CN204356792U CN201420845486.4U CN201420845486U CN204356792U CN 204356792 U CN204356792 U CN 204356792U CN 201420845486 U CN201420845486 U CN 201420845486U CN 204356792 U CN204356792 U CN 204356792U
Authority
CN
China
Prior art keywords
cofferdam
river
mozzle
conservancy diversion
water conservancy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420845486.4U
Other languages
Chinese (zh)
Inventor
赖金星
唐亚森
周慧
冯志华
毛升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201420845486.4U priority Critical patent/CN204356792U/en
Application granted granted Critical
Publication of CN204356792U publication Critical patent/CN204356792U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses the construction equipment of cofferdam, a kind of river water conservancy diversion, comprise the cofferdam be arranged on for a pair for the river that dams on riverbed, a pair described cofferdam is provided with the mozzle of through cofferdam, makes the river of a cofferdam upstream import another cofferdam downstream from mozzle; The face that described cofferdam contacts with river is provided with one deck waterproof blanket; Described mozzle outer wall is coated with one deck waterproof blanket.Cofferdam provided by the utility model parallel works makes full use of riverbed, utilize mozzle by have water in order by Effects on Engineering region, reduce the runoff in this section of river simultaneously, reduce under river and ooze.Due to the protection with mozzle, the impact that the orderly water vent in river is not constructed.And do not affect the excretory function in river, the impact of periphery life is reduced.

Description

The construction equipment of cofferdam, a kind of river water conservancy diversion
Technical field
The utility model belongs to field of road, relates to river construction, is specifically related to the construction equipment of cofferdam, a kind of river water conservancy diversion.
Background technology
When wearing river and crossing bridge engineering construction under construction of tunnel, pipe works, need to carry out cofferdam water conservancy diversion measure to river, to give tunnel, bottom and pipeline construction, or top bridge construction provides a good working environment, the water content of the upper soil horizon of tunnel and pipeline is reduced, reduce milliosmolarity under river, or be that Bridge Pile Foundation Construction provides good working environment by orderly draining, reduce the unordered draining in river to the impact caused of constructing.
The method of conventional cofferdam water conservancy diversion is mainly: cutout, employing riverbed are laid waterproof blanket, bottom arranges cover plate and excavated diversion channel four kinds of methods.Adopt the construction method of cutout, its main working measure is, arranges cofferdam and upper river water is cut off, reduce dirty come the water yield, thus reduce milliosmolarity under river, for correlation engineering provides a larger work plane.Its construction method is simple, but is the principal works problem that it is tackled to the process of upland water.And can relate to more multidisciplinary to the process of upper reaches water, its treatment measures engineering quantity and engineering cost are comparatively large, and can affect the excretion of periphery surface water in rainy season and periphery sewage.
According to the method for laying waterproof blanket bottom river, its working measure is mainly, half range construction about river dams point, build U-shaped cofferdam, cofferdam internal water accumulation and mud are cleaned out, then bottom riverbed, lays waterproof blanket, treat that waterproof blanket carries out recovery water flowing after laying.Adopt this construction method that the engineering quantity of laying will be caused larger, required construction period is longer.
When adopting bevelling lid excavation construction method, in the dry season, the construction of left and right half range branch is carried out to river, build U-shaped cofferdam, cofferdam internal water accumulation and mud are cleaned out, cover plate is laid in riverbed, to utilize cover plate as support, the earthwork, construction tunnel or pipeline configuration under excavation lid digs cover plate.When adopting the construction of cover plate method, need cover plate amount large, require higher to cover plate support, construction workload is comparatively large, and operating expenses also will increase accordingly.
Excavation diversion channel scheme is then the one or both sides excavation diversion channel in river, lays waterproof blanket, then builds cofferdam at upper river, river is introduced diversion channel bottom diversion channel.When adopting this kind of construction method, because one or both sides, river need to carry out diversion channel excavation, required construction working face will increase further, and the position often inconvenient construction carrying out diversion channel residing for river.
In sum, the major defect of existing construction method is that required engineering cost is comparatively large, and construction workload increases, construction period is longer, causes construction working face comparatively large to the underutilization in existing riverbed, larger on surrounding enviroment impact, to river water undertreatment, water treatment expense is caused to increase.
Summary of the invention
For the deficiency that prior art exists, the purpose of this utility model is, provides the construction equipment of cofferdam, a kind of river water conservancy diversion, to ooze the impact on river bottom solum under reducing river, under wear tunnel, river or pipeline construction provides a kind of good working environment.Reduce channel flow scope for the river bridge construction that collapses provides a larger construction working face simultaneously.There is provided a kind of good working environment not only to the engineering construction of engineering in river influence basin by this cofferdam parallel works, reduce the engineering cost of cofferdam construction simultaneously, reduce the engineering quantity of ancillary works, shorten construction period, for principal works construction is raced against time.
In order to solve the problems of the technologies described above, the utility model adopts following technical scheme to be achieved:
The construction equipment of cofferdam, a kind of river water conservancy diversion, comprise the cofferdam be arranged on for a pair for the river that dams on riverbed, a pair described cofferdam is provided with the mozzle of through cofferdam, makes the river of a cofferdam upstream import another cofferdam downstream from mozzle;
The face that described cofferdam contacts with river is provided with one deck waterproof blanket;
Described mozzle outer wall is coated with one deck waterproof blanket.
The utility model also has distinguishes technical characteristic as follows:
Described cofferdam is divided into outside to work out gunnysack filling cohesive soil pile, cohesive soil core-wall and inner side gunnysack and fill cohesive soil pile successively from the outside contacted with river to inner side.
Described mozzle is a pair mozzle.
Described mozzle is arranged on bottom cofferdam and makes mozzle against riverbed water conservancy diversion river on vertically.
Described mozzle is upwards arranged on the position of cofferdam both sides near river levee in level, for disperseing river to the pressure of cofferdam.
Being provided with cushion coat between described mozzle and river levee, being applied to power in cofferdam horizontal direction for disperseing mozzle.
Described cushion coat is the gunnysack that cohesive soil is housed.
Described waterproof blanket comprises one deck basic cloth, and basic cloth is provided with one group of packaging bag, packaging bag is built with sodium bentonite.
The utility model compared with prior art, has following technique effect:
(A) the cofferdam parallel works that provides of the utility model, easy construction, simply, practical, material requested very easily obtains, and has fewer environmental impacts, and mozzle and cofferdam gunnysack can reuse, and has more manifested the requirement of energy-saving and emission-reduction.
(B) cofferdam provided by the utility model parallel works makes full use of riverbed, utilize mozzle by have water in order by Effects on Engineering region, reduce the runoff in this section of river simultaneously, reduce under river and ooze.Due to the protection with mozzle, the impact that the orderly water vent in river is not constructed.And do not affect the excretory function in river, the impact of periphery life is reduced.
(C) device provided by the utility model is for the water treatment measures of upstream, cofferdam and mozzle are combined, under the effect not changing discharge of river, adopt orderly draining, what reduce that process upland water needs with multidisciplinary communication is loaded down with trivial details, reduce the disposal cost to upland water, reach good effect.
Accompanying drawing explanation
Fig. 1 is overall structure schematic diagram of the present utility model.
Fig. 2 of the present utility modelly faces structural representation.
Fig. 3 is plan structure schematic diagram of the present utility model.
Fig. 4 is the structural representation of waterproof blanket of the present utility model.
In figure, the implication of each label is: 1,2-cofferdam, 3-mozzle, 4-waterproof blanket, 5-riverbed, 6-river levee, 7-cushion coat; 1-1,2-1 are outside establishment gunnysack dress cohesive soil pile, and 1-2,2-2 are cohesive soil core-wall, and 1-3,2-3 are inner side gunnysack dress cohesive soil pile; (4-1)-basic cloth, (4-2)-packaging bag.
Below in conjunction with accompanying drawing, explanation is further explained in detail to particular content of the present utility model.
Detailed description of the invention
Below provide specific embodiment of the utility model, it should be noted that the utility model is not limited to following specific embodiment, all equivalents done on technical scheme basis all fall into protection domain of the present utility model.
Embodiment:
Defer to technique scheme, as shown in Figure 1 to Figure 3, the present embodiment provides the construction equipment of cofferdam, a kind of river water conservancy diversion, comprises the cofferdam 1 be arranged on for a pair for the river that dams on riverbed 5;
Described a pair cofferdam 1,2 is provided with the mozzle 3 of through cofferdam 1,2, makes the river of cofferdam 1 upstream import another cofferdam 1 downstream from mozzle 3;
The face that described cofferdam 1,2 contacts with river is provided with one deck waterproof blanket 4;
Described mozzle 3 outer wall is coated with one deck waterproof blanket 4.
Cofferdam 1,2 is divided into outside to work out gunnysack filling cohesive soil pile 1-1,2-1, cohesive soil core-wall 1-2,2-2 and inner side gunnysack and fill cohesive soil pile 1-3,2-3 successively from the outside contacted with river to inner side.
Mozzle 3 is a pair mozzle 3, and the flow according to actual river can arrange multiple.
Mozzle 3 is arranged on bottom cofferdam 1,2 and makes mozzle 3 against riverbed 5 water conservancy diversion river on vertically.
Mozzle 3 is upwards arranged on cofferdam 1,2 both sides near the position of river levee 6, for disperseing river to the pressure of cofferdam 1 in level.
Being provided with cushion coat 7 between mozzle 3 and river levee 6, being applied to power in cofferdam 1,2 horizontal direction for disperseing mozzle 3.Cushion coat 7 is for being equipped with the gunnysack of cohesive soil.
As shown in Figure 4, waterproof blanket 4 comprises one deck basic cloth 4-1, and basic cloth 4-1 is provided with one group of packaging bag 4-2, packaging bag 4-2 is built with sodium bentonite.
Cofferdam, the utility model river guiding device can adopt the following step to construct:
Step one, selects in the dry season, and the engineering that crosses the river enters influence area, river first about 5 months, starts construction.In both sides, center, distance construction influence area, U-shaped cut-off dam is built at each 80 meters of, and framing is constructed.Cut-off dam is formed by working out gunnysack dress cohesive soil pile, first build the U-shaped cut-off dam of left half range, after treating that one section of cofferdam 1,2 in the U-shaped cut-off dam construction area of left half range and mozzle 3 are constructed, mozzle 3 is logical river first, remove the U-shaped cut-off dam of left half range, build the U-shaped cut-off dam of right half range, and then the one section of cofferdam 1,2 built in the U-shaped cut-off dam construction area of right half range and mozzle 3.
Step 2, the cofferdam 1 that 5m place builds outside establishment gunnysack dress cohesive soil pile 1-1 after the U-shaped cut-off dam of left half range, cohesive soil core-wall 1-2 and inner side gunnysack dress cohesive soil pile 1-3 is formed, be 1:0.75 and put slope, place mozzle 3 at 0.6m place, lateral separation cofferdam 1 edge, be provided with cushion coat 7 that gunnysack that cohesive soil is housed makes between mozzle 3 and river levee and be applied to power in cofferdam 1,2 horizontal direction for disperseing mozzle 3.
Paste waterproof blanket 4 at outside establishment gunnysack dress cohesive soil pile 1-1, the ditch of 0.25 × 0.25m is stayed on outside establishment gunnysack dress cohesive soil pile 1-1 top, for fixing waterproof blanket 4 top edge.The distance that mozzle 4 stretches out outside establishment gunnysack dress cohesive soil pile 1-1 is 0.6m, and mozzle 3 and outside are worked out gunnysack and filled cohesive soil pile 1-1 intersection, process with waterproof blanket 4.
Step 3, mozzle 3 adopts external diameter 1.1m, internal diameter 1m, and the precast concrete pipeline of length 1.5 meters connects.Concrete pipe microcephaly is placed in the retaining groove place of last concrete pipe, by cement paste bonding, connector outside is coated with bentonite slurry, and wraps up waterproof blanket 4 outside mozzle 3.
Step 4, as step 3 connects cofferdam 2 place in mozzle 3 to downstream, builds the cofferdam 2 in downstream, forms one section of cofferdam 1,2 and the mozzle 3 of left bank;
Step 5, left bank mozzle 3 water flowing, removes the U-shaped cut-off dam of left half range, build the U-shaped cut-off dam of right half range, same form of construction work constructs another section of cofferdam 1,2 and mozzle 3, forms the construction equipment of complete cofferdam, a river water conservancy diversion, removes the U-shaped cut-off dam of right half range.

Claims (8)

1. a construction equipment for cofferdam, river water conservancy diversion, comprises the cofferdam (1) be arranged on for a pair for the river that dams on riverbed (5), it is characterized in that:
Described a pair cofferdam (1,2) is provided with the mozzle (3) of through cofferdam (1,2), makes the river of cofferdam (1) upstream import another cofferdam (1) downstream from mozzle (3);
The face that described cofferdam (1,2) contacts with river is provided with one deck waterproof blanket (4);
Described mozzle (3) outer wall is coated with one deck waterproof blanket (4).
2. the construction equipment of cofferdam, river as claimed in claim 1 water conservancy diversion, is characterized in that: work out gunnysack outside described cofferdam (1,2) is divided into successively from outside contact with river to inner side and fill cohesive soil pile (1-1,2-1), cohesive soil core-wall (1-2,2-2) and inner side gunnysack and fill cohesive soil pile (1-3,2-3).
3. the construction equipment of cofferdam, river as claimed in claim 1 water conservancy diversion, is characterized in that: described mozzle (3) is a pair mozzle (3).
4. the construction equipment of cofferdam, river as claimed in claim 3 water conservancy diversion, is characterized in that: described mozzle (3) is arranged on cofferdam (1,2) bottom and makes mozzle (3) against riverbed (5) water conservancy diversion river on vertically.
5. the construction equipment of cofferdam, river as claimed in claim 3 water conservancy diversion, it is characterized in that: described mozzle (3) is upwards arranged on cofferdam (1,2) both sides near the position of river levee (6), for disperseing river to the pressure of cofferdam (1) in level.
6. the construction equipment of cofferdam, river as claimed in claim 5 water conservancy diversion, it is characterized in that: between described mozzle (3) and river levee (6), be provided with cushion coat (7), being applied to power in cofferdam (1,2) horizontal direction for disperseing mozzle (3).
7. the construction equipment of cofferdam, river as claimed in claim 6 water conservancy diversion, is characterized in that: described cushion coat (7) is for being equipped with the gunnysack of cohesive soil.
8. the construction equipment of cofferdam, river as claimed in claim 1 water conservancy diversion, it is characterized in that: described waterproof blanket (4) comprises one deck basic cloth (4-1), basic cloth (4-1) is provided with one group of packaging bag (4-2), packaging bag (4-2) is built with sodium bentonite.
CN201420845486.4U 2014-12-26 2014-12-26 The construction equipment of cofferdam, a kind of river water conservancy diversion Expired - Fee Related CN204356792U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420845486.4U CN204356792U (en) 2014-12-26 2014-12-26 The construction equipment of cofferdam, a kind of river water conservancy diversion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420845486.4U CN204356792U (en) 2014-12-26 2014-12-26 The construction equipment of cofferdam, a kind of river water conservancy diversion

Publications (1)

Publication Number Publication Date
CN204356792U true CN204356792U (en) 2015-05-27

Family

ID=53258271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420845486.4U Expired - Fee Related CN204356792U (en) 2014-12-26 2014-12-26 The construction equipment of cofferdam, a kind of river water conservancy diversion

Country Status (1)

Country Link
CN (1) CN204356792U (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105003757A (en) * 2015-08-13 2015-10-28 东南大学 Buried steel pipe
CN105586977A (en) * 2016-02-03 2016-05-18 中交第三航务工程局有限公司宁波分公司 Method for diversion construction of closure gap of steel cofferdam under open sea unshielded condition by down-penetrating method
CN105714837A (en) * 2016-02-03 2016-06-29 中交第三航务工程局有限公司宁波分公司 Diversion construction method for up-pull-method open sea no-cover steel cofferdam closure gap
CN105887769A (en) * 2016-05-18 2016-08-24 王燏斌 Dam construction method
CN105926543A (en) * 2016-05-18 2016-09-07 王燏斌 Dam construction method
CN105951682A (en) * 2016-05-18 2016-09-21 王燏斌 Dam construction method
CN106320352A (en) * 2016-08-26 2017-01-11 上海市政工程设计研究总院(集团)有限公司 Construction method for multifunctional steel sheet pile cofferdam
CN107761674A (en) * 2016-08-17 2018-03-06 唐富仁 A kind of new barrage
CN108755720A (en) * 2018-06-14 2018-11-06 中国十七冶集团有限公司 The relatively narrow river water method of river diversion for crossing water river is worn under large-scale synthesis piping lane
CN108951641A (en) * 2018-07-25 2018-12-07 中国十七冶集团有限公司 It is a kind of for the compound support method of ultra-deep pipe gallery foundation trench in water river
CN109295916A (en) * 2018-11-02 2019-02-01 中交第二航务工程勘察设计院有限公司 A kind of hose can be used for river water conservancy diversion and application method
CN111305141A (en) * 2019-11-29 2020-06-19 中国一冶集团有限公司 Drainage method for underground comprehensive pipe gallery in dry season canal penetrating
CN112681350A (en) * 2020-12-16 2021-04-20 中国二冶集团有限公司 River cofferdam diversion construction method
CN113738971A (en) * 2021-07-30 2021-12-03 浙江珊溪水利水电开发股份有限公司 Assembled honeycomb duct
CN115198692A (en) * 2022-08-06 2022-10-18 四川宇硕建筑工程集团有限公司 Water conservancy project construction diversion drainage structure and construction method thereof

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105003757A (en) * 2015-08-13 2015-10-28 东南大学 Buried steel pipe
CN105586977A (en) * 2016-02-03 2016-05-18 中交第三航务工程局有限公司宁波分公司 Method for diversion construction of closure gap of steel cofferdam under open sea unshielded condition by down-penetrating method
CN105714837A (en) * 2016-02-03 2016-06-29 中交第三航务工程局有限公司宁波分公司 Diversion construction method for up-pull-method open sea no-cover steel cofferdam closure gap
CN105887769A (en) * 2016-05-18 2016-08-24 王燏斌 Dam construction method
CN105926543A (en) * 2016-05-18 2016-09-07 王燏斌 Dam construction method
CN105951682A (en) * 2016-05-18 2016-09-21 王燏斌 Dam construction method
CN107761674A (en) * 2016-08-17 2018-03-06 唐富仁 A kind of new barrage
CN106320352B (en) * 2016-08-26 2020-12-04 上海市政工程设计研究总院(集团)有限公司 Construction method of multifunctional steel sheet pile cofferdam
CN106320352A (en) * 2016-08-26 2017-01-11 上海市政工程设计研究总院(集团)有限公司 Construction method for multifunctional steel sheet pile cofferdam
CN108755720A (en) * 2018-06-14 2018-11-06 中国十七冶集团有限公司 The relatively narrow river water method of river diversion for crossing water river is worn under large-scale synthesis piping lane
CN108951641A (en) * 2018-07-25 2018-12-07 中国十七冶集团有限公司 It is a kind of for the compound support method of ultra-deep pipe gallery foundation trench in water river
CN109295916A (en) * 2018-11-02 2019-02-01 中交第二航务工程勘察设计院有限公司 A kind of hose can be used for river water conservancy diversion and application method
CN111305141A (en) * 2019-11-29 2020-06-19 中国一冶集团有限公司 Drainage method for underground comprehensive pipe gallery in dry season canal penetrating
CN111305141B (en) * 2019-11-29 2021-11-26 中国一冶集团有限公司 Drainage method for underground comprehensive pipe gallery in dry season canal penetrating
CN112681350A (en) * 2020-12-16 2021-04-20 中国二冶集团有限公司 River cofferdam diversion construction method
CN113738971A (en) * 2021-07-30 2021-12-03 浙江珊溪水利水电开发股份有限公司 Assembled honeycomb duct
CN115198692A (en) * 2022-08-06 2022-10-18 四川宇硕建筑工程集团有限公司 Water conservancy project construction diversion drainage structure and construction method thereof
CN115198692B (en) * 2022-08-06 2024-01-16 四川宇硕建筑工程集团有限公司 Water conservancy project construction diversion drainage structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN204356792U (en) The construction equipment of cofferdam, a kind of river water conservancy diversion
CN203429597U (en) Anti-underwashing protection slope structure for downstream river channel of hydropower plant
CN102660936A (en) Method for realizing seepage prevention of bridge wall by means of polyvinyl chloride film
CN210827513U (en) Self-adaptation side slope drainage seepage prevention structure
CN208563522U (en) A kind of side slope riding track Rainwater collection system
CN102767157A (en) Diking method through filling sludge into mold bags and vacuum preloading
CN107761668B (en) Coastal shore reservoir land-building type revetment structure and construction method thereof
CN202577231U (en) Interlocking ecological hydraulic building block revetment
CN204676488U (en) A kind of novel barricade anti-filter discharge structure
CN103898915B (en) Building small-area deep foundation pit anti-floating water stop construction method
CN204551510U (en) A kind of filled-up ground catchments pressure reduction well drop and drainage structure
CN107858990B (en) Diversion construction method of arrangement structure of canyon area high dam ditch water treatment engineering
CN209482261U (en) With the dam structure faced forever in conjunction with multi-functional drainage box culvert
CN103726514B (en) The anti-leakage structure of diaphragm wall and anti-seepage construction method
CN110206062A (en) The dark construction method of underground river shallow embedding is worn under a kind of Urban Underground pipe gallery
CN107687155B (en) Anti-seepage and anti-lifting structure of basin and arrangement method
CN105019466A (en) Construction method and structure of earth-rock cofferdam seepage-proofing system
CN101603299B (en) Broken line type dam joint structure and construction method thereof
CN201704090U (en) Manual infiltration system for water gotten from source close to river
CN108755724A (en) The external water drainage waterproof method of pipe gallery
CN201539266U (en) Subsurface filtration discharging device of subway/tunnel
CN211080123U (en) Ecological bank slope protection device in river lake
CN204849791U (en) Structure of earth-rock cofferdam seepage-proofing system
CN107130644A (en) Coffering composite geo-membrane and gravelly clay combination against seepage construction method
CN210151667U (en) A seepage prevention structure for city river course

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150527

Termination date: 20161226

CF01 Termination of patent right due to non-payment of annual fee