CN203822316U - Tunnel support steel bar row mounting device based on tunnelling machine - Google Patents

Tunnel support steel bar row mounting device based on tunnelling machine Download PDF

Info

Publication number
CN203822316U
CN203822316U CN201420107970.7U CN201420107970U CN203822316U CN 203822316 U CN203822316 U CN 203822316U CN 201420107970 U CN201420107970 U CN 201420107970U CN 203822316 U CN203822316 U CN 203822316U
Authority
CN
China
Prior art keywords
tunnel
steel bar
bar row
reinforcing bar
cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420107970.7U
Other languages
Chinese (zh)
Inventor
张红耀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420107970.7U priority Critical patent/CN203822316U/en
Application granted granted Critical
Publication of CN203822316U publication Critical patent/CN203822316U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a tunnel support steel bar row mounting device based on a tunnel borer. The tunnel support steel bar row mounting device comprises a top protective shield arranged at the top of the tunnelling machine, wherein rectangular cavities used for accommodating to-be-mounted steel bar rows are distributed in the top protective shield along the peripheral direction of the cross section of a tunnel; each cavity penetrates through the top protective shield along the length direction of the tunnel; one end, adjacent to the rear part of the top protective shield, of the bottom of each cavity is provided with a mounting port used for putting the to-be-mounted steel bar row into the cavity and hooking the to-be-mounted steel bar row together with the mounted steel bar row. The tunnel support steel bar row mounting device has the advantages that the front and rear steel bar rows can constantly slide out from the tail of the top protective shield of the tunnelling machine while the tunnelling machine is used for tunnelling, so that a constant dense protective net is formed at the top of the tunnel; meanwhile, the steel bar rows slide out from the cavities of the top protective shield, so that the steel bar rows can be immediately fixed by use of a steel arch bridge after being discharged out from the protective shield, the steel bar rows are prevented from sinking entirely, furthermore top macadam of the tunnel is effectively prevented from collapsing, and a rapid and effective protection effect is achieved.

Description

A kind of tunnel support reinforcing bar row erecting device based on tunnel machine
Technical field
The utility model relates to a kind of tunnel machine, especially relates to a kind of tunnel support reinforcing bar row erecting device based on tunnel machine.
Background technology
Open type development machine is the large-scale machine for construction of underground tunnel, has safety, fast, efficient, the features such as environmental protection, and that in constructing tunnel, applies is more and more extensive.But any one engineering all can run into the operating mode that unfavorable geology, particularly tunnel top cave in work progress, not only can affect programming, return construction safety and impact.How fast and effeciently to perform preliminary bracing, the construction of development machine is had to material impact.Wherein reinforcing bar row's installation is exactly one of important means of preliminary bracing.
Utility model content
In order to solve reinforcing bar row mounting technique problem, the utility model provides a kind of tunnel support reinforcing bar row erecting device based on tunnel machine.By this device, in development machine work progress, can synchronously carry out reinforcing bar row's installation work, when running into tunnel top and occur caving in early warning, carry out rapidly reinforcing bar row's installation work, thereby effectively prevent that tunnel top from caving in, realize fast and safe construction.
The utility model in order to solve the problems of the technologies described above adopted technical scheme is: a kind of tunnel support reinforcing bar row erecting device based on tunnel machine, described supporting reinforcing bar row erecting device comprises the top shield that is arranged on development machine top, being circumferentially distributed with for placing reinforcing bar row's to be installed rectangular cavity along tunnel cross section in the shield of top, each described cavity all runs through top shield along length of tunnel direction, each cavity bottom is equipped with for place reinforcing bar row to be installed in cavity near the one end at shield rear portion, top, and by its with the installing port that reinforcing bar end exhausting part articulates has been installed.
Described cavity tilts to tunnel top at the rear portion of top shield.
Beneficial effect:
Use the utility model, can make development machine when tunneling, before and after making, reinforcing bar row can skid off from development machine top shield afterbody incessantly, the reinforcing bar row who skids off fixes once going out the available steel arch frame of shield, effectively prevent that reinforcing bar row from sinking, at tunnel top, form continuously intensive protective screening, effectively stop that top, tunnel rubble caves in, and reaches supporting effect fast and effectively.
Accompanying drawing explanation
Fig. 1 is position and the structural representation of the utility model on development machine.
Fig. 2 is the utility model I place enlarged drawing in Fig. 1.
Fig. 3 is the A-A view of Fig. 2.
Fig. 4 is the B-B fan out schematic diagram of Fig. 3.
Fig. 5 is reinforcing bar row structural representation of the present utility model.
Fig. 6 is the top view of Fig. 5.
In figure, 1, Cutting tool, 2, top shield, 3, cavity, 4, reinforcing bar to be installed row, 5, installing port, 6, reinforcing bar row is installed, 7, steel arch frame, 8, hook.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the utility model is done to further concrete detailed explanation.
As shown in the figure, a kind of tunnel support reinforcing bar row erecting device based on tunnel machine ,described development machine is provided with top shield 2, on top shield 2, along tunnel axis direction, running through whole top shield 2 is provided with for depositing reinforcing bar row's 4 to be installed rectangular cavity 3, the width of cavity 3 and height adapt with the reinforcing bar row's that will install size, can hold reinforcing bar, arrange and facilitate it from cavity 3, to be hauled out and be advisable; Described cavity 3 is a plurality of, along circumferentially distributing successively of tunnel cross section, in the bottom of each cavity 3, be provided with for arranging 4 to the interior placement of cavity 3 reinforcing bar to be installed, and by its with the installing port 5 that reinforcing bar end exhausting part articulates has been installed, installing port 5 is arranged on cavity 3 near the position of top shield tail end, for the reinforcing bar row to be installed who makes to skid off from cavity 3 is adjacent to tunnel top better, described cavity 3 tilts to tunnel top at the afterbody of top shield 2
Cavity 3 can start to tilt to tunnel top from the edge near top shield tail end from installing port 5, so both can guarantee that reinforcing bar row to be installed can skid off smoothly from cavity, can make again it be adjacent to better tunnel top, further to guarantee the installation effect of the elementary protection of reinforcing bar row net.
In one end of reinforcing bar to be installed row 4, be provided with and for hook, reinforcing bar be installed and arranged the hook 8(of 6 afterbodys and come off for preventing, hook 8 can weld with electric welding), when development machine tunnels forward, the reinforcing bar row 4 to be installed of leaving 3 li of cavitys in is installed reinforcing bar row 6 drives and is skidded off from the afterbody of top shield 2, then by steel arch frame 7(steel arch frame, be the conventional part in tunnel excavation preliminary bracing, set up in advance) be fixed on tunnel top.
During the utility model work, first with manually first group of reinforcing bar row (being now reinforcing bar row to be installed) inserted respectively to each cavity 3 of top shield by installing port 5, then this being organized to all reinforcing bars sends discharged to top shield 2 afterbodys, with steel arch frame 7, all reinforcing bar rows' afterbody is pressed abd fixed on to tunnel top again, then, development machine tunnels forward, reinforcing bar row is because compressed afterbody by steel arch frame 7, thereby by the whole top shield 2 of taking out of, and arrange net at the densely covered reinforcing bar of tunnel top formation covering tunnel top, when reinforcing bar row's stem arrives installing port 5 position of erecting device, first group of reinforcing bar row installs (reinforcing bar after installing is lined up as reinforcing bar row is installed), now, to cavity front end, insert second group of reinforcing bar row (being now reinforcing bar row to be installed), and the hook of second group of reinforcing bar end exhausting part 8 is hung on the dowel of first group of reinforcing bar row stem (reinforcing bar row has been installed) end.Development machine continues driving forward, then second group of reinforcing bar row is hauled out to top shield 2, continues with steel arch frame 7 fixing.Circulation so again and again, forms continuously reinforcing bar row net at tunnel top, plays the effect that prevents that rubble from caving in.

Claims (2)

1. the tunnel support reinforcing bar based on tunnel machine is arranged erecting device, it is characterized in that: described supporting reinforcing bar row erecting device comprises the top shield (2) that is arranged on development machine top, being circumferentially distributed with for placing reinforcing bar row's to be installed (4) rectangular cavity (3) along tunnel cross section in top shield (2), described each cavity (3) all runs through top shield (2) along length of tunnel direction, each cavity (3) bottom is equipped with for place reinforcing bar row to be installed (4) in cavity (3) near the one end at top shield (2) rear portion, and by itself and the installing port (5) of reinforcing bar row (6) afterbody being installed being articulated.
2. a kind of tunnel support reinforcing bar row erecting device based on tunnel machine according to claim 1, is characterized in that: described cavity (3) tilts to tunnel top at the rear portion of top shield (2).
CN201420107970.7U 2014-03-11 2014-03-11 Tunnel support steel bar row mounting device based on tunnelling machine Expired - Fee Related CN203822316U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420107970.7U CN203822316U (en) 2014-03-11 2014-03-11 Tunnel support steel bar row mounting device based on tunnelling machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420107970.7U CN203822316U (en) 2014-03-11 2014-03-11 Tunnel support steel bar row mounting device based on tunnelling machine

Publications (1)

Publication Number Publication Date
CN203822316U true CN203822316U (en) 2014-09-10

Family

ID=51477829

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420107970.7U Expired - Fee Related CN203822316U (en) 2014-03-11 2014-03-11 Tunnel support steel bar row mounting device based on tunnelling machine

Country Status (1)

Country Link
CN (1) CN203822316U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105822314A (en) * 2016-05-23 2016-08-03 中铁隧道集团有限公司 TBM shield tail supporting device and method
CN106761790A (en) * 2017-01-12 2017-05-31 中铁隧道集团有限公司 A kind of open type TBM crosses tunneling boring carbonaceous slate driving and method for protecting support
CN109681221A (en) * 2019-02-21 2019-04-26 中水北方勘测设计研究有限责任公司 The shield tail supporting construction of open type TBM

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105822314A (en) * 2016-05-23 2016-08-03 中铁隧道集团有限公司 TBM shield tail supporting device and method
CN106761790A (en) * 2017-01-12 2017-05-31 中铁隧道集团有限公司 A kind of open type TBM crosses tunneling boring carbonaceous slate driving and method for protecting support
CN106761790B (en) * 2017-01-12 2019-04-26 中铁隧道局集团有限公司 A kind of open type TBM crosses tunneling boring carbonaceous slate driving and method for protecting support
CN109681221A (en) * 2019-02-21 2019-04-26 中水北方勘测设计研究有限责任公司 The shield tail supporting construction of open type TBM

Similar Documents

Publication Publication Date Title
CN108194081B (en) Coal mining operation method
CN102606152B (en) Novel quick digging and anchoring integrated machine for rectangular coal roadway
US20180187547A1 (en) Longwall mine construction method n00
CN102410017B (en) Supporting type integrated tunneling-anchoring machine
CN104405437A (en) Mining method employing solid filling and fully-mechanized coal mining hybrid working face
CN108131140B (en) Cantilever type longitudinal shaft digging and anchoring machine with remote control function
CN203822316U (en) Tunnel support steel bar row mounting device based on tunnelling machine
CN202500562U (en) Excavating, supporting and anchoring parallel operating system
CN103643979A (en) Hydraulic support used for roadway temporary support and erecting and use method of hydraulic support
CN110410118B (en) Novel tunneling process
CN103382844A (en) Temporary support and permanent support parallel operation excavating technology and equipment for tracked hydraulic combined support
CA2297456C (en) Method and apparatus for feeding a tunnel roof support system from the roof shield of a tbm
CN104632233A (en) Mechanical repair technology of distortional roadway and roadway repair machine
CN105240012A (en) F-type section coal-mining method allowing commingled mining of coal pillars
CN109441469B (en) Self-propelled shield tunneling machine complete equipment fitting free section and tunnel construction method
CN102877847A (en) Method for tunneling open-off cut expansion opening section of fully mechanized coal mining face
CN104500071B (en) Seam mining avoids the gob-side entry retaining method of dynamic pressure impact
CN105937400B (en) It is a kind of once to tunnel Liu Sheshuan lanes digging operation production line
CN104389605A (en) Cover retracement method of dense steel wire ropes of coal face
CN204060743U (en) Coal mining digging laneway gas buttress formula forestope temporary support device
CN113944464B (en) Coal mining method of corner coal full-negative-pressure continuous miner
CN103422865A (en) Tunnel excavation plastic cutter and tunnel arc-shaped excavation method for weak surrounding rock section
CN105041323A (en) Three-incompetent bed cutting hole large section construction and supporting method
CN104806271A (en) Precutting-groove U-shaped steel bracket with automatic propelling function and construction method thereof
CN109209485A (en) A kind of trapezoidal roadside support body of filling mining and method for protecting support

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140910

Termination date: 20150311

EXPY Termination of patent right or utility model