CN203891361U - End gutter safety measure connecting piece system - Google Patents

End gutter safety measure connecting piece system Download PDF

Info

Publication number
CN203891361U
CN203891361U CN201320843924.9U CN201320843924U CN203891361U CN 203891361 U CN203891361 U CN 203891361U CN 201320843924 U CN201320843924 U CN 201320843924U CN 203891361 U CN203891361 U CN 203891361U
Authority
CN
China
Prior art keywords
gutter
safety measure
greenhouse
railing
connecting member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320843924.9U
Other languages
Chinese (zh)
Inventor
蒋利施
杨贵
方瑞纲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Dushi Green Engineering Co Ltd
Original Assignee
Shanghai Dushi Green Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Dushi Green Engineering Co Ltd filed Critical Shanghai Dushi Green Engineering Co Ltd
Priority to CN201320843924.9U priority Critical patent/CN203891361U/en
Application granted granted Critical
Publication of CN203891361U publication Critical patent/CN203891361U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Fencing (AREA)

Abstract

The utility model relates to an end gutter safety measure connecting piece system. The end gutter safety measure connecting piece system comprises a group of steel gutters, a group of fences and a group of connecting pieces, wherein the steel gutters are arranged at the tops of upright columns of an exterior wall of a greenhouse; the fences are used for protecting installation personnel; the connecting pieces are used for connecting the steel gutters with the fences; each connecting piece comprises two parts, namely a fixed seat part and a cylinder part; each fence is installed and inserted in the corresponding cylinder part; each steel gutter is a U-shaped groove; one edge of the upper part of each U-shaped groove is connected with roof aluminum alloy, and the other edge of the upper part of each U-shaped groove is connected with wall aluminum alloy. The fences are arranged on the upright columns of the exterior wall of the greenhouse, so that when roof systems such as aluminum alloy, glass and skylights are installed at two ends of the greenhouse, an aluminum alloy roof truss system is arranged inside the greenhouse and any structure system does not exist outside the greenhouse, the safety of the installation personnel is guaranteed; after being used, the fences can be disassembled for a next greenhouse project.

Description

End gutter safety measure connecting member system
Technical field
The utility model belongs to greenhouse culture technique field, is specifically related to a kind of safety that guarantees installation personnel, and railing is after finishing using, and railing can be removed, for the end gutter safety measure connecting member system of next greenhouse project.
Background technology
The development of greenhouse technology, has promoted the develop rapidly of domestic and international agricultural, and greenhouse technology makes as the cultivation of vegetables, melon and fruit, flowers and cultivates the restriction that is no longer subject to season, region, has greatly enriched daily life.Thereby at present greenhouse technology has obtained huge development, at home and abroad, built a large amount of greenhouses and met people to anti-season melon and fruit, the needs of flower culture.
While Roof system being installed as aluminium alloys, glass, skylight at two ends, greenhouse, there is aluminium alloys roof system inner side, greenhouse, and outside, greenhouse is without any structural system, for installation personnel, there is falling from high altitude risk, especially the higher glasshouse of setting height(from bottom).How protecting installation personnel is the problem that needs solve.
Utility model content
For the problems referred to above, main purpose of the present utility model is to provide a kind of safety that guarantees installation personnel, and railing is after finishing using, and railing can be removed, for the end gutter safety measure connecting member system of next greenhouse project.
The utility model solves above-mentioned technical problem by following technical proposals: a kind of end gutter safety measure connecting member system, is characterized in that: described connected system comprises:
One group of steel gutter that is arranged on the column top of greenhouse exterior wall;
The railing of one group of protection installation personnel;
One group of connector that steel gutter is connected with railing;
Described connector comprises two parts, and first is holder part, and second portion is the barrel portion of assigning railing;
Described steel gutter is one " U " type groove, and the top of " U " type groove is connected with roofing aluminium alloys on one side, and another side is connected with metope aluminium alloys.
In preferred embodiment of the present utility model, the two ends at the top of described " U " type groove has a bending part, on roofing, near kink office, is provided with the notch that bending part is injected to roofing.
In preferred embodiment of the present utility model, on described barrel portion, be provided with a plurality of bolts hole of erection bolt.
In preferred embodiment of the present utility model, the number scope of described bolt hole is 1-3.
In preferred embodiment of the present utility model, described holder partly comprises planar section, slope section and bending segment, described slope section is between planar section and bending segment, and described planar section is fixed described barrel portion, and described bending segment is fixed on steel gutter.
In preferred embodiment of the present utility model, described steel gutter welding or the mode being bolted are arranged on the top of the column on greenhouse wall.
In preferred embodiment of the present utility model, described in assign the shape in cross section of part of railing the same with the shape in the cross section of railing.
Positive progressive effect of the present utility model is: the end gutter safety measure connecting member system that the utility model provides has the following advantages: the utility model is provided with one group and is arranged on railing on greenhouse exterior wall column, while Roof system being installed as aluminium alloys, glass, skylight at two ends, greenhouse, there is aluminium alloys roof system inner side, greenhouse, and greenhouse outside is during without any structural system, guarantee the safety of installation personnel, railing is after finishing using, and railing can be removed, for next greenhouse project.
Accompanying drawing explanation
Fig. 1 is overall structure schematic diagram of the present utility model.
Fig. 2 for having removed the structural representation after railing on the utility model.
Fig. 3 is the A place enlarged drawing of Fig. 2.
The specific embodiment
Below in conjunction with accompanying drawing, provide the utility model preferred embodiment, to describe the technical solution of the utility model in detail.
While Roof system being installed as aluminium alloys, glass, skylight at two ends, greenhouse, there is aluminium alloys roof system inner side, greenhouse, and outside, greenhouse is without any structural system, for installation personnel, there is falling from high altitude risk, especially the higher glasshouse of setting height(from bottom).On the gutter of end, increase a connector now, the hole that bottom and gutter are processed is in advance fixed with hexagon-headed bolt, entangles steel pipe and fix with hexagon-headed bolt in the tube connector of top, forms railing, protection installation personnel.After installing, steel pipe can be removed, for next greenhouse project.
That the examples of implementation of a concrete solution: Fig. 1 is overall structure schematic diagram of the present utility model below.As shown in Figure 1: the utility model comprises the railing 3 of one group of steel gutter that is arranged on exterior wall column 1 top, greenhouse 2, one group of protection installation personnel, one group of connector 4 that steel gutter 2 is connected with railing 3, connector 4 comprises two parts, first is holder part 41, and second portion is the barrel portion 42 of assigning railing; This part can be the same according to the shape of railing 3, generally can adopt barrel portion, first and second portion can weld together also and can link together by bolt, steel gutter 2 is one " U " type groove, the top of " U " type groove is connected with roofing aluminium alloys on one side, and another side is connected with metope aluminium alloys.In the process of installing, railing 3 need to be installed row's guarantee staff safety, so railing 3 row that need to distribute, the same quantity of railing 3 that the quantity of corresponding steel gutter 2 and connector 4 is also arranged with needs.
The two ends at the top of " U " type groove has a bending part 21, on roofing, near kink office, is provided with the notch 51 that bending part is injected to roofing 5.
In concrete implementation process, on barrel portion 42, be provided with a plurality of bolts hole 43 of erection bolt, the number scope of bolt hole 43 is 1-3.
Holder part 41 comprises planar section 411, slope section 412 and bending segment 413, slope section 412 between planar section 411 and bending segment 413, planar section 411 stationary cylinder parts 42, bending segment 413 is fixed on steel gutter 2.
2 welding of steel gutter or the mode being bolted are arranged on the top of the column 1 on greenhouse wall.
Fig. 2 has been for to have removed the structural representation after railing on the utility model, the A place enlarged drawing that Fig. 3 is Fig. 2, and in order to guarantee the safety of staff on roofing, the general steel pipe that adopts of railing 3.There is bolt hole the lower end of steel pipe, when mounted, with bolt, through the bolt hole 43 arranging on barrel portion 42 and the bolt hole (not shown in the figures meaning out) of steel pipe lower end, railing 3 is fixed on barrel portion 42; After installing on roofing, steel pipe can be removed, for next greenhouse project.
More than show and described basic principle of the present utility model and principal character and advantage of the present utility model.The technician of the industry should understand; the utility model is not restricted to the described embodiments; that in above-described embodiment and manual, describes just illustrates principle of the present utility model; do not departing under the prerequisite of the utility model spirit and scope; the utility model also has various changes and modifications; these changes and improvements all fall within the scope of claimed the utility model, and the claimed scope of the utility model is defined by appending claims and equivalent thereof.

Claims (7)

1. an end gutter safety measure connecting member system, is characterized in that: described connected system comprises:
One group of steel gutter that is arranged on the column top of greenhouse exterior wall;
The railing of one group of protection installation personnel;
One group of connector that steel gutter is connected with railing;
Described connector comprises two parts, and first is holder part, and second portion is the barrel portion of assigning railing;
Described steel gutter is one " U " type groove, and the top of " U " type groove is connected with roofing aluminium alloys on one side, and another side is connected with metope aluminium alloys.
2. end according to claim 1 gutter safety measure connecting member system, is characterized in that: the two ends at the top of described " U " type groove has a bending part, on roofing, near kink office, is provided with the notch that bending part is injected to roofing.
3. end according to claim 1 gutter safety measure connecting member system, is characterized in that: a plurality of bolts hole that are provided with erection bolt on described barrel portion.
4. end according to claim 3 gutter safety measure connecting member system, is characterized in that: the number scope of described bolt hole is 1-3.
5. end according to claim 1 gutter safety measure connecting member system, it is characterized in that: described holder partly comprises planar section, slope section and bending segment, described slope section is between planar section and bending segment, described planar section is fixed described barrel portion, and described bending segment is fixed on steel gutter.
6. end according to claim 1 gutter safety measure connecting member system, is characterized in that: described steel gutter welding or the mode being bolted are arranged on the top of greenhouse exterior wall column.
7. end according to claim 1 gutter safety measure connecting member system, is characterized in that: described in assign the shape in cross section of part of railing the same with the shape in the cross section of railing.
CN201320843924.9U 2013-12-19 2013-12-19 End gutter safety measure connecting piece system Expired - Fee Related CN203891361U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320843924.9U CN203891361U (en) 2013-12-19 2013-12-19 End gutter safety measure connecting piece system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320843924.9U CN203891361U (en) 2013-12-19 2013-12-19 End gutter safety measure connecting piece system

Publications (1)

Publication Number Publication Date
CN203891361U true CN203891361U (en) 2014-10-22

Family

ID=51717777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320843924.9U Expired - Fee Related CN203891361U (en) 2013-12-19 2013-12-19 End gutter safety measure connecting piece system

Country Status (1)

Country Link
CN (1) CN203891361U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106639181A (en) * 2016-12-26 2017-05-10 上海都市绿色工程有限公司 Sealing device used between side wall gutter and side wall covering glass

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106639181A (en) * 2016-12-26 2017-05-10 上海都市绿色工程有限公司 Sealing device used between side wall gutter and side wall covering glass

Similar Documents

Publication Publication Date Title
CN103669739B (en) Fully opened type aluminum alloy gutter roof system and the building method of external sunshade can be installed
CN201135056Y (en) Green vegetables, fruits shed
CN201602025U (en) Terraced plastic greenhouse
CN203891361U (en) End gutter safety measure connecting piece system
CN2809102Y (en) Car parking roof using climbing vine
CN203735170U (en) Connecting system of glass greenhouse heating pipeline and steel roof gutter
CN201781823U (en) Extensible plastic glasshouse shed
CN203654627U (en) Device for maintaining roofing glass
CN214853122U (en) Novel greenhouse main body
CN202055509U (en) Upright rod installation structure of directly-inserted scaffold
CN207960151U (en) A kind of protective fence of construction
CN204742023U (en) Vegetable greenhouse of frame is planted in area
CN210164201U (en) Roofing transformation engineering protection outrigger
CN204090647U (en) Connect a plastic tunnel
CN205623500U (en) Wire rope draws a novel antithetical couplet photovoltaic green house to one side
CN203701448U (en) Full open aluminum alloy gutter roof system capable of installing external sunshade
CN214413665U (en) Fruit tree shed frame for orchard
CN105297831A (en) Roof greening rainwater utilization system and method based on plant transpiration
CN103104055B (en) Extending structure for glass wall
CN210737855U (en) Green curtain system of planting
CN205052368U (en) Grape big -arch shelter and grape be a big -arch shelter even
CN210247745U (en) Simple and easy type grape is planted and is kept away rain cultivation frame
CN208047477U (en) A kind of assembled greenhouse of load-carrying construction combination implant system
CN104727493B (en) Supporting, pulling and bonding system of wood paike with oversized volume and construction method thereof
CN203340691U (en) External thermal insulation arched shed

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141022

Termination date: 20211219