CN203856157U - Stone dry hanging installation system - Google Patents

Stone dry hanging installation system Download PDF

Info

Publication number
CN203856157U
CN203856157U CN201420221345.5U CN201420221345U CN203856157U CN 203856157 U CN203856157 U CN 203856157U CN 201420221345 U CN201420221345 U CN 201420221345U CN 203856157 U CN203856157 U CN 203856157U
Authority
CN
China
Prior art keywords
shaped body
installation system
stone material
material dry
dry suspending
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420221345.5U
Other languages
Chinese (zh)
Inventor
岳献武
章超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Huanan Decoration Design Engineering Co ltd
Shenzhen Huanan Decoration Group Co ltd
Original Assignee
SHENZHEN HUA'NAN DECORATION DESIGN ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN HUA'NAN DECORATION DESIGN ENGINEERING Co Ltd filed Critical SHENZHEN HUA'NAN DECORATION DESIGN ENGINEERING Co Ltd
Priority to CN201420221345.5U priority Critical patent/CN203856157U/en
Application granted granted Critical
Publication of CN203856157U publication Critical patent/CN203856157U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

The utility model provides a stone dry hanging installation system. By the adoption of the stone dry hanging installation system, stone plates can be installed on a building structure. The stone dry hanging installation system comprises a connecting assembly and a fixing piece. The connecting assembly comprises a connecting piece. The connecting piece comprises a U-shaped body and bent portions which are formed by bending two branch arms of the U-shaped body reversely. An installation hole is formed in the bottom of the U-shaped body. The bent portion can be fixedly connected with the building structure. The fixing piece can be fixedly connected with the stone plates. The fixing piece penetrates through the installation hole and is fixedly connected with the bottom of the U-shaped body. The stone dry hanging installation system is simple in structure and beneficial to the improvement on construction efficiency.

Description

Stone material dry suspending installation system
Technical field
The utility model belongs to building decoration engineering field, relates in particular to a kind of stone material dry suspending installation system.
Background technology
Stone material dry suspending is a kind of construction technology of external wall, by connector, ornamental stone is for example hung over, on the external surface of building structure (body of wall).Traditional stone material dry suspending installation system is normally made up of suspension member, steel joist, fixture, fastener and ornamental stone etc., suspension member is fixed on the external surface of building structure, for fixing steel joist, fastener is fixed on steel joist by fixture, for fixing ornamental stone, and adjusts planeness by suspension member, steel joist, adjust installed height mark and position up and down by fastener, but the part of this stone material dry suspending installation system is more, complex structure, has a strong impact on efficiency of construction.
Utility model content
Given this, be necessary to provide a kind of structure comparatively simple and can improve the stone material dry suspending installation system of efficiency of construction.
A kind of stone material dry suspending installation system, can be arranged on stone plate in building structure, and described stone material dry suspending installation system comprises:
Coupling assembling, comprises connector, and described connector comprises the kink that U-shaped body and two support arms by described U-shaped body are oppositely bent to form, and the bottom of described U-shaped body offers installing hole, and described kink can be fixedly connected with described building structure; And
Fixture, can be fixedly connected with described stone plate, and described fixture is arranged in described installing hole, and is fixedly connected with the bottom of described U-shaped body.
Therein in an embodiment, described fixture comprises thread rod part, described thread rod part is arranged in described installing hole, described coupling assembling also comprises the first hold-down nut and the second hold-down nut that are sheathed on described thread rod part and are screwed with described thread rod part, and described the first hold-down nut and described the second hold-down nut connect with the relative both sides of the bottom of described U-shaped body respectively.
Therein in an embodiment, described coupling assembling also comprises on the bottom that is arranged at described U-shaped body, and with described U-shaped body by integral forming, and the stationary magazine creel being communicated with described installing hole, on the sidewall of described stationary magazine creel, offer multiple circumferential spaced screws along described stationary magazine creel, described thread rod part is arranged in described installing hole and described stationary magazine creel, use multiple screws to be arranged in respectively described multiple screw, and with described multiple screwhole spiro bondings, the end face that described multiple screw is contained in one end of described stationary magazine creel all connects with described thread rod part, the bottom of described the first hold-down nut and described U-shaped body connects away from a side of described stationary magazine creel, described the second hold-down nut and described stationary magazine creel connect away from the end face of one end of the bottom of described U-shaped body.
In an embodiment, the edge of opening of one end of described stationary magazine creel is provided with flange therein, and the other end is fixedly connected with the bottom of described U-shaped body, and described the second hold-down nut and described flange connect.
In an embodiment, the bottom of described U-shaped body is also provided with multiple reinforcing ribs that are fixedly connected with the external surface of described stationary magazine creel therein.
Therein in an embodiment, described fixture also comprises the holding section that is arranged at one end of described thread rod part and is fixedly connected with described thread rod part, and the width of described holding section is greater than the width of described thread rod part, on described stone plate, offer the draw-in groove fastening with described holding section.
Therein in an embodiment, on described kink, offer pilot hole, described stone material dry suspending installation system also comprises threaded fastener, be contained in described building structure described threaded fastener partial fixing, the part that described threaded fastener stretches out described building structure is arranged in described pilot hole, and is fixedly connected with described kink.
Therein in an embodiment, described threaded fastener is double-screw bolt, described stone material dry suspending installation system also comprises the elastic component and the adjusting nut that are sheathed on described threaded fastener, described elastic component and described adjusting nut lay respectively at the relative both sides of described kink, the two ends of described elastic component connect with described building structure and described kink respectively, described adjusting nut and described threaded fastener threaded engagement, rotate described adjusting nut to regulate the distance of described kink and described building structure.
In an embodiment, also comprise two packing rings that are sheathed on described threaded fastener therein, one of them packing ring is held between described elastic component and described building structure, and another packing ring is held between described elastic component and described kink.
In an embodiment, the bottom of described U-shaped body is provided with the first armpit angle being fixedly connected with the support arm of described U-shaped body therein; The support arm of described U-shaped body is provided with the second armpit angle being fixedly connected with described kink.
Above-mentioned stone material dry suspending installation system has following advantage at least:
(1) kink of the connector of above-mentioned stone material dry suspending installation system and building structure are fixed, fixture is fixedly connected with stone plate and connector, thereby stone plate is fixed in building structure, a connector has substituted suspension member, steel joist and three elements of fastener in conventional mounting system, reduce and in work progress, needed field erected element, simplify the structure of stone material dry suspending installation system, and be conducive to improve efficiency of construction.
(2) connector of the coupling assembling of above-mentioned stone material dry suspending installation system comprises the kink that U-shaped body and two support arms by U-shaped body are oppositely bent to form, it is U-shaped body and the kink structure that is formed in one, further reduce in work progress and needed field erected element, be more conducive to improve efficiency of construction.
Brief description of the drawings
Fig. 1 is that stone plate is arranged on the structural representation in building structure by the stone material dry suspending installation system of an embodiment;
Fig. 2 is that the stone material dry suspending installation system shown in Fig. 1 is arranged on the structural representation in building structure;
Fig. 3 is the exploded view of another angle of the coupling assembling that screw is installed, packing ring and the elastic component of the stone material dry suspending installation system shown in Fig. 1;
Fig. 4 is the structural representation that the coupling assembling shown in Fig. 3 is provided with another angle of screw;
Fig. 5 is that stone plate is arranged on the structural representation in building structure by the stone material dry suspending installation system shown in multiple Fig. 1.
Detailed description of the invention
For the ease of understanding the utility model, below with reference to relevant drawings, the utility model is described more fully.In accompanying drawing, provide preferred embodiment of the present utility model.But the utility model can be realized in many different forms, be not limited to embodiment described herein.On the contrary, providing the object of these embodiment is to make to the understanding of disclosure of the present utility model more thoroughly comprehensively.
It should be noted that, when element is called as " being fixed on " another element, it can be directly on another element or also can have an element placed in the middle.When an element is considered to " connection " another element, it can be directly connected to another element or may have centering elements simultaneously.Term as used herein " vertical ", " level ", " left side ", " right side " and similar statement are just for illustrative purposes.
Unless otherwise defined, all technology that use are herein identical with the implication that belongs to the common understanding of those skilled in the art of the present utility model with scientific terminology.The term using in manual of the present utility model herein, just in order to describe the object of specific embodiment, is not intended to be restriction the utility model.
As shown in Figures 1 and 2, the stone material dry suspending installation system 10 of an embodiment, can be arranged on stone plate 20 in building structure 30, plays a part the external surface of decorative architecture structure 30.Wherein, stone plate 20 is roughly flat stone material.The material of stone plate 20 can be lithotome or artificial stone etc.Lithotome can be marble, granite etc.Building structure 30 can be the metope of building etc.Stone material dry suspending installation system 10 comprises coupling assembling 200 and fixture 300.
See also Fig. 3, coupling assembling 200 is the connection bridge of stone plate 20 and building structure 30.Coupling assembling 200 comprises connector 210.Wherein, the material of connector 210 is steel.Connector 210 comprises the kink 214 that U-shaped body 212 and two support arms by U-shaped body 212 are oppositely bent to form.Be U-shaped body 212 and kink 214 structure that is formed in one, thereby reduced the element that will install in installation process.
See also Fig. 4, the bottom of U-shaped body 212 offers installing hole 2122.Further, the bottom of U-shaped body 212 is provided with the first armpit angle 2124 being fixedly connected with the support arm of U-shaped body 212, thereby increases the strength and stiffness of the bottom of U-shaped body 212 and the junction of support arm.
Kink 214 can be fixedly connected with building structure 30.Concrete, on kink 214, offer pilot hole 2142.Stone material dry suspending installation system 10 also comprises threaded fastener 400.Be contained in building structure 30, the part that threaded fastener 400 stretches out building structure 30 is arranged in pilot hole 2142 threaded fastener 400 partial fixings, and is fixedly connected with kink 214.
More specifically, threaded fastener 400 is double-screw bolt.Stone material dry suspending installation system 10 also comprises the elastic component 500 and the adjusting nut 600 that are sheathed on threaded fastener 400.Elastic component 500 and adjusting nut 600 lay respectively at the relative both sides of kink 214, the two ends of elastic component 500 connect with building structure 30 and kink 214 respectively, adjusting nut 600 and threaded fastener 400 threaded engagement, rotation adjusting nut 600 is to regulate the distance of kink 214 and building structure 30, thereby play the effect that regulates stone plate 20 and the distance of building structure 30, make the decorative cover that formed by multiple stone plates 20 more smooth.
In the present embodiment, elastic component 500 is spring.Be appreciated that elastic component 500 can also be resilient sleeve.
Particularly, be also provided with packing ring (figure is mark not) between adjusting nut 600 and kink 214, this gasket sleeve is located on threaded fastener 400.
Further, stone material dry suspending installation system 10 also comprises that 700, one packing rings 700 of two packing rings that are sheathed on threaded fastener 400 are held between elastic component 500 and building structure 30, and another packing ring 700 is held between elastic component 500 and kink 214.The two ends that are elastic component 500 connect with two packing rings 700 respectively.
Be appreciated that elastic component 500 and adjusting nut 600 can omit, stone plate 20 can not regulate with the distance of building structure 30, and now, threaded fastener 400 can be bolt.
Further, the support arm of U-shaped body 212 is provided with the second armpit angle 2126 being fixedly connected with kink 214, thereby increases the strength and stiffness of the junction of U-shaped body 212 and kink 214.
Fixture 300 can be fixedly connected with stone plate 20, and fixture 300 is arranged in installing hole 2122, and is fixedly connected with the bottom of U-shaped body 212.
Concrete, fixture 300 comprises thread rod part 310, thread rod part 310 is arranged in installing hole 2122, coupling assembling 200 also comprises that the first hold-down nut 800 of being sheathed on thread rod part 310 and be screwed with thread rod part 310 and the second hold-down nut 900, the first hold-down nuts 800 and the second hold-down nut 900 connect with the relative both sides of the bottom of U-shaped body 212 respectively.
Further, coupling assembling 200 also comprises on the bottom that is arranged at U-shaped body 212 and stationary magazine creel 220 one-body molded with U-shaped body 212 and that be communicated with installing hole 2122.On the sidewall of stationary magazine creel 220, offer multiple circumferential spaced screws 222 along stationary magazine creel 220, thread rod part 310 is arranged in installing hole 2122 and stationary magazine creel 220, use multiple screws 40 to be arranged in respectively multiple screws 222, and be screwed with multiple screws 222 respectively, the end face that multiple screws 40 are contained in one end of stationary magazine creel 220 all connects with thread rod part 310, the first hold-down nut 800 connects away from a side of stationary magazine creel 220 with the bottom of U-shaped body 212, the second hold-down nut 900 connects away from the end face of one end of the bottom of U-shaped body 212 with stationary magazine creel 220.By using multiple screws 40 to connect with thread rod part 310, can prevent that fixture 300 from rocking, fixture 300 is more stably fixed on the U-shaped body 212 of connector 210.
Specifically, in illustrated embodiment, screw 222 is four, and screw 40 corresponds to four, and the axis of adjacent two screws 40 is mutually vertical.Be appreciated that screw 222 can also be two, now, screw 40 corresponds to two, and the dead in line of two screws 40; Or screw 222 can also be three, now, screw 40 corresponds to three, and the angle of the axis of adjacent two screws 40 is 120 degree; Or screw 222 also can be five or more, now, screw 400 corresponds to five or more.
Further, the edge of opening of one end of stationary magazine creel 220 is provided with flange 224, and the other end is fixedly connected with the bottom of U-shaped body 212, and the second hold-down nut 900 connects with flange 224.Flange 224 is set on stationary magazine creel 220, and this flange 224 is just equivalent to the effect of packing ring, can omit herein packing ring, thereby less part has been simplified installation.
Particularly, be provided with packing ring (figure is mark not) between the first hold-down nut 800 and the bottom of U-shaped body 212, this gasket sleeve is located on thread rod part 310.
Further, the bottom of U-shaped body 212 is also provided with multiple reinforcing ribs 2128 that are fixedly connected with the external surface of stationary magazine creel 220, thereby strengthens the strength and stiffness of the junction of the bottom of stationary magazine creel 220 and U-shaped body 212.
Further, fixture 300 also comprises the holding section 320 that is arranged at one end of thread rod part 310 and is fixedly connected with thread rod part 310, and the width of holding section 320 is greater than the width of thread rod part, on stone plate 20, offer the draw-in groove 22 fastening with holding section 320.Specifically, in illustrated embodiment, holding section 320 is T font, and draw-in groove 22 corresponds to T font.Be appreciated that holding section 320 can also be L font, now, on stone plate 20, correspondence offers L-type draw-in groove.
See also Fig. 5, coupling assembling 200 can be multiple, and fixture 300 corresponds to multiple, and multiple fixture 300 is fixedly connected with multiple coupling assemblings 200 respectively with a stone plate 20.
Above-mentioned stone material dry suspending installation system 10 has following advantage at least:
(1) kink 214 of the connector 210 of above-mentioned stone material dry suspending installation system 10 is fixing with building structure 30, fixture 300 is fixedly connected with stone plate 20 and connector 210, thereby stone plate 20 is fixed in building structure 30, a connector 210 has substituted suspension member, steel joist and three elements of fastener in conventional mounting system, reduce required field erected element in work progress, simplify the structure of stone material dry suspending installation system 10, and be conducive to improve efficiency of construction.
(2) connector 210 of the coupling assembling 200 of above-mentioned stone material dry suspending installation system 10 comprises the kink 214 that U-shaped body 212 and two support arms by U-shaped body 212 are oppositely bent to form, it is U-shaped body 212 and kink 214 structure that is formed in one, further reduce in work progress and needed field erected element, be more conducive to improve efficiency of construction.
The above embodiment has only expressed several embodiment of the present utility model, and it describes comparatively concrete and detailed, but can not therefore be interpreted as the restriction to the utility model the scope of the claims.It should be pointed out that for the person of ordinary skill of the art, without departing from the concept of the premise utility, can also make some distortion and improvement, these all belong to protection domain of the present utility model.Therefore, the protection domain of the utility model patent should be as the criterion with claims.

Claims (10)

1. a stone material dry suspending installation system, can be arranged on stone plate in building structure, it is characterized in that, described stone material dry suspending installation system comprises:
Coupling assembling, comprises connector, and described connector comprises the kink that U-shaped body and two support arms by described U-shaped body are oppositely bent to form, and the bottom of described U-shaped body offers installing hole, and described kink can be fixedly connected with described building structure; And
Fixture, can be fixedly connected with described stone plate, and described fixture is arranged in described installing hole, and is fixedly connected with the bottom of described U-shaped body.
2. stone material dry suspending installation system according to claim 1, it is characterized in that, described fixture comprises thread rod part, described thread rod part is arranged in described installing hole, described coupling assembling also comprises the first hold-down nut and the second hold-down nut that are sheathed on described thread rod part and are screwed with described thread rod part, and described the first hold-down nut and described the second hold-down nut connect with the relative both sides of the bottom of described U-shaped body respectively.
3. stone material dry suspending installation system according to claim 2, it is characterized in that, described coupling assembling also comprises on the bottom that is arranged at described U-shaped body, and with described U-shaped body by integral forming, and the stationary magazine creel being communicated with described installing hole, on the sidewall of described stationary magazine creel, offer multiple circumferential spaced screws along described stationary magazine creel, described thread rod part is arranged in described installing hole and described stationary magazine creel, use multiple screws to be arranged in respectively described multiple screw, and with described multiple screwhole spiro bondings, the end face that described multiple screw is contained in one end of described stationary magazine creel all connects with described thread rod part, the bottom of described the first hold-down nut and described U-shaped body connects away from a side of described stationary magazine creel, described the second hold-down nut and described stationary magazine creel connect away from the end face of one end of the bottom of described U-shaped body.
4. stone material dry suspending installation system according to claim 3, is characterized in that, the edge of opening of one end of described stationary magazine creel is provided with flange, and the other end is fixedly connected with the bottom of described U-shaped body, and described the second hold-down nut and described flange connect.
5. stone material dry suspending installation system according to claim 3, is characterized in that, the bottom of described U-shaped body is also provided with multiple reinforcing ribs that are fixedly connected with the external surface of described stationary magazine creel.
6. stone material dry suspending installation system according to claim 2, it is characterized in that, described fixture also comprises the holding section that is arranged at one end of described thread rod part and is fixedly connected with described thread rod part, and the width of described holding section is greater than the width of described thread rod part, on described stone plate, offer the draw-in groove fastening with described holding section.
7. stone material dry suspending installation system according to claim 1, it is characterized in that, on described kink, offer pilot hole, described stone material dry suspending installation system also comprises threaded fastener, be contained in described building structure described threaded fastener partial fixing, the part that described threaded fastener stretches out described building structure is arranged in described pilot hole, and is fixedly connected with described kink.
8. stone material dry suspending installation system according to claim 7, it is characterized in that, described threaded fastener is double-screw bolt, described stone material dry suspending installation system also comprises the elastic component and the adjusting nut that are sheathed on described threaded fastener, described elastic component and described adjusting nut lay respectively at the relative both sides of described kink, the two ends of described elastic component connect with described building structure and described kink respectively, described adjusting nut and described threaded fastener threaded engagement, rotate described adjusting nut to regulate the distance of described kink and described building structure.
9. stone material dry suspending installation system according to claim 8, it is characterized in that, also comprise two packing rings that are sheathed on described threaded fastener, one of them packing ring is held between described elastic component and described building structure, and another packing ring is held between described elastic component and described kink.
10. stone material dry suspending installation system according to claim 1, is characterized in that, the bottom of described U-shaped body is provided with the first armpit angle being fixedly connected with the support arm of described U-shaped body; The support arm of described U-shaped body is provided with the second armpit angle being fixedly connected with described kink.
CN201420221345.5U 2014-04-30 2014-04-30 Stone dry hanging installation system Expired - Lifetime CN203856157U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420221345.5U CN203856157U (en) 2014-04-30 2014-04-30 Stone dry hanging installation system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420221345.5U CN203856157U (en) 2014-04-30 2014-04-30 Stone dry hanging installation system

Publications (1)

Publication Number Publication Date
CN203856157U true CN203856157U (en) 2014-10-01

Family

ID=51606019

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420221345.5U Expired - Lifetime CN203856157U (en) 2014-04-30 2014-04-30 Stone dry hanging installation system

Country Status (1)

Country Link
CN (1) CN203856157U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938828A (en) * 2014-04-30 2014-07-23 深圳市华南装饰设计工程有限公司 Stone dry hanging installation system
CN109930774A (en) * 2019-04-18 2019-06-25 新疆京奥宏博节能科技有限公司 A kind of new structure for stone material installation
CN110306696A (en) * 2019-04-12 2019-10-08 深圳全景空间工业有限公司 A kind of latch fitting
CN110528808A (en) * 2019-09-06 2019-12-03 广东玛格家居有限公司 A kind of adjustable skirting pendant

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938828A (en) * 2014-04-30 2014-07-23 深圳市华南装饰设计工程有限公司 Stone dry hanging installation system
CN110306696A (en) * 2019-04-12 2019-10-08 深圳全景空间工业有限公司 A kind of latch fitting
CN109930774A (en) * 2019-04-18 2019-06-25 新疆京奥宏博节能科技有限公司 A kind of new structure for stone material installation
CN110528808A (en) * 2019-09-06 2019-12-03 广东玛格家居有限公司 A kind of adjustable skirting pendant

Similar Documents

Publication Publication Date Title
CN203856157U (en) Stone dry hanging installation system
CN103938828A (en) Stone dry hanging installation system
CN204098422U (en) A kind of mounting mounting structure of stone material
CN108049592B (en) Floor paving base, paving assembly and paving method
CN105507478A (en) Suspended ceiling mounting component
KR20130000167U (en) A buttress for building a brick house
CN103774820B (en) A kind of decorative panel connecting elements and installation method thereof
CN204311616U (en) A kind of novel partition wall with self adaptation skirting
CN111188448B (en) Unit type adjustable suspended ceiling structure
CN202718344U (en) Connecting hanging piece of wall decorative plate
CN204435734U (en) Wood veneer buckling structure
KR100993901B1 (en) Device for finishing materials for the wall
CN103866893A (en) Composite metal ceiling
CN204754070U (en) Hang mounting structure
CN204609087U (en) A kind of furred ceiling mounts keel
CN208858020U (en) A kind of novel energy-saving building structure
CN203905254U (en) Prefabricated installation structure for special-shaped sculpture modelling hung ceiling
CN103277650B (en) A kind of suspension fastener for installing and scaffold
CN204252341U (en) Curtainwall connector
CN204385911U (en) The connector of body of wall oblique pull steel band
CN202731205U (en) Slate partial thickening and mounting structure for architectural ornament
CN205489333U (en) Fixing device of pipeline
CN210508182U (en) Novel M type structure building body frenulum veneer ordinary outer wall
CN204299216U (en) Shower house regulates upper cover
CN202868595U (en) Decorative part of lamp

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Guangdong pitaya new type material science and Technology Development Co.,Ltd.

Assignor: SHENZHEN HUANAN DECORATION DESIGN ENGINEERING Co.,Ltd.

Contract record no.: 2015440020203

Denomination of utility model: Vertical-surface stone dry-hang installing system

Granted publication date: 20141001

License type: Exclusive License

Record date: 20150604

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 518000 Guangdong city of Shenzhen province Futian District CaiTian road and Merlin eight road interchange Southern China Industrial and Trading Company office building on the third floor

Patentee after: SHENZHEN HUANAN DECORATION GROUP Co.,Ltd.

Address before: 518000 Guangdong city of Shenzhen province Futian District CaiTian road and Merlin eight road interchange Southern China Office

Patentee before: SHENZHEN HUANAN DECORATION DESIGN ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder

Address after: 518000 Guangdong city of Shenzhen province Futian District CaiTian road and Merlin eight road interchange Southern China Office

Patentee after: SHENZHEN HUANAN DECORATION DESIGN ENGINEERING Co.,Ltd.

Address before: 518000 Guangdong city of Shenzhen province Futian District CaiTian road and Merlin eight road interchange Southern China Office

Patentee before: SHENZHEN HUANAN DECORATION DESIGN ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 518000 Guangdong city of Shenzhen province Futian District CaiTian road and Merlin eight road interchange Southern China Industrial and Trading Company office building on the third floor

Patentee after: SHENZHEN HUANAN DECORATION GROUP Co.,Ltd.

Address before: 518000 Guangdong city of Shenzhen province Futian District CaiTian road and Merlin eight road interchange Southern China Office

Patentee before: SHENZHEN HUANAN DECORATION DESIGN ENGINEERING Co.,Ltd.

EC01 Cancellation of recordation of patent licensing contract

Assignee: Guangdong pitaya new type material science and Technology Development Co.,Ltd.

Assignor: SHENZHEN HUANAN DECORATION GROUP Co.,Ltd.

Contract record no.: 2015440020203

Date of cancellation: 20171208

EC01 Cancellation of recordation of patent licensing contract
EM01 Change of recordation of patent licensing contract

Change date: 20171205

Contract record no.: 2015440020203

Assignor after: SHENZHEN HUANAN DECORATION GROUP Co.,Ltd.

Assignor before: SHENZHEN HUANAN DECORATION DESIGN ENGINEERING Co.,Ltd.

EM01 Change of recordation of patent licensing contract