CN203865696U - Pay-off rack - Google Patents

Pay-off rack Download PDF

Info

Publication number
CN203865696U
CN203865696U CN201420236133.4U CN201420236133U CN203865696U CN 203865696 U CN203865696 U CN 203865696U CN 201420236133 U CN201420236133 U CN 201420236133U CN 203865696 U CN203865696 U CN 203865696U
Authority
CN
China
Prior art keywords
pay
rack
vertical lifting
lifting bracket
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201420236133.4U
Other languages
Chinese (zh)
Inventor
龚祖春
尹新卫
姚卫星
邹礼刚
李晓明
张学华
瞿峰
李良骥
严实
林学良
李磊
高鹏飞
孙舒昌
谭光勤
许涛
陈永堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GEZHOUBA GROUP'S ELECTRIC POWER Co Ltd
China Gezhouba Group No 1 Engineering Co Ltd
Original Assignee
GEZHOUBA GROUP'S ELECTRIC POWER Co Ltd
China Gezhouba Group No 1 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GEZHOUBA GROUP'S ELECTRIC POWER Co Ltd, China Gezhouba Group No 1 Engineering Co Ltd filed Critical GEZHOUBA GROUP'S ELECTRIC POWER Co Ltd
Priority to CN201420236133.4U priority Critical patent/CN203865696U/en
Application granted granted Critical
Publication of CN203865696U publication Critical patent/CN203865696U/en
Anticipated expiration legal-status Critical
Active legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A pay-off rack comprises two climbing mechanisms arranged in bilateral symmetry, wherein each climbing mechanism comprises a bottom plate, an upright post and a vertical lifting bracket; each upright post is fixedly mounted on the corresponding bottom plate; each vertical lifting bracket is assembled on the corresponding upright post; hinges are arranged on the vertical lifting brackets; a jack is arranged on the bottom plate; saddle iron is arranged in the positions of the hinges. The pay-off rack provided by the utility model can coil cables on a frame rapidly, so that the construction speed is increased, the time for erecting a disk is shortened, and the pay-off rack is high in applicability, simple and convenient.

Description

A kind of pay off rack
Technical field
A kind of pay off rack of the utility model, for small-sized cable disc unwrapping wire.
Background technology
In power cable, optical cable construction, often will use pay off rack, the pay off rack of use is mainly fixed usually, and the distance on turning cylinder and ground is very high, the strong point: the place of putting jack generally cannot be adjusted, and is applicable to large cable disc.But in construction, often run into less cable disc, and but can not be directly added, need be with crane or manpower, cable disc is added, both took time like this, also lost labor and machinery expenses, careless slightly, also easily cause cable disc extruding to hurt sb.'s feelings.
Summary of the invention
For solving the problems of the technologies described above, the utility model provides a kind of pay off rack, can be fast that cable disc is added, accelerate speed of application, the time of having saved branch, this pay off rack applicability strong, simple and convenient.
The technical scheme that the utility model is taked is: a kind of pay off rack, comprise left and right two lifting bodies that are arranged symmetrically with, each lifting body comprises base plate, column, vertical lifting bracket, on base plate, be installed with column, on column, be equipped with vertical lifting bracket, in vertical lifting bracket, be provided with hinge, base plate is provided with jack, and described hinge is provided with saddle iron.
Described column is fixedly mounted on base plate by hound, and described column is steel pipe post.
Described vertical lifting bracket is welded by channel-section steel.
Described hinge is steel pipe hinge, and for multiple, multiple steel pipe hinges are arranged symmetrically in vertical lifting bracket.
A kind of pay off rack of the utility model, can be added by cable disc fast, accelerates speed of application, saved the time of branch, and applicability is strong, simple and convenient.And all parts is drawn materials simply, processing and fabricating is convenient.Jack and drum synchronization lifting, avoided drum extruding casualty accident to occur.Be particularly suitable for middle-size and small-size cable disk, wire coil for optical cable unwrapping wire.
Brief description of the drawings
Fig. 1 is the utility model apparatus structure schematic diagram.
Fig. 2 is that the utility model device uses state reference map.
Detailed description of the invention
As shown in Figure 1 and Figure 2, a kind of pay off rack, comprise left and right two lifting bodies that are arranged symmetrically with, each lifting body comprises base plate 8, column 2, vertical lifting bracket 1, on base plate 8, be installed with column 2, on column 2, be equipped with vertical lifting bracket 1, in vertical lifting bracket 1, be provided with hinge 6, base plate 8 is provided with jack 4, and described hinge 6 is provided with saddle iron 5.Described column 2 is fixedly mounted on base plate 8 by hound 3.
Described column 2 is steel pipe post, and hound 3 is round steel strut.Described vertical lifting bracket 1 is welded by channel-section steel.Described hinge 6 is steel pipe hinge, is four, and four steel pipe hinges of sustained height are arranged symmetrically in vertical lifting bracket 1.
Implementation step:
1), according to the width of cable disc 9, two lifting bodies are symmetrically arranged.
2, paying out reel 7 is inserted in the axis hole of cable disc 9, according to the height of paying out reel 7, four saddle iron 5 are inserted respectively in steel pipe hinge, the height of saddle iron 5 is lower than the height of paying out reel 7.
3), two jacks 4 are placed on base plate 8,, carry out synchronization of jacking up operation.When cable disc 9 is pushed up overhead about 10cm by jack 4, stop jacking, locking jack 4, then starts the unfolding of cable or optical cable.
4), after cable or optical cable unfolding, jack 4 is synchronously fallen, until cable disc 9 nails, dismounting jack 4 and lifting body, end-of-job.

Claims (6)

1. a pay off rack, comprise left and right two lifting bodies that are arranged symmetrically with, it is characterized in that, each lifting body comprises base plate (8), column (2), vertical lifting bracket (1), on base plate (8), be installed with column (2), on column (2), be equipped with vertical lifting bracket (1), in vertical lifting bracket (1), be provided with hinge (6), base plate (8) is provided with jack (4), and described hinge (6) is provided with saddle iron (5).
2. a kind of pay off rack according to claim 1, is characterized in that, described column (2) is fixedly mounted on base plate (8) by hound (3).
3. according to a kind of pay off rack described in claim 1 or 2, it is characterized in that, described column (2) is steel pipe post.
4. a kind of pay off rack according to claim 1, is characterized in that, described vertical lifting bracket (1) is welded by channel-section steel.
5. a kind of pay off rack according to claim 1, is characterized in that, described hinge (6) is steel pipe hinge, and for multiple, multiple steel pipe hinges are arranged symmetrically in vertical lifting bracket (1).
6. a kind of pay off rack according to claim 2, is characterized in that, described hound (3) is round steel strut.
CN201420236133.4U 2014-05-09 2014-05-09 Pay-off rack Active CN203865696U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420236133.4U CN203865696U (en) 2014-05-09 2014-05-09 Pay-off rack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420236133.4U CN203865696U (en) 2014-05-09 2014-05-09 Pay-off rack

Publications (1)

Publication Number Publication Date
CN203865696U true CN203865696U (en) 2014-10-08

Family

ID=51646675

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420236133.4U Active CN203865696U (en) 2014-05-09 2014-05-09 Pay-off rack

Country Status (1)

Country Link
CN (1) CN203865696U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106241485A (en) * 2016-09-22 2016-12-21 国网山东省电力公司莱芜供电公司 Assembled moving cable pay off rack

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106241485A (en) * 2016-09-22 2016-12-21 国网山东省电力公司莱芜供电公司 Assembled moving cable pay off rack

Similar Documents

Publication Publication Date Title
CN203754341U (en) Lifting bracket
CN105421859A (en) Electricity grid telegraph pole erecting device and construction method
CN204588536U (en) Mobile folding weight-hauling equipment
GB201209006D0 (en) High rise building elevation concept
CN104176419A (en) Brick stacking machine
CN106241485A (en) Assembled moving cable pay off rack
CN203865696U (en) Pay-off rack
CN203833394U (en) Labor-saving winding tool flexible in winding and unwinding
CN102180381B (en) Unreeling rack
RU2016111128A (en) Tower structure
CN204675725U (en) A kind of screen cabinet carrying handling device
CN203094107U (en) Easy moving in-place device of constructional element under construction of installation project
CN104085729A (en) Dual-purpose wire unwinding rack
CN201904573U (en) Large electric cable paying-off device
CN205188867U (en) Vertical intercepting device in parking area
CN203939270U (en) Plain type verticallifting stereo jiffy stand
CN103362053A (en) Retractable pedal device and retracting method thereof
CN203567780U (en) Device used for carrying and installing distribution transformer
CN103541574B (en) Steel-making diffusing tower installation construction in narrow regions
CN202344102U (en) Novel welding machine
CN207468083U (en) A kind of movable hanging assembling device for small building equipment hoisting
CN202997427U (en) Portable electric cable pay-off rack
CN205806843U (en) A kind of elevation mechanism of communication cable support bar
CN111099429A (en) Cross-road cable pay-off device and use method
CN204873659U (en) Electric block suspension system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant