CN110397026A - A construction method and construction structure for pile foundations of bridges adjacent to existing lines - Google Patents

A construction method and construction structure for pile foundations of bridges adjacent to existing lines Download PDF

Info

Publication number
CN110397026A
CN110397026A CN201910598884.8A CN201910598884A CN110397026A CN 110397026 A CN110397026 A CN 110397026A CN 201910598884 A CN201910598884 A CN 201910598884A CN 110397026 A CN110397026 A CN 110397026A
Authority
CN
China
Prior art keywords
pile
casing
steel
pile hole
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910598884.8A
Other languages
Chinese (zh)
Inventor
梁磊磊
徐财进
王培�
郭恒
都兴龙
韩伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Second Engineering Co Ltd
Original Assignee
CCCC SHEC Second Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Second Engineering Co Ltd filed Critical CCCC SHEC Second Engineering Co Ltd
Priority to CN201910598884.8A priority Critical patent/CN110397026A/en
Publication of CN110397026A publication Critical patent/CN110397026A/en
Pending legal-status Critical Current

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/08—Removing obstacles
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00—Excavations; Bordering of excavations; Making embankments
    • E02D17/06—Foundation trenches ditches or narrow shafts
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00—Excavations; Bordering of excavations; Making embankments
    • E02D17/06—Foundation trenches ditches or narrow shafts
    • E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22—Piles
    • E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66—Mould-pipes or other moulds
    • E02D5/665—Mould-pipes or other moulds for making piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明提供了一种临近既有线桥梁桩基的施工方法及施工结构,该施工结构包括桩孔,桩孔的顶部设有锁口,所述锁口的一侧设有空压机,另一侧设有出渣机具,所述出渣机具的前侧向锁口延伸设有滑轮组,出渣机具的内部设有钢丝绳,所述钢丝绳由出渣机具的顶部穿出并绕过滑轮组后垂直向锁口的下方延伸,所述钢丝绳的底端连接有吊斗;所述桩孔的内部设有多节钢护筒,且最上端的钢护筒顶端焊接有护筒定位钢板,所述钢护筒通过护筒定位钢板固定在锁口上。本发明采用人工挖孔和水磨钻成孔相结合的施工工艺,并在施工时采用钢护筒跟进,能够有效保护既有线路基安全,施工全过程桩孔内始终处于无水的干燥环境,避免了既有线路基遭受水浸泡,实用性强。

The invention provides a construction method and a construction structure for a bridge pile foundation near an existing line. The construction structure includes a pile hole, a lock is provided on the top of the pile hole, an air compressor is provided on one side of the lock, and an air compressor is provided on the other. There is a slagging machine on the side, and the front side of the slag machine is extended to the lock with a pulley block. The inside of the slag machine is provided with a steel wire rope. The lower end of the lock mouth is extended, and the bottom end of the steel wire rope is connected with a bucket; the inside of the pile hole is provided with a multi-section steel casing, and the top of the uppermost steel casing is welded with a casing positioning steel plate, and the steel casing The positioning steel plate is fixed on the lock through the casing. The invention adopts the construction technology combining manual digging and water mill drilling, and adopts steel casing to follow up during construction, which can effectively protect the safety of the existing road foundation, and the pile hole is always in an anhydrous dry environment during the whole construction process. It avoids the existing line base from being soaked in water and has strong practicability.

Description

一种临近既有线桥梁桩基的施工方法及施工结构A construction method and construction structure for pile foundations of bridges adjacent to existing lines

技术领域technical field

本发明涉及桥梁桩基施工方法领域,尤其涉及一种临近既有线桥梁桩基的施工方法及施工结构。The invention relates to the field of bridge pile foundation construction methods, in particular to a construction method and construction structure of bridge pile foundations adjacent to existing lines.

背景技术Background technique

随着我国国民经济的快速发展,高速公路网、铁路网密度不断提升,交通通道资源日益紧缺,多种交通方式间的交叉穿越逐渐增多。多条线路之间的立体交叉主要采用上跨桥梁和下穿隧道,当采用桥梁结构上跨既有线时,桥梁桩基的施工方法就显得尤为重要。选择合适的施工方法,避免新建桥梁施工安全区域与既有交通道路(高速公路、铁路等)设备及安全运营的冲突问题。With the rapid development of my country's national economy, the density of expressway network and railway network has been continuously increased, and the resources of transportation channels have become increasingly scarce, and the crossing between various transportation modes has gradually increased. The over-span bridges and under-pass tunnels are mainly used for the three-dimensional intersection between multiple lines. When the bridge structure is used to over-span the existing line, the construction method of the bridge pile foundation is particularly important. Choose an appropriate construction method to avoid conflicts between the construction safety area of new bridges and existing traffic roads (expressways, railways, etc.) equipment and safe operation.

现行的人工挖孔桩施工方法主要为爆破法施工,该方法存在诸多弊端:由于爆破时存在诸多不稳定因素,容易对孔壁造成损伤,易造成成孔不规则,导致混凝土超方数量较大;且爆破施工噪音较大,对周边环境影响较大,安全性相对较差。而钻孔桩施工技术例如使用大型机械设备(旋挖钻机、冲击钻等)在施工过程中虽然安全度较高,施工速度快,但是设备太大,转移过程困难,特别是在狭小复杂施工场地极作业为不便;施工噪音大,污染物多,产生大量灰尘。在日常实践过程中,采用水磨钻配合人工挖孔出渣的方法不仅施工操作方便、占用场地小、对外部环境影响小,还能够以较短的工期、较低的成本、较好的效果解决复杂地质条件下和有限作业面的人工挖孔桩施工作业。The current construction method of manual excavation piles is mainly the blasting method, which has many disadvantages: due to many unstable factors during blasting, it is easy to cause damage to the hole wall, and it is easy to cause irregular hole formation, resulting in a large number of concrete oversquares ; and the blasting construction noise is relatively large, which has a great impact on the surrounding environment and relatively poor safety. The construction technology of bored piles, for example, uses large mechanical equipment (rotary drilling rigs, impact drills, etc.) in the construction process. Although the safety is relatively high and the construction speed is fast, the equipment is too large and the transfer process is difficult, especially in small and complex construction sites. The operation is very inconvenient; the construction noise is loud, there are many pollutants, and a large amount of dust is generated. In daily practice, the method of using water mill drilling combined with manual digging to remove slag is not only convenient for construction and operation, occupies a small space, and has little impact on the external environment, it can also solve the problem with a shorter construction period, lower cost, and better results. Manual excavation pile construction operation under complex geological conditions and limited working surface.

发明内容Contents of the invention

针对上述施工方法存在的不足,本发明的目的在于提供一种临近既有线桥梁桩基的施工方法及施工结构,不需要使用泥浆,不对既有线的营运造成影响。In view of the shortcomings of the above-mentioned construction methods, the purpose of the present invention is to provide a construction method and construction structure for bridge pile foundations adjacent to existing lines, which does not require the use of mud and does not affect the operation of existing lines.

为此,本发明所采用的技术方案如下:For this reason, the technical scheme adopted in the present invention is as follows:

一种临近既有线路基的桥梁桩基施工方法,包括下述步骤:A bridge pile foundation construction method adjacent to an existing road foundation, comprising the following steps:

S1.对桩孔地点进行测量定位,并在桩孔两侧施工锁口;S1. Measure and locate the pile hole location, and construct locks on both sides of the pile hole;

S2.安装出渣机具,并在出渣机具内设置配重块;S2. Install the slag-discharging tool, and set the counterweight in the slag-discharging tool;

S3.桩孔的桩位线定好之后,从上到下逐层开挖覆盖土体,先挖中间部分的土方,然后扩及周边,开挖截面尺寸应按钢护筒的外径进行控制;S3. After the pile position line of the pile hole is determined, excavate and cover the soil layer by layer from top to bottom, first excavate the middle part of the soil, and then expand to the periphery. The excavation section size should be controlled according to the outer diameter of the steel casing;

S4. 桩孔每开挖完成一节,及时设置一节钢护筒跟进;S4. After each section of pile hole is excavated, set up a section of steel casing in time to follow up;

S5. 桩孔开挖至中风化岩层后,改用水磨钻继续挖孔;S5. After the pile hole is excavated to the moderately weathered rock formation, use a hydraulic drill to continue digging;

S6. 水磨钻挖孔施工完成后,对桩孔进行修正并开始下一循环的施工。S6. After the water mill drilling is completed, the pile holes are corrected and the next cycle of construction starts.

进一步地,所述步骤S1中,锁口采用混凝土结构,并应高出地面30cm;锁口顶部设置钢板垫块,用于承受护筒跟进时定位钢板传递到护壁上的荷载,防止护筒跟进过程破坏锁口。Further, in the step S1, the lock mouth adopts a concrete structure, and should be 30cm above the ground; the top of the lock mouth is provided with a steel plate spacer, which is used to bear the load transmitted by the positioning steel plate to the retaining wall when the casing follows up, and prevents the casing from The follow-up process destroys the lock.

进一步地,所述步骤S3中,开挖上层覆盖土体时应采用镐、锹进行,遇坚硬土层,用钎破碎,开挖截面尺寸按护筒外径控制,开挖每节的高度应根据地质状况,每节开挖高度一般为1.0m。Further, in the step S3, picks and shovels should be used to excavate the upper layer of covering soil, and when the hard soil layer is encountered, it should be broken with brazing. According to the geological conditions, the excavation height of each section is generally 1.0m.

进一步地,所述步骤S4中,首节钢护筒下放时,在钢护筒的顶端焊接护筒定位钢板,钢护筒通过定位钢板固定在锁口上;然后继续开挖,开挖完成第二节后,先采用吊车起吊第二节钢护筒,然后将其与首节钢护筒焊接,并拆除首节钢护筒顶端的护筒定位钢板,通过吊车将首节钢护筒缓慢下沉至桩孔孔底;在第二节钢护筒上焊接护筒定位钢板,并将该护筒定位钢板放置在锁口上以防止开挖过程钢护筒下坠,然后继续开挖,如此循环,直至钢护筒埋设完成。Further, in the step S4, when the first steel casing is lowered, the casing positioning steel plate is welded on the top of the steel casing, and the steel casing is fixed on the lock by the positioning steel plate; then continue excavation, and the excavation completes the second After the section, use the crane to lift the second steel casing first, then weld it to the first steel casing, remove the casing positioning steel plate on the top of the first steel casing, and slowly sink the first steel casing by the crane to the bottom of the pile hole; weld the casing positioning steel plate on the second steel casing, and place the casing positioning steel plate on the lock to prevent the steel casing from falling during the excavation process, and then continue to excavate, and so on until The laying of the steel casing is completed.

进一步地,所述步骤S5包括S501.桩孔周边取芯:水磨钻开孔沿桩孔四周进行,先沿桩孔的内壁布置取芯点,使取芯圆与锁口内壁相切,然后依次以外倾角3~5°向下钻取外周的岩芯,外周岩芯取完后中间岩体便形成一个环形临空面;Further, the step S5 includes S501. Coring around the pile hole: the water mill drills the hole around the pile hole, first arranges the coring points along the inner wall of the pile hole, so that the coring circle is tangent to the inner wall of the lock, and then sequentially The outer peripheral core is drilled down at a camber angle of 3~5°, and after the outer peripheral core is taken, the middle rock mass forms a ring-shaped free surface;

S502.桩芯打孔:钻孔及取芯施工完成后,用手电钻在岩体上钻眼,再将桩芯岩石分成6等份或8等份,便于岩体破裂;S502. Pile core drilling: After the drilling and coring construction is completed, use a hand drill to drill holes in the rock mass, and then divide the pile core rock into 6 or 8 equal parts to facilitate rock mass rupture;

S503.桩芯分解:在手电钻钻出的孔内插入钢楔、击打钢楔依次分裂岩体,直至该层桩芯岩体全部被破裂;S503. Pile core decomposition: insert steel wedges into the holes drilled by the electric hand drill, and hit the steel wedges to split the rock mass in turn until the pile core rock mass of this layer is completely broken;

S504. 钻芯外运:水磨钻施工一边进行,一边对取出的钻芯进行外运,钻芯外运从桩孔的一侧进行,通过卷扬机提升吊斗至桩孔的锁口,转动卷扬机并将吊斗中的石块倾卸入出渣料斗,运至指定的弃渣场。S504. Drilling core transport: while the water milling drill is in progress, the drill cores are transported out. The drill cores are transported from one side of the pile hole, and the hoist is used to lift the bucket to the lock of the pile hole. Dump the stones in the bucket into the slag discharge hopper and transport them to the designated waste slag yard.

一种临近既有线桥梁桩基的施工结构,包括桩孔,所述桩孔的顶部两侧设有锁口,所述锁口的一侧设有空压机,锁口的另一侧设有出渣机具,所述出渣机具的前侧向锁口延伸设有滑轮组,所述出渣机具的内部设有钢丝绳,所述钢丝绳由出渣机具的顶部穿出并绕过滑轮组后垂直向锁口的下方延伸,所述钢丝绳的底端固定连接有吊斗;A construction structure for pile foundations of bridges adjacent to existing lines, comprising pile holes, lock openings are provided on both sides of the top of the pile hole, an air compressor is provided on one side of the lock opening, and an air compressor is provided on the other side of the lock opening. Slagging equipment, the front side of the slag extracting equipment is extended to the lock opening with a pulley block, and the inside of the slag extracting equipment is provided with a steel wire rope, and the steel wire rope passes through the top of the slag extracting equipment and goes around the pulley block to lock vertically. Extending below the mouth, the bottom end of the wire rope is fixedly connected with a bucket;

所述桩孔的内部设有多节钢护筒,且最上端的钢护筒顶端焊接有护筒定位钢板,所述钢护筒通过护筒定位钢板固定在锁口上,所述锁口的顶部设置有钢板垫块。The inside of the pile hole is provided with multiple steel casings, and the top of the uppermost steel casing is welded with a casing positioning steel plate, and the steel casing is fixed on the lock through the casing positioning steel plate, and the top of the locking is set There are steel plate spacers.

进一步地,所述出渣机具包括支架,及置于支架内的卷扬机,所述卷扬机与钢丝绳连接,用于收放钢丝绳。Further, the slag removing machine includes a bracket, and a hoist placed in the bracket, and the hoist is connected with the wire rope for retracting and retracting the wire rope.

进一步地,所述支架内还设置有配重块。Further, a counterweight is also arranged in the bracket.

进一步地,所述出渣机具上还连接有伸入桩孔内部的抽水设备。Further, the slag removing machine is also connected with pumping equipment extending into the pile hole.

进一步地,所述出渣机具上还连接有伸入桩孔内部的照明设备。Further, the slag extractor is also connected with lighting equipment extending into the pile hole.

进一步地,所述桩孔的底部内壁设有混凝土护壁。Further, the bottom inner wall of the pile hole is provided with a concrete retaining wall.

本发明的优点是:The advantages of the present invention are:

本发明采用钢护筒跟进的施工方法,能够有效保护既有线路基安全,施工全过程桩孔内始终处于无水的干燥环境,避免了既有线路基遭受水浸泡,实用性强;且施工过程不但可以在没有爆破的情况下在坚硬岩层中成桩,可有效避免因爆破对挖孔桩孔壁的破坏,从而避免塌孔风险;而且又很环保,不会产生过多污染物,噪声小、对周边建筑物震动和扰动小,降低施工活动对环境的影响;并具有对地质条件适应性好、稳定性强、安全性高的特点。The invention adopts the construction method followed by the steel casing, which can effectively protect the safety of the existing road foundation, and the pile hole is always in an anhydrous dry environment during the whole construction process, avoiding the existing road foundation from being soaked in water, and has strong practicability; and the construction process Not only can piles be formed in hard rock formations without blasting, it can effectively avoid the damage to the hole wall of the hole-digging pile due to blasting, thereby avoiding the risk of hole collapse; it is also very environmentally friendly, does not generate too much pollutants, and has low noise , Small vibration and disturbance to surrounding buildings, reducing the impact of construction activities on the environment; and has the characteristics of good adaptability to geological conditions, strong stability, and high safety.

附图说明Description of drawings

下面结合附图和实施例对本发明进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

图1是本发明的总体立面布置图;Fig. 1 is the overall elevation layout drawing of the present invention;

图2是钢护筒接长施工示意图。Fig. 2 is a construction schematic diagram of steel casing extension.

图中标记说明:Instructions for marks in the figure:

1、出渣机具;2、配重块;3、空压机;4、锁口;5、钢护筒;6、混凝土护壁;7、抽水设备;8、照明设备;9、护筒定位钢板;10、吊斗;11、钢丝绳;12、卷扬机;13、滑轮组。1. Slagging equipment; 2. Counterweight; 3. Air compressor; 4. Lock; 5. Steel casing; 6. Concrete wall; 7. Pumping equipment; 8. Lighting equipment; 9. Casing positioning steel plate ; 10, bucket; 11, wire rope; 12, winch; 13, pulley block.

具体实施方式Detailed ways

以下由特定的具体实施例说明本发明的实施方式,本领域技术人员可由本说明书所揭示的内容轻易地了解本发明的其他优点及功效。The implementation of the present invention will be illustrated by specific specific examples below, and those skilled in the art can easily understand other advantages and effects of the present invention from the content disclosed in this specification.

现参考附图介绍本发明的示例性实施方式,然而,本发明可以用许多不同的形式来实施,并且不局限于此处描述的实施例,提供这些实施例是为了详尽地且完全地公开本发明,并且向所属技术领域的技术人员充分传达本发明的范围。对于表示在附图中的示例性实施方式中的术语并不是对本发明的限定。在附图中,相同的单元/元件使用相同的附图标记。Exemplary embodiments of the present invention will now be described with reference to the accompanying drawings, however, the present invention may be embodied in many different forms and are not limited to the embodiments described herein, which are provided for the purpose of exhaustively and completely disclosing the present invention. invention and fully convey the scope of the invention to those skilled in the art. The terms used in the exemplary embodiments shown in the drawings do not limit the present invention. In the figures, the same units/elements are given the same reference numerals.

除非另有说明,此处使用的术语(包括科技术语)对所属技术领域的技术人员具有通常的理解含义。另外,可以理解的是,以通常使用的词典限定的术语,应当被理解为与其相关领域的语境具有一致的含义,而不应该被理解为理想化的或过于正式的意义。Unless otherwise stated, the terms (including scientific and technical terms) used herein have the meanings commonly understood by those skilled in the art. In addition, it can be understood that terms defined by commonly used dictionaries should be understood to have consistent meanings in the context of their related fields, and should not be understood as idealized or overly formal meanings.

实施方式一Implementation Mode 1

一种临近既有线路基的桥梁桩基施工方法,包括下述步骤:A bridge pile foundation construction method adjacent to an existing road foundation, comprising the following steps:

S1. 根据要施工场地周围既有线的情况,对桩孔地点进行测量定位,并在桩孔两侧施工混凝土锁口4;S1. According to the existing lines around the construction site, measure and locate the pile hole location, and construct concrete locks 4 on both sides of the pile hole;

S2.安装出渣机具1,将安装出渣机具1的场地平整并硬化,并在出渣机具1内设置配重块2;S2. Install the slagging machine tool 1, level and harden the site where the slag machine tool 1 is installed, and set the counterweight 2 in the slag machine tool 1;

S3.桩孔14的桩位线定好之后,从上到下逐层开挖覆盖土体,先挖中间部分的土方,然后扩及周边,开挖截面尺寸应按钢护筒5的外径进行控制;S3. After the pile position line of the pile hole 14 is determined, excavate and cover the soil layer by layer from top to bottom, first dig the middle part of the soil, and then expand to the surrounding area. The excavation section size should be based on the outer diameter of the steel casing 5 control;

S4. 桩孔14每开挖完成一节,及时设置一节钢护筒5跟进;S4. Every time a section of pile hole 14 is excavated, a section of steel casing 5 is set up in time to follow up;

S5. 桩孔14开挖至中风化岩层后,改用水磨钻继续挖孔;S5. After the pile hole 14 is excavated to the moderately weathered rock formation, use a hydraulic drill to continue digging;

S6. 水磨钻挖孔施工完成后,对桩孔14进行修正并开始下一循环的施工。S6. After the water mill drilling is completed, the pile hole 14 is corrected and the next cycle of construction is started.

综上所述,本发明采用人工挖孔和水磨钻成孔相结合的施工工艺,从而有效避免了塌孔风险;同时施工时不需要使用泥浆,不对既有线的营运造成影响,也不会产生过多污染物,噪声小、对周边建筑物震动和扰动小,降低施工活动对环境的影响;并具有对地质条件适应性好、稳定性强、安全性高的特点。In summary, the present invention adopts the construction technology combining manual digging and water mill drilling to effectively avoid the risk of hole collapse; at the same time, no mud is needed during construction, which will not affect the operation of existing lines and will not cause Too many pollutants, low noise, little vibration and disturbance to surrounding buildings, reducing the impact of construction activities on the environment; and it has the characteristics of good adaptability to geological conditions, strong stability, and high safety.

实施方式二Implementation mode two

在实施例1的基础上,进一步地,步骤S1中,锁口4采用混凝土结构,并应高出地面30cm;锁口4顶部设置钢板垫块,用于承受钢护筒5跟进时护筒定位钢板9传递到护壁上的荷载,防止钢护筒跟进过程破坏锁口。On the basis of Example 1, further, in step S1, the locking port 4 adopts a concrete structure, and should be 30 cm above the ground; the top of the locking port 4 is provided with a steel plate pad, which is used to bear the casing when the steel casing 5 follows up. The load transmitted by the positioning steel plate 9 to the retaining wall prevents the steel casing from destroying the lock during the follow-up process.

进一步地,步骤S3中,桩位线定好之后,采用镐、锹开挖从上到下逐层开挖覆盖土体,如遇坚硬土层,用钎破碎,开挖截面尺寸应按钢护筒5的外径进行控制;开挖每节的高度应根据地质状况,每节开挖高度一般为1.0m;先挖中间部分的土方,然后扩及周边,有效地控制开挖桩孔的截面尺寸。Further, in step S3, after the pile position line is determined, picks and shovels are used to excavate and cover the soil layer by layer from top to bottom. In case of hard soil layer, use brazing to break it. The outer diameter of 5 is controlled; the height of each excavation section should be based on the geological conditions, and the excavation height of each section is generally 1.0m; the earthwork in the middle part is excavated first, and then expanded to the surrounding area to effectively control the section size of the excavated pile hole .

进一步地,步骤S4中,首节钢护筒5下放时,在钢护筒5顶端焊接护筒定位钢板9,钢护筒5通过护筒定位钢板9固定在锁口上,然后继续开挖桩基,开挖完成第二节后接第二节钢护筒,接第二节钢护筒时,采用吊车起吊第二节钢护筒,然后与首节钢护筒5焊接,拆除首节钢护筒5顶端的护筒定位钢板9,通过吊车将钢护筒5缓慢下沉至孔底;在第二节钢护筒上焊接护筒定位钢板9,并将该护筒定位钢板9放置在锁口上以防止开挖过程钢护筒5下坠,然后继续开挖,如此循环,直至钢护筒5埋设完成。Further, in step S4, when the first steel casing 5 is lowered, the casing positioning steel plate 9 is welded on the top of the steel casing 5, and the steel casing 5 is fixed on the lock through the casing positioning steel plate 9, and then the excavation of the pile foundation is continued. After the second section is excavated, the second section of steel casing is connected. When the second section of steel casing is connected, the second section of steel casing is lifted by a crane, and then welded with the first section of steel casing 5, and the first section of steel casing is removed. The casing positioning steel plate 9 at the top of the casing 5 is slowly lowered to the bottom of the hole by a crane; the casing positioning steel plate 9 is welded on the second steel casing, and the casing positioning steel plate 9 is placed on the lock mouth to prevent the steel casing 5 from falling during the excavation process, and then continue to excavate, so that the cycle is completed until the steel casing 5 is buried.

实施方式三Implementation Mode Three

进一步地,步骤S5具体包括,S501.桩孔周边取芯:水磨钻开孔沿桩孔14四周进行,先沿桩孔14的内壁布置取芯点,使取芯圆与锁口4内壁相切,钻孔时向井孔外侧倾斜3~5度,预留出钻具的尺寸,保证循环施工时桩径不变,然后依次钻取外周的岩芯,外周岩芯取完后中间岩体便形成环形临空面;Further, step S5 specifically includes, S501. Coring around the pile hole: the water mill drills holes along the periphery of the pile hole 14, and first arranges coring points along the inner wall of the pile hole 14, so that the coring circle is tangent to the inner wall of the lock opening 4 When drilling, incline 3~5 degrees to the outside of the wellbore, reserve the size of the drilling tool to ensure that the pile diameter remains unchanged during circular construction, and then drill the outer peripheral cores in sequence. After the outer peripheral cores are taken, the intermediate rock mass will form circular free surface;

S502.桩芯打孔:钻孔及取芯施工完成后,用手电钻在岩体上钻眼,再将桩芯岩石分成6等份或8等份,具体等份根据桩径大小调整,便于岩体破裂;S502. Pile core drilling: After the drilling and coring construction is completed, use a hand drill to drill holes in the rock mass, and then divide the pile core rock into 6 or 8 equal parts. The specific equal parts are adjusted according to the size of the pile diameter, which is convenient rock mass fracture;

S503.桩芯分解:在手电钻钻出的孔内插入钢楔、击打钢楔依次分裂岩体,直至该层桩芯岩体全部被破裂;S503. Pile core decomposition: insert steel wedges into the holes drilled by the electric hand drill, and hit the steel wedges to split the rock mass in turn until the pile core rock mass of this layer is completely broken;

S504. 钻芯外运:水磨钻施工一边进行,一边对取出的钻芯进行外运,钻芯外运从桩孔14的一侧进行,通过卷扬机12提升吊斗10至桩孔14的锁口4,转动卷扬机12并将吊斗10中的石块倾卸入出渣料斗,运至指定的弃渣场,石块清运干净后继续下一轮的钻孔取芯,破碎外运施工。S504. Drilling core transport: while the water mill drilling is in progress, the drill core is transported out. The drill core is transported from the side of the pile hole 14, and the hoist 12 is used to lift the bucket 10 to the lock of the pile hole 14. 4. Rotate the winch 12 and dump the stones in the bucket 10 into the slag discharge hopper, and transport them to the designated waste slag yard. After the stones are cleaned, continue the next round of drilling and coring, crushing and transporting out.

由于水磨钻钻芯后桩基孔壁呈锯齿状,为保证有效桩径与设计桩径一致,要敲掉侵占桩基空间的岩石锯齿。因此进一步地,步骤S6包括,通过锁口护桩在桩孔内标出设计桩中心,检查桩基底部偏位情况并及时纠偏,同时标出下一个循环外周水磨钻钻孔取芯位置,进入下一循环的挖桩施工。Since the hole wall of the pile foundation is serrated after the core is drilled with water mill, in order to ensure that the effective pile diameter is consistent with the designed pile diameter, the rock serrations that occupy the space of the pile foundation should be knocked out. Therefore, further, step S6 includes marking the center of the designed pile in the pile hole through the locking pile, checking the deviation of the bottom of the pile foundation and correcting the deviation in time, and marking the coring position of the next cycle of the peripheral water mill drill hole, and entering The pile digging construction of the next cycle.

实施方式四Implementation Mode Four

如图1所示,一种临近既有线桥梁桩基的施工结构,包括桩孔14,所述桩孔14的顶部两侧设有锁口4,所述锁口4的一侧设有空压机3,锁口4的另一侧设有出渣机具1,所述出渣机具1的前侧向锁口延伸设有滑轮组13,所述出渣机具1的内部设有钢丝绳11,所述钢丝绳11由出渣机具1的顶部穿出并绕过滑轮组13后垂直向锁口4的下方延伸,所述钢丝绳11的底端固定连接有吊斗10;As shown in Fig. 1, a kind of construction structure of bridge pile foundation near the existing line includes pile hole 14, the top two sides of described pile hole 14 are provided with lock 4, and one side of described lock 4 is provided with air pressure machine 3, the other side of the lock 4 is provided with a slagging machine 1, the front side of the slag machine 1 extends to the lock with a pulley block 13, the inside of the slag machine 1 is provided with a steel wire rope 11, the The steel wire rope 11 passes through the top of the slag discharge machine 1 and extends vertically to the bottom of the lock 4 after bypassing the pulley block 13, and the bottom end of the steel wire rope 11 is fixedly connected with a bucket 10;

如图2所示,所述桩孔14的内部设有多节钢护筒5,且最上端的钢护筒5顶端焊接有护筒定位钢板9,所述钢护筒5通过护筒定位钢板9固定在锁口4上,所述锁口4的顶部设置有钢板垫块。As shown in Figure 2, the inside of the pile hole 14 is provided with multiple steel casings 5, and the top of the uppermost steel casing 5 is welded with a casing positioning steel plate 9, and the steel casing 5 is positioned through the casing positioning steel plate 9 It is fixed on the lock port 4, and the top of the lock port 4 is provided with a steel plate spacer.

所述桩孔14的底部内壁设有混凝土护壁6。The bottom inner wall of the pile hole 14 is provided with a concrete retaining wall 6 .

本发明所述的施工结构设备简单,操作方便,对场地的适应性The construction structure equipment of the present invention is simple, easy to operate, and adaptable to the site

好,占用场地小,可在复杂有限施工区域内应用;施工过程不但可以在没有爆破的情况下在坚硬岩层中成桩,可有效避免因爆破对挖孔桩孔壁的破坏,从而避免塌孔风险;而且又很环保,不会产生过多污染物,噪声小、对周边建筑物震动和扰动小,降低施工活动对环境的影Good, it occupies a small space and can be applied in complex and limited construction areas; during the construction process, not only can piles be formed in hard rock formations without blasting, but it can also effectively avoid damage to the hole wall of the excavated pile due to blasting, thereby avoiding hole collapse risk; and it is very environmentally friendly, will not produce too much pollutants, has low noise, little vibration and disturbance to surrounding buildings, and reduces the impact of construction activities on the environment

响;具有对地质条件适应性好、稳定性强、安全性高的特点,特别适用于离居民房和既有线桥梁较近的特硬岩层桩基施工;各个装置部件均能充分发挥效用,各阶段衔接流畅,可连续性操作,提高现场施工效率。It has the characteristics of good adaptability to geological conditions, strong stability, and high safety, and is especially suitable for the construction of pile foundations in extra-hard rock layers that are close to residential buildings and existing bridges; all components of the device can fully play their roles. The stages are connected smoothly and can be operated continuously, improving the efficiency of on-site construction.

实施方式五Implementation Mode Five

进一步地,所述出渣机具1包括支架,及置于支架内的卷扬机12,所述卷扬机12与钢丝绳11连接,用于收放钢丝绳11,且卷扬机12可旋转,避免与钢护筒跟进施工之间产生干扰;所述支架内还设置有配重块2,且所述支架优选三角形结构。Further, the slagging machine 1 includes a bracket, and a hoist 12 placed in the bracket, the hoist 12 is connected to the steel wire rope 11 for retracting the wire rope 11, and the hoist 12 can rotate to avoid following up with the steel casing Interference occurs between constructions; a counterweight 2 is also arranged in the support, and the support preferably has a triangular structure.

进一步地,所述出渣机具1上还连接有伸入桩孔14内部的照明设备8,所述照明设备8包括照明灯具及照明电缆,所述照明灯具采用安全矿灯或36V以下的安全灯,照明电缆为防水绝缘电缆。Further, the slagging machine 1 is also connected with a lighting device 8 extending into the pile hole 14. The lighting device 8 includes a lighting lamp and a lighting cable. The lighting lamp adopts a safety miner's lamp or a safety lamp below 36V. Lighting cables are waterproof insulated cables.

进一步地,所述出渣机具1上还连接有伸入桩孔14内部的抽水设备7。所述抽水设备7包括位于桩孔14底部的抽水机,及连接于所述抽水机上,并伸出桩孔14的水管,桩孔中如有渗水可采用抽水设备及时排干,从而确保施工全过程桩孔内始终处于无水的干燥环境,从而避免了既有线路基遭受水浸泡,实用性强。Further, the slag removing machine 1 is also connected with a pumping device 7 extending into the pile hole 14 . The pumping equipment 7 includes a water pump positioned at the bottom of the pile hole 14, and a water pipe connected to the water pump and extending out of the pile hole 14. If there is water seepage in the pile hole, the pumping equipment can be used to drain it in time, thereby ensuring that the whole process of construction The pile hole is always in an anhydrous and dry environment, thereby avoiding the existing line foundation from being soaked in water, and has strong practicability.

Claims (10)

1.一种临近既有线路基的桥梁桩基施工方法,其特征在于:包括下述步骤:1. a bridge pile foundation construction method near existing road foundation, is characterized in that: comprise the steps: S1.对桩孔(14)地点进行测量定位,并在桩孔(14)两侧施工锁口(4);S1. Measure and locate the location of the pile hole (14), and construct locks (4) on both sides of the pile hole (14); S2.安装出渣机具(1),并在出渣机具(1)内设置配重块(2);S2. Install the slagging tool (1), and set the counterweight (2) in the slag tool (1); S3.桩孔(14)的桩位线定好之后,从上到下逐层开挖覆盖土体,先挖中间部分的土方,然后扩及周边,开挖截面尺寸应按钢护筒(5)的外径进行控制;S3. After the pile position line of the pile hole (14) is determined, excavate and cover the soil layer by layer from top to bottom, first dig the middle part of the soil, and then expand to the surrounding area. The excavation section size should be according to the steel casing (5) The outer diameter is controlled; S4. 桩孔(14)每开挖完成一节,及时设置一节钢护筒(5)跟进;S4. After each section of pile hole (14) is excavated, set up a section of steel casing (5) in time to follow up; S5. 桩孔(14)开挖至中风化岩层后,改用水磨钻继续挖孔;S5. After the pile hole (14) is excavated to the moderately weathered rock formation, use a hydraulic drill to continue digging; S6. 水磨钻挖孔施工完成后,对桩孔(14)进行修正并开始下一循环的施工。S6. After the water mill drilling is completed, the pile hole (14) is corrected and the construction of the next cycle is started. 2.根据权利要求1所述的一种临近既有线路基的桥梁桩基施工方法,其特征在于:所述步骤S3中,开挖覆盖土体时采用镐、锹进行,遇坚硬土层,用钎破碎;开挖截面尺寸由钢护筒(5)的外径决定,开挖的每节高度为0.8~1.5m。2. A kind of bridge pile foundation construction method close to existing road foundation according to claim 1, it is characterized in that: in described step S3, adopt pickaxe, shovel to carry out when excavating and covering soil, meet hard soil layer, use The brazing is broken; the excavation section size is determined by the outer diameter of the steel casing (5), and the height of each excavation section is 0.8~1.5m. 3.根据权利要求1所述的一种临近既有线路基的桥梁桩基施工方法,其特征在于:所述步骤S4中,首节钢护筒(5)下放时,在钢护筒(5)的顶端焊接护筒定位钢板(9),钢护筒(5)通过定位钢板固定在锁口(4)上;然后继续开挖,开挖完成第二节后,先采用吊车起吊第二节钢护筒(5),然后将其与首节钢护筒(5)焊接,并拆除首节钢护筒(5)顶端的护筒定位钢板(9),通过吊车将首节钢护筒(5)缓慢下沉至桩孔(14)孔底;在第二节钢护筒(5)上焊接护筒定位钢板(9),并将该护筒定位钢板(9)放置在锁口(4)上以防止开挖过程钢护筒(5)下坠,然后继续开挖,如此循环,直至钢护筒(5)埋设完成。3. A bridge pile foundation construction method close to the existing road foundation according to claim 1, characterized in that: in the step S4, when the first steel casing (5) is lowered, the steel casing (5) The top of the casing is welded with the positioning steel plate (9), and the steel casing (5) is fixed on the lock (4) through the positioning steel plate; then continue to excavate, after the second section is excavated, use the crane to lift the second section of steel Casing (5), then weld it with the first steel casing (5), and remove the casing positioning steel plate (9) on the top of the first steel casing (5), and move the first steel casing (5) by a crane ) slowly sinks to the bottom of the pile hole (14); weld the casing positioning steel plate (9) on the second steel casing (5), and place the casing positioning steel plate (9) on the lock (4) To prevent the steel casing (5) from falling during the excavation process, and then continue to excavate, so that the cycle is completed until the steel casing (5) is buried. 4.根据权利要求1所述的一种临近既有线路基的桥梁桩基施工方法,其特征在于:所述步骤S5包括4. A kind of bridge pile foundation construction method adjacent to existing road foundation according to claim 1, is characterized in that: described step S5 comprises S501.桩孔周边取芯:水磨钻开孔沿桩孔(14)四周进行,先沿桩孔(14)的内壁布置取芯点,使取芯圆与锁口(4)内壁相切,然后依次以外倾角3~5°向下钻取外周的岩芯,外周岩芯取完后中间岩体便形成一个环形临空面;S501. Coring around the pile hole: drill holes around the pile hole (14) with a water mill, first arrange coring points along the inner wall of the pile hole (14), so that the coring circle is tangent to the inner wall of the lock (4), and then Drill down the outer peripheral cores at a camber angle of 3~5° in turn. After the outer peripheral cores are taken, the middle rock mass will form a ring-shaped free surface; S502.桩芯打孔:钻孔及取芯施工完成后,用手电钻在岩体上钻眼,再将桩芯岩石分成6等份或8等份,便于岩体破裂;S502. Pile core drilling: After the drilling and coring construction is completed, use a hand drill to drill holes in the rock mass, and then divide the pile core rock into 6 or 8 equal parts to facilitate rock mass rupture; S503.桩芯分解:在手电钻钻出的孔内插入钢楔、击打钢楔依次分裂岩体,直至该层桩芯岩体全部被破裂;S503. Pile core decomposition: insert steel wedges into the holes drilled by the electric hand drill, and hit the steel wedges to split the rock mass in turn until the pile core rock mass of this layer is completely broken; S504. 钻芯外运:水磨钻施工一边进行,一边对取出的钻芯进行外运,钻芯外运从桩孔(14)的一侧进行,通过卷扬机(12)提升吊斗(10)至桩孔(14)的锁口(4),转动卷扬机(12)并将吊斗(10)中的石块倾卸入出渣料斗,运至指定的弃渣场。S504. Drilling core transportation: while the water mill drilling is being carried out, the drill cores taken out are transported to the outside. The drilling cores are transported from the side of the pile hole (14), and the hoist (12) is used to lift the bucket (10) to the Lock mouth (4) of pile hole (14), rotate winch (12) and dump the stone in the bucket (10) into the slag discharge hopper, and transport to the designated waste slag yard. 5.一种临近既有线桥梁桩基的施工结构,其特征在于:包括桩孔(14),所述桩孔(14)的顶部两侧设有锁口(4),所述锁口(4)的一侧设有空压机(3),锁口(4)的另一侧设有出渣机具(1),所述出渣机具(1)的前侧向锁口延伸设有滑轮组(13),所述出渣机具(1)的内部设有钢丝绳(11),所述钢丝绳(11)由出渣机具(1)的顶部穿出并绕过滑轮组(13)后垂直向锁口(4)的下方延伸,所述钢丝绳(11)的底端固定连接有吊斗(10);5. A construction structure for pile foundations of bridges adjacent to existing lines, characterized in that: it includes pile holes (14), and locks (4) are provided on both sides of the top of the pile holes (14), and the locks (4 ) is provided with an air compressor (3), and the other side of the lock (4) is provided with a slag discharge tool (1), and the front side of the slag discharge tool (1) is provided with a pulley block ( 13), the inside of the slagging machine (1) is provided with a steel wire rope (11), and the steel wire rope (11) passes through the top of the slag machine (1) and goes around the pulley block (13) vertically to the lock ( 4) extends below, and the bottom end of the wire rope (11) is fixedly connected with a bucket (10); 所述桩孔(14)的内部设有多节钢护筒(5),且最上端的钢护筒(5)顶端焊接有护筒定位钢板(9),所述钢护筒(5)通过护筒定位钢板(9)固定在锁口(4)上,所述锁口(4)的顶部设置有钢板垫块。The inside of the pile hole (14) is provided with multiple steel casings (5), and the top of the uppermost steel casing (5) is welded with a casing positioning steel plate (9), and the steel casing (5) passes through the casing The barrel positioning steel plate (9) is fixed on the locking opening (4), and the top of the locking opening (4) is provided with a steel plate pad. 6.根据权利要求5所述的一种临近既有线桥梁桩基的施工结构,其特征在于:所述出渣机具(1)包括支架,及置于支架内的卷扬机(12),所述卷扬机(12)与钢丝绳(11)连接,用于收放钢丝绳(11)。6. The construction structure of a bridge pile foundation near an existing line according to claim 5, characterized in that: the slag removal machine (1) includes a bracket, and a hoist (12) placed in the bracket, and the hoist (12) is connected with steel wire rope (11), is used for retracting steel wire rope (11). 7.根据权利要求6所述的一种临近既有线桥梁桩基的施工结构,其特征在于:所述支架内还设置有配重块(2)。7. The construction structure of a bridge pile foundation adjacent to an existing line according to claim 6, characterized in that: a counterweight (2) is also arranged in the support. 8.根据权利要求5所述的一种临近既有线桥梁桩基的施工结构,其特征在于:所述出渣机具(1)上还连接有伸入桩孔(14)内部的抽水设备(7)。8. A construction structure for pile foundations of bridges adjacent to existing lines according to claim 5, characterized in that: the slag removal machine (1) is also connected with a pumping device (7) extending into the pile hole (14) ). 9.根据权利要求5所述的一种临近既有线桥梁桩基的施工结构,其特征在于:所述出渣机具(1)上还连接有伸入桩孔(14)内部的照明设备(8)。9. A construction structure for pile foundations of bridges adjacent to existing lines according to claim 5, characterized in that: the slag removal machine (1) is also connected with lighting equipment (8) extending into the pile hole (14) ). 10.根据权利要求5所述的一种临近既有线桥梁桩基的施工结构,其特征在于:所述桩孔(14)的底部内壁设有混凝土护壁(6)。10. The construction structure of a bridge pile foundation near an existing line according to claim 5, characterized in that: the bottom inner wall of the pile hole (14) is provided with a concrete retaining wall (6).
CN201910598884.8A 2019-07-04 2019-07-04 A construction method and construction structure for pile foundations of bridges adjacent to existing lines Pending CN110397026A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910598884.8A CN110397026A (en) 2019-07-04 2019-07-04 A construction method and construction structure for pile foundations of bridges adjacent to existing lines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910598884.8A CN110397026A (en) 2019-07-04 2019-07-04 A construction method and construction structure for pile foundations of bridges adjacent to existing lines

Publications (1)

Publication Number Publication Date
CN110397026A true CN110397026A (en) 2019-11-01

Family

ID=68323797

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910598884.8A Pending CN110397026A (en) 2019-07-04 2019-07-04 A construction method and construction structure for pile foundations of bridges adjacent to existing lines

Country Status (1)

Country Link
CN (1) CN110397026A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847809A (en) * 2019-11-21 2020-02-28 中国建筑第八工程局有限公司 Pile foundation pore-forming method next to underground structure
CN112982381A (en) * 2021-02-25 2021-06-18 中铁二十五局集团第五工程有限公司 Construction method of slide-resistant pile
CN113174968A (en) * 2021-04-13 2021-07-27 中交二公局东萌工程有限公司 Construction method of manual hole digging pile
CN113802558A (en) * 2021-09-26 2021-12-17 山东高速路桥集团股份有限公司 Pile foundation pore-forming construction device and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203223170U (en) * 2013-03-06 2013-10-02 中交二公局第二工程有限公司 Percussion drill hammerhead applied to drilling for pile foundation under inclined rock geological condition
CN106381868A (en) * 2016-09-06 2017-02-08 中交第航务工程局有限公司 Water abrasive drilling construction method for manual hole digging pile
CN107503344A (en) * 2017-08-01 2017-12-22 石家庄市道桥管理处 The construction method of turnover type merogenesis steel pile casting retaining wall manually digging hole filling pile
CN207934087U (en) * 2017-12-15 2018-10-02 中铁上海工程局集团有限公司 A kind of water mill bores the constructing structure of cooperation manually digging hole
CN210507418U (en) * 2019-07-04 2020-05-12 中交二公局第二工程有限公司 A Construction Structure Near Existing Line Bridge Pile Foundation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203223170U (en) * 2013-03-06 2013-10-02 中交二公局第二工程有限公司 Percussion drill hammerhead applied to drilling for pile foundation under inclined rock geological condition
CN106381868A (en) * 2016-09-06 2017-02-08 中交第航务工程局有限公司 Water abrasive drilling construction method for manual hole digging pile
CN107503344A (en) * 2017-08-01 2017-12-22 石家庄市道桥管理处 The construction method of turnover type merogenesis steel pile casting retaining wall manually digging hole filling pile
CN207934087U (en) * 2017-12-15 2018-10-02 中铁上海工程局集团有限公司 A kind of water mill bores the constructing structure of cooperation manually digging hole
CN210507418U (en) * 2019-07-04 2020-05-12 中交二公局第二工程有限公司 A Construction Structure Near Existing Line Bridge Pile Foundation

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847809A (en) * 2019-11-21 2020-02-28 中国建筑第八工程局有限公司 Pile foundation pore-forming method next to underground structure
CN110847809B (en) * 2019-11-21 2021-06-11 中国建筑第八工程局有限公司 Pile foundation pore-forming method next to underground structure
CN112982381A (en) * 2021-02-25 2021-06-18 中铁二十五局集团第五工程有限公司 Construction method of slide-resistant pile
CN113174968A (en) * 2021-04-13 2021-07-27 中交二公局东萌工程有限公司 Construction method of manual hole digging pile
CN113802558A (en) * 2021-09-26 2021-12-17 山东高速路桥集团股份有限公司 Pile foundation pore-forming construction device and method
CN113802558B (en) * 2021-09-26 2022-09-16 山东高速路桥集团股份有限公司 Pile foundation pore-forming construction device and method

Similar Documents

Publication Publication Date Title
CN101761083B (en) Underground continuous wall obstacle clearing construction method for traversing ultra-thick obstacle
CN112761076A (en) Lock catch steel pipe pile cofferdam applied to water level change condition and construction method
CN113431490B (en) Large-diameter tubular pile construction equipment and method for karst area
WO2021088349A1 (en) Method for excavating tunnel shaft
CN104746519A (en) Obstacle clearing construction method
CN116220546A (en) A construction method for combining large-diameter and long piles into holes in ultra-thick hard rock conditions
CN106545007A (en) The method of pile in stratum of the bottom for hard rock stratum
CN112281880A (en) A kind of construction method of long spiral guide hole inserting and locking steel pipe pile cofferdam in complex stratum
CN111962507A (en) Pile foundation hole forming method
CN105019431B (en) Crush and complete alternate steep dip stratified rock masses Large Diameter Super-long Bored Piles construction method
CN112942399A (en) Open caisson mechanical construction device and method for penetrating rock stratum
CN111577118A (en) Mechanical rapid hole forming construction method for anti-sliding piles
JP6319935B2 (en) Tubing pile driving method
CN108547628B (en) Quick construction method for pipe-jacking working well in upper-soft and lower-hard stratum
CN109208594B (en) Treatment method for steel casing sinking meeting boulder, steel casing structure and drilled pile
CN115419409B (en) A method for reverse well construction of a large diameter shaft in deep surface soil
CN114086964A (en) Mine non-blasting vertical shaft construction method
CN217053672U (en) Large-diameter inspection well pile drilling method construction system
CN108071110A (en) Rotary drilling rig Pile method under complex geological condition
CN115573378A (en) Platform construction method
CN214423184U (en) Be applied to hasp steel-pipe pile cofferdam under water level variation condition
CN114482078A (en) Hole forming construction method for square slide-resistant pile
CN212614488U (en) Special rotary drilling equipment for deep concrete block and gravel layer
CN210507418U (en) A Construction Structure Near Existing Line Bridge Pile Foundation
CN119083433A (en) A method for pile extraction construction using a hydraulic full-sleeve full-rotation drilling rig

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191101