CN204035911U - Stainless steel tube splicing bracing frame - Google Patents

Stainless steel tube splicing bracing frame Download PDF

Info

Publication number
CN204035911U
CN204035911U CN201420491448.3U CN201420491448U CN204035911U CN 204035911 U CN204035911 U CN 204035911U CN 201420491448 U CN201420491448 U CN 201420491448U CN 204035911 U CN204035911 U CN 204035911U
Authority
CN
China
Prior art keywords
stainless steel
steel tube
strip back
block
bracing frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420491448.3U
Other languages
Chinese (zh)
Inventor
陆奇宇
刘凤妍
白战良
王维
赵欣欣
刘文友
陶晶
庞杰伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangnan Shipyard Group Co Ltd
Original Assignee
Shanghai Jiangnan Changxing Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiangnan Changxing Heavy Industry Co Ltd filed Critical Shanghai Jiangnan Changxing Heavy Industry Co Ltd
Priority to CN201420491448.3U priority Critical patent/CN204035911U/en
Application granted granted Critical
Publication of CN204035911U publication Critical patent/CN204035911U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model provides a kind of stainless steel tube splicing bracing frame, support frame as described above at least comprises: the crossbeam be made up of channel-section steel, and be located at the left support pin be made up of channel-section steel and the right support pin at two ends, described crossbeam bottom surface respectively, described crossbeam is provided with along its length the strip back-up block be made up of wood, and described strip back-up block offers several first bolt hole, described crossbeam offers the second bolt hole, in described first bolt and the second corresponding bolt hole, be equipped with bolt; Described strip back-up block end face offers the several grooves matched with stainless outer circle wall.Described strip back-up block is made up of wood, and wood can not pollute stainless steel tube, and wood easy to drawing materials is not easy to wear, easily process and low cost of manufacture, and use cost is low; For the stainless steel tube to be spliced of different-diameter, as long as replace with the described strip back-up block offering the groove that stainless steel tube outer circle wall to be spliced with this mates, applicability is strong.

Description

Stainless steel tube splicing bracing frame
Technical field
The utility model relates to a kind of bracing frame, particularly relates to a kind of stainless steel tube splicing bracing frame.
Background technology
When splicing stainless steel tube peculiar to vessel, should be less than 0.4mm according to the splicing Central Symmetry deviation of technological requirement stainless steel tube and stainless steel tube, stainless steel tube groove welding gap is less than or equal to 2mm; Also should meet other techniques and technical requirement simultaneously.Therefore, in order to ensure the quality of splicing stainless steel tube, need to design a kind of bracing frame effectively to fix stainless steel tube.
Bracing frame traditionally for fixing stainless steel tube is all be made up of iron, in splicing stainless steel tube process, the bracing frame that stainless steel tube will be fabricated from iron at this rotates and moves, iron ion meeting osmosis pollution stainless steel in the bracing frame should be made up of iron; The bracing frame should be made up of iron is eliminated gradually.
At present, in the bracing frame be made up of iron, iron ion can osmosis pollution stainless steel, and on the bracing frame be made up of iron, the isolated substance such as spray paint, prevents iron contamination stainless steel.Although the isolated substances such as paint can prevent iron contamination stainless steel, but after using a period of time, the isolated substances such as paint can be worn and expose iron, even if if do not repair or change this bracing frame being coated with the isolated substances such as paint the stainless problem of iron ion osmosis pollution will occur, visible use cost is high.Meanwhile, the isolated substances such as spray paint add the technique making bracing frame, and add manufacture difficulty, thus considerably increase manufacturing cost.In addition, all parts of bracing frame welds mutually, not easily changes the support sector of bracing frame, and inconvenience is applicable to the stainless steel tube of different-diameter, poor for applicability.
Utility model content
The shortcoming of prior art in view of the above, the purpose of this utility model is to provide one can avoid polluting stainless steel tube, easily processing, uses and low cost of manufacture and the strong stainless steel tube splicing bracing frame of applicability.
For achieving the above object and other relevant objects, the utility model provides a kind of stainless steel tube splicing bracing frame, support frame as described above at least comprises: the crossbeam be made up of channel-section steel, and be located at the left support pin be made up of channel-section steel and the right support pin at two ends, described crossbeam bottom surface respectively, described crossbeam is provided with along its length at least one the strip back-up block be made up of wood, and described strip back-up block offers several first bolt hole from top to bottom, described crossbeam also offers and described first bolt hole several second bolt hole one to one, bolt is equipped with in described first bolt and the second corresponding bolt hole, described strip back-up block end face is parallel in the width direction offers the several grooves matched with stainless outer circle wall, and described groove and described first bolt hole are staggered and arrange.
Further, described crossbeam is provided with along its length several strip back-up block, and adjacent two described strip back-up blocks are connected by connecting plate.
Further, described connecting plate is positioned at described strip back-up block side, and described connecting plate is connected with corresponding two described strip back-up blocks by screw.
Further, described left support pin and right support pin include the first supporting leg and the second supporting leg, and the first described supporting leg is connected with described crossbeam with the second supporting leg end face, and between the first described supporting leg and the second supporting leg, angle is 60 °.
Further, the first stiffener is provided with between the first described supporting leg and the second supporting leg.
Further, the second stiffener is provided with between described left support pin and right support pin.
As mentioned above, stainless steel tube splicing bracing frame of the present utility model, has following beneficial effect:
Described strip back-up block end face is provided with several groove, stainless steel tube to be spliced and described groove fit, this groove facilitates stainless steel tube to rotate and moves, described strip back-up block is made up of wood, wood can not pollute stainless steel tube, and wood easy to drawing materials, greatly reduce manufacturing cost, and easily process, meanwhile, described strip back-up block is not easily worn, even if there is the problem that iron ion osmosis pollution stainless steel tube also can not occur in wearing and tearing, greatly reduce the frequency repairing and change described strip back-up block, therefore use cost is low; In addition, being fixedly linked to make described strip back-up block and described crossbeam by being equipped with bolt in described first bolt and the second corresponding bolt hole, as long as disassemble described bolt, just can changing described strip back-up block; For the stainless steel tube to be spliced of different-diameter, as long as replace with the described strip back-up block offering the groove that stainless steel tube outer circle wall to be spliced with this mates, applicability is strong.
Accompanying drawing explanation
Fig. 1 is shown as the schematic diagram of the first embodiment of stainless steel tube splicing bracing frame of the present utility model.
Fig. 2 is shown as the schematic diagram of the second embodiment of stainless steel tube splicing bracing frame of the present utility model.
Fig. 3 is shown as the stereogram of strip back-up block of the present utility model.
Element numbers explanation
1 crossbeam
21 left support pin
22 right support pin
201 first supporting legs
202 second supporting legs
3 strip back-up blocks
31 first bolts hole
32 grooves
4 connecting plates
41 screws
5 first stiffeners
Detailed description of the invention
By particular specific embodiment, embodiment of the present utility model is described below, person skilled in the art scholar the content disclosed by this description can understand other advantages of the present utility model and effect easily.
Refer to Fig. 1 to Fig. 3.Notice, structure, ratio, size etc. that this description institute accompanying drawings illustrates, content all only in order to coordinate description to disclose, understand for person skilled in the art scholar and read, and be not used to limit the enforceable qualifications of the utility model, therefore the not technical essential meaning of tool, the adjustment of the modification of any structure, the change of proportionate relationship or size, do not affecting under effect that the utility model can produce and the object that can reach, all should still drop in scope that technology contents that the utility model discloses can contain.Simultaneously, quote in this description as " on ", D score, "left", "right", " centre " and " one " etc. term, also only for ease of understanding of describing, and be not used to limit the enforceable scope of the utility model, the change of its relativeness or adjustment, under changing technology contents without essence, when being also considered as the enforceable category of the utility model.
Fig. 1 shows the first embodiment of a kind of stainless steel tube splicing bracing frame that the utility model provides, support frame as described above at least comprises: the crossbeam 1 be made up of channel-section steel, and be located at the left support pin 21 be made up of channel-section steel and the right support pin 22 at two ends, described crossbeam 1 bottom surface respectively, described crossbeam 1 is provided with along its length the strip back-up block 3 be made up of wood, and described strip back-up block 3 offers several first bolt hole 31 from top to bottom, described crossbeam 1 also offers and described first bolt hole 31 several second bolt hole one to one, bolt is equipped with in described first bolt and the second corresponding bolt hole, described strip back-up block 3 end face is parallel in the width direction offers the several grooves 32 matched with stainless outer circle wall, and described groove 32 and described first bolt hole 31 are staggered and arrange, and see Fig. 3.
With reference to figure 1 and Fig. 3, during use, as long as several stainless steel tube splicing bracing frames are formed a line, then stainless steel tube to be spliced is placed in described groove 32, and the termination making stainless steel tube to be spliced is between adjacent two this stainless steel tube splicing bracing frames, just can splice.Because stainless steel tube to be spliced coordinates with described groove 32, this groove 32 facilitates stainless steel tube to rotate and moves, described strip back-up block 3 is made up of wood, wood can not pollute stainless steel tube, eliminate the isolated substances such as spray paint to prevent iron contamination stainless steel, processing technology is relatively simple, and wood easy to drawing materials, greatly reduce manufacturing cost, and easily process; Meanwhile, described strip back-up block 3 is not easily worn, even if there is the problem that iron ion osmosis pollution stainless steel tube also can not occur in wearing and tearing, greatly reduce the frequency repairing and change described strip back-up block 3, therefore use cost is low; In addition, as long as disassemble described bolt, described strip back-up block 3 just can be changed; For the stainless steel tube to be spliced of different-diameter, as long as replace with the described strip back-up block 3 of the groove 32 that the outer circle wall that offers stainless steel tube to be spliced with this mates, applicability is strong.
Preferably, in order to ensure the mechanical strength of described left support pin 21 and right support pin 22 and the left support pin 21 described in reducing and the processing cost of right support pin 22, described left support pin 21 and right support pin 22 include the first supporting leg 201 and the second supporting leg 202, the first described supporting leg 201 is connected with described crossbeam 1 with the second supporting leg 202 end face, and between the first described supporting leg 201 and the second supporting leg 202, angle is 60 °, sees Fig. 1.
In addition, in order to improve the first described supporting leg 201 and the mechanical strength of the second supporting leg 202, between the first described supporting leg 201 and the second supporting leg 202, being provided with the first stiffener 5, seeing Fig. 1.
In addition, in order to improve described left support pin 21 and the mechanical strength of right support pin 22, the second stiffener (not shown) between described left support pin 21 and right support pin 22, is provided with.Preferably, the first described stiffener 5 second stiffener surrounds a rectangle, sees Fig. 1.
Fig. 2 shows the second embodiment of a kind of stainless steel tube splicing bracing frame that the utility model provides, mainly be with the first embodiment difference: described crossbeam 1 is provided with several strip back-up block 3, described strip back-up block 3 arranges along described crossbeam 1 length direction, and adjacent two described strip back-up blocks 3 are connected by connecting plate 4.Preferably, described connecting plate 4 is positioned at described strip back-up block 3 side, and described connecting plate 4 is connected with corresponding two described strip back-up blocks 3 by screw 41.The two ends of best described connecting plate 4 are connected with corresponding described strip back-up block 3 respectively by three screws 41, and the distribution triangular in shape of three described screws 41.
In sum, stainless steel tube splicing bracing frame of the present utility model can not only be avoided polluting stainless steel tube, easily processing, uses and low cost of manufacture and applicability is strong.So the utility model effectively overcomes various shortcoming of the prior art and tool high industrial utilization.
Above-described embodiment is illustrative principle of the present utility model and effect thereof only, but not for limiting the utility model.Any person skilled in the art scholar all without prejudice under spirit of the present utility model and category, can modify above-described embodiment or changes.Therefore, such as have in art and usually know that the knowledgeable modifies or changes not departing from all equivalences completed under the spirit and technological thought that the utility model discloses, must be contained by claim of the present utility model.

Claims (6)

1. a stainless steel tube splicing bracing frame, it is characterized in that, support frame as described above at least comprises: the crossbeam (1) be made up of channel-section steel, and be located at the left support pin (21) be made up of channel-section steel and the right support pin (22) at described crossbeam (1) two ends, bottom surface respectively, described crossbeam (1) is provided with along its length at least one the strip back-up block (3) be made up of wood, and described strip back-up block (3) offers several first bolt hole (31) from top to bottom, described crossbeam (1) also offers and described first bolt hole (31) several second bolt hole one to one, bolt is equipped with in described first bolt and the second corresponding bolt hole, described strip back-up block (3) end face is parallel in the width direction offers the several grooves (32) matched with stainless outer circle wall, and described groove (32) and described first bolt hole (31) are staggered and arrange.
2. stainless steel tube splicing bracing frame according to claim 1, it is characterized in that: described crossbeam (1) is provided with along its length several strip back-up block (3), and adjacent two described strip back-up blocks (3) are connected by connecting plate (4).
3. stainless steel tube splicing bracing frame according to claim 2, it is characterized in that: described connecting plate (4) is positioned at described strip back-up block (3) side, and described connecting plate (4) is connected with corresponding two described strip back-up blocks (3) by screw (41).
4. stainless steel tube splicing bracing frame according to claim 1, it is characterized in that: described left support pin (21) and right support pin (22) include the first supporting leg (201) and the second supporting leg (202), described the first supporting leg (201) is connected with described crossbeam (1) with the second supporting leg (202) end face, and between described the first supporting leg (201) and the second supporting leg (202), angle is 60 °.
5. stainless steel tube splicing bracing frame according to claim 4, is characterized in that: be provided with the first stiffener (5) between described the first supporting leg (201) and the second supporting leg (202).
6. stainless steel tube splicing bracing frame according to claim 1, is characterized in that: be provided with the second stiffener between described left support pin (21) and right support pin (22).
CN201420491448.3U 2014-08-28 2014-08-28 Stainless steel tube splicing bracing frame Expired - Lifetime CN204035911U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420491448.3U CN204035911U (en) 2014-08-28 2014-08-28 Stainless steel tube splicing bracing frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420491448.3U CN204035911U (en) 2014-08-28 2014-08-28 Stainless steel tube splicing bracing frame

Publications (1)

Publication Number Publication Date
CN204035911U true CN204035911U (en) 2014-12-24

Family

ID=52236619

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420491448.3U Expired - Lifetime CN204035911U (en) 2014-08-28 2014-08-28 Stainless steel tube splicing bracing frame

Country Status (1)

Country Link
CN (1) CN204035911U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155778A (en) * 2015-09-29 2015-12-16 江苏沪宁钢机股份有限公司 Combined steel pipe column component and manufacturing method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105155778A (en) * 2015-09-29 2015-12-16 江苏沪宁钢机股份有限公司 Combined steel pipe column component and manufacturing method thereof
CN105155778B (en) * 2015-09-29 2017-10-10 江苏沪宁钢机股份有限公司 A kind of processing method of combined steel pipe post component

Similar Documents

Publication Publication Date Title
CN203419349U (en) Plastic pallet with detachable piers capable of being assembled
CN204504612U (en) Positioning limit frock
CN204035911U (en) Stainless steel tube splicing bracing frame
CN105113638B (en) A kind of new box corner of arch and preparation method thereof
CN204038843U (en) One stands up lifting frame
CN207492366U (en) A kind of frame equipments for goods
CN204868207U (en) Flange processing workstation
CN205703104U (en) A kind of stainless steel tube apparatus for welding and positioning
CN203485169U (en) Liquid crystal glass substrate arranging device
CN107150200A (en) A kind of Combined sheet metal part weld job platform
CN204913095U (en) It rules and measuring caliper to weld welding hole
CN203830476U (en) Novel small-radius bending tool assembly for bending machine
CN203853708U (en) Dual steel-wheel roller cross beam splicing fixture
CN202684397U (en) Pressure explorator for splicing flat-bulb steel
CN205008166U (en) Application is wallboard for sealing chamber
CN208519490U (en) A kind of clamping structure for I-steel connection
CN204938054U (en) A kind of metal shelf of adjustable space
CN204122949U (en) A kind of track of submerged arc welding machine
CN205386020U (en) Concatenation formula exhibition frame
CN204818525U (en) Frame welding frock commonly used
CN204248724U (en) Frock reprocessed by a kind of large prism
CN202702661U (en) Drum pressing machine
CN204917889U (en) Tin seamer gyro wheel reset structure
CN203862457U (en) Steel-plastic composite pipe supporting frame
CN204773174U (en) Structure is changed to casting machine mould

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20181225

Address after: 201913 No. 988 Changxing Jiangnan Avenue, Chongming County, Chongming District, Shanghai

Patentee after: JIANGNAN SHIPYARD (GROUP) Co.,Ltd.

Address before: 201913 1888 Jiangnan Avenue, Changxing Township, Chongming County, Shanghai

Patentee before: Shanghai Jiangnan Changxing Heavy Industry Co.,Ltd.

TR01 Transfer of patent right
CX01 Expiry of patent term

Granted publication date: 20141224