CN203834958U - Rust prevention device for constructional engineering embedded exposed reinforcement - Google Patents

Rust prevention device for constructional engineering embedded exposed reinforcement Download PDF

Info

Publication number
CN203834958U
CN203834958U CN201420275638.1U CN201420275638U CN203834958U CN 203834958 U CN203834958 U CN 203834958U CN 201420275638 U CN201420275638 U CN 201420275638U CN 203834958 U CN203834958 U CN 203834958U
Authority
CN
China
Prior art keywords
steel bar
closing device
exposed steel
rust prevention
construction work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420275638.1U
Other languages
Chinese (zh)
Inventor
王清江
王悦
胡奇
刘进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Technology and Business Institute
Original Assignee
Chongqing Technology and Business Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Technology and Business Institute filed Critical Chongqing Technology and Business Institute
Priority to CN201420275638.1U priority Critical patent/CN203834958U/en
Application granted granted Critical
Publication of CN203834958U publication Critical patent/CN203834958U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a rust prevention device for a constructional engineering embedded exposed reinforcement. The rust prevention device comprises a rust prevention cover, a sealing device and an air exhaust hole; an orifice is formed at one end of the rust prevention cover and the rust prevention cover is arranged to cover the outer wall of the exposed reinforcement by virtue of the orifice; the air exhaust hole is formed in a sidewall of the rust prevention cover and only allows air to flow out of the rust prevention cover via the air exhaust hole; the sealing device is an elastic pipe fitting of which the two ends are open, and the two ends of the sealing device sleeve the rust prevention cover, respectively, so as to form sealed contact surfaces with the outer wall of the exposed reinforcement. The rust prevention device is used for solving the problems of weakened building durability and the like due to that the exposed part of the embedded reinforcement at the constructional engineering concrete joint is extremely easy to rust as being exposed in air and affected by rain, sunshine and damp air; the reinforcement rust prevention device provided is capable of protecting the reinforcement against the influence of rain and damp air and retarding the rusting of the constructional engineering embedded exposed reinforcement.

Description

The pre-buried exposed steel bar Rustproofing apparatus of construction work
Technical field
The utility model belongs to the device field of construction work, is specifically related to the pre-buried exposed steel bar Rustproofing apparatus of a kind of construction work.
Background technology
When construction work design of reinforced concrete structure and construction, cause the problems such as structure crack for eliminating shrinkage strain in course of hardening, how in reinforced concrete structure, every certain length, deformation joint and rear pouring concrete band to be set, need embedded bar at seam crossing, to ensure the globality of concrete structure more.Deformation joint embedded bar is exposed to the airborne time, determines according to the deformation requirements of structural concrete and construction technology, is not generally 30d~90d not etc., and what have is even longer, and interval is more than 1 year.These exposed steel bars get rusty very soon in air, and along with the lengthening of time, to there is corrosion, slacken the cross section of reinforcing bar, cause after seam crossing concrete construction, overall structure will form weak link at seam crossing, even cause structural deterioration accident, and not carry out antirust special purpose device for the pre-buried exposed steel bar of construction work in prior art.
Therefore,, for overcoming the above problems, need to a kind ofly can carry out the pre-buried exposed steel bar Rustproofing apparatus of antirust construction work to the pre-buried exposed steel bar of construction work easily and effectively.
Utility model content
In view of this, the purpose of this utility model is to be exposed to the problem such as corrosion in air for the pre-buried exposed steel bar of existing construction work, provides a kind of construction work pre-buried exposed steel bar Rustproofing apparatus.
The pre-buried exposed steel bar Rustproofing apparatus of construction work of the present utility model, comprise antirust sleeve, closing device and aspirating hole, antirust sleeve one end is provided with the mouth of pipe and is placed on exposed steel bar outer wall by this mouth of pipe, extract opening is located at antirust sleeve sidewall and is only allowed gas to pass through this extract opening and flows out antirust sleeve, and the Flexible pipe fitting that closing device is both ends open and this closing device two ends are placed on respectively antirust sleeve and exposed steel bar outer wall and form sealing contact surface;
Further, described antirust sleeve comprises pipe shaft section and is one-body molded and insert in the mouth of pipe section in closing device with pipe shaft section;
Further, described closing device comprises soft cotton layer and is sheathed on the rubber layer outside soft cotton layer;
Further, described closing device two ends are wound with adhesive type sealing restraint zone;
Further, described antirust sleeve adopts durable rubber to be made;
Further, described mouth of pipe section outer circumference surface is provided with sealing internal thread;
Further, described closing device inner tubal wall is provided with the sealing external screw thread coordinating with described sealing thread;
Further, described closing device is bellows;
The beneficial effects of the utility model are: the pre-buried exposed steel bar Rustproofing apparatus of construction work of the present utility model, antirust sleeve is by after exposed steel bar parcel, by closing device, the antirust sleeve mouth of pipe is shut, by existing exhaust plant, the gas in antirust sleeve is extracted out from extract opening again, make antirust sleeve closely be wrapped in exposed steel bar surface and in antirust sleeve, form a vacuum wall body, thereby blocking-up reinforcing bar contacts with air, slow down the corrosion of reinforcing bar, the pre-buried exposed steel bar Rustproofing apparatus of construction work of the present utility model can effectively slow down the corrosion of exposed steel bar, avoid after the concrete construction of steel and concrete structure seam crossing, seam crossing is because of strength deficiency recurring structure malicious event, the utility model has overcome existing construction work concrete joint embedded bar exposed parts, because being exposed in air, drenched with rain, the impact of Exposure to Sunlight and moisture laden air, very easily get rusty, if be exposed to for a long time in air, even there is corrosion of steel bar, bottom structure bearing capacity falls, affect structural safety, slacken the problems such as building durability, can effectively block rainwater and the impact of wet damp air on reinforcing bar.
Brief description of the drawings
Below in conjunction with drawings and Examples, technical solutions of the utility model are further illustrated:
Fig. 1 is structural representation of the present utility model.
Detailed description of the invention
Fig. 1 is structural representation of the present utility model, as shown in the figure, pre-buried exposed steel bar 5 Rustproofing apparatus of construction work in the present embodiment, comprise antirust sleeve 4, closing device 2 and aspirating hole 9, antirust sleeve 4 one end are provided with the mouth of pipe and are placed on exposed steel bar 5 outer walls by this mouth of pipe, extract opening is located at antirust sleeve 4 sidewalls and is only allowed gas to pass through this extract opening and flows out antirust sleeve 4, and the Flexible pipe fitting that closing device 2 is both ends open and this closing device 2 two ends are placed on respectively antirust sleeve 4 with exposed steel bar 5 outer walls and form sealing contact surface.
In the present embodiment, described antirust sleeve 4 comprises pipe shaft section 3 and is one-body molded and insert in the mouth of pipe section 6 in closing device 2 with pipe shaft section 3, closing device 2 two ends form sealing contact surface with mouth of pipe section 6 and exposed steel bar 5 surfaces respectively, thereby make the interior formation seal chamber of antirust sleeve 4.
In the present embodiment, described closing device 2 comprises soft cotton layer 7 and is sheathed on the rubber layer 8 outside soft cotton layer 7, the flexible thin-walled rubber of closing device 2 can compress rebar surface, and space between the further filling thin-walled rubber of soft cotton material and reinforcing bar, and then significantly promote the sealing performance in antirust sleeve 4.
In the present embodiment, described closing device 2 two ends are wound with adhesive type sealing restraint zone 1, when operating personnel uses closing device 2 by after antirust sleeve 4 ferrules, can adopt adhesive type sealing restraint zone 1 to be wound around closing device 2 two ends, make it further promote the sealing performance of closing device 2.
In the present embodiment, described antirust sleeve 4 adopts durable rubber to be made, because durable rubber has good elasticity, therefore after antirust sleeve 4 internal gas being extracted out by existing exhaust plant, can there is elastic deformation and closely be wrapped in rebar surface in antirust sleeve 4, when before concrete construction, take off after antirust sleeve 4, antirust sleeve 4 can return to initial configuration, is convenient to use next time.
In the present embodiment, described mouth of pipe section 6 outer circumference surfaces are provided with sealing internal thread, are connection reliability and the sealing effectiveness that promotes closing device 2 and mouth of pipe section 6, can adopt sealed tube be threaded closing device 2 and antirust sleeve 4 mouth of pipe sections 6.
In the present embodiment, described closing device 2 inner tubal walls are provided with the sealing external screw thread coordinating with described sealing thread, adopt sealed tube be threaded closing device 2 and antirust sleeve 4 mouth of pipe sections 6, can promote connection reliability and the sealing effectiveness of closing device 2 and mouth of pipe section 6.
Further, described closing device 2 is bellows, and when carrying out when antirust the exposed steel bar of bending 5, the bending that closing device 2 also should be able to adapt to exposed steel bar 5 bends, and bellows is easy to bending and toughness is better, can use the exposed steel bar 5 of differently curved degree.
Finally explanation is, above embodiment is only unrestricted in order to the technical solution of the utility model to be described, although the utility model is had been described in detail with reference to preferred embodiment, those of ordinary skill in the art is to be understood that, can modify or be equal to replacement the technical solution of the utility model, and not departing from the spirit and scope of technical solutions of the utility model, it all should be encompassed in the middle of claim scope of the present utility model.

Claims (8)

1. the pre-buried exposed steel bar Rustproofing apparatus of construction work, is characterized in that: comprise antirust sleeve, closing device and aspirating hole; Described antirust sleeve one end is provided with the mouth of pipe and is placed on exposed steel bar outer wall by this mouth of pipe; Described extract opening is located at antirust sleeve sidewall and is only allowed gas to pass through this extract opening and flows out antirust sleeve; Described closing device is that Flexible pipe fitting and this closing device two ends of both ends open are placed on respectively antirust sleeve and exposed steel bar outer wall and form sealing contact surface.
2. the pre-buried exposed steel bar Rustproofing apparatus of construction work according to claim 1, is characterized in that: described antirust sleeve comprises pipe shaft section and be one-body molded and insert in the mouth of pipe section in closing device with pipe shaft section.
3. the pre-buried exposed steel bar Rustproofing apparatus of construction work according to claim 2, is characterized in that: described closing device comprises soft cotton layer and is sheathed on the rubber layer outside soft cotton layer.
4. the pre-buried exposed steel bar Rustproofing apparatus of construction work according to claim 3, is characterized in that: described closing device two ends are wound with adhesive type sealing restraint zone.
5. the pre-buried exposed steel bar Rustproofing apparatus of construction work according to claim 4, is characterized in that: described antirust sleeve adopts durable rubber to be made.
6. the pre-buried exposed steel bar Rustproofing apparatus of construction work according to claim 5, is characterized in that: described mouth of pipe section outer circumference surface is provided with sealing internal thread.
7. the pre-buried exposed steel bar Rustproofing apparatus of construction work according to claim 6, is characterized in that: described closing device inner tubal wall is provided with the sealing external screw thread coordinating with described sealing thread.
8. the pre-buried exposed steel bar Rustproofing apparatus of construction work according to claim 7, is characterized in that: described closing device is bellows.
CN201420275638.1U 2014-05-27 2014-05-27 Rust prevention device for constructional engineering embedded exposed reinforcement Withdrawn - After Issue CN203834958U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420275638.1U CN203834958U (en) 2014-05-27 2014-05-27 Rust prevention device for constructional engineering embedded exposed reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420275638.1U CN203834958U (en) 2014-05-27 2014-05-27 Rust prevention device for constructional engineering embedded exposed reinforcement

Publications (1)

Publication Number Publication Date
CN203834958U true CN203834958U (en) 2014-09-17

Family

ID=51512818

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420275638.1U Withdrawn - After Issue CN203834958U (en) 2014-05-27 2014-05-27 Rust prevention device for constructional engineering embedded exposed reinforcement

Country Status (1)

Country Link
CN (1) CN203834958U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967287A (en) * 2014-05-27 2014-08-06 重庆工商职业学院 Construction engineering embedded exposed steel bar rust-proof device
CN104674954A (en) * 2015-02-16 2015-06-03 中交一航局第一工程有限公司 Structure and method for preventing reinforcing steel from being corroded in highly-corrosive environment
CN110067397A (en) * 2019-04-19 2019-07-30 安徽企服工程技术有限公司 A kind of pre-buried leakage reinforcing bar protection component of architectural engineering

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967287A (en) * 2014-05-27 2014-08-06 重庆工商职业学院 Construction engineering embedded exposed steel bar rust-proof device
CN103967287B (en) * 2014-05-27 2016-03-23 重庆工商职业学院 The pre-buried exposed steel bar Rustproofing apparatus of construction work
CN104674954A (en) * 2015-02-16 2015-06-03 中交一航局第一工程有限公司 Structure and method for preventing reinforcing steel from being corroded in highly-corrosive environment
CN110067397A (en) * 2019-04-19 2019-07-30 安徽企服工程技术有限公司 A kind of pre-buried leakage reinforcing bar protection component of architectural engineering
CN110067397B (en) * 2019-04-19 2020-12-15 安徽省华腾农业科技有限公司经开区分公司 Pre-buried outer steel bar protection component that leaks of building engineering

Similar Documents

Publication Publication Date Title
CN203834958U (en) Rust prevention device for constructional engineering embedded exposed reinforcement
CN204645688U (en) The pre-buried exposed steel bar Rustproofing apparatus of vacuum-pumping type
CN103967287B (en) The pre-buried exposed steel bar Rustproofing apparatus of construction work
CN206449309U (en) Composite water-stop sleeve pipe
CN207032902U (en) A kind of pre-buried exposed steel bar Rustproofing apparatus of architectural engineering
CN203442411U (en) Tube cover for tube plugging
CN203247543U (en) Novel reinforced concrete causing seam
CN202266018U (en) Template sealing structure for grouting of connecting sleeve
CN105019941B (en) Composite, water-drain blind pipe can be safeguarded
CN204609334U (en) Exposed steel bar Rustproofing apparatus
CN203979674U (en) A kind of circulating water pipeline that is lined with Glass Steel Tube
CN204645687U (en) Adjustable pre-buried exposed steel bar Rustproofing apparatus
CN204042221U (en) Thermal insulation pipe
CN201474301U (en) Template lacing wire component
CN201027746Y (en) Expansion tube with sealing ring
CN202546024U (en) Reinforced wall-through pipeline
CN107100284B (en) Prevent iron tower of power transmission line bottom column material from corroding device
CN204876108U (en) Assembled wall body preformed hole is from sealing waterproof cover
CN207525743U (en) A kind of anchor pole with bushing
WO2015192407A1 (en) Construction engineering well body structure
CN205136908U (en) A sail tee bend assembly for aquarium
CN203375163U (en) Drainage leak stoppage gas valve
CN210104914U (en) Multifunctional drainage pipeline
CN210827139U (en) A mud jacking pipe and mud jacking device for prestressing force pipeline
CN211775811U (en) Novel split water stop bolt

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20140917

Effective date of abandoning: 20160323

C25 Abandonment of patent right or utility model to avoid double patenting