CN204083610U - Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee - Google Patents

Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee Download PDF

Info

Publication number
CN204083610U
CN204083610U CN201420576847.XU CN201420576847U CN204083610U CN 204083610 U CN204083610 U CN 204083610U CN 201420576847 U CN201420576847 U CN 201420576847U CN 204083610 U CN204083610 U CN 204083610U
Authority
CN
China
Prior art keywords
pipe
crosslinked polyethylene
spanning tee
pipe fitting
outer pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420576847.XU
Other languages
Chinese (zh)
Inventor
张居山
赖贞澄
庄须文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Langge Site Energy Saving Technology Co Ltd
Original Assignee
Harbin Langge Site Energy Saving Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Langge Site Energy Saving Technology Co Ltd filed Critical Harbin Langge Site Energy Saving Technology Co Ltd
Priority to CN201420576847.XU priority Critical patent/CN204083610U/en
Application granted granted Critical
Publication of CN204083610U publication Critical patent/CN204083610U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Thermal Insulation (AREA)

Abstract

Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee.At present, domestic what generally adopt for two triode net cold and heat supplies is all steel insulating pipe spanning tee preparation process, will not reach standard far away in environmental protection, energy-conservation, economy, safety, stability etc.The utility model composition comprises: the outer pillar (1) of PE, the outer pillar of described PE comprises supervisor (5), tipping tube (6), connecting tube (7), arm (8), the outer pillar nested inside of described PE has crosslinked polyethylene working pipe pipe fitting spanning tee (4), described crosslinked polyethylene working pipe pipe fitting spanning tee comprises straight tube (9), crossing pipe (10), described straight tube is connected with described crossing pipe, polyurethane insulation coating (3) is provided with between described crosslinked polyethylene working pipe pipe fitting spanning tee and the outer pillar of described PE, alarming line (2) is embedded with in described polyurethane insulation coating.

Description

Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee
technical field:
the utility model relates to a kind of intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee.
background technique:
at present, it is domestic that what generally adopt for triode net cold and heat supply is all steel insulating pipe spanning tee preparation process, continuous intercept is needed to weld and add a large amount of difficulty of construction when installing in cell unit corridor, a large amount of economic losses is created from construction cost, thermal losses has occurred a large amount of unnecessary losses, pipeline conveying aspect also exists steel pipe and to get rusty the problems such as operation troubles, original technology and technique in a word, in environmental protection, energy-conservation, economical, safety, the aspects such as stability will not reach the performance standard of prefabricated direct-buried thermal insulation pipe crosslinked polyethylene work pipe fitting reducing far away.
summary of the invention:
the purpose of this utility model is to provide a kind of intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee.
above-mentioned object is realized by following technological scheme:
a kind of intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee, its composition comprises: the outer pillar of PE, the outer pillar of described PE comprises supervisor, tipping tube, connecting tube, arm, the outer pillar nested inside of described PE has crosslinked polyethylene working pipe pipe fitting spanning tee, described crosslinked polyethylene working pipe pipe fitting spanning tee comprises straight tube, crossing pipe, described straight tube is connected with described crossing pipe, polyurethane insulation coating is provided with between described crosslinked polyethylene working pipe pipe fitting spanning tee and the outer pillar of described PE, alarming line is embedded with in described polyurethane insulation coating.
described intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee, described supervisor is connected with one end of described tipping tube, the other end of described tipping tube is connected with described arm by described connecting tube, and described supervisor is vertical with described arm.
described intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee, described alarming line comprises straight pipe-line, crossover line, described straight pipe-line is embedded in the upper right of described straight tube, described crossover line is embedded in above described crossing pipe, and described straight pipe-line is connected with described crossover line.
the beneficial effects of the utility model:
the utility model is different from traditional prefabricated direct-buried thermal insulation pipe, getting with existing crosslinked polyethylene pipe has replaced original seamless steel pipe to be the working steel tube of prefabricated direct-buried thermal insulation pipe, the convenience that prefabricated direct-buried thermal insulation pipe crosslinked polyethylene working pipe is installed is far longer than traditional type thermal insulation pipe, heat loss 34% can be saved in heat waste consumption, year cost-saving 34% can be reached in operating cost, operating cost can save 54%, can 34% be reduced in minimizing carbon emission amount, can meet international standards in working life minimum 30 years.
the utility model arranges tipping tube for avoiding adjacent, parallel pipeline, the tipping tube of different amount can be selected to be welded into the cross-domain threeway of different size and model, more effectively be connected to the pipeline of embedded underground, use RPUF as thermal insulation layer, high insulating effect, water absorption rate is low, effectively ensure that the safety assurance of the pipeline intersection of different circuit, alarming line is set, once seepage occurs in pipeline somewhere, pass to by alarming line the exact position and leak magnitude knowing and leak.
accompanying drawing illustrates:
accompanying drawing 1 is front elevation of the present utility model.
accompanying drawing 2 is plan views of the present utility model.
accompanying drawing 3 is left views of the present utility model.
embodiment:
embodiment 1:
a kind of intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee, its composition comprises: the outer pillar 1 of PE, the outer pillar of described PE comprises supervisor 5, tipping tube 6, connecting tube 7, arm 8, the outer pillar nested inside of described PE has crosslinked polyethylene working pipe pipe fitting spanning tee 4, described crosslinked polyethylene working pipe pipe fitting spanning tee comprises straight tube 9, crossing pipe 10, described straight tube is connected with described crossing pipe, polyurethane insulation coating 3 is provided with between described crosslinked polyethylene working pipe pipe fitting spanning tee and the outer pillar of described PE, alarming line 2 is embedded with in described polyurethane insulation coating.
embodiment 2:
intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee according to embodiment 1, described supervisor is connected with one end of described tipping tube, the other end of described tipping tube is connected with described arm by described connecting tube, and described supervisor is vertical with described arm.
embodiment 3:
intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee according to embodiment 1 or 2, described alarming line comprises straight pipe-line 11, crossover line 12, described straight pipe-line is embedded in the upper right of described straight tube, described crossover line is embedded in above described crossing pipe, and described straight pipe-line is connected with described crossover line.
embodiment 4:
described intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee, crosslinked polyethylene is adopted to be pipeline foundation raw material, at the surface spraying polyurethane foam of crosslinked polyethylene, outer pillar adopts high density polyethylene (HDPE) and HDPE100 level raw material, is made into prefabricated direct-buried thermal insulation pipe crosslinked polyethylene work pipe fitting spanning tee.After crosslinked polyethylene pipe is installed support, the hdpe pipe of different amount is made to form the outer pillar of prefabricated direct-buried thermal insulation pipe crosslinked polyethylene work pipe fitting spanning tee by highi degree of accuracy PE welding gun, then pipe ends installed foaming guard seal and leave exhaust sieve, eventually pass foaming machine spray foam to foam, carry out end face finishing process after slaking, after more than completing, namely form final finished.

Claims (3)

1. an intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee, its composition comprises: the outer pillar of PE, it is characterized in that: the outer pillar of described PE comprises supervisor, tipping tube, connecting tube, arm, the outer pillar nested inside of described PE has crosslinked polyethylene working pipe pipe fitting spanning tee, described crosslinked polyethylene working pipe pipe fitting spanning tee comprises straight tube, crossing pipe, described straight tube is connected with described crossing pipe, polyurethane insulation coating is provided with between described crosslinked polyethylene working pipe pipe fitting spanning tee and the outer pillar of described PE, alarming line is embedded with in described polyurethane insulation coating.
2. intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee according to claim 1, it is characterized in that: described supervisor is connected with one end of described tipping tube, the other end of described tipping tube is connected with described arm by described connecting tube, and described supervisor is vertical with described arm.
3. intelligent prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee according to claim 1 and 2, it is characterized in that: described alarming line comprises straight pipe-line, crossover line, described straight pipe-line is embedded in the upper right of described straight tube, described crossover line is embedded in above described crossing pipe, and described straight pipe-line is connected with described crossover line.
CN201420576847.XU 2014-10-08 2014-10-08 Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee Expired - Fee Related CN204083610U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420576847.XU CN204083610U (en) 2014-10-08 2014-10-08 Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420576847.XU CN204083610U (en) 2014-10-08 2014-10-08 Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee

Publications (1)

Publication Number Publication Date
CN204083610U true CN204083610U (en) 2015-01-07

Family

ID=52176331

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420576847.XU Expired - Fee Related CN204083610U (en) 2014-10-08 2014-10-08 Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee

Country Status (1)

Country Link
CN (1) CN204083610U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104266024A (en) * 2014-10-08 2015-01-07 哈尔滨朗格斯特节能科技有限公司 Intelligent prefabricated direct burial thermal insulation pipe cross linked polyethylene pipe fitting span tee joint and manufacture method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104266024A (en) * 2014-10-08 2015-01-07 哈尔滨朗格斯特节能科技有限公司 Intelligent prefabricated direct burial thermal insulation pipe cross linked polyethylene pipe fitting span tee joint and manufacture method

Similar Documents

Publication Publication Date Title
CN204127495U (en) The prefabricated direct-buried crosslinked polyethylene of intelligence two-tube reducing work thermal insulation pipe
CN204083610U (en) Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting spanning tee
CN204176222U (en) Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene work pipe elbow
CN104295844A (en) Crosslinked polyethylene pipe fitting parallel tee joint for intelligent prefabricated directly-buried insulating pipe and manufacturing method thereof
CN104455878A (en) Working steel tube double-tube tube fitting bend of intelligent prefabricated direct buried heating insulating tube and manufacturing method
CN104266024A (en) Intelligent prefabricated direct burial thermal insulation pipe cross linked polyethylene pipe fitting span tee joint and manufacture method
CN104455940A (en) Crosslinked polyethylene double-tube parallel tee joint of intelligent prefabricated direct buried heating insulating tube and foaming method
CN104295845A (en) Crosslinked polyethylene work pipe fitting elbow for directly-buried heat preservation pipe intelligently prefabricated and manufacturing method
CN204099798U (en) The two-tube parallel tee of intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene
CN204176167U (en) Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene working pipe
CN104373699A (en) Intelligent prefabricated directly-buried thermal insulation pipe crosslinked polyethylene working pipe and manufacturing method
CN204356915U (en) The self waterproof structure that steel pipe column is crossing with concrete of basement exterior wall
CN204062283U (en) The two-tube reducing tee of intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene
CN204187193U (en) Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene pipe fitting reducing tee
CN204062285U (en) Intelligence prefabricated direct-buried thermal insulation pipe crosslinked polyethylene work two-tube spanning tee
CN204176131U (en) There is the prefabricated direct-buried thermal insulation pipe of crosslinked polyethylene reducing work pipe fitting
CN205276383U (en) Fire hydrant water supply system
CN204062286U (en) Intelligence prefabricated direct-buried thermal insulation pipe double steel tube pipe fitting reducing tee
CN204176224U (en) The two-tube pipe elbow of intelligence prefabricated direct-buried thermal insulation pipe working steel tube
CN203927236U (en) A kind of fault pipeline maintenance device
CN104455877A (en) Crosslinked polyethylene double-tube tube fitting bend of intelligent prefabricated direct buried heating insulating tube and manufacturing method
CN104295842B (en) Intelligent prefabricated direct-buried heat preservation pipe cross-linked polyethylene double-pipe reducing tee joint and installation method
CN203412006U (en) Around-flow prevention device for concrete construction
CN204062284U (en) The two-tube pipe fitting parallel tee of intelligence prefabricated direct-buried thermal insulation pipe working steel tube
CN104279389A (en) Intelligent prefabricated directly-buried thermal insulation pipe crosslinked polyethylene pipe fitting reducer tee joint

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150107

Termination date: 20211008

CF01 Termination of patent right due to non-payment of annual fee