CN204142777U - Voltage transformer (VT) calibrating termination - Google Patents
Voltage transformer (VT) calibrating termination Download PDFInfo
- Publication number
- CN204142777U CN204142777U CN201420673589.7U CN201420673589U CN204142777U CN 204142777 U CN204142777 U CN 204142777U CN 201420673589 U CN201420673589 U CN 201420673589U CN 204142777 U CN204142777 U CN 204142777U
- Authority
- CN
- China
- Prior art keywords
- terminal
- voltage
- transformer
- voltage transformer
- chip switch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Coils Or Transformers For Communication (AREA)
Abstract
本实用新型公开了一种电压互感器检定用接线装置,其特征在于:包括低压配电盒、单片开关、监视电压表、接线端子和导线,单片开关装于低压配电盒内,所述接线装置的三个输入接线端子接被检互感器测试端子,输出接线端子接互感器校验仪采样端子,其中两个输出接线端子接入监视电压表,用于切换回路时保护互感器校验仪免受冲击电压损坏,使用时通过操作单片开关的通断,在三个不同测量回路间切换。应用本装置只通过一次升压过程,即可完成对多只互感器进行检定,大大提高检定工作效率,减少了人员配置,减少装拆高压测试线的次数,减少高压测试带电时间,降低了试验过程中的安全风险,提高了企业安全效益。
The utility model discloses a wiring device for voltage transformer verification, which is characterized in that it comprises a low-voltage power distribution box, a single-chip switch, a monitoring voltmeter, connecting terminals and wires, and the single-chip switch is installed in the low-voltage power distribution box. The three input terminals of the wiring device are connected to the test terminals of the tested transformer, and the output terminals are connected to the sampling terminals of the transformer calibrator, and two of the output terminals are connected to the monitoring voltmeter, which is used to protect the transformer calibration when switching circuits. The tester is protected from impact voltage damage. When in use, switch between three different measurement circuits by operating the on-off of the single-chip switch. Applying this device can complete the verification of multiple transformers through only one step-up process, which greatly improves the verification work efficiency, reduces the number of personnel configuration, reduces the number of assembly and disassembly of high-voltage test lines, reduces the charging time of high-voltage tests, and reduces the test time. The safety risks in the process have been improved, and the safety benefits of the enterprise have been improved.
Description
技术领域 technical field
本实用新型涉及电压互感器检定技术领域。 The utility model relates to the technical field of voltage transformer verification.
背景技术 Background technique
电压互感器的作用是把高电压按比例关系变换成100V或更低等级的标准二次电压,供保护、计量、仪表装置使用,同时,使用电压互感器可以将高电压与电气工作人员隔离,保障了人员安全。由于上述功能,电压互感器广泛使用在电力的发电、输配电领域。在供计量、仪表装置使用时,为了计量或仪表数值的准确,则必然需要定期对电压互感器做计量检定,否则无法保证其准确性,造成保护误动、计量差错等。在检定过程中,需要依次连接交流电源、调压器、升压器和标准电压互感器,标准电压互感器再与被测电压互感器连接,一只标准电压互感器在每一次升降压过程中,只能检定一只被检电压互感器,而现场一般每组互感器为两到三只,需要多次装拆高压测试线,进行多次升高压过程,需要多个检定工作人员配合,带高压操作时间长,安全风险高,检定工作效率低。 The function of the voltage transformer is to transform the high voltage into a standard secondary voltage of 100V or lower in proportion to the use of protection, metering, and instrumentation devices. At the same time, the high voltage can be isolated from the electrical workers by using the voltage transformer. The safety of personnel is guaranteed. Due to the above functions, voltage transformers are widely used in the fields of power generation, transmission and distribution. When used for metering and instrumentation devices, in order to measure or measure accurately, it is necessary to regularly perform metering verification on voltage transformers, otherwise the accuracy cannot be guaranteed, resulting in protection malfunctions and metering errors. During the verification process, it is necessary to connect the AC power supply, the voltage regulator, the booster and the standard voltage transformer in sequence, and the standard voltage transformer is then connected to the voltage transformer under test. In the process, only one tested voltage transformer can be verified, and there are usually two to three transformers in each group on site. It needs to assemble and disassemble the high-voltage test line many times, and carry out the process of raising the voltage multiple times. It requires the cooperation of multiple verification staff. The operation time with high voltage is long, the safety risk is high, and the verification work efficiency is low.
实用新型内容 Utility model content
本实用新型要解决的技术问题是提供一种电压互感器检定用接线装置,只通过一次升压过程,即可完成对两只或三只互感器进行检定,大大提高检定工作效率,降低安全风险。 The technical problem to be solved by the utility model is to provide a wiring device for the verification of voltage transformers, which can complete the verification of two or three transformers only through one boosting process, greatly improving the verification work efficiency and reducing safety risks .
为解决上述技术问题,本实用新型所采取的技术方案是:一种电压互感器检定用接线装置,其特征在于:包括低压配电盒、单片开关、监视电压表、接线端子和导线,单片开关装于低压配电盒内,第一输入接线端子与第一输出接线端子之间串联第二单片开关,第二输入接线端子与第一输出接线端子之间串联第四单片开关,第一输入接线端子与第二输出接线端子之间串联第一单片开关,第二输入接线端子与第二输出接线端子之间串联第三单片开关,第二输出接线端子和第三输出接线端子之间串联监视电压表,所述第一输入接线端子和第二输入接线端子分别用来连接两只被检定电压互感器的二次绕线端子,所述第一输出接线端子和第三输出接线端子连接互感器校验仪。 In order to solve the above technical problems, the technical solution adopted by the utility model is: a wiring device for voltage transformer verification, which is characterized in that it includes a low-voltage power distribution box, a single-chip switch, a monitoring voltmeter, a terminal block and a wire, and a single The chip switch is installed in the low-voltage distribution box, the second single-chip switch is connected in series between the first input terminal and the first output terminal, and the fourth single-chip switch is connected in series between the second input terminal and the first output terminal. The first single-chip switch is connected in series between the first input connection terminal and the second output connection terminal, the third single-chip switch is connected in series between the second input connection terminal and the second output connection terminal, and the second output connection terminal and the third output connection terminal are connected in series. Monitor the voltmeter in series between the terminals, the first input terminal and the second input terminal are respectively used to connect the secondary winding terminals of two verified voltage transformers, the first output terminal and the third output terminal Connect the terminal to the transformer calibrator.
在电压互感器检定时,将交流电源、调压器、升压器和标准电压互感器依次进行连接,将标准电压互感器的一次线圈和两只待测电压互感器的一次线圈并联,标准电压互感器的的二次线圈x0端和互感器校验仪的x端连接,标准电压互感器的的二次线圈a0端、两只待测电压互感器的二次线圈a1端和a2端分别与互感器校验仪的a端连接,待测电压互感器一的二次线圈x1端连接所述接线装置的第一输入接线端子,待测电压互感器二的二次线圈x2端连接所述接线装置的第二输入接线端子,第一输出接线端子与互感器校验仪的D端连接,第三输出接线端子与互感器校验仪的K端连接,互感器校验仪的D端和a端之间串联阻抗,接线装置的单片开关常置为断开。检定待测电压互感器一时先合上第一单片开关,电压表指示不大于5%时认为极性及接线正确,断开第一单片开关,合上第二单片开关,此时互感器校验仪测量回路接通可从互感器校验仪测出待测电压互感器一的误差,测量后断开第二单片开关;检定待测电压互感器二时先合上第三单片开关,电压表指示不大于5%时认为极性及接线正确,断开第三单片开关,合上第四单片开关,此时互感器校验仪测量回路接通可从互感器校验仪测出待测电压互感器二的误差,测量后断开第四单片开关。 When verifying the voltage transformer, connect the AC power supply, the voltage regulator, the booster and the standard voltage transformer in sequence, connect the primary coil of the standard voltage transformer and the primary coils of the two voltage transformers to be tested in parallel, and the standard voltage The secondary coil x 0 terminal of the transformer is connected to the x terminal of the transformer calibrator, the secondary coil a 0 terminal of the standard voltage transformer, the secondary coil a 1 terminal of the two voltage transformers to be tested and a The 2 terminals are respectively connected to the a terminal of the transformer calibrator, the secondary coil x of the voltage transformer to be tested is connected to the first input terminal of the wiring device, and the secondary coil of the voltage transformer to be tested is x The 2 terminals are connected to the second input terminal of the wiring device, the first output terminal is connected to the D terminal of the transformer calibrator, the third output terminal is connected to the K terminal of the transformer calibrator, and the transformer calibrator The series impedance between the D terminal and the A terminal of the instrument, the monolithic switch of the wiring device is always set to open. When verifying the voltage transformer to be tested, first close the first single-chip switch. When the voltmeter indicates that it is not more than 5%, it is considered that the polarity and wiring are correct. Turn off the first single-chip switch and close the second single-chip switch. At this time, the mutual inductance The error of the voltage transformer 1 to be tested can be measured from the transformer calibrator when the measurement circuit of the instrument calibrator is connected, and the second single-chip switch is disconnected after measurement; when the voltage transformer 2 to be tested is verified, the third single-chip switch is first closed When the indication of the voltmeter is not more than 5%, it is considered that the polarity and wiring are correct. Turn off the third single-chip switch and close the fourth single-chip switch. At this time, the measurement circuit of the transformer calibrator is connected. The tester measures the error of the second voltage transformer to be tested, and disconnects the fourth single-chip switch after measurement.
作为本技术方案的一种改进,一种电压互感器检定用接线装置,其特征在于:还包括第三输入接线端子与第一输出接线端子之间串联第六单片开关,第三输入接线端子与第二输出接线端子之间串联第五单片开关,所述第三输入接线端子连接第三只被检定电压互感器的二次绕线端子。 As an improvement of this technical solution, a wiring device for voltage transformer verification is characterized in that it also includes a sixth single-chip switch connected in series between the third input terminal and the first output terminal, and the third input terminal The fifth monolithic switch is connected in series with the second output connection terminal, and the third input connection terminal is connected to the secondary winding terminal of the third verified voltage transformer.
在电压互感器检定时,将交流电源、调压器、升压器和标准电压互感器依次进行连接,将标准电压互感器的一次线圈和待测电压互感器的一次线圈并联,标准电压互感器的的二次线圈x0端和互感器校验仪的x端连接,标准电压互感器的的二次线圈a0端、三个待测电压互感器的二次线圈a1端、a2端和a3端分别与互感器校验仪的a端连接,待测电压互感器一的二次线圈x1端连接所述接线装置的第一输入接线端子,待测电压互感器二的二次线圈x2端连接所述接线装置的第二输入接线端子,待测电压互感器三的二次线圈x3端连接所述接线装置的第三输入接线端子,第一输出接线端子与互感器校验仪的D端连接,第三输出接线端子与互感器校验仪的K端连接,互感器校验仪的D端和a端之间串联阻抗,接线装置的单片开关常置为断开。检定待测电压互感器一时先合上第一单片开关,电压表指示不大于5%时认为极性及接线正确,断开第一单片开关,合上第二单片开关,此时互感器校验仪测量回路接通可从互感器校验仪测出待测电压互感器一的误差,测量后断开第二单片开关;检定待测电压互感器二时先合上第三单片开关,电压表指示不大于5%时认为极性及接线正确,断开第三单片开关,合上第四单片开关,此时互感器校验仪测量回路接通可从互感器校验仪测出待测电压互感器二的误差,测量后断开第四单片开关;检定待测电压互感器三时先合上第五单片开关,电压表指示不大于5%时认为极性及接线正确,断开第五单片开关,合上第六单片开关,此时互感器校验仪测量回路接通可从互感器校验仪测出待测电压互感器三的误差,测量后断开第六单片开关。 When verifying the voltage transformer, connect the AC power supply, voltage regulator, booster and standard voltage transformer in sequence, connect the primary coil of the standard voltage transformer and the primary coil of the voltage transformer to be tested in parallel, and connect the standard voltage transformer Connect the terminal x 0 of the secondary coil to the terminal x of the transformer calibrator, the terminal a 0 of the secondary coil of the standard voltage transformer, the terminals a 1 and a 2 of the secondary coils of the three voltage transformers to be tested and a 3 terminals are respectively connected to the a terminal of the transformer calibrator, the secondary coil x 1 terminal of the voltage transformer to be tested is connected to the first input terminal of the wiring device, and the secondary coil of the voltage transformer to be tested The coil x 2 ends are connected to the second input terminal of the wiring device, the secondary coil x 3 of the voltage transformer to be tested is connected to the third input terminal of the wiring device, and the first output terminal is connected to the transformer calibrating terminal. The D terminal of the transformer calibrator is connected, the third output terminal is connected to the K terminal of the transformer calibrator, the impedance is connected in series between the D terminal and the a terminal of the transformer calibrator, and the single-chip switch of the wiring device is always set to off. When verifying the voltage transformer to be tested, first close the first single-chip switch. When the voltmeter indicates that it is not more than 5%, it is considered that the polarity and wiring are correct. Turn off the first single-chip switch and close the second single-chip switch. At this time, the mutual inductance The error of the voltage transformer 1 to be tested can be measured from the transformer calibrator when the measurement circuit of the instrument calibrator is connected, and the second single-chip switch is disconnected after measurement; when the voltage transformer 2 to be tested is verified, the third single-chip switch is first closed When the indication of the voltmeter is not more than 5%, it is considered that the polarity and wiring are correct. Turn off the third single-chip switch and close the fourth single-chip switch. At this time, the measurement circuit of the transformer calibrator is connected. The tester measures the error of the second voltage transformer to be tested, and disconnects the fourth single-chip switch after measurement; when verifying the third voltage transformer to be tested, first close the fifth single-chip switch, and when the voltmeter indicates that it is not greater than 5%, it is considered extremely The sex and wiring are correct, turn off the fifth single-chip switch, close the sixth single-chip switch, at this time, the measurement circuit of the transformer calibrator is connected, and the error of the voltage transformer three to be tested can be measured from the transformer calibrator. Open the sixth monolithic switch after measurement.
采用上述技术方案所产生的有益效果在于:应用本装置只通过一次升压过程,即可完成对多只互感器进行检定,大大提高检定工作效率,减少了人员配置,减少装拆高压测试线的次数,减少高压测试带电时间,降低了试验过程中的安全风险,提高了企业安全效益。 The beneficial effect of adopting the above-mentioned technical scheme is that: the application of this device can complete the verification of multiple transformers through only one step-up process, which greatly improves the verification work efficiency, reduces the staffing, and reduces the installation and disassembly of high-voltage test lines. The number of times, reducing the electrification time of the high-voltage test, reduces the safety risk during the test process, and improves the safety benefits of the enterprise.
附图说明 Description of drawings
图1是本实用新型的结构示意图; Fig. 1 is a structural representation of the utility model;
图2是本实用新型的电路示意图。 Fig. 2 is a schematic circuit diagram of the utility model.
1、第一单片开关;2、第二单片开关;3、第三单片开关;4、第四单片开关;5、第五单片开关;6、第六单片开关;7、第一输入接线端子;8、第二输入接线端子;9、第三输入接线端子;10、第一输出接线端子;11、第二输出接线端子;12、第三输出接线端子;13、监视电压表;14、待测电压互感器;15、标准电压互感器;16、升压器;17、调压器;18、交流电源;19、互感器校验仪;20、接线装置; 1. The first single-chip switch; 2. The second single-chip switch; 3. The third single-chip switch; 4. The fourth single-chip switch; 5. The fifth single-chip switch; 6. The sixth single-chip switch; 7. The first input terminal; 8. The second input terminal; 9. The third input terminal; 10. The first output terminal; 11. The second output terminal; 12. The third output terminal; 13. Monitoring voltage Table; 14. Voltage transformer to be tested; 15. Standard voltage transformer; 16. Booster; 17. Voltage regulator; 18. AC power supply; 19. Transformer calibrator; 20. Wiring device;
下面结合附图和具体实施方式对本实用新型作进一步详细的说明。 Below in conjunction with accompanying drawing and specific embodiment, the utility model is described in further detail.
具体实施方式 Detailed ways
具体实施方式一 Specific implementation mode one
电压互感器检定用接线装置,包括低压配电盒、四个单片开关、一个监视电压表13、接线端子和导线,单片开关装于低压配电盒内,第一输入接线端子7与第一输出接线端子10之间串联第二单片开关2,第二输入接线端子8与第一输出接线端子10之间串联第四单片开关4,第一输入接线端子7与第二输出接线端子11之间串联第一单片开关1,第二输入接线端子8与第二输出接线端子11之间串联第三单片开关3,第二输出接线端子11和第三输出接线端子12之间串联监视电压表13。 The wiring device for voltage transformer verification includes a low-voltage power distribution box, four single-chip switches, a monitoring voltmeter 13, terminals and wires, the single-chip switch is installed in the low-voltage power distribution box, the first input terminal 7 and the second The second single-chip switch 2 is connected in series between an output connection terminal 10, the fourth single-chip switch 4 is connected in series between the second input connection terminal 8 and the first output connection terminal 10, and the first input connection terminal 7 and the second output connection terminal The first single-chip switch 1 is connected in series between 11, the third single-chip switch 3 is connected in series between the second input terminal 8 and the second output terminal 11, and the second output terminal 11 and the third output terminal 12 are connected in series Monitor voltmeter 13.
在对两只电压互感器检定时,将交流电源18、调压器17、升压器16和标准电压互感器15依次进行连接,将标准电压互感器15的一次线圈和两只待测电压互感器的一次线圈并联,标准电压互感器15的的二次线圈x0端和互感器校验仪19的x端连接,标准电压互感器15的的二次线圈a0端、两只待测电压互感器的二次线圈a1端和a2端分别与互感器校验仪19的a端连接,待测电压互感器一的二次线圈x1端连接所述接线装置的第一输入接线端子7,待测电压互感器二的二次线圈x2端连接所述接线装置的第二输入接线端子8,第一输出接线端子10与互感器校验仪19的D端连接,第三输出接线端子12与互感器校验仪19的K端连接,互感器校验仪19的D端和a端之间串联阻抗,接线装置的单片开关常置为断开。检定待测电压互感器一时先合上第一单片开关1,电压表指示不大于5%时认为极性及接线正确,断开第一单片开关1,合上第二单片开关2,此时互感器校验仪19测量回路接通可从互感器校验仪19测出待测电压互感器一的误差,测量后断开第二单片开关2;检定待测电压互感器二时先合上第三单片开关3,电压表指示不大于5%时认为极性及接线正确,断开第三单片开关3,合上第四单片开关4,此时互感器校验仪19测量回路接通可从互感器校验仪19测出待测电压互感器二的误差,测量后断开第四单片开关4。 When verifying the two voltage transformers, connect the AC power supply 18, the voltage regulator 17, the booster 16 and the standard voltage transformer 15 in sequence, and connect the primary coil of the standard voltage transformer 15 and the two voltage transformers to be tested. The primary coil of the standard voltage transformer 15 is connected in parallel with the secondary coil x 0 terminal of the standard voltage transformer 15 and the x terminal of the transformer calibrator 19, the secondary coil a 0 terminal of the standard voltage transformer 15, two voltages to be measured Terminal a1 and terminal a2 of the secondary coil of the transformer are respectively connected to terminal a of the transformer calibrator 19, and terminal x1 of the secondary coil of the voltage transformer to be tested is connected to the first input terminal of the wiring device 7. The secondary coil x 2 of the voltage transformer to be tested is connected to the second input terminal 8 of the wiring device, the first output terminal 10 is connected to the D terminal of the transformer calibrator 19, and the third output connection The terminal 12 is connected to the K terminal of the transformer calibrator 19, and the impedance is connected in series between the D terminal and the a terminal of the transformer calibrator 19, and the monolithic switch of the wiring device is always set to be disconnected. To test the voltage transformer to be tested, first close the first single-chip switch 1, and when the voltmeter indicates that it is not more than 5%, it is considered that the polarity and wiring are correct, disconnect the first single-chip switch 1, and close the second single-chip switch 2, Now the transformer calibrator 19 measurement loops are connected and can measure the error of the voltage transformer to be measured from the transformer calibrator 19, and disconnect the second monolithic switch 2 after the measurement; First close the third single-chip switch 3, when the indication of the voltmeter is not more than 5%, it is considered that the polarity and wiring are correct, disconnect the third single-chip switch 3, and close the fourth single-chip switch 4, at this time the transformer calibrator 19 When the measurement circuit is connected, the error of the voltage transformer 2 to be tested can be measured from the transformer calibrator 19, and the fourth single-chip switch 4 is disconnected after the measurement.
具体实施方式二 Specific implementation mode two
作为具体实施方式一的一种改进,一种电压互感器检定用接线装置,其特征在于:还包括第三输入接线端子9与第一输出接线端子10之间串联第六单片开关6,第三输入接线端子9与第二输出接线端子11之间串联第五单片开关5,所述第三输入接线端子9连接待检定电压互感器三的二次绕线端子,待检定电压互感器三的二次线圈a3端与互感器校验仪19的a端连接,待测电压互感器三的二次线圈x3端连接所述接线装置的第三输入接线端子9。其余连接方式与具体实施方式一相同。 As an improvement of the first specific embodiment, a wiring device for voltage transformer verification is characterized in that it also includes a sixth single-chip switch 6 connected in series between the third input terminal 9 and the first output terminal 10, the first The fifth single-chip switch 5 is connected in series between three input terminals 9 and the second output terminal 11, and the third input terminal 9 is connected to the secondary winding terminal of the voltage transformer three to be verified, and the voltage transformer three to be verified The terminal a 3 of the secondary coil of the voltage transformer to be tested is connected to the terminal a of the transformer calibrator 19, and the terminal x 3 of the secondary coil of the voltage transformer to be tested is connected to the third input terminal 9 of the wiring device. The remaining connection modes are the same as those in the first embodiment.
检定待测电压互感器三时先合上第五单片开关5,电压表指示不大于5%时认为极性及接线正确,断开第五单片开关5,合上第六单片开关6,此时互感器校验仪19测量回路接通可从互感器校验仪19测出待测电压互感器三的误差,测量后断开第六单片开关6。 When verifying the voltage transformer to be tested, first close the fifth single-chip switch 5, and when the voltmeter indicates that the polarity and wiring are not greater than 5%, disconnect the fifth single-chip switch 5 and close the sixth single-chip switch 6 At this time, the transformer calibrator 19 measuring circuit is connected and the error of the voltage transformer three to be tested can be measured from the transformer calibrator 19, and the sixth single-chip switch 6 is disconnected after measurement.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420673589.7U CN204142777U (en) | 2014-11-06 | 2014-11-06 | Voltage transformer (VT) calibrating termination |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420673589.7U CN204142777U (en) | 2014-11-06 | 2014-11-06 | Voltage transformer (VT) calibrating termination |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN204142777U true CN204142777U (en) | 2015-02-04 |
Family
ID=52419457
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420673589.7U Expired - Lifetime CN204142777U (en) | 2014-11-06 | 2014-11-06 | Voltage transformer (VT) calibrating termination |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN204142777U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104297532A (en) * | 2014-11-06 | 2015-01-21 | 国家电网公司 | Wiring device for detecting voltage transformer |
| CN110927649A (en) * | 2019-12-02 | 2020-03-27 | 云南电网有限责任公司玉溪供电局 | A modular verification device for voltage transformers |
| CN111929526A (en) * | 2020-07-29 | 2020-11-13 | 国网冀北电力有限公司计量中心 | Electronic voltage transformer calibration system and method |
-
2014
- 2014-11-06 CN CN201420673589.7U patent/CN204142777U/en not_active Expired - Lifetime
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104297532A (en) * | 2014-11-06 | 2015-01-21 | 国家电网公司 | Wiring device for detecting voltage transformer |
| CN104297532B (en) * | 2014-11-06 | 2017-03-08 | 国家电网公司 | Voltage transformer calibrating termination |
| CN110927649A (en) * | 2019-12-02 | 2020-03-27 | 云南电网有限责任公司玉溪供电局 | A modular verification device for voltage transformers |
| CN111929526A (en) * | 2020-07-29 | 2020-11-13 | 国网冀北电力有限公司计量中心 | Electronic voltage transformer calibration system and method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104297532B (en) | Voltage transformer calibrating termination | |
| CN205103361U (en) | High voltage electric energy metering device detector of working a telephone switchboard | |
| CN204116545U (en) | A kind of equal compression testing device of thyristor unit of converter valve | |
| CN101806848A (en) | Detection device for preventing mis-wiring of voltage transformer and detection method thereof | |
| CN105510714A (en) | Intelligent substation pressure transmitter secondary automatic phase tester | |
| CN104749484B (en) | Leakage monitoring device | |
| CN204142777U (en) | Voltage transformer (VT) calibrating termination | |
| CN103487617B (en) | Three-phase once logical pressure and the most through-flow device | |
| CN202502242U (en) | Error measurement device for voltage transformer | |
| CN105548821A (en) | Lightning arrester live detection method | |
| CN204359883U (en) | A kind of transformer multifunctional tester | |
| CN103323808A (en) | Simple faulted electric energy meter test method and device | |
| CN104111438B (en) | Primary large-current loop monitoring method in current transformer error test | |
| CN204203447U (en) | A kind of voltage transformer error of safety and environmental protection measures training set | |
| CN104698335A (en) | Method for realizing systematic debugging of high-voltage transformer substation by using low-voltage electricity | |
| CN106546940A (en) | A kind of field testing procedure of optical voltage transformer | |
| CN103983936B (en) | A kind of single three-phase electric energy meter integration calibration equipment | |
| CN203950029U (en) | The integrated calibration equipment of a kind of novel single three-phase electric energy meter | |
| CN201757762U (en) | Circuit breaker tripping and closing voltage tester | |
| CN204945358U (en) | A kind of various dimensions information monitoring instrument for current mutual inductor on site verification | |
| CN202870285U (en) | A portable simulation detection device of high-voltage live display apparatuses | |
| CN204789785U (en) | Portable intelligent substation relay protection testing arrangement | |
| CN116908768A (en) | A comprehensive experimental system for error calibration of low-voltage current transformers resistant to DC bias magnetism | |
| CN102323563A (en) | Secondary current loop checking method of sealing type switching cabinet in power substation | |
| CN203519812U (en) | Current transformer on-site verifying unit |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| AV01 | Patent right actively abandoned | ||
| AV01 | Patent right actively abandoned |
Granted publication date: 20150204 Effective date of abandoning: 20171114 |