CN203967429U - Copper bar earth connection is assisted hanging mechanisms - Google Patents

Copper bar earth connection is assisted hanging mechanisms Download PDF

Info

Publication number
CN203967429U
CN203967429U CN201420358019.9U CN201420358019U CN203967429U CN 203967429 U CN203967429 U CN 203967429U CN 201420358019 U CN201420358019 U CN 201420358019U CN 203967429 U CN203967429 U CN 203967429U
Authority
CN
China
Prior art keywords
arc
copper bar
earth connection
hook
bearing pin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420358019.9U
Other languages
Chinese (zh)
Inventor
李洪强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd, Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201420358019.9U priority Critical patent/CN203967429U/en
Application granted granted Critical
Publication of CN203967429U publication Critical patent/CN203967429U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model provides a kind of copper bar earth connection to assist hanging mechanisms, and it comprises: hook; The first arc be conductive material, and its two ends is positioned at sustained height; The second arc, lower end is hinged by the first end of one first bearing pin and the first arc, and is positioned at the inner side of the first arc; The first torsion spring, is sheathed on the first bearing pin, makes the upper end of the second arc away from the inner side of the first arc; The 3rd arc, lower end is hinged by the second end of one second bearing pin and the first arc, and is positioned at the inner side of the first arc; The second torsion spring, is sheathed on the second bearing pin, makes the upper end of the 3rd arc away from the inner side of the first arc; Insulating bar, the outside of the first arc is fixed in upper end; Conductive pole, is fixed on the upper end of insulating bar, for being connected with copper bar earth connection.The utility model can be as required very simply, easily by earth connection and copper bar conducting, and is not subject to weather effect.

Description

Copper bar earth connection is assisted hanging mechanisms
Technical field
The utility model relates to transformer station's accessory technical field, and particularly, the utility model is particularly related to the auxiliary hanging mechanisms of a kind of copper bar earth connection.
Background technology
Installing earth connection is the requisite ring of Substation Switch Changing Operation, but always stalls for time while installing the earth connection on capacitor or main transformer at every turn, in especially winter, on copper bar, freezes, and installing earth connection is more difficult, greatly increases operating personnel's labour intensity.For example, current copper bar earth connection needs installing at least 30 minutes in the situation that weather is fine.In winter because cold weather can produce one deck frost on copper bar, installing earth connection difficulty strengthen, the head of earth connection horizontally slips on copper bar, can not tighten, the operating time also can extend to 50 minutes even longer.
Utility model content
The purpose of this utility model is to provide a kind of copper bar earth connection to assist hanging mechanisms, to solve the problems such as earth connection installing difficulty, installing effect that prior art exists be poor.
In order to address the above problem, the technical scheme that the utility model provides is as follows:
The auxiliary hanging mechanisms of a kind of copper bar earth connection, it comprises: hook, comprise vertical portion and hook portion, the upper end of described vertical portion is used for being fixed on copper bar, described hook portion comprises horizontally disposed cylinder and the short column vertically arranging, and the two ends of described cylinder are connected to the lower end of described vertical portion and the lower end of described short column; The first arc, is conductive material, is the platy structure of circular arc bending, and its two ends are positioned at sustained height; The second arc, is the platy structure of circular arc bending, and lower end is hinged by the first end of one first bearing pin and described the first arc, and is positioned at the inner side of described the first arc; The first torsion spring, is sheathed on described the first bearing pin, and two ends are individually fixed in the inner side of described the first arc, the second arc, so that the upper end of described the second arc is away from the inner side of described the first arc; The 3rd arc, is the platy structure of circular arc bending, and lower end is hinged by the second end of one second bearing pin and described the first arc, and is positioned at the inner side of described the first arc; The second torsion spring, is sheathed on described the second bearing pin, and two ends are individually fixed in the inner side of described the first arc, the 3rd arc, so that the upper end of described the 3rd arc is away from the inner side of described the first arc; Insulating bar, the outside of described the first arc is fixed in upper end, for described the first arc is suspended to described hook; Conductive pole, is fixed on the upper end of described insulating bar, is connected, for being connected with copper bar earth connection with described the first arc conduction; And, described the first torsion spring, the second torsion spring drive the outside, middle part of described the second arc, the 3rd arc mutually close, and the inner side, middle part of described the first arc, the upper outside of described the second arc, the upper outside of described the 3rd arc enclose the passage that is formed for by and clamps the cylinder of described hook.
Preferably, in the auxiliary hanging mechanisms of above-mentioned copper bar earth connection, the stage casing, vertical portion of described hook is welded with the location-plate of a level, on described vertical portion, above described location-plate, is provided with screw thread.
Preferably, in the auxiliary hanging mechanisms of above-mentioned copper bar earth connection, on described the first arc, the position corresponding with the upper end of described the second arc is provided with the first through hole, and in the time that the anglec of rotation of described the second arc is excessive, described the first through hole is for by the upper end of described the second arc; On described the first arc, the position corresponding with the upper end of described the 3rd arc is provided with the second through hole, and in the time that the anglec of rotation of described the 3rd arc is excessive, described the second through hole is for by the upper end of described the 3rd arc.
Analyze known, after hook of the present utility model is fixed on to copper bar, can be as required very simply, easily by earth connection and copper bar conducting, and be not subject to weather effect, when improving earth connection installing efficiency, workman's labour intensity also obviously reduces, and the stability of installing obviously improves.
Brief description of the drawings
Fig. 1 is that the hook of the utility model embodiment is fixed on the structural representation on copper bar;
Fig. 2 is the structural representation of the parts outside the hook of the utility model embodiment.
Embodiment
Below in conjunction with the drawings and specific embodiments, the utility model is described in further details.
As shown in the figure, the utility model embodiment comprises the insulating bar 3 shown in the hook shown in Fig. 1 and Fig. 2, conductive pole 31, the first arc 4, the second arc 5, the 3rd arc 6, the first bearing pin 7, the first torsion spring 71, the second bearing pin 8, the second torsion spring 81.
Particularly, as shown in Figure 1, the hook portion that hook comprises vertical portion 21 and formed by cylinder 22, short column 23.Copper bar 1 is straight platy structure, and the upper end of vertical portion 21 is passed and is fixed on copper bar 1.Preferably, the stage casing of vertical portion 21 is welded with the location-plate 24 of a level, and while being fixed on copper bar 1 in vertical portion 21, as shown in Figure 1, location-plate 24 is close to the lower surface of copper bar 1; Vertical portion 21 is connected with nut 25 at the screw thread of location-plate 24 upper section settings, thereby vertical portion 21 is fixed on copper bar 1.Again as shown in Figure 1, the cylinder 22 of hook portion is horizontally disposed with, and 23 of short columns are vertical settings,, the two ends of cylinder 22 are connected to the lower end of vertical portion 21 and the lower end of short column 23, form a hook-type.
As shown in Figure 2, the first arc 4 of the utility model embodiment is conductive material, and it is the platy structure of circular arc bending, and its two ends are positioned at sustained height.Preferably, the central angle of the first arc 4 is greater than 180 degree.The second arc 5, the 3rd arc 6 are all the platy structure of circular arc bending, and the two structure is basic identical, are symmetrical arranged, and are that outside is relative.The lower end of the second arc 5 is hinged by the first end of the first bearing pin 7 and the first arc 4, and is positioned at the inner side of the first arc 4, and is that the inner surface of the first arc 4, the second arc 5 is relative.The first torsion spring 71 is sheathed on the first bearing pin 7, and its two ends are individually fixed in the inner side of the first arc 4, the second arc 5, so that the upper end of the second arc 5 is away from the inner side (inner surface in other words) of the first arc 4.
The setting of the 3rd arc 6, the second bearing pin 8, the second torsion spring 81 and the second arc 5, the first bearing pin 7, the first torsion spring 71 are basic identical.For example, the lower end of the 3rd arc 6 is hinged by the second end of the second bearing pin 8 and the first arc 4, and is positioned at the inner side of the first arc 4.The second torsion spring 81 is sheathed on the second bearing pin 8, and two ends are individually fixed in the inner side of the first arc 4, the 3rd arc 6, so that the upper end of the 3rd arc 6 is away from the inner side of the first arc 4.
The right-hand outside (outer surface) of the first arc 4 is fixed in the upper end of insulating bar 3, for the first arc 4 being suspended to the cylinder 22 of hook; Conductive pole 31 is fixed on the upper end of insulating bar 3, is connected, for being connected with the earth connection of copper bar 1 with the first arc 4 conductions.
Again as shown in Figure 2, the first torsion spring 71, the second torsion spring 81 drive the middle part outside of the second arc 5, the 3rd arc 6 mutually close, the upper outside of the inner side, middle part of the first arc 4, the upper outside of the second arc 5, the 3rd arc 6 enclose be formed for by and the path 10 0 of the cylinder 22 of securing pothook.
In the time of application the present embodiment, the earth connection of copper bar 1 is connected with conductive pole 31, then lift insulating bar 3, by the first arc 4, the second arc 5, the 3rd arc 6 is placed in the top of cylinder 22, then the drop-down insulating bar 3 of exerting oneself a little, cylinder 22 pushes the second arc 5 to the inner surface of the first arc 4, the 3rd arc 6, cylinder 22 is from the second arc 5, the 3rd arc 6 middle parts are slipped in path 10 0, now, at the first torsion spring 71, under the driving of the second torsion spring 81, the second arc 5, the 3rd arc 6 is again mutually close, be close together, thereby cylinder 22 is limited in path 10 0, cylinder 22 at least contacts with the first arc 4, because the first arc 4 is conductive material, now, copper bar 1 and its earth connection conducting.
For the present embodiment can be suspended on the cylinder 22 of different thicknesses, tackle the second arc 5, the 3rd arc 6 rotational angles are excessive, on the first arc 4, the position corresponding with the upper end of the second arc 5 is provided with the first through hole 41, in the time that the anglec of rotation of the second arc 5 is excessive, the upper end that the first through hole 41 can make the second arc 5 is by wherein.On the first arc 4, the position corresponding with the upper end of the 3rd arc 6 is provided with the second through hole 42, and in the time that the anglec of rotation of the 3rd arc 6 is excessive, the second 42 of through holes can pass through the upper end of the 3rd arc 6.
Adopt after equipment of the present utility model, operating efficiency improves greatly.Such as one group of original copper bar earth connection of installing at least needs 6 minutes above (power station just needs more than 30 minutes), need more than at least 10 minutes in winter (power station must more than 50 minutes), after auxiliary hanging point, can make the operating time be reduced in 2 minutes (power station need about 10 minutes just much of that) installing additional, and there is no the requirement of weather, even winter too, after contrast is used auxiliary hook, operating time has shortened 70% left and right, easily loosening after earth connection installing originally, earth rod head and copper bar contact area are reduced, increase potential safety hazard, and use after auxiliary hanging point, coupling type earth rod contacts and is closely difficult for becoming flexible with auxiliary hook, greatly increase the fail safe of ground connection.
In sum, the utility model can be established the grounding wire mounting of copper bar thereon very quickly, the operating time of installing earth connection shortens greatly, when raising the efficiency, not only reduce operating personnel's labour intensity, and not being subject to the impact in weather, season, installing effect, stability are also comparatively outstanding.
As known by the technical knowledge, the utility model can be realized by other the embodiment that does not depart from its Spirit Essence or essential feature.Therefore, above-mentioned disclosed embodiment, with regard to each side, all just illustrates, and is not only.Allly within the scope of the utility model or in the change being equal in scope of the present utility model, be all included in the utility model.

Claims (3)

1. the auxiliary hanging mechanisms of copper bar earth connection, is characterized in that, comprising:
Hook, comprise vertical portion and hook portion, the upper end of described vertical portion is used for being fixed on copper bar, and described hook portion comprises horizontally disposed cylinder and the short column vertically arranging, and the two ends of described cylinder are connected to the lower end of described vertical portion and the lower end of described short column;
The first arc, is conductive material, is the platy structure of circular arc bending, and its two ends are positioned at sustained height;
The second arc, is the platy structure of circular arc bending, and lower end is hinged by the first end of one first bearing pin and described the first arc, and is positioned at the inner side of described the first arc;
The first torsion spring, is sheathed on described the first bearing pin, and two ends are individually fixed in the inner side of described the first arc, the second arc, so that the upper end of described the second arc is away from the inner side of described the first arc;
The 3rd arc, is the platy structure of circular arc bending, and lower end is hinged by the second end of one second bearing pin and described the first arc, and is positioned at the inner side of described the first arc;
The second torsion spring, is sheathed on described the second bearing pin, and two ends are individually fixed in the inner side of described the first arc, the 3rd arc, so that the upper end of described the 3rd arc is away from the inner side of described the first arc;
Insulating bar, the outside of described the first arc is fixed in upper end, for described the first arc is suspended to described hook;
Conductive pole, is fixed on the upper end of described insulating bar, is connected, for being connected with copper bar earth connection with described the first arc conduction;
And, described the first torsion spring, the second torsion spring drive the outside, middle part of described the second arc, the 3rd arc mutually close, and the inner side, middle part of described the first arc, the upper outside of described the second arc, the upper outside of described the 3rd arc enclose the passage that is formed for by and clamps the cylinder of described hook.
2. the auxiliary hanging mechanisms of copper bar earth connection according to claim 1, is characterized in that, the stage casing, vertical portion of described hook is welded with the location-plate of a level, on described vertical portion, above described location-plate, is provided with screw thread.
3. the auxiliary hanging mechanisms of copper bar earth connection according to claim 1, it is characterized in that, on described the first arc, the position corresponding with the upper end of described the second arc is provided with the first through hole, in the time that the anglec of rotation of described the second arc is excessive, described the first through hole is for by the upper end of described the second arc;
On described the first arc, the position corresponding with the upper end of described the 3rd arc is provided with the second through hole, and in the time that the anglec of rotation of described the 3rd arc is excessive, described the second through hole is for by the upper end of described the 3rd arc.
CN201420358019.9U 2014-06-30 2014-06-30 Copper bar earth connection is assisted hanging mechanisms Expired - Fee Related CN203967429U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420358019.9U CN203967429U (en) 2014-06-30 2014-06-30 Copper bar earth connection is assisted hanging mechanisms

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420358019.9U CN203967429U (en) 2014-06-30 2014-06-30 Copper bar earth connection is assisted hanging mechanisms

Publications (1)

Publication Number Publication Date
CN203967429U true CN203967429U (en) 2014-11-26

Family

ID=51927974

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420358019.9U Expired - Fee Related CN203967429U (en) 2014-06-30 2014-06-30 Copper bar earth connection is assisted hanging mechanisms

Country Status (1)

Country Link
CN (1) CN203967429U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106654628A (en) * 2015-11-04 2017-05-10 国网辽宁省电力有限公司本溪供电公司 Temporary composite ground wire clamp for power delivery field

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106654628A (en) * 2015-11-04 2017-05-10 国网辽宁省电力有限公司本溪供电公司 Temporary composite ground wire clamp for power delivery field

Similar Documents

Publication Publication Date Title
CN204230457U (en) Universal connector earth wire operation rod
CN206309110U (en) Electric pole pole centralizing device
CN204266201U (en) A kind of guy anchor
CN203967429U (en) Copper bar earth connection is assisted hanging mechanisms
CN203251017U (en) Insulation ladder tail end fixing device
CN101378153B (en) Diverter for grounding wire
CN201266689Y (en) 220kv and 66kv ground wire hanging insulated operating lever
CN104124584A (en) Hanging assisting mechanism of copper bar grounding wire
CN202736754U (en) Frame-type capacitor set discharging rod
CN204205428U (en) The special line lifter of wire
CN202888418U (en) Portable self-tapping grounding pin
CN203522016U (en) Device for lifting overhead ground wire
CN203109899U (en) Insulating tool for installing bird repellent device without power failure
CN205609783U (en) Emergent short circuit tubulose fastener
CN203406589U (en) Concrete pole grounding lead wire protecting apparatus
CN104348122B (en) Ground potential mounting type shunt wire clamp device and mounting method thereof
CN205377164U (en) Special fixture of large -tonnage II type suspension insulator wire end
CN106099412B (en) A kind of Portable power construction grounding device and its application method
CN201821036U (en) Overhead line dewinder
CN207994340U (en) A kind of parallel clearance lightning protection device
CN203961417U (en) A kind of electric pole cross-arm and thread-laying device thereof
CN207004140U (en) A kind of anchor ear pole
CN205846395U (en) Lifting vehicle earthing of casing line apparatus
CN205863440U (en) A kind of reliability and durability short-circuit earthing bar
CN205400233U (en) Install cross arm on wire pole

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141126

Termination date: 20190630

CF01 Termination of patent right due to non-payment of annual fee