CN204205395U - Cross-arm bracket - Google Patents

Cross-arm bracket Download PDF

Info

Publication number
CN204205395U
CN204205395U CN201420530917.8U CN201420530917U CN204205395U CN 204205395 U CN204205395 U CN 204205395U CN 201420530917 U CN201420530917 U CN 201420530917U CN 204205395 U CN204205395 U CN 204205395U
Authority
CN
China
Prior art keywords
square steel
cross
lead screw
steel tube
steel pipes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420530917.8U
Other languages
Chinese (zh)
Inventor
侯克文
刘庆峰
吴勇
张雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinzhou Power Supply Co of State Grid Liaoning Electric Power Co Ltd
State Grid Corp of China
Original Assignee
Jinzhou Power Supply Co of State Grid Liaoning Electric Power Co Ltd
State Grid Corp of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinzhou Power Supply Co of State Grid Liaoning Electric Power Co Ltd, State Grid Corp of China filed Critical Jinzhou Power Supply Co of State Grid Liaoning Electric Power Co Ltd
Priority to CN201420530917.8U priority Critical patent/CN204205395U/en
Application granted granted Critical
Publication of CN204205395U publication Critical patent/CN204205395U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

一种横担托架,包括二个平行放置的方钢管,在方钢管上设有靠架,每个方钢管的内侧设有二个左右布置的顶紧架,二个方钢管对应的一端铰接有二个上、下错位布置的连接板,二个连接板上设有多个连接位置调整孔,在上下对应的二个调整孔内安装有连接螺栓和螺母,在二个方钢管另一侧设有丝杠,丝杠的后端铰接在后面的方钢管上,所述前面的方钢管对应丝杠的一端开有豁口,所述丝杠前部插入豁口内,在丝杠的前部设有螺纹,通过螺纹安装有锁紧螺母,通过锁紧螺母调整对应该端的二个方钢管之间的距离。有益效果是:结构简单,拆装方便,作业效率高,劳动强度低,安全系数高,杆上一人即可作业。

A cross-arm bracket, including two square steel pipes placed in parallel, a support frame is provided on the square steel pipes, two top tension frames arranged left and right are arranged on the inner side of each square steel pipe, and the corresponding ends of the two square steel pipes are hinged There are two upper and lower connecting plates arranged in dislocation. There are multiple connecting position adjustment holes on the two connecting plates. Connecting bolts and nuts are installed in the two adjustment holes corresponding to the upper and lower sides. On the other side of the two square steel pipes A lead screw is provided, the rear end of the lead screw is hinged on the back square steel pipe, the front square steel pipe has a gap corresponding to one end of the lead screw, the front part of the lead screw is inserted into the gap, and the front part of the lead screw is provided with a There are threads, and lock nuts are installed through the threads, and the distance between the two square steel pipes corresponding to the ends is adjusted through the lock nuts. The beneficial effects are: simple structure, convenient assembly and disassembly, high working efficiency, low labor intensity, high safety factor, and one person on the pole can work.

Description

横担托架Cross Arm Bracket

技术领域 technical field

本实用新型涉及一种横担托架。 The utility model relates to a cross arm bracket.

背景技术 Background technique

横担是架空电力线路上最基本的材料之一,主要的作用是支撑电力线,其使用的范围广、频率高,更换横担、新装横担的作业非常多。电力作业检修更换横担时,主要采用以下两种方法。第一种方法,人员登杆更换横担:需要两人进行,将横担放在安全带上,不稳妥;拆装调整需要用手扶持,人员比较吃力;所需时间30分钟。第二种方法利用高空作业车更换横担,需要用手臂扶持横担本身,人体承受力矩加大,拆装调整更为吃力,容易发生高空坠落。所需时间30分钟。 The cross-arm is one of the most basic materials on the overhead power line. Its main function is to support the power line. It is used in a wide range and has a high frequency. There are many operations to replace the cross-arm and install a new cross-arm. The following two methods are mainly used when replacing the cross-arm in electric power work maintenance. The first method is to replace the cross-arm by climbing on the pole: two people are required, and it is not safe to put the cross-arm on the safety belt; the disassembly and adjustment need to be supported by hands, and the personnel are laborious; the time required is 30 minutes. The second method is to use an aerial work vehicle to replace the cross-arm. It is necessary to support the cross-arm itself with the arm, the human body bears a larger moment, the disassembly and adjustment are more difficult, and it is easy to fall from a height. The time required is 30 minutes.

实用新型内容 Utility model content

本实用新型是要解决现有技术存在的上述问题,提供一种结构简单,拆装方便,作业效率高,劳动强度低,安全系数高,杆上一人即可作业的横担托架。 The utility model aims to solve the above-mentioned problems in the prior art, and provides a cross-arm bracket with simple structure, convenient assembly and disassembly, high working efficiency, low labor intensity, high safety factor, and one person on the pole can work.

本实用新型的技术解决方案是: The technical solution of the utility model is:

一种横担托架,包括二个前后平行放置的方钢管,在方钢管上设有向上伸展的靠架,每个方钢管的内侧设有二个左右布置的顶紧架,二个方钢管对应的一端铰接有二个上、下错位布置的连接板,二个连接板上设有多个连接位置调整孔,在上下对应的二个调整孔内安装有连接螺栓和螺母,在二个方钢管另一侧设有丝杠,丝杠的后端铰接在后面的方钢管上,所述前面的方钢管对应丝杠的一端开有豁口,所述丝杠前部插入豁口内,在丝杠的前部设有螺纹,通过螺纹安装有锁紧螺母,通过锁紧螺母调整对应该端的二个方钢管之间的距离。 A cross-arm bracket, including two square steel pipes placed in parallel front and back, on the square steel pipes, there is an upwardly extending support frame, and the inner side of each square steel pipe is provided with two top tensioning frames arranged left and right, and the two square steel pipes The corresponding one end is hinged with two upper and lower connecting plates arranged in dislocation. The two connecting plates are provided with a plurality of connection position adjustment holes, and connecting bolts and nuts are installed in the two corresponding upper and lower adjustment holes. The other side of the steel pipe is provided with a lead screw, the rear end of the lead screw is hinged on the back square steel pipe, the front square steel pipe corresponding to one end of the lead screw has a gap, the front part of the lead screw is inserted into the gap, The front part is provided with threads, and lock nuts are installed through the threads, and the distance between the two square steel pipes corresponding to the ends is adjusted through the lock nuts.

所述顶紧架为直角三角形,位于同一个方钢管上的顶紧架的直角边相对。 The clamping frame is a right-angled triangle, and the right-angle sides of the clamping frame on the same square steel pipe are opposite to each other.

本实用新型的有益效果是:结构简单,拆装方便,操作灵活,导线规整,大大降低作业人员的劳动强度,作业效率高,更换横担作业时间由30分钟缩短至15分钟; 安全性好,避免因配合不当发生横担脱落事故,杆上一人即可作业,减少了杆上作业人员。 The beneficial effects of the utility model are: simple structure, convenient disassembly and assembly, flexible operation, regular wires, greatly reducing the labor intensity of operators, high operating efficiency, shortening the operating time for changing the cross arm from 30 minutes to 15 minutes; good safety, To avoid the accident of the cross arm falling off due to improper cooperation, one person on the pole can work, reducing the number of operators on the pole.

附图说明 Description of drawings

图1是本实用新型的横担托架的结构示意图; Fig. 1 is the structural representation of cross-arm bracket of the present utility model;

图2是图1的A-A剖视图。 Fig. 2 is an AA sectional view of Fig. 1 .

图中:方钢管1、2,靠架3,顶紧架4,连接板5,连接螺栓6,丝杠7,锁紧螺母8,豁口101,调整孔501。 Among the figure: square steel pipe 1,2, by frame 3, top tight frame 4, connecting plate 5, connecting bolt 6, leading screw 7, lock nut 8, gap 101, adjustment hole 501.

具体实施方式 Detailed ways

如图所示 本实用新型涉及的横担托架,包括二个前后平行放置的方钢管1、2,在方钢管1、2上设有向上伸展的靠架3,每个方钢管1的内侧设有二个左右布置的顶紧架4,二个方钢管1对应的一端铰接有二个上、下错位布置的连接板5,二个连接板5上设有多个连接位置调整孔501,在上下对应的二个调整孔501内安装有连接螺栓6和螺母,在二个方钢管1另一侧设有丝杠7,丝杠7的后端铰接在后面的方钢管2上,所述前面的方钢管1对应丝杠7的一端开有豁口101,所述丝杠7前部插入豁口101内,在丝杠7的前部设有螺纹,通过螺纹安装有锁紧螺母8,通过锁紧螺母8调整对应该端的二个方钢管1、2之间的距离。 As shown in the figure, the cross-arm bracket involved in the utility model includes two square steel pipes 1 and 2 placed in parallel in front and back, on the square steel pipes 1 and 2, there is an upwardly extending support frame 3, and the inner side of each square steel pipe 1 There are two top tensioning frames 4 arranged left and right, and two connecting plates 5 arranged up and down are hinged at the corresponding ends of the two square steel pipes 1. The two connecting plates 5 are provided with a plurality of connection position adjustment holes 501, Connecting bolts 6 and nuts are installed in the two adjustment holes 501 corresponding up and down, and a lead screw 7 is arranged on the other side of the two square steel pipes 1, and the rear end of the lead screw 7 is hinged on the square steel pipe 2 at the back. One end of the front square steel pipe 1 corresponding to the lead screw 7 has a gap 101, the front part of the lead screw 7 is inserted into the gap 101, the front part of the lead screw 7 is provided with threads, and a lock nut 8 is installed through the threads, and the lock nut 8 is installed through the lock. Tight nut 8 adjusts the distance between two square steel pipes 1,2 corresponding to this end.

所述顶紧架4为直角三角形,位于同一个方钢管上的顶紧架4的直角边相对。 The clamping frame 4 is a right-angled triangle, and the right-angled sides of the clamping frame 4 on the same square steel pipe are opposite.

采用该横担托架更换横担时,操作过程如下: When using the cross-arm bracket to replace the cross-arm, the operation process is as follows:

1、更换横担前,将丝杠7打开,将横架托架套在水泥杆上,根据水泥杆规格,调整方钢管1、2对应连接板5侧前后距离,调整后用连接螺栓6和螺母将二个连接板5之间连接; 1. Before replacing the cross arm, open the lead screw 7, put the cross bracket bracket on the cement rod, adjust the front and rear distances of the square steel pipes 1 and 2 corresponding to the side of the connecting plate 5 according to the specifications of the cement rod, and use the connecting bolts 6 and 5 after adjustment. The nut is connected between the two connecting plates 5;

2、由杆上人员用绝缘绳将横担托架升至横担下方靠近横担位置,使一侧靠架3正对旧横担下方,再将丝杠7装入前面的方钢管1的豁口101内并用锁紧螺母8锁紧,使顶紧架4紧紧地卡住水泥杆; 2. The staff on the pole raises the cross-arm bracket to the lower part of the cross-arm and close to the position of the cross-arm with an insulating rope, so that one side of the support frame 3 is directly under the old cross-arm, and then install the screw 7 into the front square steel pipe 1. Lock the gap 101 with the lock nut 8, so that the top clamp 4 tightly blocks the cement rod;

3、用绝缘绳将新横担传至横担托架上并靠在另一侧靠架3上,用抱箍将新横担安装在该侧靠架上方即水泥杆旧横担对面位置,固定好导线; 3. Use the insulating rope to transfer the new cross-arm to the cross-arm bracket and lean on the other side support frame 3. Use the hoop to install the new cross-arm above the side support frame, which is opposite to the old cross-arm of the cement pole. Fix the wire;

4、将旧横担拆下,放在横担托架上并靠在旧横担正下方的靠架3上;用绝缘绳系牢并将旧横担传至地面。 4. Remove the old cross-arm, put it on the cross-arm bracket and lean against the frame 3 directly below the old cross-arm; fasten it with an insulating rope and pass the old cross-arm to the ground.

Claims (2)

1. a cross-arm bracket, comprise the square steel tube of two parallel placements in front and back, it is characterized in that: be provided with on square steel tube stretch upwards by frame, the inner side of each square steel tube be provided with about two arrange hold out against frame, one end that two square steel tubes are corresponding is hinged with on two, the connecting plate that lower dislocation is arranged, two connecting plates are provided with multiple link position adjusting hole, in two corresponding up and down adjusting holes, connecting bolt and nut are installed, leading screw is provided with at two square steel tube opposite sides, the rear end of leading screw is hinged on square steel tube below, one end of the corresponding leading screw of square steel tube before described has gap, described leading screw front portion is inserted in gap, screw thread is provided with in the front portion of leading screw, by screw thread, locking nut is installed, by locking nut adjustment to the distance between two square steel tubes that should hold.
2. cross-arm bracket according to claim 1, is characterized in that: described in hold out against frame be right-angled triangle, the right-angle side holding out against frame be positioned on same square steel tube is relative.
CN201420530917.8U 2014-09-16 2014-09-16 Cross-arm bracket Expired - Fee Related CN204205395U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420530917.8U CN204205395U (en) 2014-09-16 2014-09-16 Cross-arm bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420530917.8U CN204205395U (en) 2014-09-16 2014-09-16 Cross-arm bracket

Publications (1)

Publication Number Publication Date
CN204205395U true CN204205395U (en) 2015-03-11

Family

ID=52663315

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420530917.8U Expired - Fee Related CN204205395U (en) 2014-09-16 2014-09-16 Cross-arm bracket

Country Status (1)

Country Link
CN (1) CN204205395U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106329437A (en) * 2016-10-12 2017-01-11 国网辽宁省电力有限公司鞍山供电公司 10kV cross arm brace of adjustable distribution overhead line and method of use
CN108756435A (en) * 2018-07-21 2018-11-06 国家电网有限公司 Cross-arm locator
CN114905442A (en) * 2022-06-21 2022-08-16 哈尔滨工业大学 Special fixture for loading and positioning high-strength steel wire

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106329437A (en) * 2016-10-12 2017-01-11 国网辽宁省电力有限公司鞍山供电公司 10kV cross arm brace of adjustable distribution overhead line and method of use
CN106329437B (en) * 2016-10-12 2018-02-23 国网辽宁省电力有限公司鞍山供电公司 The adjustable distribution network overhead line cross arm support devices of 10kV and application method
CN108756435A (en) * 2018-07-21 2018-11-06 国家电网有限公司 Cross-arm locator
CN114905442A (en) * 2022-06-21 2022-08-16 哈尔滨工业大学 Special fixture for loading and positioning high-strength steel wire
CN114905442B (en) * 2022-06-21 2024-01-30 哈尔滨工业大学 Special fixture for loading and positioning high-strength steel wire

Similar Documents

Publication Publication Date Title
CN205141520U (en) Split pin remounting specialized tool
CN103944107A (en) Tool for electrified replacement of 500kV strain insulator string
CN204793865U (en) Novel tight line frame of multi -functional distribution lines
CN103117522A (en) Front cable plug separation device
CN203481420U (en) Grounding wire device used for power transmission line overhauling
CN107508192B (en) An adjustable wire inspection pulley
CN103500961B (en) A special tool for live replacement of tension insulator strings
CN203412354U (en) Cross arm clamp
CN105490203A (en) Cross-arm bracket and method for replacing cross arm through employing same
CN203813330U (en) Tool for live-line replacement of 500 kV strain insulator strings
CN103350469B (en) A kind of fan blade mould mismatch control method and device
CN103683098A (en) Method of replacing strain poles without laying down lines
CN204167793U (en) Straight line steel tube tower side, double loop cross-arm jig
CN104253394B (en) A kind of replacing instrument of strain insulator string
CN103520852A (en) Spacing-adjustable safety belt hanging device for disconnecting switch overhaul
CN204144800U (en) The special cross-arm card of a kind of ZML type tower
CN104348100B (en) Substation maintenance platform with multiple installation modes and installation method thereof
CN204651789U (en) The special hanger of hot-line insulator string replacement
CN203942212U (en) wire stretcher special safety clip
CN203205771U (en) Tensioning insulating clamp for live replacement of tension insulator
CN204967124U (en) G5 turriform overhead earth wire lifting mechanism and link fitting change device
CN208835588U (en) A kind of bottle-holding rack fixture
CN205391498U (en) Novel safety belt fixed bolster for power maintenance
CN203415903U (en) Special tool for replacing strain insulator string on hot line
CN203447667U (en) Interval-adjustable safety belt suspension device for maintaining isolating switch

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150311