CN203977384U - Pre-buried guide rail - Google Patents

Pre-buried guide rail Download PDF

Info

Publication number
CN203977384U
CN203977384U CN201420394160.4U CN201420394160U CN203977384U CN 203977384 U CN203977384 U CN 203977384U CN 201420394160 U CN201420394160 U CN 201420394160U CN 203977384 U CN203977384 U CN 203977384U
Authority
CN
China
Prior art keywords
buried
guide rail
bellows
construction
buried guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420394160.4U
Other languages
Chinese (zh)
Inventor
翟俊勇
江道远
文小林
陈程
张立军
马海军
张昌田
李翔
赖勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd
Original Assignee
Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd filed Critical Chengdu Hydropower Construction Engineering Co Ltd of Sinohydro Bureau 7 Co Ltd
Priority to CN201420394160.4U priority Critical patent/CN203977384U/en
Application granted granted Critical
Publication of CN203977384U publication Critical patent/CN203977384U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

Pre-buried guide rail, relates to the pre-buried device in duct in the construction projects such as water conservancy and hydropower.It as one group, is laid in circular holes chamber surface by two reinforcing bars, forms circuit, and pre-buried guide rail two ends are connected to prefabricated ground tackle groove, between ground tackle groove two-port, horn mouth are installed in advance.The beneficial effect the utlity model has is: in the Embedment Construction of pressure pipeline construction pre-stress anchor cable duct, pre-buried guide rail is installed, can the pre-buried bellows line style of guiding keep smooth, guarantee the installation accuracy of pre-buried bellows, effectively solve the guiding difficult problem in bellows installation process.

Description

Pre-buried guide rail
Technical field:
Pre-buried guide rail, relates to the pre-buried device in duct in the construction projects such as water conservancy and hydropower.
Background technology:
In the pressure pipeline structure construction of the construction projects such as water conservancy and hydropower, ring anchor pre-stress construction is a crucial step, and duct pre-buried be the first step of whole ring anchor pre-stress construction operation.The conventional method of duct Embedment Construction is: with galvanized wire, bellows and structure reinforcing bars are carried out to colligation and fix, this method is simple, but defect is more, as fixing in colligation insecure, location is inaccurate, bellows line style is not smooth, during concreting, bellows is easily shifted, distortion, breakage, stop up bellows duct etc., cause postorder work cannot carry out or carry out and be the devil.For guaranteeing the total quality of ring anchor prestress engineering, pre-buried as the duct of first operation, it is particularly important that quality control on construction seems.How to guarantee the precision (mm level) of duct Embedment Construction, improve ring anchor stretch-draw success rate and reduce loss of prestress, guarantee the validity of prestress application, most important to the prestressed integral construction quality of ring anchor, construction speed, cost consumption etc.The pre-buried construction prestressed cable mainly for the pre-buried bellows of needs in duct pre-buried, the key of controlling duct Embedment Construction quality is must accurately limit the installation site of pre-buried bellows and the trend of pre-buried bellows before pre-buried bellows, guide pre-buried bellows line style to keep smooth, guarantee installation accuracy.And cavern's wall very thin (bellows and the structure reinforcing bars concrete of building above only have 45cm thick) in ring anchor pre-stress construction, ring anchor spacing only has 45cm, and its operating space is not enough, accurately limit pre-buried bellows installation site, guiding pre-buried bellows line style to keep smooth, is also a difficult problem.
Summary of the invention:
Problem to be solved in the utility model provides exactly a kind of and in the Embedment Construction of pressure pipeline construction pre-stress anchor cable duct, can guide pre-buried bellows line style to keep smooth for above deficiency, guarantee the duct pre-embedded device of pre-buried bellows installation accuracy.Its technical scheme is as follows:
It as one group, is laid in circular holes chamber surface by two reinforcing bars, forms circuit, and pre-buried guide rail two ends are connected to prefabricated ground tackle groove, between ground tackle groove two-port, horn mouth are installed in advance.
Described two rebar spacings are 100mm~120mm.
Described reinforcing bar adopts Φ 12mm~Φ 14mm screw-thread steel.
Compared with prior art, the beneficial effect the utlity model has is:
1, in the Embedment Construction of pressure pipeline construction pre-stress anchor cable duct, pre-buried guide rail is installed, can be guided pre-buried bellows line style to keep smooth, guarantee the installation accuracy of pre-buried bellows, effectively solve the guiding difficult problem in bellows installation process.
2, the scientific construction of pre-buried guide rail in duct is pre-buried, simple, saves manpower financial capacity.COMPREHENSIVE CALCULATING, raises the efficiency 1~2 times than traditional construction method.
Accompanying drawing explanation:
Fig. 1 is the pre-buried guide rail structure schematic diagram of the utility model;
Fig. 2 is that the pre-buried guide rail of the utility model is used state Local map;
Fig. 3 is that the U-shaped caliber of the utility model limits card structure schematic diagram;
Fig. 4 is the use view of the pre-buried guide rail of the utility model in circular cavern.
The specific embodiment:
Referring to Fig. 1~Fig. 4, the pre-buried guide rail of the utility model by two reinforcing bars 1 as one group, by bending welding, it after moulding, is annular, be laid in the front whole shield structure lining cutting circular holes chamber surface of concreting, form circuit, pre-buried guide rail two ends are connected to prefabricated ground tackle groove 9, between ground tackle groove 9 two-port, horn mouth 10 are installed in advance.In figure, 7 is Dong Shibi, and 8 is concrete floor.
Described two reinforcing bar 1 spacing are 100mm~120mm.
Described reinforcing bar 1 adopts Φ 12mm~Φ 14mm screw-thread steel.
The construction method of pre-buried guide rail in duct is pre-buried, comprises the following steps:
1) by measuring and locating, determine the mounting center line of every bellows 4 in tunnel, according to bellows mounting center line, determine the installation site of pre-buried guide rail 2;
2) pre-buried guide rail 2 by two reinforcing bars as one group, two rebar spacings are 100mm~120mm, the mounting center line of pre-buried guide rail overlaps with bellows mounting center line, length and trend that the trend of pre-buried guide rail is installed with bellows with length are consistent, pre-buried guide rail circularizes and is laid in the front whole shield structure lining cutting circular holes chamber surface of concreting, forms circuit; Pre-buried guide rail two ends are connected to prefabricated ground tackle groove 9, between ground tackle groove 9 two-port, horn mouth 10 are installed in advance;
3) at the interior installation bellows 4 of pre-buried guide rail 2, the line style of pre-buried guide rail 2 guiding bellowss 4;
4) accurately location and installation good after, pre-buried guide rail and bellows and tunnel lining structure reinforcing bars are welded and fixed;
5) complete after above-mentioned operation, on bellows, every 0.8m~1.0m, U-shaped caliber is installed and is limited card 3, shape and cross-sectional shape of bellows that U-shaped caliber limits card adapt, U-shaped caliber limits card and is staggeredly arranged with the galvanized wire of colligation bellows and pre-buried guide rail, and the card article 6 that U-shaped caliber limits card is welded and fixed with pre-buried guide rail; Make U-shaped caliber limit card and limit fixedly bellows installation site, guarantee bellows install after in concrete casting process not because concrete is built uplift pressure and vibration is subjected to displacement and damages.
Described bellows adopts Φ 90mm~Φ 95mm steel screw thread bellows.
Described U-shaped caliber limits the card article 6 that card 3 comprises arc top 5 and 5 two ends, arc top, and arc top 5 and card article 6 form U-shaped body.
Institute is set forth in U-shaped body and adopts 8# round steel to make, and round steel is the round steel of available other model also, and 8# round steel is cost-saving.
Long 24cm~the 30cm of described round steel.

Claims (3)

1. a pre-buried guide rail, it is characterized in that by two reinforcing bars (1), as one group, being laid in circular holes chamber surface, form circuit, pre-buried guide rail two ends are connected to prefabricated ground tackle groove (9), between ground tackle groove (9) two-port, horn mouth (10) are installed in advance.
2. pre-buried guide rail according to claim 1, is characterized in that two reinforcing bars (1) spacing is 100mm~120mm.
3. pre-buried guide rail according to claim 1, is characterized in that reinforcing bar (1) adopts Φ 12mm~Φ 14mm screw-thread steel.
CN201420394160.4U 2014-07-16 2014-07-16 Pre-buried guide rail Withdrawn - After Issue CN203977384U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420394160.4U CN203977384U (en) 2014-07-16 2014-07-16 Pre-buried guide rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420394160.4U CN203977384U (en) 2014-07-16 2014-07-16 Pre-buried guide rail

Publications (1)

Publication Number Publication Date
CN203977384U true CN203977384U (en) 2014-12-03

Family

ID=51974842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420394160.4U Withdrawn - After Issue CN203977384U (en) 2014-07-16 2014-07-16 Pre-buried guide rail

Country Status (1)

Country Link
CN (1) CN203977384U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104088262A (en) * 2014-07-16 2014-10-08 中国水利水电第七工程局成都水电建设工程有限公司 Pre-embedded guide rail and pre-embedded guide rail construction method in duct pre-embedding

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104088262A (en) * 2014-07-16 2014-10-08 中国水利水电第七工程局成都水电建设工程有限公司 Pre-embedded guide rail and pre-embedded guide rail construction method in duct pre-embedding

Similar Documents

Publication Publication Date Title
CN103255840A (en) Combined built-in fitting for concrete walls and column tie bars and installation construction method thereof
CN204984424U (en) Prevent submerged cushion device of opening shield tail pipe piece
CN202125080U (en) Heat dissipation device for concrete
CN203230046U (en) Combined embedded part for concrete wall, column and splice bars
CN103485370B (en) A kind of concrete construction control method preventing wallboard harmful cracks
CN204459477U (en) A kind of pre-buried pipeline fixing bracket
CN203977384U (en) Pre-buried guide rail
CN110700319A (en) Comprehensive pipe gallery is with unilateral formwork frock
CN203979648U (en) U-shaped caliber limits card
CN104121423A (en) U-shaped pipe diameter limit clamp and construction method of U-shaped pipe diameter limit clamp in pore way embedment
CN204645423U (en) Cassette ceiling high intensity thinner tube hollow section anti-floating stopping means and prepare instrument
CN206408951U (en) A kind of architectural industrialization project conversion layer position level ladder muscle
CN206071601U (en) The device that a kind of prevention tunnel double-lining vault comes to nothing
CN102071801A (en) Positioning method and structure for hollow pipes in concrete hollow slab
CN104153451A (en) Construction method for installing concrete pipeline through prefabricated supporting block
CN209350546U (en) The installation of steel strand prestress anchor clipper and quick centering device
CN103453843A (en) Installation method of tunnel ruler-free measurement detachable reflector
CN104088262A (en) Pre-embedded guide rail and pre-embedded guide rail construction method in duct pre-embedding
CN205209847U (en) Concrete sample making devices who contains built -in longitudinal reinforcement
CN204728701U (en) Shear wall junction box positioning supporting part
CN207620379U (en) A kind of side mould fixing device
CN201762890U (en) Positioning strip for steel bar and template of reinforced concrete wall
CN104695604A (en) Anti-floating limiting device for high-strength thin-walled hollow tube of hollow floorslab and preparation tool of anti-floating limiting device
CN205088676U (en) Shaped steel - concrete makes up stress tube stake in advance
CN105421780A (en) Construction method of prefabricated concrete structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20141203

Effective date of abandoning: 20160817

C25 Abandonment of patent right or utility model to avoid double patenting