CN204112376U - The system of sediment at the bottom of a kind of detect aperture - Google Patents

The system of sediment at the bottom of a kind of detect aperture Download PDF

Info

Publication number
CN204112376U
CN204112376U CN201420426460.6U CN201420426460U CN204112376U CN 204112376 U CN204112376 U CN 204112376U CN 201420426460 U CN201420426460 U CN 201420426460U CN 204112376 U CN204112376 U CN 204112376U
Authority
CN
China
Prior art keywords
sediment
standard value
punching hole
module
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420426460.6U
Other languages
Chinese (zh)
Inventor
孙志伟
舒阳
叶如跃
徐健
许小永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420426460.6U priority Critical patent/CN204112376U/en
Application granted granted Critical
Publication of CN204112376U publication Critical patent/CN204112376U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The utility model proposes the system of sediment at the bottom of a kind of detect aperture, comprise the pneumatics blower fan extracting sediment, described system also comprises: supply module, powers for giving the consuming parts in described system; Air mass sensor, for detecting the sediment at the bottom of punching hole; Man-machine interaction unit, for arranging the real time value of sediment and display sediment; Comparator circuit, for the sediment got and standard value being compared, if higher than standard value, sends enabling signal to pneumatics blower fan, extracts the sediment at the bottom of punching hole, until the sediment at the bottom of punching hole is lower than standard value.The system implementing sediment at the bottom of detect aperture of the present utility model thoroughly can remove sediment, decreases that pile position deviation is excessive, stake holes tilts to exceed standard, the deficiency of pipe laying, reinforcement cover, improves construction quality.

Description

The system of sediment at the bottom of a kind of detect aperture
Technical field
The utility model relates to concrete field, particularly the system of sediment at the bottom of a kind of detect aperture.
Background technology
Concrete refer to gathered materials by cementitious matter (organic, inorganic or organo-mineral complexing), graininess, chemical admixture that water and needs add and mineral admixture be by the compound of proper proportion mixing, or after sclerosis, form the composite material (common is with cementitious material, water, fines, coarse aggregate) with heap poly structure, mix Admixture and mineral admixture when needing, coordinate by proper proportion.
In recent years, along with the development of builing industry, super highrise building gets more and more in China, needs to adopt pile foundation in super highrise building in the place that soil property is bad, and the stake footpath of general pile foundation is all larger, and wherein the utilization of Punching Borehole Cast-in-place Concrete Pile is also many.In drilled pile pore forming process, often there will be repetition fragmentation, drill bit easily weares and teares, the situation of the irregular or oversize in aperture; When creeping into; in hole, dehydration is larger; bit balling creeps into difficulty; easy undergauge; the maximum defect of Punching Borehole Cast-in-place Concrete Pile is exactly that sediment at the bottom of hole can not thoroughly be removed totally; sediment super thick at the bottom of hole by occurring that pile position deviation is excessive, stake holes tilts to exceed standard, pipe laying, reinforcement cover deficiency, Isolation of pile body concrete, broken pile and reveal the quality problems such as muscle, these quality problems often make pile be difficult to meet design requirement, and remedy difficulty.
Utility model content
The utility model proposes the system of sediment at the bottom of a kind of detect aperture, in super highrise building, so that sediment at the bottom of hole is thoroughly removed totally.
The technical solution of the utility model is:
The utility model provides the system of sediment at the bottom of a kind of detect aperture, and comprise the pneumatics blower fan extracting sediment, described system also comprises:
Supply module, powers for giving the consuming parts in described system;
Air mass sensor, for detecting the sediment at the bottom of punching hole;
Man-machine interaction unit, for arranging the real time value of sediment and display sediment;
Comparator circuit, for the sediment got and standard value being compared, if higher than standard value, sends enabling signal to pneumatics blower fan, extracts the sediment at the bottom of the hole of punching, until the sediment at the bottom of the hole of punching is lower than standard value.
Further, described system also comprises the minisize pick-up head for absorbing the geological condition at the bottom of hole.
Further, described camera is connected with communication module.
Further, described communication module comprises 3G module, 4G module, WIFI module or bluetooth module.
Implement the system of sediment at the bottom of a kind of detect aperture of the present utility model, there is following useful technique effect:
Be different from the deficiency that prior art thoroughly can not remove sediment, the technical program thoroughly can remove sediment, decreases that pile position deviation is excessive, stake holes tilts to exceed standard, the deficiency of pipe laying, reinforcement cover, improves construction quality.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is only embodiments more of the present utility model, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of the system of sediment at the bottom of a kind of detect aperture of the utility model.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the utility model embodiment, be clearly and completely described the technical scheme in the utility model embodiment, obviously, described embodiment is only the utility model part embodiment, instead of whole embodiments.Based on the embodiment in the utility model, those of ordinary skill in the art are not making the every other embodiment obtained under creative work prerequisite, all belong to the scope of the utility model protection.
Refer to Fig. 1, the preferred embodiment of the technical program, the system 1 of sediment at the bottom of a kind of detect aperture, comprise the pneumatics blower fan 10 extracting sediment, system 1 also comprises:
Supply module 11, powers for giving the consuming parts in described system;
Air mass sensor 12, for detecting the sediment at the bottom of punching hole;
Man-machine interaction unit 13, for arranging the real time value of sediment and display sediment;
Comparator circuit 14, for the sediment got and standard value being compared, if higher than standard value, sends enabling signal to pneumatics blower fan 10, extracts the sediment at the bottom of punching hole, until the sediment at the bottom of punching hole is lower than standard value.
Further, system 1 also comprises the minisize pick-up head 15 for absorbing the geological condition at the bottom of hole.Camera 15 is connected with communication module 16.
Communication module 15 comprises 3G module, 4G module, WIFI module or bluetooth module.
Further describe in detail below.
The technological process of Percussion Piles construction is as follows:
One, surveying setting-out
The datum mark provided according to proprietor by professional survey engineer, accurately measures the stake position of every pile with total powerstation, and is buried in the earth with reinforcing bar and performs mark, and fixing, notices that protecting the stake position of non-construction stake to mark does not destroy by disturbance before construction.
Two, pile-forming machine perching
Stake machine telephone-moving align piles position, makes a machine overhead traveling crane leading edge, board on same plumb line, and levels up by Zhuan Wei center, pad.
Three, bury casing underground
Casing adopts steel pile casting, and diameter is greater than intended diameter 20cm, and casing is imbedded to firm stratum, casing top 20 ~ 30cm above ground level, and casing center line and pile center's line hang down and close.
Four, pore-forming
Adopt mud off pore-forming, in creeping into, the scarfing cinder of slag cylinder and the clear hole of gas lift reverse circulation are drawn in the employing of clear quarrel.
Bright according to geology MSDS, there is thicker gravel in this place, medium-sand seam, bedrock surface big rise and fall, inclination angle is large, and the feature of hole deviation easily occurs, and keeps noticing that mud balance controls at 1.2 ~ 1.45kg/L, viscosity 25 ~ 30S during pore-forming.At loose stratum and sandy gravel stratum, keep mud balance at 1.3 ~ 1.45kg/L when creeping into, drilling speed is unsuitable too fast, to form good pit protection mud cake, keeps punching to stablize.Pore-forming must enter middle decayed rock sand and be not less than 0.5m, reaches design elevation.
Along with the increase of hole depth in rushing in, for making sediment return out aperture in a large number, improving pore-forming efficiency, adopting pneumatics blower fan to send at the bottom of compressed air to hole during scarfing cinder, utilizing gas lift reverse circulation to carry out scarfing cinder at the bottom of hole.
When rushing in bedrock surface, must the speed of rushing in be slowed down, avoid inclined hole.When impact holing, should hole quality be kept a close eye on, for Different Strata, select different stroke and regulate mud property, should low hammer be close hits during initial punching, after entering basement rock, higher hammer detritus.
Five, clear hole
Rush in and adopt the clear hole of gas lift reverse circulation to projected depth, sediment thickness should be less than 50mm, in order to ensure clear hole quality, after descending reinforcing cage, still must continue clear hole.
Implement the system of sediment at the bottom of a kind of detect aperture of the present utility model, there is following useful technique effect:
Be different from the deficiency that prior art thoroughly can not remove sediment, the technical program thoroughly can remove sediment, decreases that pile position deviation is excessive, stake holes tilts to exceed standard, the deficiency of pipe laying, reinforcement cover, improves construction quality.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all within spirit of the present utility model and principle, any amendment done, equivalent replacement, improvement etc., all should be included within protection domain of the present utility model.

Claims (4)

1. a system for sediment at the bottom of detect aperture, comprise the pneumatics blower fan extracting sediment, it is characterized in that, described system also comprises:
Supply module, powers for giving the consuming parts in described system;
Air mass sensor, for detecting the sediment at the bottom of punching hole;
Man-machine interaction unit, for arranging the real time value of sediment and display sediment;
Comparator circuit, for the sediment got and standard value being compared, if higher than standard value, sends enabling signal to pneumatics blower fan, extracts the sediment at the bottom of punching hole, until the sediment at the bottom of punching hole is lower than standard value.
2. system according to claim 1, is characterized in that, described system also comprises the minisize pick-up head for absorbing the geological condition at the bottom of hole.
3. system according to claim 2, is characterized in that, described camera is connected with communication module.
4. system according to claim 3, is characterized in that, described communication module comprises 3G module, 4G module, WIFI module or bluetooth module.
CN201420426460.6U 2014-07-30 2014-07-30 The system of sediment at the bottom of a kind of detect aperture Expired - Fee Related CN204112376U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420426460.6U CN204112376U (en) 2014-07-30 2014-07-30 The system of sediment at the bottom of a kind of detect aperture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420426460.6U CN204112376U (en) 2014-07-30 2014-07-30 The system of sediment at the bottom of a kind of detect aperture

Publications (1)

Publication Number Publication Date
CN204112376U true CN204112376U (en) 2015-01-21

Family

ID=52329704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420426460.6U Expired - Fee Related CN204112376U (en) 2014-07-30 2014-07-30 The system of sediment at the bottom of a kind of detect aperture

Country Status (1)

Country Link
CN (1) CN204112376U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105971584A (en) * 2016-06-29 2016-09-28 武汉天宸伟业物探科技有限公司 Multi-parameter comprehensive detection device and method for hole forming and groove forming
CN113774966A (en) * 2021-09-10 2021-12-10 李忠春 Device and method for detecting thickness of concrete cast-in-place pile bottom sediment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105971584A (en) * 2016-06-29 2016-09-28 武汉天宸伟业物探科技有限公司 Multi-parameter comprehensive detection device and method for hole forming and groove forming
CN105971584B (en) * 2016-06-29 2023-02-17 武汉天宸伟业物探科技有限公司 Multi-parameter comprehensive detection device and method for hole forming and grooving
CN113774966A (en) * 2021-09-10 2021-12-10 李忠春 Device and method for detecting thickness of concrete cast-in-place pile bottom sediment

Similar Documents

Publication Publication Date Title
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN107938676A (en) A kind of pile base construction method for passing through full packing type solution cavity
CN104747088B (en) A kind of leafy hosqe bit of cast-in-situ bored pile list waist and drilling construction method
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN203846485U (en) Long pile percussion drill hole forming construction device
CN103485336A (en) Drilling pile drilling construction method of bead-type karst area
CN103526747B (en) Morning and evening tides environmental impact pore-creating filling pile construction
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN105780763A (en) Construction method of medium-hole vibrating casing wall protection type long spiral cast-in-situ bored pile
CN103290840A (en) Prestressed pipe pile construction method under boulder group geological conditions
CN102654056A (en) Shield construction method for clearing obstacles by punching rock stratum section
CN104110028B (en) A kind of dry operation boring is without the cast-in-place pile construction method of water law concrete perfusion
CN102182399B (en) Construction method and equipment for reverse circulation drill to drill hole, hammer to form hole, expand hole and remove slag
CN103046931A (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN106284311B (en) A kind of dry efficient construction technology of pore-forming cast-in-place concrete pile of rotary drilling rig
CN109915021A (en) A kind of aquatic pile foundation construction drill method
CN106677168A (en) Construction method of cast-in-place superfluid concrete pile
CN106988305A (en) A kind of pile-column pier construction method of underground integrated molding
CN107989057A (en) A kind of Bridge Pile Foundation Construction method
CN110397026A (en) A kind of construction method and constructing structure for closing on both wired bridge pile foundations
CN105926592A (en) Construction method of hole drilling pile
CN206204978U (en) For the miniature grouting steel pipe pile multi-column pier foundation structure of Selection of Urban Pedestrian Overpass
CN204112376U (en) The system of sediment at the bottom of a kind of detect aperture
CN112281880A (en) Construction method of complex stratum long spiral hole-leading inserting-driving locking opening steel pipe pile cofferdam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150121

Termination date: 20150730

EXPY Termination of patent right or utility model