CN204139173U CN201420643736.6U CN201420643736U CN204139173U CN 204139173 U CN204139173 U CN 204139173U CN 201420643736 U CN201420643736 U CN 201420643736U CN 204139173 U CN204139173 U CN 204139173U
Authority
CN
China
Prior art keywords
grouting
backfill
contact
high pressure
major diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420643736.6U
Other languages
Chinese (zh)
Inventor
邱云
杨怀德
苟芳蓉
石江涛
刘宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201420643736.6U priority Critical patent/CN204139173U/en
Application granted granted Critical
Publication of CN204139173U publication Critical patent/CN204139173U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of major diameter high pressure duct grouting structure, particularly a kind of major diameter high pressure duct grouting structure being applied to the realm of building construction.The utility model provides a kind of structure simple, does not need reserved perforate on steel lining, simple to operate, effectively can save the major diameter high pressure duct grouting structure of duration.Comprise steel lining, contact grouting pipeline and backfill grouting pipeline; The contact grouting arm that described contact grouting pipeline comprises contact grouting supervisor and formed by contact grouting supervisor branch, described contact grouting arm is arranged on the outer wall of steel lining; The backfill grouting arm that described backfill grouting pipeline comprises backfill grouting supervisor and formed by backfill grouting supervisor branch, described backfill grouting arm is arranged on the outer wall of steel lining.The making and the sealing of hole welding procedure that eliminate steel lining are complicated, greatly reduce the requirement of environment temperature and humidity higher, have saved the construction period.

Description

Major diameter high pressure duct grouting structure
Technical field
The utility model relates to a kind of major diameter high pressure duct grouting structure and grouting method, particularly a kind of major diameter high pressure duct grouting structure and grouting method being applied to the realm of building construction.
Background technology
The novel grouting way of high pressure pipeline that the utility model relates to, refers to and is applicable to high water head, large discharge, major diameter and 10m and above diameter, needs the water delivery pressure diversion road of higher-strength steel lining, the pressure pipeline especially in Hydraulic and Hydro-Power Engineering.The head of this kind of derivation conduit or pipeline and the long-pending often comparatively large of diameter, at 3000mm 2above, the steel lining tensile strength of employing is higher than 610MPa.Relative to Traditional project experience, concrete backfill grouting, country rock consolidation grouting and steel plate contact grouting need reserved perforate on steel lining, and perform hole of going forward side by side mouth is reinforced, the making of steel lining and sealing of hole welding procedure complexity, higher to the requirement of environment temperature and humidity, unfavorable to the construction period.Therefore also do not have a kind of structure simple in prior art, do not need reserved perforate on steel lining, simple to operate, effectively can save the major diameter high pressure duct grouting structure of duration.
Utility model content
It is simple that technical problem to be solved in the utility model is to provide a kind of structure, do not need reserved perforate on steel lining, simple to operate, effectively can save the major diameter high pressure duct grouting structure of duration.
For solving the problems of the technologies described above, the major diameter high pressure duct grouting structure that the utility model adopts, comprises steel lining, contact grouting pipeline and backfill grouting pipeline; The contact grouting arm that described contact grouting pipeline comprises contact grouting supervisor and formed by contact grouting supervisor branch, described contact grouting supervisor is arranged on the outer wall of steel lining; The backfill grouting arm that described backfill grouting pipeline comprises backfill grouting supervisor and formed by backfill grouting supervisor branch, described backfill grouting supervisor is arranged on the outer wall of steel lining.
Further, also comprise contact grouting stiffening ring, described contact grouting stiffening ring is responsible for contact grouting and is fixedly connected with.
Further, also comprise contact grouting plain steel-bar, described contact grouting plain steel-bar is fixedly connected with contact grouting arm, and the two ends of contact grouting plain steel-bar are fixedly connected with contact grouting stiffening ring.
Further, also comprise backfill grouting stiffening ring, described backfill grouting stiffening ring is responsible for backfill grouting and is fixedly connected with.
Further, also comprise backfill grouting plain steel-bar, described backfill grouting plain steel-bar is fixedly connected with backfill grouting arm, and the two ends of backfill grouting plain steel-bar are fixedly connected with backfill grouting stiffening ring.
Further, also comprise steel mesh reinforcement, described steel mesh reinforcement is arranged on the outer wall of steel lining.
Further, the mouth of pipe of described backfill grouting arm is horn mouth.
The beneficial effects of the utility model are: the utility model is the novel grouting way of major diameter high pressure pipeline, steel pipe can according to underground buried tube Theoretical Design, steel pipe, concrete lining, country rock shared internal water pressure, steel plate thickness is thinner, the dry requirement of steel pipe site operation environment can be reduced simultaneously, thus reduce costs.Owing to not needing plugging holes to weld, can the reduction of erection time, thus play project benefit in advance as generating, water delivery.The process such as perforate are not carried out to high strength steel plate, the performance of high-strength steel can be guaranteed, welding especially can be avoided to occur crackle, and bring potential safety hazard to engineering.
Accompanying drawing explanation
Fig. 1 is contact grouting of the present utility model and backfill grouting main line arrangement diagram;
Fig. 2 is the utility model backfill grouting arm arrangement diagram;
Fig. 3 is the utility model contact grouting arm arrangement diagram;
Component, position and numbering in figure: steel lining 1, contact grouting supervisor 2, contact grouting arm 3, contact grouting stiffening ring 4, contact grouting plain steel-bar 5, backfill grouting supervisor 6, backfill grouting arm 7, backfill grouting plain steel-bar 8.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described in further detail.
For solving the problems of the technologies described above, the major diameter high pressure duct grouting structure that the utility model adopts, comprises steel lining 1, contact grouting pipeline and backfill grouting pipeline; Described contact grouting pipeline comprises contact grouting supervisor 2 and is responsible for by contact grouting the contact grouting arm 3 that 2 branches are formed, and described contact grouting is responsible for 2 and is arranged on the outer wall of steel lining 1; Described backfill grouting pipeline comprises backfill grouting supervisor 6 and is responsible for by backfill grouting the backfill grouting arm 7 that 6 branches are formed, and described backfill grouting is responsible for 6 and is arranged on the outer wall of steel lining 1.Owing to have employed contact grouting pipeline and backfill grouting pipeline, slurries are filled into the position of setting under the guiding of contact grouting pipeline and backfill grouting pipeline, so just do not need reserved perforate on steel lining 1, perform hole of going forward side by side mouth is reinforced, the making and the sealing of hole welding procedure that eliminate steel lining 1 are complicated, greatly reduce the requirement of environment temperature and humidity higher, saved the construction period.Adopt supervisor to add the form of structure of arm, both facilitated the injection of slurries, and can ensure again can flow to from slurries each position set.
Also comprise contact grouting stiffening ring 4, described contact grouting stiffening ring 4 and contact grouting are responsible for 2 and are fixedly connected with.Contact grouting stiffening ring 4 be used for strengthen supervisor structural strength.
Also comprise contact grouting plain steel-bar 5, described contact grouting plain steel-bar 5 is fixedly connected with contact grouting arm 3, and the two ends of contact grouting plain steel-bar 5 are fixedly connected with contact grouting stiffening ring 4.Contact grouting plain steel-bar 5 and contact grouting stiffening ring 4 combinationally use, and form a firm permanent piping system again, the fastness of total and stability are got a promotion.
Also comprise backfill grouting stiffening ring, described backfill grouting stiffening ring and contact grouting are responsible for 2 and are fixedly connected with.Backfill grouting stiffening ring be used for strengthen supervisor structural strength.
Also comprise backfill grouting plain steel-bar 8, described backfill grouting plain steel-bar 8 is fixedly connected with backfill grouting arm 7, and the two ends of backfill grouting plain steel-bar 8 are fixedly connected with backfill grouting stiffening ring.Backfill grouting plain steel-bar 8 and backfill grouting stiffening ring combinationally use, and form a firm permanent piping system again, the fastness of total and stability are got a promotion.
Also comprise steel mesh reinforcement, described steel mesh reinforcement is arranged on the outer wall of steel lining 1.The steel mesh reinforcement set up can increase the intensity of structure.
The mouth of pipe of described backfill grouting arm 7 is horn mouth.The mouth of pipe of arm is set to horn mouth, is convenient to slurries and flows out from arm.

Claims (7)

1. major diameter high pressure duct grouting structure, is characterized in that: comprise steel lining (1), contact grouting pipeline and backfill grouting pipeline; The contact grouting arm (3) that described contact grouting pipeline comprises contact grouting supervisor (2) and formed by contact grouting supervisor (2) branch, described contact grouting supervisor (3) is arranged on the outer wall of steel lining (1); The backfill grouting arm (7) that described backfill grouting pipeline comprises backfill grouting supervisor (6) and formed by backfill grouting supervisor (6) branch, described backfill grouting supervisor (7) is arranged on the outer wall of steel lining (1).
2. major diameter high pressure duct grouting structure as claimed in claim 1, it is characterized in that: also comprise contact grouting stiffening ring (4), described contact grouting stiffening ring (4) is responsible for (2) and is fixedly connected with contact grouting.
3. major diameter high pressure duct grouting structure as claimed in claim 2, it is characterized in that: also comprise contact grouting plain steel-bar (5), described contact grouting plain steel-bar (5) is fixedly connected with contact grouting arm (3), and the two ends of contact grouting plain steel-bar (5) are fixedly connected with contact grouting stiffening ring (4).
4. major diameter high pressure duct grouting structure as claimed in claim 1, it is characterized in that: also comprise backfill grouting stiffening ring, described backfill grouting stiffening ring is responsible for (6) and is fixedly connected with backfill grouting.
5. major diameter high pressure duct grouting structure as claimed in claim 4, it is characterized in that: also comprise backfill grouting plain steel-bar (8), described backfill grouting plain steel-bar (8) is fixedly connected with backfill grouting arm (7), and the two ends of backfill grouting plain steel-bar (8) are fixedly connected with backfill grouting stiffening ring.
6. major diameter high pressure duct grouting structure as claimed in claim 1, it is characterized in that: also comprise steel mesh reinforcement, described steel mesh reinforcement is arranged on the outer wall of steel lining (1).
7. major diameter high pressure duct grouting structure as claimed in claim 1, is characterized in that: the mouth of pipe of described backfill grouting arm (7) is horn mouth.
CN201420643736.6U 2014-10-31 2014-10-31 Major diameter high pressure duct grouting structure Withdrawn - After Issue CN204139173U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420643736.6U CN204139173U (en) 2014-10-31 2014-10-31 Major diameter high pressure duct grouting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420643736.6U CN204139173U (en) 2014-10-31 2014-10-31 Major diameter high pressure duct grouting structure

Publications (1)

Publication Number Publication Date
CN204139173U true CN204139173U (en) 2015-02-04

Family

ID=52415870

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420643736.6U Withdrawn - After Issue CN204139173U (en) 2014-10-31 2014-10-31 Major diameter high pressure duct grouting structure

Country Status (1)

Country Link
CN (1) CN204139173U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104294827A (en) * 2014-10-31 2015-01-21 中国电建集团成都勘测设计研究院有限公司 Large-diameter high-strength pressure pipeline grouting structure and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104294827A (en) * 2014-10-31 2015-01-21 中国电建集团成都勘测设计研究院有限公司 Large-diameter high-strength pressure pipeline grouting structure and method
CN104294827B (en) * 2014-10-31 2016-06-08 中国电建集团成都勘测设计研究院有限公司 Major diameter high pressure duct grouting structure and grouting method

Similar Documents

Publication Publication Date Title
CN204456128U (en) A kind of delamination pour slurry rifle
CN106337570B (en) Steel pipe grouting rapid reinforcement rod structure and construction method
CN103257219B (en) Novel pouring device for model test and application method
CN105297755A (en) High-pressure water aid-sinking type construction device of open caisson
CN204139173U (en) Major diameter high pressure duct grouting structure
CN204491645U (en) A kind of deep foundation pit precipitation well-sealing device
CN202544903U (en) Hole packer
CN205908277U (en) Be used for tunnel concrete no. 2 to serve as a contrast hole packer device for slip casting that comes to nothing
CN204343286U (en) A kind of steel pipe pile support
CN104653199A (en) Multifunctional informatization grouting device and relevant grouting method thereof
CN204492746U (en) A kind of multifunctional information grouting device
CN204174638U (en) Underground structure ruggedized construction
CN204252165U (en) The artificial upper pipe working well of a kind of two way alternate
CN104131799A (en) Artesian well sealing and blocking device
CN104294827B (en) Major diameter high pressure duct grouting structure and grouting method
CN203823346U (en) Plugging device for high-strength steel penstock hole
CN203441508U (en) Special device for grouting deep hole in crushing section of surrounding rock
CN202165095U (en) Tunnel grouting and grout stopping device
CN104018475B (en) A kind of embedded penstock backfill grouting structure and grouting process thereof
CN203925521U (en) A kind of shield tunnel bottom stratum consolidation channels configuration
CN203130097U (en) Small guide pipe for grouting
CN203546725U (en) Backfilling grouting device capable of being recycled
CN202787228U (en) Loose earth body anchor pipe grouting device
CN104213628B (en) Jacking mechanism for underground pipe culvert engineering
CN204385748U (en) A kind of novel tunnel structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20150204

Effective date of abandoning: 20160608

C25 Abandonment of patent right or utility model to avoid double patenting