CN204215634U - Bus duct field engineering actual training device - Google Patents

Bus duct field engineering actual training device Download PDF

Info

Publication number
CN204215634U
CN204215634U CN201420701767.2U CN201420701767U CN204215634U CN 204215634 U CN204215634 U CN 204215634U CN 201420701767 U CN201420701767 U CN 201420701767U CN 204215634 U CN204215634 U CN 204215634U
Authority
CN
China
Prior art keywords
bus duct
training device
actual training
field engineering
engineering actual
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420701767.2U
Other languages
Chinese (zh)
Inventor
杨斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang College of Construction
Original Assignee
Zhejiang College of Construction
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang College of Construction filed Critical Zhejiang College of Construction
Priority to CN201420701767.2U priority Critical patent/CN204215634U/en
Application granted granted Critical
Publication of CN204215634U publication Critical patent/CN204215634U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of bus duct field engineering actual training device, comprise the bus duct be formed by connecting by terminal end socket, straight-line segment, threeway, horizontal curved, vertically curved, top joint of full open model, described bus duct is connected with power distribution cabinet by top joint, bus duct is connected with jack box for power taking.The effect that utility model is useful is: the utility model is a set of bus duct field engineering actual training device reflecting engineering reality, promotes practical teaching.By this cover actual training device, can carry out bus duct connection technique, with power distribution cabinet connection, with multiple practical training project such as crane span structure Joining Technology, vertical shaft mounting process, filled up the deficiency of architectural electricity specialty group teaching median generatrix groove mounting process training skill.

Description

Bus duct field engineering actual training device
Technical field
The utility model relates to a kind of Practical teaching device, especially a kind of bus duct field engineering actual training device.
Background technology
Along with emerging in large numbers of modernization project facility and equipment, the fast increasing of power consumption of all trades and professions, the appearance in especially numerous skyscrapers and large-sized workshop workshop, traditional cable as transmission pressure can not meet the demands in big current induction system, and the parallel connection of multiway cable uses and brings inconvenience to in-site installation construction connection.Plug type bus duct arises at the historic moment as a kind of new distribution wire, bus duct is compared with traditional cable, its superiority is fully demonstrated when big current is carried, simultaneously owing to have employed new technology, new technology, the junction, bus duct both ends greatly reduced and the contact resistance of branching port splicing position and temperature rise, and in bus duct, employ high-quality insulating material, thus improve the safe reliability of bus duct, make whole system more perfect.It is a basis and important content in architectural electricity specialty group that bus duct is installed, and to bus duct field engineering real training never good actual training device, more mainly go study to working-yard, and on-the-spot many field engineerings are all concealed works, be difficult to see, there is danger.
Utility model content
The utility model will solve the shortcoming of above-mentioned prior art, provides a kind of bus duct field engineering actual training device reflecting engineering practice, promote practical teaching.
The utility model solves the technical scheme that its technical matters adopts: this bus duct field engineering actual training device, comprise the bus duct be formed by connecting by terminal end socket, straight-line segment, threeway, horizontal curved, vertically curved, top joint of full open model, described bus duct is connected with power distribution cabinet by top joint, bus duct is connected with jack box for power taking.
As preferably, described bus duct is arranged through the fireproof blocking of wall, and bus duct is through the spring suppport of floor.
As preferably, bus duct is provided with fixed support along wall cabling.
As preferably, the air switch of described power distribution cabinet is connected with top joint by cable, and junction is positioned at top case.
As preferably, described jack box, by the spliced eye place power taking on bus duct, is provided with air switch in jack box.
As preferably, each section of bus duct metal shell adopts copper litz wire to connect and protective ground.
As preferably, the connection that bus duct is each section: show the Joining Technology between each section of bus duct Three-phase five-wire copper bar.
The effect that utility model is useful is: the utility model is a set of bus duct field engineering actual training device reflecting engineering reality, promotes practical teaching.By this cover actual training device, can carry out bus duct connection technique, with power distribution cabinet connection, with multiple practical training project such as crane span structure Joining Technology, vertical shaft mounting process, filled up the deficiency of architectural electricity specialty group teaching median generatrix groove mounting process training skill.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Description of reference numerals: terminal end socket 1, threeway 2, horizontal curved 3, vertically curved 4, top joint 5, top case 6, power distribution cabinet 7, jack box 8, spring suppport 9, fireproof blocking arranges 10, fixed support 11, straight-line segment 12.
Embodiment
Below in conjunction with accompanying drawing, the utility model is described in further detail:
Embodiment:
Actual training device design can show technology and the component of engineering site reality, rationally takies coach concourse again, so this device adopts the 200A air-type bus duct mounting process training skill device that capacity is less, takes up an area about 2 squares.
As described in Figure 1, bus duct system and each connecting link major design: bus duct field engineering actual training device, comprise the bus duct be formed by connecting by terminal end socket 1, straight-line segment 12, threeway 2, horizontal curved 3, vertically curved 4, top joint 5 of full open model, described bus duct one end is top joint 5, and top joint 5 is connected with power distribution cabinet 7.Bus duct is connected with jack box 8.Described bus duct arranges 10 through fireproof blocking, and the spring suppport 9 through floor of bus duct is installed and arranged.Bus duct is provided with fixed support 11 along wall cabling.
This actual training device comprises shows the actual bus duct system of engineering and each connecting link and following mounting process:
Bus duct is connected with power distribution cabinet 7: the air switch comprising power distribution cabinet 7 is by the Joining Technology of cable and bus duct top joint 5, and junction is positioned at top case 6, and top case 6 can be opened and conveniently observe its syndeton.
The mounting process of bus duct vertical shaft: spring suppport 9 mounting process of bus duct through-flooring, spring suppport 9 plays buffer action, prevents sedimentation and causes the bus duct between each floor to rupture; Bus duct arranges the installation plugging technology of 10 through the fireproof blocking of wall, and fireproof blocking arranges 10 and plays buffer action, prevents that floor is on fire to be spread along bus duct.
Busway inserting case 8 power taking technique: described jack box 8 is located at spliced eye place jack box on bus duct 8 and is responsible for getting from bus duct a little, is provided with air switch in jack box 8, and jack box 8 one is inserted in bus duct simultaneously, one what connect is cable.
Bus duct ground connection: the Joining Technology of the copper litz wire of each section of bus duct shell.
The connection of each link of bus duct: show the Joining Technology between each link bus duct Three-phase five-wire copper bar.
In addition to the implementation, the utility model can also have other embodiments.All employings are equal to the technical scheme of replacement or equivalent transformation formation, all drop on the protection domain of the utility model requirement.

Claims (6)

1. a bus duct field engineering actual training device, it is characterized in that: the bus duct be formed by connecting by terminal end socket (1), straight-line segment (12), threeway (2), horizontal curved (3), vertically curved (4), top joint (5) comprising full open model, described bus duct is connected with power distribution cabinet (7) by top joint (5), bus duct is connected with jack box (8) for power taking.
2. bus duct field engineering actual training device according to claim 1, is characterized in that: described bus duct is arranged (10) through the fireproof blocking of wall, and bus duct is through the spring suppport (9) of floor.
3. bus duct field engineering actual training device according to claim 1 and 2, is characterized in that: bus duct is provided with fixed support (11) along wall cabling.
4. bus duct field engineering actual training device according to claim 1 and 2, is characterized in that: the air switch of described power distribution cabinet (7) is connected with top joint (5) by cable, and junction is positioned at top case (6).
5. bus duct field engineering actual training device according to claim 1 and 2, is characterized in that: described jack box (8) is by the spliced eye place power taking on bus duct, and jack box is provided with air switch in (8).
6. bus duct field engineering actual training device according to claim 1 and 2, is characterized in that: each section of bus duct metal shell adopts copper litz wire to connect and protective ground.
CN201420701767.2U 2014-11-20 2014-11-20 Bus duct field engineering actual training device Active CN204215634U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420701767.2U CN204215634U (en) 2014-11-20 2014-11-20 Bus duct field engineering actual training device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420701767.2U CN204215634U (en) 2014-11-20 2014-11-20 Bus duct field engineering actual training device

Publications (1)

Publication Number Publication Date
CN204215634U true CN204215634U (en) 2015-03-18

Family

ID=52984286

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420701767.2U Active CN204215634U (en) 2014-11-20 2014-11-20 Bus duct field engineering actual training device

Country Status (1)

Country Link
CN (1) CN204215634U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104376766A (en) * 2014-11-20 2015-02-25 浙江建设职业技术学院 Bus duct installation technology practical training device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104376766A (en) * 2014-11-20 2015-02-25 浙江建设职业技术学院 Bus duct installation technology practical training device
CN104376766B (en) * 2014-11-20 2017-01-25 浙江建设职业技术学院 Bus duct installation technology practical training device

Similar Documents

Publication Publication Date Title
CN201408939Y (en) Electrified arc extinguishing tool for dismounting and jointing cable tail wires with 10 kV
CN105298201A (en) Electric-transmission-line cable-terminal three-dimensional downwards-leading device
CN203654846U (en) Steel pipe pole used for cable terminal of electric transmission line
CN205116866U (en) Device is down drawn to transmission line cable termination solid
CN203352080U (en) Cable splitter
CN204215634U (en) Bus duct field engineering actual training device
CN204333317U (en) Insulation electricity-inspection ground loop
CN202084665U (en) Portable universal short circuit grounding wire
CN204205494U (en) A kind of high pressure closes common box bus
CN104376766A (en) Bus duct installation technology practical training device
CN204167694U (en) Switch cubicle secondary line routing device
CN103296497A (en) Multi-branch wire connecting board
CN204212513U (en) The support of outdoor power distribution unit
CN204030505U (en) Bus duct
CN203932355U (en) Multifunctional grounded excellent line scan pickup coil side wire clamp
CN203951151U (en) The European front connector of 10kV
CN205194876U (en) Test electricity and touch ring
CN103647164B (en) Multifunctional grounded excellent wire end wire clamp
CN203300991U (en) Wall-mounted distribution box and emergency access system
CN106207530A (en) The complete thread guide devices in a kind of 10KV transformer platform area
CN202444183U (en) Stepped maintenance power box
CN204156468U (en) Drainage thread in a kind of 500kV cubicle
CN204089146U (en) Underground type 10 kv cable splitter
CN105305290A (en) High-safety power cable practical training apparatus
CN203367918U (en) Downlead structure of 500kV HGIS distribution equipment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model