A kind of Phase of Electric Power Projects operation measuring instrument Download PDFInfo
- Publication number
- CN203928972U CN203928972U CN201420372428.4U CN201420372428U CN203928972U CN 203928972 U CN203928972 U CN 203928972U CN 201420372428 U CN201420372428 U CN 201420372428U CN 203928972 U CN203928972 U CN 203928972U
- Authority
- CN
- China
- Prior art keywords
- measuring instrument
- insulating bar
- electric power
- phase
- power projects
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000002184 metal Substances 0.000 claims abstract description 19
- OAICVXFJPJFONN-UHFFFAOYSA-N Phosphorus Chemical compound [P] OAICVXFJPJFONN-UHFFFAOYSA-N 0.000 claims description 5
- 238000004146 energy storage Methods 0.000 claims description 5
- 239000000463 material Substances 0.000 claims description 5
- 239000000843 powder Substances 0.000 claims description 5
- 238000005507 spraying Methods 0.000 claims description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000011521 glass Substances 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000010276 construction Methods 0.000 abstract description 7
- 238000005259 measurement Methods 0.000 abstract description 6
- 238000005516 engineering process Methods 0.000 abstract description 5
- 238000009434 installation Methods 0.000 abstract description 4
- 230000001131 transforming effect Effects 0.000 abstract description 4
- 238000001514 detection method Methods 0.000 abstract description 2
- 238000012795 verification Methods 0.000 abstract description 2
- 230000000694 effects Effects 0.000 description 1
Landscapes
- Electric Cable Installation (AREA)
Abstract
A Phase of Electric Power Projects operation measuring instrument, belongs to power technology field, is specifically related to a kind of survey instrument.Main this measuring instrument comprises insulating gel lid, insulating bar, scale mark, internal thread metal clamp structure and annex; This measuring instrument adopts telescopic structure, and the insulating bar isometric by some joints nests together; At the built-in tapped metal clamp structure in the top of insulating bar, on metal clamp structure, annex is set.The utility model realized to power circuit over the ground, to the safe distances such as buildings and scissors crossing charged canonical measure; Realized the Quick Measurement of construction operation content, such as: foundation ditch detection, the installation of distribution transforming stand, electric pole installation etc., guaranteed construction technology and quality; Measurement needs while having realized night or the bad operation of light; The problem of galvanoscopic insulating bar insufficient height while having solved power circuit electrical verification.
Description
Technical field
The utility model belongs to power technology field, is specifically related to a kind of survey instrument.
Background technology
During the corresponding construction operation of power engineering, often relate to height or length data, the instrument of current measurement mainly uses tape measure or box chi, sometimes forget electric power standard just by rule of thumb, measurement is inconvenient, and measuring accuracy is inaccurate, easily produce error, or even mistake, reduced engineering construction efficiency, make engineering not meet relevant technological standards and job specifications.
Summary of the invention
The purpose of this utility model is to provide a kind of Phase of Electric Power Projects operation measuring instrument, to solve prior art, measures inconvenience, and measuring accuracy is inaccurate, easily produce error, or even mistake, reduced engineering construction efficiency, make engineering not meet the problems such as relevant technological standards and job specifications.
The utility model is mainly comprised of length scale mark and scale mark supporting body, solves the technical scheme that its technical matters adopts to be: this measuring instrument comprises insulating gel lid, insulating bar, scale mark, internal thread metal clamp structure and annex; This measuring instrument adopts telescopic structure, and the insulating bar isometric by some joints nests together; At the built-in tapped metal clamp structure in the top of insulating bar, on metal clamp structure, annex is set.
The diameter at described single-unit insulating bar two ends is poor is 0.2-0.4mm.
Described insulating bar two ends adopt insulating gel lid to carry out shutoff.
Described insulating bar one side indicates length scale mark, take one centimetre as unit, and after the nested pretension of adjacent two joint insulating bar, its scale is continuous.
Described insulating bar opposite side indicates corresponding Phase of Electric Power Projects master scale.
The hook of described annex is ┬ structure, and screw thread is arranged at bottom, connects with metal clamp structure silk.
Described insulating bar is the high-quality expoxy glass steel pipe of processing through protection against the tide, has good insulating property and physical strength, quality is light, and use is easy to carry.
Photo-induced energy storage phosphor material powder spraying for described length scale mark and Phase of Electric Power Projects master scale, can realize night work.
Adopt good effect of the present utility model to be:
1. realized to power circuit over the ground, to the safe distances such as buildings and scissors crossing charged canonical measure.
2. realized the Quick Measurement of construction operation content, such as: foundation ditch detection, the installation of distribution transforming stand, electric pole installation etc., guaranteed construction technology and quality.
3. the measurement needs while having realized night or the bad operation of light.
4. the inadequate problem of galvanoscopic insulating bar height while having solved power circuit electrical verification.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the utility model is further illustrated:
Fig. 1 is the utility model structural representation;
Fig. 1 insulating gel lid, 2 Phase of Electric Power Projects master scale lines, 3 insulating bars, 4 metal clamp structures, 5 annexes, 6 length scale marks.
Embodiment
Embodiment 1
As shown in the figure: this measuring instrument comprises insulating gel lid, insulating bar, scale mark, internal thread metal clamp structure and hook; This measuring instrument adopts telescopic structure, and the insulating bar 3 isometric by four joints nests together; At the built-in tapped metal clamp structure 4 in the top of insulating bar 3, annex hook is set on metal clamp structure.
The diameter at described single-unit insulating bar 3 two ends is poor is 0.2mm.
Described insulating bar 3 two ends adopt insulating gel lid 1 to carry out shutoff.
Described insulating bar 3 one sides indicate length scale mark 6, take one centimetre as unit, and after the nested pretension of adjacent two joint insulating bar, its scale is continuous.
Described insulating bar 3 opposite sides indicate 2,2.0 meters of of corresponding Phase of Electric Power Projects master scale and indicate " 12 meters of electric pole foundation depths "; At 3.2 meters of, indicate " distribution transforming stand height ".
The hook of described annex is ┬ structure, and screw thread is arranged at bottom, connects with metal clamp structure silk.
Described insulating bar 3 is the high-quality expoxy glass steel pipe of processing through protection against the tide, has good insulating property and physical strength, quality is light, and use is easy to carry.
Described length scale mark 6 and the 2 use photo-induced energy storage phosphor material powder sprayings of Phase of Electric Power Projects master scale, can realize night work.
Embodiment 2
As shown in the figure: this measuring instrument comprises insulating gel lid, insulating bar, scale mark, internal thread metal clamp structure and electroscope; This measuring instrument adopts telescopic structure, and the insulating bar 3 isometric by four joints nests together; At the built-in tapped metal clamp structure 4 in the top of insulating bar 3, annex 5 electroscopes are set on metal clamp structure.
The diameter at described single-unit insulating bar 3 two ends is poor is 0.3mm.
Described insulating bar 3 two ends adopt insulating gel lid 1 to carry out shutoff.
Described insulating bar 3 one sides indicate length scale mark 6, take one centimetre as unit, and after the nested pretension of adjacent two joint insulating bar, its scale is continuous.
Described insulating bar 3 opposite sides indicate 2,2.0 meters of of corresponding Phase of Electric Power Projects master scale and indicate " 12 meters of electric pole foundation depths "; At 3.2 meters of, indicate " distribution transforming stand height ".
Described insulating bar 3 is the high-quality expoxy glass steel pipe of processing through protection against the tide, has good insulating property and physical strength, quality is light, and use is easy to carry.
Described length scale mark 6 and the 2 use photo-induced energy storage phosphor material powder sprayings of Phase of Electric Power Projects master scale, can realize night work.
Claims (9)
1. a Phase of Electric Power Projects operation measuring instrument, is mainly comprised of length scale mark and scale mark supporting body, it is characterized in that being: this measuring instrument comprises insulating gel lid, insulating bar, scale mark, internal thread metal clamp structure and annex; This measuring instrument adopts telescopic structure, and the insulating bar isometric by some joints nests together; At the built-in tapped metal clamp structure in the top of insulating bar, on metal clamp structure, annex is set.
2. Phase of Electric Power Projects operation measuring instrument according to claim 1, is characterized in that: the diameter at single-unit insulating bar two ends is poor is 0.2-0.4mm.
3. Phase of Electric Power Projects operation measuring instrument according to claim 1, is characterized in that: insulating bar two ends adopt insulating gel lid to carry out shutoff.
4. Phase of Electric Power Projects operation measuring instrument according to claim 1, is characterized in that: insulating bar one side indicates length scale mark, take one centimetre as unit, and after the nested pretension of adjacent two joint insulating bar, its scale is continuous.
5. Phase of Electric Power Projects operation measuring instrument according to claim 1, is characterized in that: insulating bar opposite side indicates corresponding Phase of Electric Power Projects master scale.
6. Phase of Electric Power Projects operation measuring instrument according to claim 1, is characterized in that: the hook of annex is ┬ structure, and screw thread is arranged at bottom, connects with metal clamp structure silk.
7. according to Phase of Electric Power Projects operation measuring instrument described in claim 1-6, it is characterized in that: the high-quality expoxy glass steel pipe of insulating bar for processing through protection against the tide.
8. Phase of Electric Power Projects operation measuring instrument according to claim 4, is characterized in that: photo-induced energy storage phosphor material powder spraying for length scale mark.
9. Phase of Electric Power Projects operation measuring instrument according to claim 5, is characterized in that: photo-induced energy storage phosphor material powder spraying for Phase of Electric Power Projects master scale.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420372428.4U CN203928972U (en) | 2014-07-08 | 2014-07-08 | A kind of Phase of Electric Power Projects operation measuring instrument |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420372428.4U CN203928972U (en) | 2014-07-08 | 2014-07-08 | A kind of Phase of Electric Power Projects operation measuring instrument |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203928972U true CN203928972U (en) | 2014-11-05 |
Family
ID=51824774
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420372428.4U Expired - Fee Related CN203928972U (en) | 2014-07-08 | 2014-07-08 | A kind of Phase of Electric Power Projects operation measuring instrument |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203928972U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104953510A (en) * | 2015-07-03 | 2015-09-30 | 国网山东商河县供电公司 | Insulating operation rod capable of measuring distances and heights |
CN108759751A (en) * | 2018-06-09 | 2018-11-06 | 袁美华 | A kind of collodion silk width size and elastomeric check device |
-
2014
- 2014-07-08 CN CN201420372428.4U patent/CN203928972U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104953510A (en) * | 2015-07-03 | 2015-09-30 | 国网山东商河县供电公司 | Insulating operation rod capable of measuring distances and heights |
CN104953510B (en) * | 2015-07-03 | 2017-07-07 | 国网山东商河县供电公司 | A kind of insulating bar high that can find range |
CN108759751A (en) * | 2018-06-09 | 2018-11-06 | 袁美华 | A kind of collodion silk width size and elastomeric check device |
CN108759751B (en) * | 2018-06-09 | 2020-12-15 | 日照市睿尔泽新材料科技有限公司 | Device for detecting width and elasticity of rubber silk |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203928972U (en) | A kind of Phase of Electric Power Projects operation measuring instrument | |
CN105222737B (en) | Transmission line of electricity bow line sag measuring method | |
CN204085399U (en) | A kind of vernier caliper of on-line measurement heavy caliber pipe external diameter | |
CN203310337U (en) | Quick range finder for electric pole root spacing | |
CN204301742U (en) | 10kV electric pole group founds chassis orientator | |
CN212539016U (en) | Standard ruler | |
CN105155916A (en) | Single-loop angle steel tower with positive and negative phase-sequence transformation | |
CN205046930U (en) | Positive negative phase sequence of single loop transform angle -steel tower | |
CN207263064U (en) | Irregular mutual inductor coiling multiangular measurement ruler | |
CN203642841U (en) | Simple measuring plate | |
CN204881373U (en) | Multifunctional measuring tape | |
CN205785030U (en) | Busbar makes survey tool | |
CN203929812U (en) | The universal measurement support of single-hand handling & pen meter of universal meter | |
CN103615954A (en) | Electric line pit measuring instrument | |
CN202403628U (en) | Insulated ruler | |
CN203024782U (en) | Lining pole vertical collimator | |
CN204329788U (en) | A kind of multifunction insulating tape measure based on fluorescent material | |
CN202709906U (en) | Multifunctional steel tape | |
CN203731988U (en) | Tower material measurement scale | |
CN203281680U (en) | Pipe fitting bending machine | |
CN204007378U (en) | A kind of electric power tower private volumn angle square | |
CN202471058U (en) | L-shaped horizontal measuring instrument | |
CN201922439U (en) | Tool for drawing line on insulating cylinder of transformer coil | |
CN203396326U (en) | Three-phase transformer iron core clamping measurement device | |
CN204514324U (en) | Pantograph establishes locating device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20141105 Termination date: 20160708 |
|
CF01 | Termination of patent right due to non-payment of annual fee |