CN203891037U - Anchor bolt and tree pile combined retaining structure - Google Patents

Anchor bolt and tree pile combined retaining structure Download PDF

Info

Publication number
CN203891037U
CN203891037U CN201420248026.3U CN201420248026U CN203891037U CN 203891037 U CN203891037 U CN 203891037U CN 201420248026 U CN201420248026 U CN 201420248026U CN 203891037 U CN203891037 U CN 203891037U
Authority
CN
China
Prior art keywords
pile
soil
root pile
root
anchor pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420248026.3U
Other languages
Chinese (zh)
Inventor
张坤勇
李凡
王耀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN201420248026.3U priority Critical patent/CN203891037U/en
Application granted granted Critical
Publication of CN203891037U publication Critical patent/CN203891037U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model relates to an anchor bolt and tree pile combined retaining structure comprising root piles in double rows and serving as a vertical retaining structure and side oblique anchor bolts serving as an external stay system. The double-row root piles and the side oblique anchor bolts are connected through pile-top beams and are arranged along the whole length of a loose soil range of a landslide to be improved. The pile-top beams and the double-row root piles are connected by means of hinging. The pile-top beams and the side oblique anchor bolts are connected in a rigid manner. One end (head) of each of in-soil anchor bolts serving the external stay system is connected with the corresponding root pile through the corresponding pile-top beams (a capping beam and a breast beam); the other end of each in-soil anchor bolt serves as an anchor member; the anchor members are arranged in a stable soil layer. The root piles and the side oblique anchor bolts are integrally connected through the pile-top beams which are cast-in-place concrete beams arranged at the top of the root piles; the root piles are arranged in two parallel rows; row spacing is 5-7 times of pile spacing, and a center-to-center distance of each two longitudinal piles is 1.0-1.2m. The anchor bolt and tree pile combined retaining structure has good overall stress conditions and has great spatial effect; self-stability of the soil layer can be given to full play; the problems such that an excavated face for slide-resistant piles, commonly used in controlling instability and slide of a soil slope, is excessive, severe disturbances are caused to the slope soil layer, and construction is difficult are effectively solved; cost can be effectively reduced, and efficiency can be effectively improved.

Description

The compound soil-baffling structure of a kind of anchor pole-root pile
Technical field
The utility model relates to Geotechnical Engineering field, relating in particular to a kind of Stability of Earth Slopes reinforces and supporting and protection structure, (may slide at dangerous slopes, slide) region, set vertical root pile soil-baffling structure by fracture grouting, and by stake head piece and the combination of oblique soil bolt, form compound soil-baffling structure, greatly improve and reinforce and support capacity.
Background technology
Soil-baffling structure, can be described as again supporting and protection structure, and space enclosing structure is mainly used in stability of slope in geotechnical engineering field, pattern foundation pit supporting structure, cavern excavation, coastal engineering.Have multi-form according to its effect field difference: in the time being mainly used in stability of slope, have retaining wall, antislide pile, the forms such as anchored bolt retaining wall; In the time of supporting for excavation of foundation pit, there is cantilevered space enclosing structure, gravity wall, inner bearing type space enclosing structure, draws anchor formula space enclosing structure, soil nail wall space enclosing structure and gantry type, open caisson, arch formula combined enclosure, spray anchor net is gone along with sb. to guard him etc.; In coastal engineering, mainly contain sheet pile wing wall, mole etc.; In cavern excavation engineering, there is lining cutting, vertical supporting etc.
At present, stability of slope structure has a lot, and conventional have antislide pile, anchor pole, a retaining wall.Antislide pile stake footpath is large, and difficulty of construction is large, and cost is high, large to soil layer disturbance, and work plane requires high.Anchor pole is to simple soil layer, and small-sized slight slope landslide antiskid effect is obvious, unstable to major landslip effect.Rigid retaining wall earthwork excavated volume is large, and disturbance is large, need to excavate base plate, and cost is high.And to there is the region on landslide, excavation slight slope can cause the further increasing on landslide.How effectively to administer landslide and soil layer around landslide do not caused to large disturbance, avoiding further destruction, and how to improve efficiency of construction, convenient construction, cost-saving is to need to consider.
In view of traditional soil-baffling structure exists cost high, difficulty of construction is large, cost is higher and the low grade of efficiency is not enough, taking into full account the horizontal anti-slide performance of root pile and the tensile property of anchor pole, the utility model proposes the compound soil-baffling structure of a kind of anchor pole-root pile, can give full play to the self-stable ability of the landslide soil body, and cost is low, easy construction, Space is obvious.And to expansive soil slope, the root pile that fracture grouting is technical foundation can form the compound soil body, increase the anti-slide performance of root pile.In addition, root pile easy construction, establishes a position flexible, little to soil layer disturbance; Special secondary high-pressure slip-casting technology in root pile work progress, the stake Zhou Fuhe soil body forming through fracture grouting, can make pile body be anchored at reliably in the soil body and improve soil strength.
Summary of the invention
The utility model provides a kind of anchor pole-root pile compound soil-baffling structure, by double root pile is set as vertical soil-baffling structure in side slope, form compound soil-baffling structure by stake head piece and soil bolt, can give full play to soil layer self-stability, effectively solve in soil-slope generation unstability preventing land slide conventional antislide pile excavation face excessive, strong to the disturbance of side slope soil layer, the problems such as constructional difficulties, and can effectively reduce costs, raise the efficiency.
In order to address the above problem, the utility model adopts following technical scheme:
The compound soil-baffling structure of a kind of anchor pole-root pile, comprises by the double root pile as vertical soil-baffling structure with as the lateral tilt anchor pole of outer pull system, connects and along the loosening elongated layout of soil body scope in the landslide that needs regulation by stake head piece.Between crossbeam and root pile, adopt hinged connected mode, being connected between crossbeam and anchor pole is to be rigidly connected; As the soil bolt of outer pull system, its one end is connected with root pile by stake head piece, and the other end is anchoring body, and anchoring body is located in steady soil; Root pile stake top adopts cast-in-situ concrete crossbeam that root pile and anchor pole are connected as a single entity, and crossbeam physical dimension is determined according to root pile and anchor pole dimension synthesis, to ensure that stake-anchor pole forms composite construction, brings into play space and keeps off native effect.Root pile becomes two rows to be arranged in parallel, and front and back two campsheds are apart from getting 5~7 times of stake footpaths, and longitudinally pile center is apart from getting 1.0~1.2m.Result, according to landslide on-the-spot soil property and side slope physical dimension situation, is calculated in conjunction with landslide soil pressure in the long and stake footpath of the stake of root pile, adopts the long and stake footpath of piles with different according to root pile design specifications comprehensive Design, and the enough degree of depth of guarantee buried depth are to provide corresponding skid resistance.
Described root pile length is got 10~15m, root pile aperture 150mm~250mm.
Soil bolt length should be according to landslide soil property and landslide physical dimension, the comprehensive compound soil-baffling structure result of calculation of stake-beam-anchor pole, comprehensively determine with reference to soil bolt design specifications, to guarantee deeply sliding bed of anchor pole, enough bond stresss are provided, the every long 10~20m of anchor pole, aperture 100~150mm, the angle between inclination anchor pole and vertical root pile is 45 °.
The beneficial effects of the utility model are:
Root pile is as mini pile, and construction equipment is light, becomes hole dimension little, compares with general major diameter antislide pile, and easy construction, establishes a position flexible, little to soil layer disturbance, can avoid the secondary landslide causing due to construction;
Special secondary high-pressure slip-casting technology in root pile work progress, the stake Zhou Fuhe soil body forming through fracture grouting, can make pile body be anchored at reliably in the soil body and improve soil strength.Not only played the effect as antislide pile, and the compound soil body can more effectively improve landslide soil strength, thereby improve slope stability.
The vertical soil-baffling structure of double root pile and the combination of drawing anchor rod type soil-baffling structure, the more independent antislide pile of whole composite construction or the separately lateral stiffness of anchor pole significantly improve, and lateral deformation is little, and the supporting degree of depth and supporting scope all strengthen; When bearing landslide horizontal thrust, double root pile does the used time, by stake head piece, part sliding force is delivered to soil bolt, then is delivered in steady soil by soil bolt, structural entity stress condition is good, can give full play to the acting in conjunction of structure and the soil body, transfer the self-stable ability of the soil body.
Brief description of the drawings
Fig. 1 is the generalized section of the compound soil-baffling structure of anchor pole-root pile described in the utility model
Fig. 2 is the generalized section of the described stake of the utility model head piece
Fig. 3 is root pile construction flow chart
Fig. 4 is anchor rod construction process flow chart
In figure: 1, root pile, 2, stake head piece, 3, anchor pole, 4, slide plane or potential slide plane.
Detailed description of the invention
According to following embodiment, can understand better the utility model, the described particular content of embodiment is only for the utility model is described, and should also can not limit the interest field described in claims.
Referring to Fig. 1, Fig. 2, the compound soil-baffling structure of a kind of novel anchor rod-root pile, comprises following part: root pile 1, stake head piece 2, anchor pole 3,4th, slide plane or potential slide plane.By the contact of stake head piece and along the loosening elongated layout of soil body scope in the landslide that needs regulation, between crossbeam and root pile 1, adopt hinged connected mode; Being connected between crossbeam and anchor pole 3 is to be rigidly connected, and as the soil bolt of outer pull system, its one end (anchor head) is connected with root pile 1 by stake head piece (capping beam, waist rail); The other end is anchoring body, anchoring body is located in steady soil, and root pile stake top adopts cast-in-situ concrete crossbeam that root pile and anchor pole 3 are connected as a single entity, and root pile 1 one-tenth two row be arranged in parallel, front and back two campsheds are apart from getting 5~7 times of stake footpaths, and longitudinally pile center is apart from getting 1.0~1.2m.
The wherein long 10m of stake of root pile 1, aperture 200mm, becomes two rows to be arranged in parallel, front and back pilespacing 1.40m, longitudinally pile center is apart from 1.0m.
Wherein anchor pole 3 every long 17m, aperture 110mm.Angle between anchor pole 3 and root pile 1 is 45 °.
The very useful crossbeam of its king-pile is connected as a single entity root pile 1 and anchor pole 3; The thick 250mm of crossbeam, long 80m, wide 1.7m, the high 550m of girt strip, wide 250mm.
Its middle cross beam elevation does dry pitching with slope, the thick 300mm of piece stone, and the thick 100mm of hardcore bed, plinth is 500 × 700 to grout rubble.
Wherein gutter is V-shaped, bottom width 300mm, thick 80mm, the high 300mm of ditch, total length 253m.
A construction method for the compound soil-baffling structure of anchor pole-root pile, construction sequence is as follows:
Step 1, root pile construction
Root pile construction adopts interval to jump play parallel direction and advances, and its construction technology process as shown in Figure 3.
Step 2, anchor bolt construction
Anchor bolt construction also takes interval to jump the propelling of play parallel direction, plays construction technology process as shown in Figure 4.
Step 3, crossbeam
1. foundation trench excavation
2. tile floor mould is built by laying bricks or stones
3. reinforcing bar processing and reinforcing cage colligation are laid
4. crossbeam concrete is built
Step 4, dry rubble bank protection, rubble mound is built by laying bricks or stones by the sequence construction on Xia Xiang slope, slope from West to East.Dry rubble immediately after paving 100mm thick hardcore bed; The thick 300mm of dry rubble.Bank protection is built by laying bricks or stones complete, starts construction and grout plinth at the bottom of canal, and plinth is that 500 × 700mm grouts rubble.
The above; it is only detailed description of the invention of the present utility model; but protection domain of the present utility model is not limited to this; any those of ordinary skill in the art are in the disclosed technical scope of the utility model; the variation that can expect easily or replacement, within all should being encompassed in protection domain of the present utility model.Therefore, protection domain of the present utility model should be as the criterion with the protection domain that claims were limited.

Claims (3)

1. the compound soil-baffling structure of anchor pole-root pile, it is characterized in that: comprise by the double root pile as vertical soil-baffling structure with as the lateral tilt anchor pole of outer pull system, connect and along the loosening elongated layout of soil body scope in the landslide that needs regulation by stake head piece; Between crossbeam and root pile, adopt hinged connected mode, being connected between crossbeam and anchor pole is to be rigidly connected; As the soil bolt of outer pull system, its one end is connected with root pile by stake head piece, and the other end is anchoring body, and anchoring body is located in steady soil; Root pile stake top adopts cast-in-situ concrete crossbeam that root pile and anchor pole are connected as a single entity, and root pile becomes two rows to be arranged in parallel, and front and back two campsheds are apart from getting 5~7 times of stake footpaths, and longitudinally pile center is apart from getting 1.0~1.2m.
2. the compound soil-baffling structure of anchor pole-root pile according to claim 1, is characterized in that: described root pile length is got 10~15m, root pile aperture 150mm~250mm.
3. the compound soil-baffling structure of anchor pole-root pile according to claim 1, is characterized in that: the long 10~20m of described anchor pole, and aperture 100~150mm, the angle between inclination anchor pole and vertical root pile is 45 degree.
CN201420248026.3U 2014-05-14 2014-05-14 Anchor bolt and tree pile combined retaining structure Expired - Fee Related CN203891037U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420248026.3U CN203891037U (en) 2014-05-14 2014-05-14 Anchor bolt and tree pile combined retaining structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420248026.3U CN203891037U (en) 2014-05-14 2014-05-14 Anchor bolt and tree pile combined retaining structure

Publications (1)

Publication Number Publication Date
CN203891037U true CN203891037U (en) 2014-10-22

Family

ID=51717458

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420248026.3U Expired - Fee Related CN203891037U (en) 2014-05-14 2014-05-14 Anchor bolt and tree pile combined retaining structure

Country Status (1)

Country Link
CN (1) CN203891037U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013180A (en) * 2016-05-31 2016-10-12 重庆交通大学 Novel stability control system for pile foundation in deep filling slope
CN109183819A (en) * 2018-11-12 2019-01-11 攀钢集团矿业有限公司 A kind of refuse dump granular media slope reinforcement component and reinforcement means
CN112554243A (en) * 2020-11-27 2021-03-26 苏州市中坚建设工程有限责任公司 Construction process of prestressed anti-floating anchor cable of tree root pile
CN112832191A (en) * 2021-01-13 2021-05-25 中国电建集团贵阳勘测设计研究院有限公司 Dyke heightening and reinforcing structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013180A (en) * 2016-05-31 2016-10-12 重庆交通大学 Novel stability control system for pile foundation in deep filling slope
CN109183819A (en) * 2018-11-12 2019-01-11 攀钢集团矿业有限公司 A kind of refuse dump granular media slope reinforcement component and reinforcement means
CN112554243A (en) * 2020-11-27 2021-03-26 苏州市中坚建设工程有限责任公司 Construction process of prestressed anti-floating anchor cable of tree root pile
CN112832191A (en) * 2021-01-13 2021-05-25 中国电建集团贵阳勘测设计研究院有限公司 Dyke heightening and reinforcing structure

Similar Documents

Publication Publication Date Title
CN106677189B (en) A kind of taper pile wall supporting type foundation pit supporting construction and its construction method
CN104532868B (en) High abrupt change shape sloped region bridge anchor pull-type high cap pile group basis construction method
CN103485363B (en) Three-dimensional continuous frame formula reinforced concrete structure retaining wall
CN205134331U (en) Foundation ditch excavation bearing structure
CN103711135B (en) Anti-slide pile of jointed arch structure
CN101418570A (en) Foundation pit supporting method with double rows of piles
CN203891037U (en) Anchor bolt and tree pile combined retaining structure
CN207130754U (en) The large-span arch bridge combined type pile foundation construction of two-way cooperative bearing
CN109610481B (en) Support treatment construction method for tunnel portal bedding strong weathering rock high and steep side slope
CN104727340A (en) High cutting slope anchor rope space framework supporting and retaining structure
CN105155548A (en) Cable double-row pile (wall) supporting structure
CN104131571B (en) A kind of deep foundation pit supporting construction method
CN109667273A (en) A kind of construction method of deep foundation pit supporting structure
CN202730796U (en) Existing retaining wall rib plate type unloading reinforcing structure
CN206956744U (en) A kind of compound retaining structure of curb
CN109403339A (en) The deep basal pit composite supporting construction and its method for protecting support of double-row pile combination method of center island
CN117646437A (en) Side slope and foundation pit double-row pile supporting structure and construction method
CN211174126U (en) Open cut tunnel structure
CN209243910U (en) A kind of side slope building structure
CN204491683U (en) A kind of ruggedized construction to municipal piping lane existing within the scope of deep pit digging
CN108035360A (en) A kind of method for pattern foundation pit supporting structure
CN205188976U (en) Drag -line double row pile supporting construction
CN105696701A (en) Along-slope shear wall building development platform and construction method thereof
CN217354388U (en) Combined retaining type tunnel portal structure suitable for bias steep slope terrain
CN111911183B (en) Tunnel hole entering construction method based on end wall type guide wall structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20141022

Termination date: 20180514