The added performance test apparatus of a kind of cabinet-type server and rack
Technical field
The utility model relates to field of computer technology, particularly relates to the added performance test apparatus of a kind of cabinet-type server and rack.
Background technology
The normal operation of server needs two Essential Environments, the electrical environment of first high-quality, high security and high-reliability, and it two is high-quality humiture environment.
At present, server, from businessman buys, is directly arranged on server in rack and comes into operation, and cannot learn the duty quality after server comes into operation before use.After server comes into operation, if some device failure in server can cause server normally to work, traffic affecting is normally carried out, and will cause huge economic loss and social influence.Because server comes into operation, cannot judge that causing the reason of server operation irregularity is that before dispatching from the factory, server exists defect, or the server device failure that comes into operation and cause in process.
The normal operation of server has very strict requirement to its residing humiture environment, when humiture exceeds the required scope of server steady operation, can affect the duty of server.
Whether in prior art, do not provide a kind of testing apparatus to be used for testing added front server can normally work, do not provide a kind of testing apparatus testing server required humiture environment, to provide required humiture parameter for server use from now on yet.
Utility model content
In view of this, the utility model provides the added performance test apparatus of a kind of cabinet-type server and rack, before server comes into operation, the duty of testing server under different electricity quality parameters and humiture parameter, for server provides reliable electricity quality parameter and humiture parameter after coming into operation.
The added performance test apparatus of cabinet-type server, described equipment comprises:
Two-way power supply, two electricity quality processors, two power distribution sockets, a centralized monitor, an air-conditioning equipment, a rack, a surveying instrument and tested equipment, described tested equipment is comprised of one or more servers;
An electricity quality processor accesses a road power supply, changes the electricity quality parameter of power supply, and the power supply changing after electricity quality parameter is exported by a power distribution socket;
Tested equipment is connected with two power distribution sockets respectively, and power distribution socket is that tested equipment output changes the electric energy after electricity quality parameter;
Air-conditioning equipment is arranged on the Qianmen of rack, and Yu Yi road power supply is connected, and air-conditioning equipment, for being fed through the air inlet of tested equipment after the air outside rack is processed, regulates server humiture parameter around in rack;
Surveying instrument is used for measuring the running state parameter of tested equipment, and described running status is sent to centralized monitor;
Centralized monitor is connected respectively with two electricity quality processors, air-conditioning equipment, surveying instrument and tested equipment;
Centralized monitor is used for carrying out following policer operation: control the electricity quality parameter that electricity quality processor changes power supply; Control the electric power of air-conditioning equipment, and the operational factor of the condenser of air-conditioning equipment, evaporator and solenoid valve; The electricity quality parameter of tested equipment is inputted in monitoring, monitors the humiture parameter of air inlet and the air outlet of tested equipment; Monitor CPU, internal memory, calculating and memory property parameter in tested equipment; Monitoring equipment under test application software running state parameter.
Optionally, described electricity quality parameter comprises:
Any one of current quality parameter, quality of voltage parameter and power quality parameter or multiple.
Optionally, described centralized monitor also comprises:
Display, for showing the electricity quality parameter of the tested equipment of input that centralized monitor is monitored, the humiture parameter of the air inlet of tested equipment and exhaust outlet, the CPU in tested equipment, internal memory, calculating and memory property parameter, tested equipment application software running state parameter.
Optionally, described rack is of a size of:
2m is high, and 600mm is wide, the 42U rack that 1100mm is dark.
Optionally,
Described centralized monitor is also for by any one or more derivation of the CPU in monitored tested equipment, internal memory, calculating, memory property parameter and application software running state parameter.
As shown in the above, the utility model has following beneficial effect:
The utility model provides the added performance test apparatus of a kind of cabinet-type server and rack, described equipment comprises: two-way power supply, two electricity quality processors, two power distribution sockets, a centralized monitor, an air-conditioning equipment, surveying instrument of a rack and tested equipment, described tested equipment is comprised of one or more servers, an electricity quality processor accesses a road power supply, changes the electricity quality parameter of power supply, and the power supply changing after electricity quality parameter is exported by a power distribution socket, tested device server is connected with two power distribution sockets respectively, and power distribution socket is that tested device server output changes the electric energy after electricity quality parameter, air-conditioning equipment is arranged on the Qianmen of rack, and Yu Yi road power supply is connected, and air-conditioning equipment is fed through tested device server air inlet for after the air outside rack is processed, and regulates tested device server humiture parameter around in rack, centralized monitor is connected respectively with two electricity quality processors, air-conditioning equipment and servers, surveying instrument is used for measuring the running state parameter of tested equipment, and described running status is sent to centralized monitor, centralized monitor is used for carrying out following policer operation: control the electricity quality parameter that electricity quality processor changes power supply, control the electric power of air-conditioning equipment, and the operational factor of the condenser of air-conditioning equipment, evaporator and solenoid valve, the electricity quality parameter of the tested equipment of server is inputted in monitoring, monitors the humiture parameter of tested device server air inlet and air outlet, monitor CPU, internal memory, calculating and memory property parameter in tested device server, monitor tested device server application software running state parameter, added, front server is carried out to special project test, first can testing server whether just defective when dispatching from the factory, the malfunction that prevents from cannot determining after coming into operation server is defective or because improper use is caused by producing, and cannot investigate the responsibility of server malfunction, and, relation between the device resource utilization rate of testing server and different electricity quality parameters and humiture parameter, can provide more pointed service condition for server, can record the duty of server under different electricity quality parameters and humiture parameter, for server from now on provides reliable data foundation in the process of coming into operation, guarantee that server is operated under satisfactory electricity quality parameter and humiture parameter, to save the inputs such as electric power and air-conditioning in the process of follow-up use server, meet the safety of server, reliable and high-efficiency operation demand.
Accompanying drawing explanation
In order to be illustrated more clearly in the utility model embodiment or technical scheme of the prior art, to the accompanying drawing of required use in embodiment or description of the Prior Art be briefly described below, apparently, accompanying drawing in the following describes is only embodiment more of the present utility model, for those of ordinary skills, do not paying under the prerequisite of creative work, can also obtain according to these accompanying drawings other accompanying drawing.
Fig. 1 is added performance test apparatus embodiment mono-structural representation of a kind of cabinet-type server of the utility model.
Embodiment
The utility model discloses the added performance test apparatus of a kind of cabinet-type server and rack, before added, server is carried out to special project test, relation between the running software parameter of testing server and electricity quality parameter and humiture parameter, to save the inputs such as electric power and air-conditioning in the process of follow-up use server, meet safe, the reliable and high-efficiency operation demand of server.
Below in conjunction with accompanying drawing, the utility model specific embodiment is elaborated.
Embodiment mono-
Fig. 1 is added performance test apparatus embodiment mono-structural representation of a kind of cabinet-type server of the utility model, and described equipment comprises:
Two-way power supply E1 and E2, two electricity quality processor D1 and D2, one or two power distribution socket PDU1 and PDU2, tested equipment 101, a centralized monitor 102,103, one racks 104 of an air-conditioning equipment and a surveying instrument 105, described tested equipment 101 is comprised of one or more servers.
Two-way power supply E1 and E2 are common out-put supply, 220V or 380V, 50Hz.Two-way power supply can be directly from the outside two-way power supply accessing of rack; Also can be from the outside access of rack one road power supply, then this road power supply is divided into two-way in rack.
Power distribution socket (Power Distribution Unit, PDU) is conventional rack PDU, and each PDU has a plurality of jacks, can change the electric energy after electricity quality parameter to tested equipment output.PDU can make that power distribution in rack is more neat, reliable, safety, specialty and attractive in appearance, and makes in rack the maintenance of power supply more convenient and reliable.
An electricity quality processor accesses a road power supply, changes the electricity quality parameter of power supply, and the power supply changing after electricity quality parameter is exported by a power distribution socket.
As described in Figure 1, electricity quality processor D1 access first via power supply E1, changes the electricity quality parameter of first via power supply E1, and by PDU1, exports the power supply E1 changing after electricity quality parameter to tested equipment 101.Here it should be noted that, tested equipment 101 can comprise a server, also can comprise it being a plurality of servers, can to the one or more servers in rack, test according to actual conditions.
Electricity quality processor D2 access first via power supply E2, changes the electricity quality parameter of first via power supply E2, and by PDU2, exports the power supply E2 changing after electricity quality parameter to tested equipment 101.
Electricity quality processor D1 is connected with centralized monitor 102 with D2, receive the control signal of centralized monitor 102, according to received control signal, change the electricity quality parameter of first via power supply E1 and the second road power supply E2, and export tested equipment 101 to by PDU1 and PDU2.For testing the duty of tested equipment 101 under different electricity quality parameters.
Wherein, described electricity quality parameter comprises: any one of current quality parameter, quality of voltage parameter and power quality parameter or multiple.Here it should be noted that, electricity quality parameter can also comprise power supply quality parameter and power quality parameter etc., is not limited in above-mentioned several expression form, repeats no longer one by one here.
Tested equipment 101 is connected with one or two power distribution socket.When tested equipment 101 is single supply server, tested equipment 101 is connected with a power distribution socket; When tested equipment 101 is two-way power supply server, tested equipment 101 is connected with two power distribution sockets respectively.The present embodiment is connected to example with two power distribution socket PDU1 and PDU2 respectively with tested equipment 101, and power distribution socket PDU1 and PDU2 are that server output changes the electric energy after electricity quality parameter.
Electricity quality processor D1 and D2 export by PDU1 and PDU2 the power supply changing after electricity quality parameter to tested equipment 101 respectively.The electricity quality parameter of the two-way power supply that PDU1 and PDU2 provide to tested equipment 101 can be the same or different.
Air-conditioning equipment 103 is arranged on the Qianmen of rack 104, and Yu Yi road power supply E3 is connected, and air-conditioning equipment 103 is fed through server 101 air inlets for after the air outside rack 104 is processed, and regulates tested equipment 101 humiture parameter around in rack.
Here it should be noted that, power supply E3 can be from access Yi road, the rack outside power supply different with E2 from power supply E1, can be also from power supply E1 or E2, to pick out Lai mono-road power supply, does not specifically limit here.
Air-conditioning equipment 103 comprises compressor, condenser, evaporator and solenoid valve.Air-conditioning equipment 103 is connected with centralized monitor 102, receives the control signal of centralized monitor 102, regulates the humiture parameter of the air inlet of tested equipment 101 according to control signal.For testing the duty of tested equipment 101 under different humiture parameters.
Surveying instrument 105 is for measuring the running state parameter of tested equipment 101, and described running status is sent to centralized monitor.
The running state parameter of tested equipment 101 comprises current parameters, voltage parameter, power parameter CPU, internal memory, calculating and memory property parameter etc.
Centralized monitor 102 is connected respectively with D2, air-conditioning equipment 103, surveying instrument 101 and tested equipment 101 with two electricity quality processor D1.
Centralized monitor 102 is for carrying out following policer operation: control the electricity quality parameter that electricity quality processor D1 and D2 change power supply; Control the electric power of air-conditioning equipment 103, and the operational factor of the condenser of air-conditioning equipment 103, evaporator and solenoid valve; The electricity quality parameter of tested equipment 101 is inputted in monitoring, monitors the humiture parameter of tested equipment 101 air inlets and air outlet; Monitor CPU, internal memory, calculating and memory property parameter in tested equipment 101; Monitor tested equipment 101 application software running state parameters.
Centralized Monitoring server 102 provides the electricity quality processor D1 in whole server test equipment and D2, air-conditioning equipment 103 and server 101 is carried out to total control and monitoring function.The display that the parameters that Centralized Monitoring server 102 is monitored can export rack outside to shows, also can Centralized Monitoring server 102 self comprises a display and shows, specifically do not limit here.
Described centralized monitor is also for by any one or more derivation of the CPU in monitored tested equipment, internal memory, calculating, memory property parameter and application software running state parameter.
Rack 104 is mainly used in placing each proving installation in above-mentioned testing apparatus.Electricity quality processor D1 and D2 are placed on the top of rack, and air-conditioning equipment 103 is arranged on the Qianmen of rack 104, PDU1, and PDU2, tested equipment 101 and Centralized Monitoring server 102 can be placed in rack according to actual demand, do not limit here.
Rack 104 can adopt existing conventional cabinet dimensions, and the dimensions of rack is as follows:
22U, 27U, 32U, 37U, 42U and 47U
Wherein, U is a kind of unit that represents server external dimensions, is the abbreviation of unit, and detailed size is determined by EIA (EIA).For example: the utility model can adopt 2m high, and 600mm is wide, the 42U rack that 1100mm is dark.
The foregoing is only preferred embodiment of the present utility model; not in order to limit the utility model; all within spirit of the present utility model and principle, any modification of doing, be equal to replacement, improvement etc., within all should being included in protection domain of the present utility model.