shaped steel beam 10 are fixedly connected together by bolts, a support frame 13 is arranged between two adjacent radial steel trusses 12, a scaffold plate 14 is laid on the support frame 13, and the ring-shaped steel beam 10 is fixedly welded on On the sliding mold inner mold enclosing circle 6.
滑模内模模板4设置有上、中、下三道滑模内模围圈。 The sliding mold inner mold template 4 is provided with upper, middle and lower three sliding mold inner mold enclosures.
一种大直径筒体构筑物的滑模体系的施工方法,包括以下步骤: A construction method of a sliding form system for a large-diameter cylindrical structure, comprising the following steps:
第一步、在已浇筑的筒壁1中预埋支撑杆2,在支撑杆2上安装门型提升架7,在已浇筑的筒壁1的内侧面上设置滑模内模模板4,在已浇筑的筒壁1的外侧面上设置滑模外模模板3,在滑模外模模板3的外侧面上设置滑模外模围圈5,在滑模内模模板4的内侧设置滑模内模围圈6; The first step is to pre-embed the support rod 2 in the poured cylinder wall 1, install the door-type lifting frame 7 on the support rod 2, set the slip-form inner mold template 4 on the inner side of the poured cylinder wall 1, and The outer surface of the poured cylinder wall 1 is provided with a sliding form outer formwork 3, the outer surface of the sliding form outer formwork 3 is provided with a sliding form outer circle 5, and the inner side of the sliding form inner formwork 4 is provided with a sliding form Inner mold enclosure 6;
第二步、将滑模内模围圈6与门型提升架7的内侧吊杆9的下端固定连接在一起,将下圈的滑模外模围圈5与门型提升架7的外侧吊杆8的下端固定连接在一起; The second step is to connect the lower end of the inner suspender 9 of the sliding form inner mold enclosure 6 with the door type lifting frame 7, and hang the sliding form outer mold enclosure 5 of the lower ring with the outer side of the door type lifting frame 7. The lower ends of the rods 8 are fixedly connected together;
第三步、在结构中心筒11的外圆周上等间隔弧度地焊接辐射状轻型钢桁架12,将辐射状轻型钢桁架12的外端与环形钢梁10通过螺栓连接在一起,组成了滑模体系内操作平台;将环形钢梁10焊接到滑模内模围圈6上; The third step is to weld the radial light steel trusses 12 at equal intervals on the outer circumference of the structural central cylinder 11, and connect the outer ends of the radial light steel trusses 12 with the ring steel beams 10 through bolts to form a sliding form The operating platform in the system; the ring steel beam 10 is welded to the inner mold enclosure 6 of the sliding form;
第四步、将提升架7沿支撑杆2向上移动构筑下一段筒壁的模板体系,然后进行下一段筒体混凝土浇筑,在最后一段筒体混凝土浇筑中,沿筒体内壁等间隔的预埋牛腿焊接埋件15,浇注完成整个筒体的混凝土; The fourth step is to move the lifting frame 7 upward along the support rod 2 to construct the formwork system of the next section of the cylinder wall, and then perform the concrete pouring of the next section of the cylinder. In the concrete pouring of the last section of the cylinder, the pre-embedded The corbel is welded with embedded parts 15, and the concrete of the whole cylinder is poured;
第五步、在预埋牛腿焊接埋件15的内侧焊接钢牛腿16; Step 5, welding steel corbel 16 on the inner side of pre-embedded corbel welding embedment 15;
第六步、将环形钢梁10与滑模内模围圈6脱离,将由结构中心筒11、辐射状轻型钢桁架12和环形钢梁10组成的平台的外圈固定焊接在钢牛腿16上,构成顶盖模板支撑体系。 The sixth step is to separate the annular steel beam 10 from the inner mold enclosure 6 of the sliding form, and weld the outer ring of the platform composed of the structural central cylinder 11, the radial light steel truss 12 and the annular steel beam 10 to the steel corbel 16 , forming a roof formwork support system.
本发明是将大直径筒体构筑物的滑模体系与筒体构筑物的顶盖的支撑体系合二为一的,利用滑模提升架做为支撑点,利用滑模顶升设备达到垂直提升,筒体内模板的支撑体系可兼作内操作平台。环形钢梁10,在滑模外模模板3、滑模内模模板4、滑模外模围圈5、滑模内模围圈6、门型提升架7(包括外侧吊杆8、内侧吊杆9)全部就位后,将环形钢梁10与滑模提升架内侧吊杆9进行焊接,再将结构中心筒11放置在筒体结构中心位置,然后一榀一榀的组装辐射状轻型钢桁架12,辐射状轻型钢桁架12沿径向环状布置,辐射状轻型钢桁架12一侧与中心结构筒11连接,另一侧与环形钢梁10连接,辐射状轻型钢桁架12组装完成后,在上下弦之间焊接支撑架13,最后满铺脚手架板14,操作平台拼装完成。起动滑模液压控制系统,打开各油路阀门开关,液压油泵向筒壁周圈千斤顶供油,周圈千斤顶带动环形钢梁10沿着支撑杆2开始向上爬行,从而将整体操作平台一起向上提升。当连续提升一定高度后,即可向筒壁周围的模板内浇筑混凝土,混凝土注满模板后又开始继续提升,就这样重复作业直到把操作平台从最低处提升到筒壁顶端,完成筒壁的施工。提前在筒壁1的顶部预埋牛腿焊接埋件15,焊接钢牛腿16,将操作平台环形钢梁10与滑模门型提升架内侧吊杆9拆开,与钢牛腿16进行焊接,改变操作平台支承点,此操作平台转变为筒体结构顶盖施工的承载平台,最后即可利用操作平台进行顶盖施工。 The present invention combines the sliding form system of the large-diameter cylindrical structure and the support system of the top cover of the cylindrical structure into one, uses the sliding form lifting frame as the support point, and uses the sliding form jacking equipment to achieve vertical lifting. The support system of the template in the body can double as the inner operating platform. Annular steel beam 10, in the sliding form outer formwork 3, sliding form inner formwork 4, sliding form outer form enclosure 5, sliding form inner form enclosure 6, door type lifting frame 7 (including outer suspender 8, inner suspender After the rods 9) are all in place, weld the ring-shaped steel beam 10 and the inner suspender 9 of the sliding form lifting frame, and then place the structural center cylinder 11 at the center of the cylinder structure, and then assemble the radial light steel beams one by one. Trusses 12, radial light steel trusses 12 are arranged radially and annularly, one side of the radial light steel trusses 12 is connected to the central structural tube 11, and the other side is connected to the ring steel beam 10, after the radial light steel trusses 12 are assembled , Weld the support frame 13 between the upper and lower chords, and finally spread the scaffolding boards 14, and the assembly of the operating platform is completed. Start the sliding mode hydraulic control system, open the valve switch of each oil circuit, the hydraulic oil pump supplies oil to the cylinder wall circumference jack, and the circumference jack drives the ring steel beam 10 to crawl upward along the support rod 2, thereby lifting the entire operation platform upward together . After continuous lifting to a certain height, concrete can be poured into the formwork around the cylinder wall. After the concrete fills the formwork, it will continue to lift. Repeat the operation until the operation platform is lifted from the lowest point to the top of the cylinder wall to complete the cylinder wall. construction. Pre-embed the corbel welding embedment 15 on the top of the cylinder wall 1 in advance, weld the steel corbel 16, disassemble the ring steel beam 10 of the operating platform and the inner suspender 9 of the sliding form door type lifting frame, and weld the steel corbel 16 , change the supporting point of the operating platform, the operating platform is transformed into a bearing platform for the roof construction of the cylinder structure, and finally the operating platform can be used for roof construction.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420807872.4U CN204386152U (en) | 2014-12-19 | 2014-12-19 | The sliding formwork system of large-diameter cylinder body structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420807872.4U CN204386152U (en) | 2014-12-19 | 2014-12-19 | The sliding formwork system of large-diameter cylinder body structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204386152U true CN204386152U (en) | 2015-06-10 |
Family
ID=53358884
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420807872.4U Expired - Lifetime CN204386152U (en) | 2014-12-19 | 2014-12-19 | The sliding formwork system of large-diameter cylinder body structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204386152U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104499707A (en) * | 2014-12-19 | 2015-04-08 | 山西省第三建筑工程公司 | Slip form system of large-diameter cylindrical structure and construction method thereof |
| CN106193568A (en) * | 2016-08-26 | 2016-12-07 | 中建三局安装工程有限公司 | Mobile steel truss operating platform |
| CN109469308A (en) * | 2018-10-26 | 2019-03-15 | 何嘉文 | Structure of large-diameter group cabin supporting platform |
| CN112727093A (en) * | 2020-12-28 | 2021-04-30 | 中材建设有限公司 | Climbing construction method for constructing large-span high-rise building |
-
2014
- 2014-12-19 CN CN201420807872.4U patent/CN204386152U/en not_active Expired - Lifetime
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104499707A (en) * | 2014-12-19 | 2015-04-08 | 山西省第三建筑工程公司 | Slip form system of large-diameter cylindrical structure and construction method thereof |
| CN104499707B (en) * | 2014-12-19 | 2016-08-24 | 山西省第三建筑工程公司 | The sliding formwork system of large-diameter cylinder body structures and construction method thereof |
| CN106193568A (en) * | 2016-08-26 | 2016-12-07 | 中建三局安装工程有限公司 | Mobile steel truss operating platform |
| CN109469308A (en) * | 2018-10-26 | 2019-03-15 | 何嘉文 | Structure of large-diameter group cabin supporting platform |
| CN112727093A (en) * | 2020-12-28 | 2021-04-30 | 中材建设有限公司 | Climbing construction method for constructing large-span high-rise building |
| CN112727093B (en) * | 2020-12-28 | 2022-09-09 | 中材建设有限公司 | Climbing construction method for constructing large-span high-rise building |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110230393B (en) | Large concrete tank dome climbing high formwork support system and installation method | |
| CN105649325B (en) | The adjustable tripod support system of assembly concrete shear wall structure and method | |
| WO2020118563A1 (en) | Design and rapid construction methods for flush assembly of prefabricated steel beams and floor | |
| CN101892710B (en) | Structure node for steel girder and reinforced column and construction method thereof | |
| CN115369748A (en) | Construction method of template system for integrally pouring pier and tie beam | |
| CN105297635A (en) | Assembled lifting type construction platform for pier column construction and construction method thereof | |
| CN104372947A (en) | Integral mold plate feeding and retreating construction method for elevator shaft | |
| CN106192758A (en) | Construction method for constructing large high pier column by using cantilever formwork | |
| CN104088397A (en) | Prefabricated column and precast construction method thereof | |
| CN114033234B (en) | A new type of main tower crown structure and its segmented installation method | |
| CN204386152U (en) | The sliding formwork system of large-diameter cylinder body structure | |
| CN108755439B (en) | Universal telescopic support frame suitable for V-shaped bridge piers and its installation method | |
| CN105780922A (en) | Construction method for segmental formwork hoisting system of large-span steel reinforced concrete transfer truss | |
| CN205636516U (en) | Convertible template system of hollow concrete leaning tower | |
| CN105862602A (en) | Turnover formwork system of hollow inclined concrete pylon and construction method thereof | |
| CN205653708U (en) | Work platform that inclined plane climbed follows | |
| CN103485574A (en) | Method for constructing reinforced concrete structure of tower top of prilling tower | |
| CN100365237C (en) | A self-elevating deformable and detachable overall lifting steel platform system and construction method | |
| CN104499707B (en) | The sliding formwork system of large-diameter cylinder body structures and construction method thereof | |
| CN205112085U (en) | Hydraulic pressure centre form construction system | |
| CN110130676B (en) | A bolt ball node type grid frame and its green construction method | |
| CN116771116A (en) | Construction method of suspension structure reverse construction complete equipment system | |
| CN203200664U (en) | Slip-form construction device for variable cross-section hollow high pier | |
| CN106013784A (en) | Angle iron frame template and construction method | |
| CN104453217A (en) | Elevator shaft whole formwork lifting construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term |
Granted publication date: 20150610 |
|
| CX01 | Expiry of patent term |