CN204113292U - Shield constructs quick-witted sewage treatment plant in subway tunnel shield method construction - Google Patents

Shield constructs quick-witted sewage treatment plant in subway tunnel shield method construction Download PDF

Info

Publication number
CN204113292U
CN204113292U CN201420398121.1U CN201420398121U CN204113292U CN 204113292 U CN204113292 U CN 204113292U CN 201420398121 U CN201420398121 U CN 201420398121U CN 204113292 U CN204113292 U CN 204113292U
Authority
CN
China
Prior art keywords
shield
sewage
subway tunnel
pump
treatment plant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420398121.1U
Other languages
Chinese (zh)
Inventor
刘学
李仲峰
朱川鄂
吴院生
邓能伟
蒋燕伟
郭春林
金康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201420398121.1U priority Critical patent/CN204113292U/en
Application granted granted Critical
Publication of CN204113292U publication Critical patent/CN204113292U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model provides a shield constructs quick-witted sewage treatment plant in subway tunnel shield method construction, is including establishing the pneumatic diaphragm pump at the shield tail of shield structure machine, and shield tail sewage is put into through the pipeline to pneumatic diaphragm pump water inlet one end, and the sewage case of fifth section platform truck is put into to the delivery port end, the sewage case is tertiary sedimentation tank structure, is equipped with the stirring rod in the one-level sedimentation tank, installs the otter board that punches a hole between one-level sedimentation tank and second grade sedimentation tank, and tertiary sedimentation tank output is through valve connection filter pump, and filter pump output connection is located the bentonite case of second section platform truck, and the sewage after the filtration is in the bentonite case with the bentonite intensive mixing inflation back, carries the bentonite to shield excavation face, in soil storehouse and the screw machine through face pipeline, soil storehouse pipeline, screw machine pipeline with the bentonite extrusion pump, improves the dregs. The problem of sewage treatment reuse in the shield method construction subway tunnel is solved, have simple structure, characteristics with low costs, and when carrying out reuse to sewage, saved the construction water.

Description

Shield machine sewage-treatment plant in a kind of subway tunnel shield method construction
Technical field
The utility model relates to shield machine sewage-treatment plant in the construction of a kind of subway tunnel shield method.
Background technology
Along with the raising of urban compact degree and urban congestion constantly increase, ground can utilize space fewer and feweri, and developing the underground space now becomes each metropolitan Main way, in this context, and the technology develop rapidly of shield construction.But the difference in geographical position residing for every city determines the soil layer run in shield-tunneling construction is various, shield structure is in different geology work progresss, suitable mode can be adopted to improve the dregs in excavation face, shield machine Tu Cang and conveying worm, in order to reduce the wearing and tearing of cutter, evade the formation of mud cake and to ensure that spiral shell machine is slagged tap smooth and easy.
In Yangtze River Delta Area, because water system is flourishing and the geological conditions of more complicated, a large amount of sewage can be produced in Analysis on Shield Tunnel Driven Process, sewage mud content is large, and containing many greases and chemical substance in sewage, the processing method of discharging after general employing carries out multi stage precipitation to sewage in the industry at present, but the waste water after the method process is still difficult to the standard reaching environmental emission, therefore how the sewage produced in Analysis on Shield Tunnel Driven Process is processed and recycled into an important problem in construction.
Utility model content
Shield machine sewage-treatment plant during its object of the utility model is just to provide a kind of subway tunnel shield method to construct, solve the problem of sewerage treatment recycling in shield construction subway tunnel, have the advantages that structure is simple, cost is low, and while sewage is utilized again, save construction water.
Realize above-mentioned purpose and the technical scheme taked, comprise the pneumatic diaphragm pump being located at shield machine shield tail, pneumatic diaphragm pump water inlet one end puts into shield tail sewage by the road, the foul water tank of Section of five chassis is put in delivery port termination, described foul water tank is three grades of sedimentation basin structures, stirring rod is provided with in first stage precipitation tank, punching web plate is installed between first stage precipitation tank and second-level settling pond, three grades of sedimentation basin outputs connect filter pump through valve, filter pump exports the swell soil case connecting and be positioned at second section chassis, after sewage after filtration is fully mixed expanded with swell soil in swell soil case, by swell soil extrusion pump through face pipeline, Tu Cangguanlu, swell soil is delivered to shield tunneling face by screw machine pipeline, in Tu Cang and screw machine, dregs is improved.
beneficial effect
Compared with prior art the utility model has the following advantages.
1) simple and reasonable for structure, the waste water produced in shield-tunneling construction is collected, filters and recycled, solves a difficult problem for sewerage treatment recycling in construction;
2) while again utilizing sewage, save construction water, the saving for water resource creates active influence.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, the utility model is described in further detail.
Fig. 1 is this apparatus structure principle schematic;
Fig. 2 is the structural representation of foul water tank in this device;
Fig. 3 is A-A sectional view in Fig. 2.
Detailed description of the invention
Comprise the pneumatic diaphragm pump 4 being located at shield machine shield tail, shield tail sewage 5 is put into by the road in pneumatic diaphragm pump 4 water inlet one end, the foul water tank 9 of Section of five chassis is put in delivery port termination, as shown in Figure 1, described foul water tank 9 is three grades of sedimentation basin structures, as Fig. 1, shown in Fig. 2, stirring rod 17 is provided with in first stage precipitation tank 14, punching web plate 18 is installed between first stage precipitation tank 14 and second-level settling pond 15, three grades of sedimentation basin 16 outputs connect filter pump 10 through valve 6, filter pump 10 exports the swell soil case 8 connecting and be positioned at second section chassis, after sewage after filtration is fully mixed expanded with swell soil in swell soil case 8, by swell soil extrusion pump 7 through face pipeline 13, soil storekeeper road 3, swell soil is delivered to shield tunneling face by screw machine pipeline 2, soil storehouse 11 and screw machine 12 li, dregs is improved.
First stage precipitation tank 14 in described foul water tank 9, second-level settling pond 15, three grades of sedimentation basin 16 volume ratios are 5:3:2.
Described filter pump 10 filtering accuracy is 3000 μm.
Described punching web plate 18 aperture is 6mm.
This device installs pneumatic diaphragm pump additional at shield tail, is arranged on below connecting bridge walkway board, and the water inlet of pneumatic diaphragm pump connects the suitable steel wire tube of a diameter, and the steel wire tube other end is placed in shield tail sewage, is pumped to by sewage in foul water tank below.Foul water tank is transformed into three grades of settlers, one-level settling tank is installed stirring rod and is fully stirred sewage, three grades of settling tanks install filter pump (16m3/h) by sewage pump drainage to swell soil case, after sewage and swell soil fully stir, by controlling the switch of pneumatic swell soil pipe-line control valve, swell soil is joined in excavation face, Tu Cang or conveying worm.Swell soil case comprises native case, extrusion pump, three pneumatic swell soil pipe-line control valves and connecting line.
Embodiment
For middle iron equipment CTE6440,
A, install a QBY-40 type pneumatic diaphragm pump 4 additional at shield machine 1 shield tail, to be arranged on below connecting bridge walkway board on steel work, the intake-outlet of pneumatic diaphragm pump 4 connects the steel wire tube 5 that a diameter is 40mm respectively, shield tail sewage is put in water inlet one end, and the foul water tank 9 of Section of five chassis is put in delivery port termination;
B, the foul water tank 9 be positioned on Section of five chassis to be transformed, be transformed into three grades of sedimentation basin styles, one-level, secondary, three grades of sedimentation basins are the design of 5:3:2 size according to volume ratio respectively.In first stage precipitation tank 14, install stirring rod 17 pairs of sewage additional fully stir; Punching web plate 18 is installed between I and II sedimentation basin, mainly the stone grain that particle diameter is greater than 6mm is precipitated; Installing a flow at three grades of sedimentation basins 16 is 40m3/h, and filtering accuracy is the filter pump 10 of 3000 μm, by filter pump 10, the foul water pump after sedimentation and filtration is delivered to the swell soil case 8 being arranged in second section chassis;
After sewage after c, filtration fully mixes microdilatancy with swell soil in swell soil case 8, by controlling the switch of pneumatic swell soil pipe-line control valve, through extrusion pump 7, swell soil is delivered to shield tunneling face, native storehouse 11 and screw machine 12 li, dregs is improved.

Claims (4)

1. shield machine sewage-treatment plant in a subway tunnel shield method construction, comprise the pneumatic diaphragm pump (4) being located at shield machine shield tail, shield tail sewage is put in pneumatic diaphragm pump (4) water inlet one end by the road (5), the foul water tank (9) of Section of five chassis is put in delivery port termination, it is characterized in that, described foul water tank (9) is three grades of sedimentation basin structures, stirring rod (17) is provided with in first stage precipitation tank (14), punching web plate (18) is installed between first stage precipitation tank (14) and second-level settling pond (15), three grades of sedimentation basin (16) outputs connect filter pump (10) through valve (6), filter pump (10) exports the swell soil case (8) connecting and be positioned at second section chassis, after sewage after filtration is fully mixed expanded with swell soil in swell soil case (8), by swell soil extrusion pump (7) through face pipeline (13), Tu Cangguanlu (3), swell soil is delivered to shield tunneling face by screw machine pipeline (2), Tu Cang (11) and screw machine (12) inner, dregs is improved.
2. shield machine sewage-treatment plant in a kind of subway tunnel shield method construction according to claim 1, it is characterized in that, the first stage precipitation tank (14) in described foul water tank (9), second-level settling pond (15), three grades of sedimentation basin (16) volume ratios are 5:3:2.
3. shield machine sewage-treatment plant in a kind of subway tunnel shield method construction according to claim 1, it is characterized in that, described filter pump (10) filtering accuracy is 3000 μm.
4. shield machine sewage-treatment plant in a kind of subway tunnel shield method construction according to claim 1, it is characterized in that, described punching web plate (18) aperture is 6mm.
CN201420398121.1U 2014-07-18 2014-07-18 Shield constructs quick-witted sewage treatment plant in subway tunnel shield method construction Expired - Fee Related CN204113292U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420398121.1U CN204113292U (en) 2014-07-18 2014-07-18 Shield constructs quick-witted sewage treatment plant in subway tunnel shield method construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420398121.1U CN204113292U (en) 2014-07-18 2014-07-18 Shield constructs quick-witted sewage treatment plant in subway tunnel shield method construction

Publications (1)

Publication Number Publication Date
CN204113292U true CN204113292U (en) 2015-01-21

Family

ID=52330616

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420398121.1U Expired - Fee Related CN204113292U (en) 2014-07-18 2014-07-18 Shield constructs quick-witted sewage treatment plant in subway tunnel shield method construction

Country Status (1)

Country Link
CN (1) CN204113292U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105964031A (en) * 2016-05-27 2016-09-28 中交二航局第三工程有限公司 Shield construction waste drilling mud treatment device and method
CN109231516A (en) * 2018-09-27 2019-01-18 中铁工程装备集团有限公司 The transmission of shield-tunneling construction sewage, sewage recovery reutilization device and system
CN110040867A (en) * 2019-03-20 2019-07-23 中铁四局集团有限公司 Engineering site sewage treatment method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105964031A (en) * 2016-05-27 2016-09-28 中交二航局第三工程有限公司 Shield construction waste drilling mud treatment device and method
CN109231516A (en) * 2018-09-27 2019-01-18 中铁工程装备集团有限公司 The transmission of shield-tunneling construction sewage, sewage recovery reutilization device and system
CN110040867A (en) * 2019-03-20 2019-07-23 中铁四局集团有限公司 Engineering site sewage treatment method
CN110040867B (en) * 2019-03-20 2021-10-29 中铁四局集团有限公司 Engineering site sewage treatment method

Similar Documents

Publication Publication Date Title
CN201245519Y (en) Sewage purification processing and recycling system for shield construction
CN204113292U (en) Shield constructs quick-witted sewage treatment plant in subway tunnel shield method construction
CN104276638B (en) A kind of constructing tunnel drainage processing method and treatment unit thereof
CN104016520B (en) Device for pre-treating coal chemical industry wastewater by air flotation coupled with coagulation and method for pre-treating coal chemical industry wastewater by device
CN204151169U (en) A kind of fracturing outlet liquid recycling and processing equipment
CN110448940B (en) Mud water treatment system and mud water treatment method for water purification plant
CN204162495U (en) A kind of constructing tunnel drain treatment apparatus
CN105776807A (en) Movable rapid on-site dewatering system and method for building mud
CN202390268U (en) In-situ reuse treatment system for downhole directional drilling machine medium circulation water
CN104773880A (en) Sewage treatment technology and equipment for well drilling
CN207769375U (en) A kind of sewage catchment promotion integrated apparatus
CN207142894U (en) System for coal mine water process
CN212894250U (en) Container type high-efficiency clarified water treatment device
CN205616704U (en) Fracturing flow -back fluid treatment device
CN204097283U (en) Air supporting integrated device for biochemical treatment
CN205011602U (en) On -vehicle floating ring piece formula slurry treatment device
CN104743713B (en) Oil drilling and service shaft fracturing wastewater do not land process device
CN204625221U (en) A kind of filling preparation facilities with sewage discharge emergency handling function
CN207294427U (en) A kind of quick processing system of beneficiation wastewater
CN103304053A (en) Treatment system for converting mine waste-rock dredging drainage water into production water
CN207957997U (en) A kind of mine tailing wastewater cyclic utilization system
CN205822328U (en) A kind of making use of rain and flood device
CN201240951Y (en) Siliceous skin integrated reaction sedimentation filtering device
CN105130155A (en) Vehicle-mounted swinging annular-sheet type sludge processing apparatus
CN204058131U (en) A kind of concrete-agitating system wastewater treatment equipment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150121

Termination date: 20150718

EXPY Termination of patent right or utility model