CN204225471U - A kind of cantilever steel girder structure through walls - Google Patents
A kind of cantilever steel girder structure through walls Download PDFInfo
- Publication number
- CN204225471U CN204225471U CN201420653128.3U CN201420653128U CN204225471U CN 204225471 U CN204225471 U CN 204225471U CN 201420653128 U CN201420653128 U CN 201420653128U CN 204225471 U CN204225471 U CN 204225471U
- Authority
- CN
- China
- Prior art keywords
- pull ring
- steel
- sides
- tenon
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 42
- 239000010959 steel Substances 0.000 title claims abstract description 42
- 230000000149 penetrating effect Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 6
- 239000000463 material Substances 0.000 abstract description 5
- 230000000694 effects Effects 0.000 abstract description 2
- 230000002093 peripheral effect Effects 0.000 abstract description 2
- -1 wooden tenon Substances 0.000 abstract 1
- 238000000034 method Methods 0.000 description 3
- 239000002390 adhesive tape Substances 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Revetment (AREA)
Abstract
本实用新型提供一种悬挑钢梁穿墙结构,它包括有拉环、角钢、木榫、钢榫,其中,拉环由钢筋折弯成U形,其U形顶部设有螺纹,拉环两侧侧壁套装PVC管后预埋在楼板混凝土内,拉环底部与楼板底部的模块接触;工字钢穿过拉环两侧侧壁之间后挑出墙体;工字钢底部与楼板之间垫装有钢榫,工字钢两侧侧壁与拉环两侧内壁之间嵌插有木榫;工字钢顶部设有角钢,角钢紧压在工字钢顶部,其两端通过螺栓铰在拉环两侧侧壁顶部的螺纹上。本方案将耗材转化成可循环使用的周材,既满足规范要求,又符合“两型社会”需要。实验结果表明,其效果良好,施工中节约了项目成本、保证了工程质量、施工安全可靠。
The utility model provides a wall-penetrating structure of cantilevered steel beams, which includes a pull ring, angle steel, wooden tenon, and steel tenon, wherein the pull ring is bent into a U shape by a steel bar, and the top of the U shape is provided with threads, and the pull ring The side walls on both sides are fitted with PVC pipes and embedded in the concrete of the floor. The bottom of the pull ring is in contact with the module at the bottom of the floor; There is a steel tenon in between, and a wooden tenon is embedded between the side walls on both sides of the I-beam and the inner wall on both sides of the pull ring; the top of the I-beam is equipped with an angle steel, which is pressed tightly on the top of the I-beam, and its two ends pass through The bolts are hinged on threads at the top of the sidewalls on both sides of the pull ring. This scheme transforms consumable materials into recyclable peripheral materials, which not only meets the requirements of the regulations, but also meets the needs of the "two-oriented society". The experimental results show that the effect is good, the project cost is saved during construction, the project quality is guaranteed, and the construction is safe and reliable.
Description
技术领域 technical field
本实用新型涉及建筑技术领域,尤其是指一种悬挑钢梁穿墙结构。 The utility model relates to the technical field of buildings, in particular to a wall-penetrating structure of cantilevered steel beams.
背景技术 Background technique
随着建筑施工扣件式钢管脚手架安全技术规范JGJ130-2011标准在2011年01月28日的发布,至2011年12月1日实施。经过将近一年的过渡期,对重大危险项悬挑架规范有了进一步的规范要求。其中,对于悬挑脚手架工字钢拉环,其型钢悬挑固定端应采用2个(对)及以上U型钢拉环或锚固螺栓与建筑结构梁板固定,U型钢筋拉环或锚固螺栓应预埋至混凝土梁底板层钢筋位置,并应与混凝土梁、板底层钢筋焊接或者绑扎牢固,其锚固长度应符合现行国家标准《混凝土结构设计规范》GB50010中钢筋锚固的规定。在锚固环上设置两根1.5m长直径为18mmHRB335的钢筋,如梁板处设有≥18mm钢筋时可不另外加。现有的做法是悬挑钢梁完成后,是直接将U型钢筋切割,如此造成了材料浪费,进而增加了施工成本。 With the release of the JGJ130-2011 safety technical specification for fastener-type steel pipe scaffolding in construction on January 28, 2011, it will be implemented on December 1, 2011. After a transition period of nearly one year, there are further specification requirements for the specification of cantilever frames for major hazard items. Among them, for the I-shaped steel pull ring of the cantilevered scaffold, the cantilevered fixed end of the shaped steel should be fixed with two (pairs) or more U-shaped steel pull rings or anchor bolts and the building structure beam plate, and the U-shaped steel bar pull ring or anchor bolts should be It should be pre-buried to the position of the steel bars at the bottom of the concrete beam, and should be welded or bound firmly with the steel bars at the bottom of the concrete beam and slab. The anchorage length should meet the current national standard "Code for Design of Concrete Structures" GB50010. Set two 1.5m long and 18mm HRB335 steel bars on the anchor ring, if there is a ≥18mm steel bar at the beam plate, no additional addition is required. The existing method is to directly cut the U-shaped steel bar after the cantilevered steel beam is completed, which causes material waste and increases the construction cost.
发明内容 Contents of the invention
本实用新型的目的在于克服现有技术的不足,提供一种可循环利用的悬挑钢梁穿墙结构。 The purpose of the utility model is to overcome the deficiencies of the prior art and provide a recyclable cantilevered steel beam wall-through structure.
为实现上述目的,本实用新型所提供的技术方案为:一种悬挑钢梁穿墙结构,它包括有拉环、角钢、木榫、钢榫,其中,拉环由钢筋折弯成U形,其U形顶部设有螺纹,拉环两侧侧壁套装PVC管后预埋在楼板混凝土内,拉环底部与楼板底部的模块接触;工字钢穿过拉环两侧侧壁之间后挑出墙体;工字钢底部与楼板之间垫装有钢榫,工字钢两侧侧壁与拉环两侧内壁之间嵌插有木榫;工字钢顶部设有角钢,角钢紧压在工字钢顶部,其两端通过螺栓铰在拉环两侧侧壁顶部的螺纹上。 In order to achieve the above purpose, the technical solution provided by the utility model is: a cantilevered steel beam through the wall structure, which includes a pull ring, an angle steel, a wooden tenon, and a steel tenon, wherein the pull ring is bent into a U shape by a steel bar , the U-shaped top is provided with threads, the side walls on both sides of the pull ring are set with PVC pipes and embedded in the floor concrete, the bottom of the pull ring is in contact with the module at the bottom of the floor; Pick out the wall; there is a steel tenon between the bottom of the I-beam and the floor, and a wooden tenon is inserted between the side walls on both sides of the I-beam and the inner walls on both sides of the pull ring; It is pressed on the top of the I-beam, and its two ends are hinged on the threads on the top of the side walls on both sides of the pull ring through bolts.
所述的拉环底部包覆有胶带或工程薄膜,PVC管的直径大于拉环两侧钢筋的直径。 The bottom of the pull ring is covered with adhesive tape or engineering film, and the diameter of the PVC pipe is larger than that of the steel bars on both sides of the pull ring.
本方案将耗材转化成可循环使用的周材,既满足规范要求,又符合“两型社会”需要。实验结果表明,其效果良好,施工中节约了项目成本、保证了工程质量、施工安全可靠。 This scheme transforms consumable materials into recyclable peripheral materials, which not only meets the requirements of the regulations, but also meets the needs of the "two-oriented society". The experimental results show that the effect is good, the project cost is saved during construction, the project quality is guaranteed, and the construction is safe and reliable.
附图说明 Description of drawings
图1为本实用新型的整体结构示意图。 Figure 1 is a schematic diagram of the overall structure of the utility model.
具体实施方式 Detailed ways
下面结合所有附图对本实用新型作进一步说明,本实用新型的较佳实施例为:参见附图1,本实施例所述的悬挑钢梁穿墙结构,其特征在于:它包括有拉环1、角钢2、木榫4、钢榫5,其中,拉环1由钢筋折弯成U形,其U形顶部设有螺纹,拉环1两侧侧壁套装PVC管7后预埋在楼板6混凝土内,拉环1底部包覆有胶带或工程薄膜,PVC管7的直径大于拉环1两侧钢筋的直径。拉环1底部与楼板6底部的模块接触;工字钢3穿过拉环1两侧侧壁之间后挑出墙体;工字钢3底部与楼板6之间垫装有钢榫5,工字钢3两侧侧壁与拉环1两侧内壁之间嵌插有木榫4;工字钢3顶部设有角钢2,角钢2紧压在工字钢3顶部,其两端通过螺栓铰在拉环1两侧侧壁顶部的螺纹上。本实施例的U型环的制作过程可单独加工,不受时间、地点及天气的影响。在安装前在U型竖向杆环套至大一个直径等级的PVC管,用胶带纸包裹好U型拉环底部即可。使用后,在拆除过程中,不影响混凝土结构,拆除方便,其组成部件皆可回收重复利用。拉环在拆除后,在楼板内将会留下洞口。封堵洞口需清理壁内PVC残渣及松动混凝土,然后用高于原混凝土一个标号的微膨胀细石混凝土,先封堵下部1/3,上部2/3在一次性封堵。本方案适用范围广,工业与民用建筑的悬挑脚手架及悬挑卸料平台的拉环均可适用。 The utility model will be further described below in conjunction with all the accompanying drawings. The preferred embodiment of the present utility model is: referring to accompanying drawing 1, the cantilevered steel beam wall-through structure described in this embodiment is characterized in that it includes a pull ring 1. Angle steel 2, wooden tenon 4, and steel tenon 5, wherein the pull ring 1 is bent into a U shape by steel bars, and the top of the U shape is provided with threads, and the side walls on both sides of the pull ring 1 are set with PVC pipes 7 and then embedded in the floor 6 In the concrete, the bottom of the pull ring 1 is covered with adhesive tape or engineering film, and the diameter of the PVC pipe 7 is larger than the diameter of the steel bars on both sides of the pull ring 1. The bottom of the pull ring 1 is in contact with the module at the bottom of the floor 6; the I-shaped steel 3 passes through the side walls on both sides of the pull ring 1 and picks out the wall; the bottom of the I-shaped steel 3 and the floor 6 are padded with a steel tenon 5, A wooden tenon 4 is embedded between the side walls on both sides of the I-beam 3 and the inner walls on both sides of the pull ring 1; the top of the I-beam 3 is provided with an angle steel 2, which is tightly pressed on the top of the I-beam 3, and its two ends are passed through bolts. Hinge on the thread on the top of the side wall on both sides of the pull ring 1. The manufacturing process of the U-shaped ring in this embodiment can be processed independently without being affected by time, place and weather. Before installation, wrap the U-shaped vertical rod ring to a PVC pipe with a larger diameter, and wrap the bottom of the U-shaped pull ring with tape. After use, the concrete structure is not affected during the demolition process, and the demolition is convenient, and its components can be recycled and reused. After the pull ring is removed, an opening will be left in the floor slab. To seal the hole, it is necessary to clean the PVC residue and loose concrete in the wall, and then use micro-expansion fine stone concrete one grade higher than the original concrete to seal the lower 1/3 first, and then seal the upper 2/3 at one time. This scheme has a wide range of applications, and can be applied to the cantilevered scaffolding of industrial and civil buildings and the pull ring of the cantilevered unloading platform.
以上所述之实施例只为本实用新型之较佳实施例,并非以此限制本实用新型的实施范围,故凡依本实用新型之形状、原理所作的变化,均应涵盖在本实用新型的保护范围内。 The above-described embodiments are only preferred embodiments of the present utility model, and are not intended to limit the scope of implementation of the present utility model, so all changes made according to the shape and principle of the present utility model should be covered by the scope of the present utility model. within the scope of protection.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420653128.3U CN204225471U (en) | 2014-11-05 | 2014-11-05 | A kind of cantilever steel girder structure through walls |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420653128.3U CN204225471U (en) | 2014-11-05 | 2014-11-05 | A kind of cantilever steel girder structure through walls |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204225471U true CN204225471U (en) | 2015-03-25 |
Family
ID=52923584
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420653128.3U Expired - Lifetime CN204225471U (en) | 2014-11-05 | 2014-11-05 | A kind of cantilever steel girder structure through walls |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204225471U (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107013032A (en) * | 2017-06-04 | 2017-08-04 | 中国建筑第七工程局有限公司 | A kind of outer builder's jack of antiseep eye pre-embedded device through walls |
| CN107524288A (en) * | 2016-06-20 | 2017-12-29 | 中国二十冶集团有限公司 | The U-shaped anchoring ring construction method of builder's jack |
| CN109441094A (en) * | 2018-12-20 | 2019-03-08 | 上海建工七建集团有限公司 | The fixed pre-embedded device of builder's jack I-steel and its installation method |
| CN113323358A (en) * | 2021-06-11 | 2021-08-31 | 浙江奔腾市政园林建设工程有限公司 | Pull-up type profile steel overhanging scaffold structure and construction method thereof |
-
2014
- 2014-11-05 CN CN201420653128.3U patent/CN204225471U/en not_active Expired - Lifetime
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107524288A (en) * | 2016-06-20 | 2017-12-29 | 中国二十冶集团有限公司 | The U-shaped anchoring ring construction method of builder's jack |
| CN107013032A (en) * | 2017-06-04 | 2017-08-04 | 中国建筑第七工程局有限公司 | A kind of outer builder's jack of antiseep eye pre-embedded device through walls |
| CN109441094A (en) * | 2018-12-20 | 2019-03-08 | 上海建工七建集团有限公司 | The fixed pre-embedded device of builder's jack I-steel and its installation method |
| CN113323358A (en) * | 2021-06-11 | 2021-08-31 | 浙江奔腾市政园林建设工程有限公司 | Pull-up type profile steel overhanging scaffold structure and construction method thereof |
| CN113323358B (en) * | 2021-06-11 | 2022-05-10 | 浙江奔腾市政园林建设工程有限公司 | Pull-up type section steel overhanging scaffold structure and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204225388U (en) | A kind of Protective angle for stairs structure | |
| CN203808484U (en) | Integrated cantilevered and attached external scaffolding | |
| CN204225471U (en) | A kind of cantilever steel girder structure through walls | |
| CN203475806U (en) | Tool type anchoring bolt assembly used for fixing shape steel cantilever beam in construction sites | |
| CN102900021A (en) | Split mounting type bridge wet joint construction method | |
| CN204299162U (en) | To encorbelment steel I-beam anchor structure | |
| CN104032945A (en) | Recyclable rebar anchor pull ring and mounting support thereof | |
| CN202248831U (en) | Flying ring used for lacing diagonal steel wire rope and building structure | |
| CN205348724U (en) | Detachable wire rope rings anchor structure of external scaffolding of encorbelmenting | |
| CN204850414U (en) | Shaped steel of encorbelmenting draws wire rope instrument formula anchor to one side | |
| CN204960289U (en) | Builder's jack is encorbelmented whole combination of girder steel and can be had enough to meet need anchor assembly | |
| CN105507573B (en) | The installation method of shaped steel Overhanging Outside Scaffold | |
| CN204456810U (en) | A kind of gaily decorated basket pull bar suspension scaffold | |
| CN209244242U (en) | A semi-tool-type U-shaped bolt fixing device for a section steel cantilevered scaffold | |
| CN206319597U (en) | A kind of cantilever steel girder erecting device | |
| CN205314534U (en) | Frame post can't harm drawknot steel form structure | |
| CN101761233B (en) | Beam slab template supporting system and concrete column drawknot method | |
| CN203547114U (en) | Wall connecting assembly | |
| CN208202513U (en) | A kind of overhanging I-steel security hardening structure | |
| CN207348426U (en) | A kind of overhanging scaffold easy to girder steel welding | |
| CN204326498U (en) | Screw outrigger oblique pull wire rope fixing device | |
| CN206815804U (en) | A kind of new builder's jack girder steel built-in fitting | |
| CN204571266U (en) | A kind of anchor structure for builder's jack i iron | |
| CN204876565U (en) | Fixed concrete connects simple and easy device of stubble department template | |
| CN202391092U (en) | U-shaped anchor bolt fixing device of overhanging steel beam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CX01 | Expiry of patent term | ||
| CX01 | Expiry of patent term |
Granted publication date: 20150325 |