CN203951267U - A kind of intelligent substation comprehensive monitoring system - Google Patents

A kind of intelligent substation comprehensive monitoring system Download PDF

Info

Publication number
CN203951267U
CN203951267U CN201420267769.5U CN201420267769U CN203951267U CN 203951267 U CN203951267 U CN 203951267U CN 201420267769 U CN201420267769 U CN 201420267769U CN 203951267 U CN203951267 U CN 203951267U
Authority
CN
China
Prior art keywords
subsystem
transformer station
video
monitoring system
intelligent substation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420267769.5U
Other languages
Chinese (zh)
Inventor
尹涛
王红光
王皓
王成进
余娟
张骥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Nanrui Jiyuan Power Grid Technology Co ltd
Original Assignee
ANHUI JIYUAN POWER SYSTEM TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI JIYUAN POWER SYSTEM TECHNOLOGY Co Ltd filed Critical ANHUI JIYUAN POWER SYSTEM TECHNOLOGY Co Ltd
Priority to CN201420267769.5U priority Critical patent/CN203951267U/en
Application granted granted Critical
Publication of CN203951267U publication Critical patent/CN203951267U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Alarm Systems (AREA)

Abstract

The utility model provides a kind of intelligent substation comprehensive monitoring system, comprise: main website end and transformer station's end, described main website end arranges work station and server, described transformer station end comprises video monitoring subsystem, environmental monitoring subsystem, safety precaution subsystem, fire alarm subsystem, illumination control subsystem, described main website end is held and is connected by electric power data network with transformer station, and described main website end and transformer station's end arrange respectively memory cell in video set.The utility model adopts high-definition video monitoring technology, makes scene coverage wider, reduces the quantity of unit are control point, improves monitoring usefulness, reduces equipment investment; Reduce transformer substation construction cost of investment, reduced staff's line service amount, reduced work difficulty.

Description

A kind of intelligent substation comprehensive monitoring system
Technical field
The utility model relates to transformer station's integrated synthesis supervisory control system, is specifically related to a kind of intelligent substation comprehensive monitoring system.
Background technology
Guo Wang company " three collection five large " System Construction planning new demand: the integration that (1) requires to realize substation equipment and system, realize information sharing, pushing structure compactness, function are integrated, information fusion; (2) requirement realizes the height fusion of substation equipment operation centralized monitor and electrical network business; (3) scheduling station has the demand of centralized monitor, remote browse, remote maintenance; (4) require to realize the integrated and equipment account maintenance of information of equipment state overhauling, O&M.
Disperse for each monitoring unit module placement of transformer station at present, communication interface is various, need to be equipped with multiple interfaces to realize the transfer of data of different monitoring unit module, and connection complexity, is unfavorable for management and the maintenance in later stage.
Utility model content
The utility model, according to above-mentioned new demand, proposes a kind of intelligent substation comprehensive monitoring system.
The solution that the utility model adopts is: a kind of intelligent substation comprehensive monitoring system, comprise: main website end and transformer station's end, described main website end arranges work station and server, described transformer station end comprises video monitoring subsystem, environmental monitoring subsystem, safety precaution subsystem, fire alarm subsystem, illumination control subsystem, described main website end is held and is connected by electric power data network with transformer station, and described main website end and transformer station's end arrange respectively memory cell in video set.
Further, described environmental monitoring subsystem comprises humiture detector, SF6 gas detecting instrument, blower fan and air-conditioning.
Further, described video monitoring subsystem Adoption Network video camera.
Further, described safety precaution subsystem comprises access controller, infrared emission device and fence, and the each detector of described safety precaution subsystem is directly connected with environmental data processing unit by alarm cables.
Further, described illumination control subsystem adopts lamp dimmer.
Further, described work station arranges video wall decoder.
Further, described fire alarm subsystem is connected with described video monitoring subsystem by interlock interface with illumination control subsystem.
The utility model has the advantages that: adopt high-definition video monitoring technology, resolution meets 720p, makes scene coverage wider, reduce the quantity of unit are control point, improve monitoring usefulness, reduce equipment investment; Integral system is fully integrated, is optimized the configuration of resources, and has reduced transformer substation construction cost of investment, and configuration tool is more efficiently provided aspect through engineering approaches, has reduced staff's line service amount, has reduced work difficulty.
Brief description of the drawings
Fig. 1 is the system physical structure schematic diagram the utility model proposes;
Fig. 2 is the intelligent switching control schematic diagram the utility model proposes;
Fig. 3 is that the video cloud storage flow that the utility model proposes is to schematic diagram.
Embodiment
Referring to Fig. 1, it is the system physical structure schematic diagram the utility model proposes.
As shown in Figure 1, a kind of intelligent substation comprehensive monitoring system, comprise: main website end and transformer station's end, described main website end arranges work station and server, described transformer station end comprises video monitoring subsystem, environmental monitoring subsystem, safety precaution subsystem, fire alarm subsystem, illumination control subsystem, described main website end is held and is connected by electric power data network with transformer station, and described main website end and transformer station's end arrange respectively memory cell in video set.
Further, described video monitoring subsystem Adoption Network video camera.Main being responsible for carried out round-the-clock conventional video monitoring to full station electric equipments, infield and surrounding enviroment, can carry out alarm linkage with other subsystem simultaneously, by multiple technologies means such as the comprehensively analysis of video monitor, supplementary, intelligent alarm, overview display, for substation operation situation is understood at regulation and control center in time, equipment running status provides technical support.
Further, described illumination control subsystem adopts lamp dimmer.
Further, described work station arranges video wall decoder.By video wall decoder, video information is decoded, and show by video wall.
In the utility model embodiment, transformer station is the hinge of power transmission and transformation net, a large amount of primary equipments are installed, also supporting have secondary device, computer equipment, a communication equipment, and any equipment is all related to the safe operation of transformer station, and place environment also affects the operation conditions of equipment simultaneously.The transformer station of different electric pressures, control point quantity is also different, as limited in deployment point bit quantity, need be deployed in important area: be for example arranged on substation gate and monitor the situation that passes in and out transformer station personnel and vehicle, can coordinate gate inhibition to use, for the personnel of swiping the card or leave behind card personnel's authentication;
At transformer station's enclosure wall, transformer station's circumference is carried out to anti-intrusive monitoring, the report to the police video that can link of security device;
By the field condition of the monitoring overall understanding transformer station to transformer station's panorama, monitor turnover transformer station, building, the personnel in equipment place, vehicle, the environmental aspect in surveillance equipment place;
Monitor the apparent condition, oil level, gear, sleeve pipe, porcelain vase, leakage of oil, fan-status etc. of main transformer in main transformer place, monitor this region circuit breaker, isolating switch, grounding switch apparent condition, divide/close state, monitor female (or busbar) apparent condition of this region pipe and and the contact condition of disconnecting link;
Monitor in circuit place this region circuit breaker, isolating switch, grounding switch apparent condition, divide/close state, monitor female (or busbar) apparent condition of this region pipe and the contact condition with disconnecting link, monitor the apparent condition of this region parallel reactance, CT, PT, lightning arrester and porcelain vase etc.;
Monitor the operation conditions of transformer station's inner high voltage chamber (switch gear room, capacitor chamber, change used chamber, arc suppression coil chamber), the apparent condition of equipment in hyperbaric chamber;
At indoor important area: monitor personnel's situation of turnover indoor (master-control room, relay protection chamber, communication room, battery room) and the apparent condition of indoor equipment.
Further, described environmental monitoring subsystem comprises humiture detector, SF6 gas detecting instrument, blower fan and air-conditioning, utilizes environmental data processing unit to realize environmental information, warning message is processed in real time, transmits, stored.
Further, described access control system, mainly formed by access controller, card reader (comprising keyboard card reader), electric control lock, door magnetic and gate inhibition's power supply, by being arranged on the main gateway of building, the passway of important area, thereby realize control and the attendance checking function to gateway.
Described fire protection alarm system, utilizes fire trigger equipment to carry out picket surveillance to defence area, and trigger equipment is sent to on-the-spot fire signal the fire protection warning main frame of Zhu Zhi center and sub-control room in real time, and opening gate can be escaped the personnel of conflagration area; , linked: warning message is uploaded center by environmental data processing unit according to presetting rule, security personnel can come rapidly spot meanwhile; The corresponding lighting that links, calls presetting bit, makes front end and Surveillance center can understand in time the on-the-spot intensity of a fire; Realize and the interlock of power control switch, automatically cut off the power supply of visual plant.
Further, described safety precaution subsystem, is mainly made up of fence, infrared emission, vibration detector and infrared dual-technology equipment.Each detector is directly connected with environmental data processing unit by alarm cables, and in the time occurring to report to the police, warning message can be uploaded to environmental data processing unit in time, and linkage relevant device, as started intelligent lighting light, audible-visual annunciator etc.
Described intelligent linkage control technology and multisystem interlock, be divided into according to on-the-spot control appliance: smart machine control and intelligent switching control.The realization of described smart machine control, sends control command by system by the interface protocol of network or each subsystem, and intelligent control device receives the control command of management platform, realizes the opening of interlock control appliance, stops, the operation such as adjusting.The realization of described intelligent switching control, a kind of mode is, by system by network transmit button control command, the opening, stop of control appliance; Another kind of mode arranges corresponding interlock rule in system, opens the door etc. such as leak link lighting, firefighting warning linkage gate inhibition of linkage fan exhaust, infrared dual-technology by the draining of water logging alarm linkage starting mode of pump, SF6.Referring to Fig. 2, it is the intelligent switching control schematic diagram the utility model proposes.
The thermal infrared imager of disposing by transformer station commanding elevation in the utility model embodiment is as video routing inspection technology, visual plant is carried out to taking turn, and utilize audio frequency and video technology, status monitoring is analyzed, realize the combination of work on the spot and remote monitoring, for operation and maintenance process provide process controlled technique guarantee.The path of cruising can be set according to demand, automatically order Switch Video picture by path.
The storage system of the intelligent substation comprehensive monitoring system that the utility model provides mainly adopts video cloud storage mode: Operation and Maintenance Center is concentrated video recording storage to front end important area and important video image, front end system adopts video processing unit to realize distributed storage, effective combination of distributed storage and centralized backup storage, improve the safety and reliability that Video Document is preserved, reduce because video resource is lost the risk of bringing.
Video cloud memory device CVR (Cloud Video Recorder) is the video special purpose memory devices that integrates encoding device management, management of video, storage and forwarding capability.Recording function and playing function are embedded in memory device, realize the storage of writing direct of encoder data stream, or forward and write storage by Streaming Media.Directly program request from storage, the download of platform and client.
Referring to Fig. 3, be that the video cloud storage flow that the utility model proposes is to schematic diagram.
Video cloud storage mode described in the utility model, supports the video flowing encoded device memory device that writes direct; Can bear concurrent the writing of a large amount of monitoring code streams, improve systematic function; Realize distribution according to need storage, dispose simply, easily expansion, supports distributed storage and centralised storage; Solve the monitor service that the power down failure problems of storage and the file system corruption of storage cause and stopped, the problems such as loss of data.
Above a kind of intelligent substation comprehensive monitoring system provided by the utility model is described in detail, by video monitoring, information processing to multiple systems such as fire-fighting, gate inhibition, environment, network, antitheft, electric power, realize the intelligent linkage with the headend equipment of each subsystem.System possesses the key technologies such as high performance Real-Time Databases System Technique, flexible bus technology, business service redundant technique, intelligent linkage technology.Meanwhile, building of system adopts layer-stepping, modularized design, can carry out according to demand cutting, and equipment and function applying flexible configure, and are applicable to the monitoring demand of various different majors, have versatility and autgmentability.In sum, this description should not be construed as restriction of the present utility model.

Claims (7)

1. an intelligent substation comprehensive monitoring system, it is characterized in that, comprise: main website end and transformer station's end, described main website end arranges work station and server, described transformer station end comprises video monitoring subsystem, environmental monitoring subsystem, safety precaution subsystem, fire alarm subsystem, illumination control subsystem, described main website end is held and is connected by electric power data network with transformer station, and described main website end and transformer station's end arrange respectively memory cell in video set.
2. a kind of intelligent substation comprehensive monitoring system according to claim 1, is characterized in that: described environmental monitoring subsystem comprises humiture detector, SF6 gas detecting instrument, blower fan and air-conditioning.
3. a kind of intelligent substation comprehensive monitoring system according to claim 1, is characterized in that: described video monitoring subsystem Adoption Network video camera.
4. a kind of intelligent substation comprehensive monitoring system according to claim 1, it is characterized in that: described safety precaution subsystem comprises access controller, infrared emission device and fence, the each detector of described safety precaution subsystem is directly connected with environmental data processing unit by alarm cables.
5. a kind of intelligent substation comprehensive monitoring system according to claim 1, is characterized in that: described illumination control subsystem adopts lamp dimmer.
6. a kind of intelligent substation comprehensive monitoring system according to claim 1, is characterized in that: described work station arranges video wall decoder.
7. a kind of intelligent substation comprehensive monitoring system according to claim 1, is characterized in that: described fire alarm subsystem is connected with described video monitoring subsystem by interlock interface with illumination control subsystem.
CN201420267769.5U 2014-05-25 2014-05-25 A kind of intelligent substation comprehensive monitoring system Expired - Fee Related CN203951267U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420267769.5U CN203951267U (en) 2014-05-25 2014-05-25 A kind of intelligent substation comprehensive monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420267769.5U CN203951267U (en) 2014-05-25 2014-05-25 A kind of intelligent substation comprehensive monitoring system

Publications (1)

Publication Number Publication Date
CN203951267U true CN203951267U (en) 2014-11-19

Family

ID=51893284

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420267769.5U Expired - Fee Related CN203951267U (en) 2014-05-25 2014-05-25 A kind of intelligent substation comprehensive monitoring system

Country Status (1)

Country Link
CN (1) CN203951267U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104581063A (en) * 2014-12-29 2015-04-29 李宗翰 Residential area monitoring and tour inspection system
CN105762930A (en) * 2015-06-30 2016-07-13 巫立斌 Power management networking system
CN110853273A (en) * 2019-10-16 2020-02-28 华翔翔能电气股份有限公司 Security protection system of transformer substation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104581063A (en) * 2014-12-29 2015-04-29 李宗翰 Residential area monitoring and tour inspection system
CN105762930A (en) * 2015-06-30 2016-07-13 巫立斌 Power management networking system
CN110853273A (en) * 2019-10-16 2020-02-28 华翔翔能电气股份有限公司 Security protection system of transformer substation
CN110853273B (en) * 2019-10-16 2021-10-26 华翔翔能科技股份有限公司 Security protection system of transformer substation

Similar Documents

Publication Publication Date Title
CN104052151B (en) Intelligent substation aided synthesis is monitored and D5000 cooler interlock platforms
CN104269936A (en) Comprehensive monitoring method and system
CN102801214A (en) Transformer substation comprehensive monitoring system based on subsystem across linkage and linkage planning
CN105425711A (en) Integrated management system of intelligent building
CN214429325U (en) Comprehensive monitoring linkage platform for auxiliary system of intelligent substation
CN102789223A (en) Intelligent auxiliary real-time monitoring system of iSaSCADA transformer substation
CN111147823B (en) Method for realizing remote monitoring and supporting for transformer substation emergency repair by adopting monitoring platform
CN102723782A (en) Substation integrated information processing platform based on hardware superposition technique
CN104300678A (en) Intelligent comprehensive on-line monitoring system based on power equipment operation
CN111641674A (en) Underground piping lane control wireless communication system
CN111145482A (en) Fire control command control system
CN203951267U (en) A kind of intelligent substation comprehensive monitoring system
CN111147822B (en) Monitoring system for transformer substation emergency repair
CN112994230A (en) Environment monitoring system for intelligent substation auxiliary system and use method thereof
CN104362737A (en) Intelligent comprehensive on-line monitoring system
Chan et al. Internet based transmission substation monitoring
CN101005610A (en) Long-range digital monitor system for transformer station
CN202616876U (en) Substation visualization system based on operating perceiving
CN111179120A (en) Monitoring and emergency repair platform for transformer substation
CN102769339A (en) Intelligent security auxiliary system based on IEC 61850
CN209046360U (en) Extra-high pressure passageway visualization and inspection change system
CN113162233A (en) Auxiliary equipment monitoring system for third-generation intelligent substation
CN108390457A (en) A kind of intelligent electric power Synthesis Support System
CN201846134U (en) Automatic inspecting system for transformer substation
CN202721502U (en) Transformer station integrated monitoring apparatus based on subsystem-striding linkage and linkage planning

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 230031 science Avenue, 669 West Changjiang Road, Anhui, Hefei

Patentee after: ANHUI NANRUI JIYUAN POWER GRID TECHNOLOGY Co.,Ltd.

Address before: 230031 science Avenue, 669 West Changjiang Road, Anhui, Hefei

Patentee before: ANHUI JIYUAN POWER SYSTEM TECHNOLOGY Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141119