CN203809220U - Wind driven generator tower - Google Patents

Wind driven generator tower Download PDF

Info

Publication number
CN203809220U
CN203809220U CN201420204401.4U CN201420204401U CN203809220U CN 203809220 U CN203809220 U CN 203809220U CN 201420204401 U CN201420204401 U CN 201420204401U CN 203809220 U CN203809220 U CN 203809220U
Authority
CN
China
Prior art keywords
tower
steel
concrete
section
prestressed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420204401.4U
Other languages
Chinese (zh)
Inventor
许斌
牛家兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University
Original Assignee
Hunan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University filed Critical Hunan University
Priority to CN201420204401.4U priority Critical patent/CN203809220U/en
Application granted granted Critical
Publication of CN203809220U publication Critical patent/CN203809220U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/50—Manufacturing or production processes characterised by the final manufactured product

Landscapes

  • Wind Motors (AREA)

Abstract

本实用新型涉及一种风力发电机塔架,包括塔架基础和塔架基础上方的钢制塔段,所述钢制塔段的下端面安装钢制塔段下法兰盘,所述塔架基础为混凝土梁板基础,所述混凝土梁板基础顶部设有混凝土底段塔筒,并在混凝土底段塔筒与钢制塔段之间设置钢制过渡塔段;所述混凝土底段塔筒与混凝土梁板基础通过竖向预应力锚固机构连接,而钢制塔段与钢制过渡塔段之间通过紧固机构连接。本实用新型可充分发挥混凝土以及钢结构的优势,降低结构本身的直接造价、降低结构维护费用、降低道路建设成本、提高结构性能和安全性、延长结构使用年限,实现生命期成本最小。

The utility model relates to a wind power generator tower, comprising a tower foundation and a steel tower section above the tower foundation, the lower end surface of the steel tower section is equipped with a steel tower section lower flange, the tower The foundation is a concrete beam-slab foundation, and the top of the concrete beam-slab foundation is provided with a concrete bottom tower, and a steel transition tower is set between the concrete bottom tower and the steel tower; the concrete bottom tower It is connected with the concrete beam-slab foundation through a vertical prestressed anchorage mechanism, and the steel tower section and the steel transition tower section are connected through a fastening mechanism. The utility model can give full play to the advantages of concrete and steel structures, reduce the direct cost of the structure itself, reduce the structure maintenance cost, reduce the road construction cost, improve the structural performance and safety, prolong the service life of the structure, and realize the minimum life-cycle cost.

Description

一种风力发电机塔架wind turbine tower

技术领域 technical field

本实用新型涉及一种风力发电机塔架。 The utility model relates to a wind power generator tower.

背景技术 Background technique

风能是一种清洁能源,资源储备量大,也是目前国内外重点开发的新能源型式之一。我国风力资源分布广泛,在西北部、中部以及东部沿海地区都有很好的风力资源,故风力发电的发展前景相当广阔。我国现阶段广泛使用水平轴风力发电机组,一般使用全钢制塔架,基础为钢筋混凝土独立扩展基础,钢制塔架通过预埋基础环与基础直接连接。 Wind energy is a clean energy with a large resource reserve, and it is also one of the new energy types that are currently being developed at home and abroad. my country's wind resources are widely distributed, and there are good wind resources in the northwest, central and eastern coastal areas, so the development prospect of wind power is quite broad. Horizontal axis wind turbines are widely used in my country at this stage. Generally, all-steel towers are used. The foundation is an independent expansion foundation of reinforced concrete. The steel tower is directly connected to the foundation through a pre-embedded foundation ring.

随着塔架高度的增加,塔筒钢板厚度随着增加,钢塔架的生产制造变得越发困难,道路运输尺寸的限制不允许钢制塔筒直径进一步增大,目前国内使用的钢制塔筒的直径都限制在4.5米一下,这限制了全钢制塔架结构在更大功率发电机上的应用。其次,钢制塔架结构力学性能也存在不足,其刚度小,在风作用下塔顶变形大,振幅大,给维护带来极大困难,直接造价和运行维护费用高。特别是在山区建设风场时,全钢制塔筒的运输越发困难、危险性高,而且为了运输直径大、长度长而重量大的全钢塔筒需要建设专门的上山道路,大大提高了建设成本,而且修建道路直接破坏环境。传统全钢制塔筒结构的力学性能不足、直接成本和间接成本高,以及建设过程的风险大、维护成本高以及使用年限较短等大大限制了其在山区风场建设中的应用,也难以满足风力发电机单机装机容量向着大型化的发展要求。最后,目前广泛使用的传统基础环埋入式独立扩展基础受力性能与经济性不佳。该种基础与上部钢制塔筒的连接通过埋入式基础法兰来实现,便于标准化,施工较为简便,当风机功率较小而基础底板悬挑长度较小时, 此基础型式较合理。但其传力机理复杂,塔筒底部截面刚度和强度在基础顶面出现突变,应力集中明显,容易导致脆性破坏,耐久性差,其竖向承载力有余但抗倾覆和抗弯性能不佳。而且在大偏心荷载作用下,基础边缘与地基的脱开面积常起控制作用,特别是对于大功率风机而言,这种基础的悬挑长度太大,经济性变差。必须开发新型的风电塔架结构体系,降低直接造价、降低维护费用、降低道路建设成本、提高结构性能和安全性。 With the increase of the height of the tower, the thickness of the steel plate of the tower tube increases, and the production and manufacture of the steel tower becomes more and more difficult. The limitation of the road transportation size does not allow the diameter of the steel tower tube to increase further. The diameter of the cylinder is limited to less than 4.5 meters, which limits the application of the all-steel tower structure on higher power generators. Secondly, the mechanical properties of the steel tower structure are also insufficient. Its rigidity is small, and the deformation of the tower top under the action of wind is large, and the vibration amplitude is large, which brings great difficulties to maintenance, and the direct cost and operation and maintenance costs are high. Especially in the construction of wind farms in mountainous areas, the transportation of all-steel towers is more difficult and dangerous, and in order to transport all-steel towers with large diameters, long lengths and heavy weights, it is necessary to build special uphill roads, which greatly improves the construction cost, and building roads directly damages the environment. The lack of mechanical properties of the traditional all-steel tower structure, high direct and indirect costs, high risks in the construction process, high maintenance costs, and short service life greatly limit its application in the construction of wind farms in mountainous areas, and it is difficult to It meets the development requirements of wind power generator single installed capacity towards large-scale development. Finally, the widely used traditional foundation ring embedded independent expansion foundation has poor mechanical performance and economical efficiency. The connection between the foundation and the upper steel tower is realized through the embedded foundation flange, which is convenient for standardization and construction is relatively simple. When the power of the fan is small and the cantilever length of the foundation bottom plate is small, this type of foundation is more reasonable. However, its force transmission mechanism is complex. The stiffness and strength of the bottom section of the tower suddenly change on the top surface of the foundation. The stress concentration is obvious, which is easy to cause brittle failure and poor durability. Its vertical bearing capacity is sufficient but its overturning and bending resistance are not good. Moreover, under the action of large eccentric loads, the detachment area between the foundation edge and the foundation often plays a controlling role, especially for high-power fans, the overhang length of this foundation is too large, and the economy becomes poor. It is necessary to develop a new type of wind power tower structure system to reduce direct costs, reduce maintenance costs, reduce road construction costs, and improve structural performance and safety.

授权实用新型《预应力混凝土钢结构复合风电塔架》(授权公告号:CN201962693U)提出了一种预应力混凝土钢结构复合风电塔架,在现浇混凝土基础上通过预埋基础钢制法兰以及高强螺栓与下部混凝土塔段连接,混凝土塔段之间、混凝土塔段与上部钢制塔段之间也是通过钢制法兰以及高强螺栓连接。该实用新型专利的混凝土塔段采用预制预应力混凝土构件,在塔筒竖直方向没有施加贯通的预应力,仅是预制混凝土塔段在预制时存在预应力。由于螺栓无法传递预应力,这种方式导致预应力没有在混凝土段连续施加。混凝土塔筒在风机的大弯矩作用下容易开裂,对实用性和混凝土段塔筒的耐久性带来负面影响。 The authorized utility model "Prestressed Concrete Steel Structure Composite Wind Power Tower" (authorized announcement number: CN201962693U) proposes a prestressed concrete steel structure composite wind power tower. The high-strength bolts are connected to the lower concrete tower section, and the concrete tower sections, and the concrete tower section and the upper steel tower section are also connected by steel flanges and high-strength bolts. The concrete tower section of this utility model patent adopts prefabricated prestressed concrete components, and there is no through-through prestress in the vertical direction of the tower tube, and only the prefabricated concrete tower section has prestress during prefabrication. This way the prestress is not applied continuously in the concrete section because the bolts cannot transmit the prestress. The concrete tower is easy to crack under the large bending moment of the fan, which has a negative impact on the practicality and durability of the concrete tower.

授权实用新型《一种混凝土-钢结构复合风电塔架》(授权公告号:CN202031370U)公开一种混凝土-钢结构复合风电塔架,包括基座和塔体,其特征在于:所述基座为中空圆盘状结构,其上端预埋有钢制法兰;所述塔体为锥筒形结构,塔体分成多个塔段,塔段包括混凝土塔段和钢制塔段,塔段的两端预埋有钢制法兰,钢制法兰埋入混凝土塔段和基座的部分预设加强钢筋;钢制法兰与塔体空腔对应的圆周位置均匀布置有连接孔;基座与塔体及相邻两塔段的钢制法兰的连接孔对正,高强螺栓贯穿连接孔且两端利用螺母固定。该实用新型中混凝土塔段为普通钢筋混凝土结构,没有在混凝土塔段整体施加预应力,混凝土塔筒在风机的大弯矩作用下容易开裂,对实用性和混凝土段塔筒的耐久性带来负面影响。  The authorized utility model "A Concrete-Steel Structure Composite Wind Power Tower" (authorized announcement number: CN202031370U) discloses a concrete-steel structure composite wind power tower, including a base and a tower body, characterized in that: the base is Hollow disk-shaped structure, the upper end of which is pre-embedded with a steel flange; the tower body is a cone-shaped structure, and the tower body is divided into multiple tower sections, the tower section includes a concrete tower section and a steel tower section, and the two tower sections Steel flanges are pre-embedded at the end, and the steel flanges are embedded in the concrete tower section and the part of the base to reinforce the reinforcement; the steel flanges and the corresponding circumferential positions of the tower cavity are evenly arranged with connection holes; the base and the base The connection holes of the tower body and the steel flanges of the adjacent two tower sections are aligned, and the high-strength bolts pass through the connection holes and the two ends are fixed with nuts. The concrete tower section in this utility model is an ordinary reinforced concrete structure, and no prestress is applied to the concrete tower section as a whole. Negative impact. the

实用新型《体外预应力钢-混凝土风电塔架》(授权公告号:CN202493386U)公开一种体外预应力钢-混凝土风电塔架,包括混凝土段和钢结构段,以及连接二者的过渡段,所述过渡段包括混凝土过渡段和钢结构过渡段;塔架按照混凝土段、过渡混凝土段、过渡钢结构段、钢结构段依序连接;且所述过渡钢结构段和所述过渡混凝土段通过双头螺栓连接。该风电塔架的过渡段之间双头螺栓连接。该实用新型中的混凝土段以及混凝土过渡段均为预制,现场吊装安装。 The utility model "External Prestressed Steel-Concrete Wind Power Tower" (authorized announcement number: CN202493386U) discloses an external prestressed steel-concrete wind power tower, including a concrete section and a steel structure section, and a transition section connecting the two. The transition section includes a concrete transition section and a steel structure transition section; the tower is connected in sequence according to the concrete section, the transition concrete section, the transition steel structure section, and the steel structure section; and the transition steel structure section and the transition concrete section pass through a double head bolt connection. The transition sections of the wind power towers are connected by stud bolts. The concrete section and the concrete transition section in the utility model are all prefabricated and hoisted and installed on site.

授权实用新型《体内预应力钢-混凝土风电塔架》(授权公告号:CN202500731U)公开一种体内预应力钢-混凝土风电塔架,包括混凝土段和钢结构段,以及连接二者的过渡段,所述过渡段包括过渡混凝土段和钢结构过渡段;按照混凝土段、过渡混凝土段、过渡钢结构段、钢结构段依序连接;所述过渡钢结构段和所述过渡混凝土段双头螺栓连接,同时还通过钢绞线连接,所述钢绞线连接所述过渡钢结构段,并贯穿所述过渡混凝土段和混凝土段内部设置的钢绞线埋管且张拉固定于塔架基础内部。该风电塔架的过渡段之间通过钢绞线连接以及双头螺栓连接。该实用新型中的混凝土段以及混凝土过渡段均为预制,现场吊装安装。 The authorized utility model "Internal Prestressed Steel-Concrete Wind Power Tower" (authorized announcement number: CN202500731U) discloses an internal prestressed steel-concrete wind power tower, including a concrete section and a steel structure section, and a transition section connecting the two. The transition section includes a transition concrete section and a steel structure transition section; it is connected in sequence according to the concrete section, transition concrete section, transition steel structure section, and steel structure section; the transition steel structure section and the transition concrete section are connected by stud bolts At the same time, it is also connected by steel strands, and the steel strands are connected to the transitional steel structure section, and run through the transitional concrete section and the steel strand buried pipe arranged inside the concrete section and are tensioned and fixed inside the tower foundation. The transition sections of the wind power towers are connected by steel strands and stud bolts. The concrete section and the concrete transition section in the utility model are all prefabricated and hoisted and installed on site.

以上授权实用新型《体外预应力钢-混凝土风电塔架》(授权公告号:CN202493386U)与《体内预应力钢-混凝土风电塔架》(授权公告号:CN202500731U)均未考虑基础结构型式以及预应力施加时工艺上的困难。预应力钢绞线如何锚固入现浇钢筋混凝土基础。由于混凝土塔段是预制,预应力筋必须在混凝土塔段安装就位后通过预应力孔道伸入混凝土基础中,而基础已经现浇成型,如何将基础中预应力孔道与预制混凝土塔筒中的预应力孔道对齐在施工上难以保证。必须针对混凝土塔筒预应力的施加对传统基础结构型式进行改进。 The above authorized utility models "External Prestressed Steel-Concrete Wind Power Tower" (Authorization No.: CN202493386U) and "Inner Prestressed Steel-Concrete Wind Power Tower" (Authorization No.: CN202500731U) did not consider the basic structure type and prestress Difficulties in the process of application. How prestressed steel strands are anchored into cast-in-place reinforced concrete foundations. Since the concrete tower section is prefabricated, the prestressed tendons must be inserted into the concrete foundation through the prestressed tunnel after the concrete tower section is installed in place, and the foundation has been cast in place. How to combine the prestressed tunnel in the foundation with the prestressed tunnel in the precast concrete The alignment of stress channels is difficult to guarantee in construction. The traditional foundation structure type must be improved for the prestressing of the concrete tower.

授权实用新型专利《基础承压梁板式风力发电塔基础》(授权公告号:CN 202152463 U)涉及一种基础承压梁板式风力发电塔基础结构。本实用新型混凝土垫层呈圆环形,圆环形内嵌有垫板,垫层设有混凝土基础底板,基础底板的中部设有圆环形混凝土柱墩,靠近边缘处设有边缘小梁,柱墩与边缘小梁通过悬臂梁连接,形成米字形结构,两个相临的边缘小梁通过悬臂梁连接在一起,形成环形;柱墩中锚栓一端与基础下锚板连接,另一端与塔筒连接。本实用新型米字梁减少基础混凝土的工程量。基础与地基承压面积减小,环形垫层压应力增大,抵抗上部结构弯矩引起基础底面的拔力,从而减小基础底面积。将风力发电塔塔筒与基础的连接由基础环式改为预应力锚栓式。保证了塔筒与基础的刚性连接,减少了用钢量。该实用新型是对传统基础环埋入式独立扩展基础的改进,配合全钢制塔筒使用的,基础顶面直接与上端钢制塔筒连接,但没有将预应力引入塔筒。 The authorized utility model patent "Basic Compression Beam-Slab Wind Power Tower Foundation" (authorized announcement number: CN 202152463 U) relates to a foundation structure of foundation pressure-bearing beam-slab wind power tower. The concrete cushion of the utility model is in the shape of a circular ring, with a backing plate embedded in the circular ring, a concrete base plate is provided on the cushion, a circular concrete column pier is provided in the middle of the base plate, and edge beams are provided near the edge. The column pier and the edge girder are connected by a cantilever beam to form a rice-shaped structure, and two adjacent edge girders are connected together by a cantilever beam to form a ring; one end of the anchor bolt in the column pier is connected to the lower anchor plate of the foundation, and the other end is connected to the Tower connection. The utility model reduces the engineering quantity of foundation concrete for the rice-shaped beam. The pressure-bearing area of the foundation and the foundation is reduced, and the compressive stress of the annular cushion is increased, which resists the pulling force of the bottom surface of the foundation caused by the bending moment of the upper structure, thereby reducing the bottom area of the foundation. The connection between the wind power tower and the foundation is changed from the foundation ring type to the prestressed anchor bolt type. The rigid connection between the tower and the foundation is guaranteed, and the steel consumption is reduced. This utility model is an improvement on the traditional foundation ring embedded independent expansion foundation, which is used in conjunction with an all-steel tower. The top surface of the foundation is directly connected to the upper steel tower, but no prestress is introduced into the tower.

授权实用新型专利《井格式承台风力发电塔桩基础》(授权公告号:CN 201358468 Y)涉及一种井格式承台风力发电塔桩基础。由桩、承台底板、悬臂梁、边缘梁、锚栓、小承台、混凝土垫层和混凝土基础中心筒组成,悬臂梁共有8根,均由混凝土基础中心筒伸出,形成井字形,混凝土基础中心筒位于井字形的中心,每根悬臂梁的外端均设有小承台,相互平行的悬臂梁外端的小承台通过边缘梁连接;桩伸入承台中一定深度,小承台、悬臂梁以及混凝土基础中心筒固定于承台底板上方,承台底板下方为混凝土垫层,混凝土基础中心筒的筒壁中均匀埋有锚栓,各锚栓组成一个锚栓群,锚栓群顶部设有锚栓顶板,锚栓顶板以下为调节螺母,锚栓顶板顶面与混凝土基础中心筒的筒壁顶部平齐。能够提高该型桩基础的抗弯效率,从而减少承台混凝土的用量。该实用新型也是针对全钢制塔筒的,锚栓预应力不引入塔筒。 The authorized utility model patent "Pile Foundation of Wind Power Tower with Well-capped Platform" (authorized announcement number: CN 201358468 Y) relates to a pile foundation of wind-power generation tower with well-capped platform. It is composed of piles, cap floor, cantilever beam, edge beam, anchor bolt, small cap, concrete cushion and concrete foundation center tube. There are 8 cantilever beams, all protruding from the concrete foundation center tube, forming a well shape. The center tube of the foundation is located in the center of the well-shaped shape, and the outer ends of each cantilever beam are equipped with small caps, and the small caps at the outer ends of the parallel cantilever beams are connected by edge beams; the piles extend into the caps to a certain depth, and the small caps, The cantilever beam and the concrete foundation central cylinder are fixed above the cap bottom plate, and the concrete cushion is below the cap platform bottom plate. Anchor bolts are evenly buried in the wall of the concrete foundation central cylinder. Each anchor bolt forms an anchor bolt group, and the top of the anchor bolt group An anchor bolt top plate is provided, below the anchor bolt top plate is an adjusting nut, and the top surface of the anchor bolt top plate is flush with the top of the cylinder wall of the concrete foundation central cylinder. The anti-bending efficiency of this type of pile foundation can be improved, thereby reducing the amount of cap concrete. This utility model is also aimed at the all-steel tower, and the anchor bolt prestress is not introduced into the tower.

发明内容 Contents of the invention

本实用新型的目的在于,针对传统全钢制塔筒与独立扩展基础结构体系的力学性能不足,施工建设的直接成本和间接成本高,建设过程的风险大、维护成本高、比混凝土结构设计使用年限短、结构难以满足风力发电机单机装机容量向着大型化的发展要求等问题,提供一风力发电机塔架,充分发挥混凝土以及钢结构的优势,降低结构本身的直接造价、降低结构维护费用、降低道路建设成本、提高结构性能和安全性、延长结构使用年限,实现生命期成本最小。 The purpose of this utility model is to solve the problem of insufficient mechanical properties of the traditional all-steel tower tube and independent expansion foundation structure system, high direct and indirect costs of construction, high risks in the construction process, high maintenance costs, and higher maintenance costs than concrete structures. Short service life, the structure is difficult to meet the development requirements of large-scale wind turbine installed capacity, etc., provide a wind turbine tower, give full play to the advantages of concrete and steel structure, reduce the direct cost of the structure itself, reduce the structure maintenance cost, Reduce road construction costs, improve structural performance and safety, extend the service life of structures, and minimize life-cycle costs.

本实用新型的技术方案为,一种风力发电机塔架,包括塔架基础和塔架基础上方的钢制塔段,所述钢制塔段的下端面安装钢制塔段下法兰盘,所述塔架基础为混凝土梁板基础,所述混凝土梁板基础顶部设有混凝土底段塔筒,并在混凝土底段塔筒与钢制塔段之间设置钢制过渡塔段;所述混凝土底段塔筒与混凝土梁板基础通过竖向预应力锚固机构连接,而钢制塔段与钢制过渡塔段之间通过紧固机构连接。 The technical solution of the present utility model is, a wind power generator tower, including a tower foundation and a steel tower section above the tower foundation, the lower end surface of the steel tower section is equipped with a steel tower section lower flange, The tower foundation is a concrete beam-slab foundation, and the top of the concrete beam-slab foundation is provided with a concrete bottom section tower tube, and a steel transition tower section is set between the concrete bottom section tower tube and the steel tower section; the concrete The bottom tower and the concrete beam-slab foundation are connected by a vertical prestressed anchorage mechanism, while the steel tower section and the steel transition tower section are connected by a fastening mechanism.

本实用新型改进传统钢制基础环埋入式独立扩展钢筋混凝土基础为预应力梁板式柔性基础。此举可以大大节省基础的混凝土用量并省去钢制埋入式基础环,同时此举的经济效益十分明显。通过在混凝土梁板基础中引入竖向预应力,使得混凝土梁板基础的混凝土处于受压状态,避免混凝土开裂,基础受力形式明确,力学性能优于传统钢制基础环埋入式独立扩展基础。将传统全钢制塔筒的下部替换为混凝土底段塔筒,混凝土底段塔筒与预应力混凝土梁板基础通过现浇混凝土分段施工,形成整体结构。混凝土底段塔筒位于塔架结构体系的底段,钢制塔段位于塔架结构体系的上段,二者之间通过钢制塔段连接。钢制塔段置于预应力混凝土底段塔筒的上方,通过预应力的施加,使得混凝土梁板基础以及混凝土底段塔筒均处于受压状态,达到塔筒混凝土结构混凝土不受拉,不会产生开裂现象的目的,大大提高预应力混凝土基础和塔筒的耐久性以及抗疲劳性能。上段钢制塔段与钢制连接塔段的上法兰通过高强螺栓连接,最终形成一个整体塔架。上部钢制塔段维持原有设计,可以避免高空混凝土施工的困难,也可以充分发挥预制钢制塔筒的优势。 The utility model improves the traditional steel foundation ring embedded independent expanded reinforced concrete foundation into a prestressed beam-slab type flexible foundation. This can greatly save the amount of concrete used for the foundation and save the steel embedded foundation ring, and the economic benefits of this move are very obvious. By introducing vertical prestress in the concrete beam-slab foundation, the concrete of the concrete beam-slab foundation is in a state of compression, avoiding concrete cracking, the foundation stress form is clear, and the mechanical properties are better than the traditional steel foundation ring-buried independent expansion foundation . The lower part of the traditional all-steel tower is replaced by a concrete bottom tower. The concrete bottom tower and the prestressed concrete beam-slab foundation are constructed in sections by cast-in-place concrete to form an overall structure. The concrete bottom section tower tube is located at the bottom section of the tower structure system, and the steel tower section is located at the upper section of the tower structure system, and the two are connected by a steel tower section. The steel tower section is placed above the prestressed concrete bottom section of the tower. Through the application of prestress, the concrete beam-slab foundation and the concrete bottom section of the tower are both in a state of compression, so that the concrete structure of the tower is not stretched, and the concrete is not stretched. The purpose of cracking will be generated, and the durability and fatigue resistance of the prestressed concrete foundation and tower can be greatly improved. The upper steel tower section and the upper flange of the steel connecting tower section are connected by high-strength bolts to finally form an integral tower. The upper steel tower section maintains the original design, which can avoid the difficulties of high-altitude concrete construction, and can also give full play to the advantages of prefabricated steel towers.

所述混凝土梁板基础包括底板、设在底板顶面中心的圆形的环壁、底板外边沿的纵向设置的边梁、连接边梁与环壁的大梁,所述竖向预应力锚固机构沿纵向穿过环壁而与底板连接。 The concrete beam-slab foundation includes a base plate, a circular ring wall arranged at the center of the top surface of the base plate, side beams arranged longitudinally on the outer edge of the base plate, and a girder connecting the side beams and the ring wall. It passes through the ring wall longitudinally and connects with the bottom plate.

混凝土梁板基础分为以下两种:底板的形状为正多边形,且大梁与环壁的外壁相切;底板的形状为圆形,大梁沿底板径向布置。 Concrete beam-slab foundations are divided into the following two types: the shape of the bottom slab is a regular polygon, and the girders are tangent to the outer wall of the ring wall; the shape of the bottom slab is circular, and the girders are arranged radially along the bottom slab.

所述钢制过渡塔段的上端面安装钢制过渡塔段上法兰盘,钢制过渡塔段的下端面安装钢制过渡塔段下法兰盘。 The upper end surface of the steel transition tower section is equipped with a steel transition tower section upper flange, and the lower end surface of the steel transition tower section is equipped with a steel transition tower section lower flange.

所述竖向预应力锚固机构包括沿圆周方向均匀设置的多个预应力张拉部件,该预应力张拉部件顺次穿过混凝土底段塔筒和混凝土梁板基础的环壁,且预应力张拉部件的顶端锚固在钢制过渡塔段下法兰盘而底端锚固在混凝土梁板基础的底板上。钢制过渡塔段的下法兰盘充当预应力张拉部件的锚板。 The vertical prestressed anchoring mechanism includes a plurality of prestressed tensioning parts uniformly arranged along the circumferential direction, the prestressed tensioning parts pass through the ring wall of the concrete bottom tower and the concrete beam slab foundation in sequence, and the prestressed The top end of the tension member is anchored to the lower flange of the steel transition tower section and the bottom end is anchored to the bottom plate of the concrete beam-slab foundation. The lower flange of the steel transition tower section acts as an anchor plate for the prestressed tension member.

所述钢制过渡塔段下法兰盘设有供预应力张拉部件穿过的钢制过渡塔段下法兰盘预应力孔洞,所述混凝土底段塔筒设有供预应力张拉部件穿过的混凝土底段塔筒预应力孔道。 The lower flange of the steel transition tower section is provided with a prestressed hole for the prestressed tensioning parts to pass through the lower flange of the steel transition tower section, and the concrete bottom tower is provided with prestressed tensioning parts The prestressed tunnel in the concrete bottom section of the tower passing through.

所述预应力张拉部件为预应力钢绞线、预应力钢筋或预应力锚栓中的一种或多种。 The prestressed tension member is one or more of prestressed steel strands, prestressed steel bars or prestressed anchor bolts.

所述预应力混凝土底段塔筒沿环向设置内外两层竖向钢筋、环向钢筋以及水平向拉筋;所述预应力混凝土底段塔筒顶部设置钢筋网。 The prestressed concrete bottom section tower is provided with inner and outer two layers of vertical steel bars, circumferential steel bars and horizontal tension bars along the ring; the top of the prestressed concrete bottom section tower is provided with a reinforcement mesh.

所述紧固机构为连接钢制塔段下法兰盘与钢制过渡塔段上法兰盘的高强螺栓。 The fastening mechanism is a high-strength bolt connecting the lower flange of the steel tower section and the upper flange of the steel transition tower section.

与传统的全钢制塔筒以及钢筋混凝土独立扩展基础加钢制埋入式基础环结构体系相比,本实用新型所具有的有益效果是:本实用新型提出的风力发电塔架充分发挥预应力混凝土结构和钢结构的优点,通过与塔筒一道施加预应力和改进基础结构型式的措施,大大优化了基础的受力性能;采用预应力钢筋混凝土结构部分代替传统的全钢制塔筒结构,直接明显降低了塔筒的造价、降低维护费用;由于混凝土采用现场浇筑,运输工作量大大降低,同时降低了运输难度、风险性和费用;对运输道路的要求大为降低,大大降低了修建道路所带来的额外投资,降低了每单位发电功率的造价;由于采用部分采用预应力混凝土结构代替钢塔筒结构,提高了结构体系的刚度,塔顶在风荷载作用下的位移大大减少,能够减轻结构振动;塔架结构上段保持原有钢制塔筒设计,可以加快施工进度,也避免混凝土高空施工的困难;此外,这种新型组合结构体系避免了大直径全钢塔筒运输上的限制,可以满足更大发电功率风电塔架结构的需要。此外,由于混凝土结构的50年的设计使用年限远远大于现有钢制塔筒的20年的设计使用年限,采用预应力混凝土塔筒和基础结构以后混凝土不开裂,能够大大改善结构体系的耐久性和抗疲劳特性,结构体系的生命期成本大大降低,延长结构的使用年限,大大提高收益率;在上部钢制塔筒达到设计使用年限时在保存下段预应力混凝土塔段继续使用的情况下可以仅更换上部钢制塔段即可继续产生发电效益,而且避免重建、增加工期带来的经济损失;预应力混凝土塔筒结构运行期间无需特殊维护,塔架的后期维护上的成本变低;预应力混凝土塔筒在成型后重量相比钢制塔筒大,对于风机塔架这种大偏心结构来说,有利于减小基础偏心荷载,有利于基础的抗倾覆稳定性。本实用新型对山区风场的风电建设具有十分重要的意义。 Compared with the traditional all-steel tower and the reinforced concrete independent expansion foundation plus steel embedded foundation ring structure system, the utility model has the beneficial effect that: the wind power generation tower proposed by the utility model fully exerts the prestress The advantages of concrete structure and steel structure, through the measures of applying prestress together with the tower and improving the type of foundation structure, the mechanical performance of the foundation is greatly optimized; the prestressed reinforced concrete structure is used to partially replace the traditional all-steel tower structure, Directly and significantly reduce the cost of the tower and reduce the maintenance cost; because the concrete is poured on site, the transportation workload is greatly reduced, and the difficulty, risk and cost of transportation are reduced at the same time; the requirements for transportation roads are greatly reduced, and the construction of roads is greatly reduced. The additional investment brought about reduces the cost per unit of power generation; as part of the prestressed concrete structure is used to replace the steel tower structure, the rigidity of the structural system is improved, and the displacement of the tower top under the wind load is greatly reduced. Reduce structural vibration; the upper part of the tower structure maintains the original steel tower design, which can speed up the construction progress and avoid the difficulty of concrete high-altitude construction; in addition, this new composite structure system avoids the restrictions on the transportation of large-diameter all-steel towers , which can meet the needs of wind power tower structures with greater power generation. In addition, since the 50-year design service life of the concrete structure is far greater than the 20-year design service life of the existing steel tower, the concrete will not crack after the prestressed concrete tower and foundation structure are used, which can greatly improve the durability of the structural system and anti-fatigue characteristics, the life cycle cost of the structural system is greatly reduced, the service life of the structure is extended, and the rate of return is greatly increased; when the upper steel tower reaches the design service life, the lower prestressed concrete tower section is preserved and continues to be used Only the upper steel tower section can be replaced to continue to generate power generation benefits, and economic losses caused by reconstruction and increased construction period can be avoided; no special maintenance is required during the operation of the prestressed concrete tower structure, and the cost of post-maintenance of the tower becomes lower; The weight of the prestressed concrete tower is larger than that of the steel tower after forming. For the large eccentric structure of the wind turbine tower, it is beneficial to reduce the eccentric load of the foundation and the stability of the foundation against overturning. The utility model has very important significance to the wind power construction of the wind field in mountainous areas.

附图说明 Description of drawings

图1为本实用新型实施例1的塔架结构图; Fig. 1 is the tower structure diagram of the utility model embodiment 1;

图2为图1的半剖视图; Fig. 2 is a half-sectional view of Fig. 1;

图3为本实用新型实施例1中混凝土梁板基础的结构俯视图; Fig. 3 is the top view of the structure of the concrete beam-slab foundation in Example 1 of the utility model;

图4为本实用新型实施例1中混凝土梁板基础与混凝土底段塔筒连接的结构主视图; Fig. 4 is the front view of the structure connecting the concrete beam-slab foundation and the concrete bottom section tower tube in Embodiment 1 of the utility model;

图5为本实用新型实施例1中钢制过渡塔段与混凝土底段塔筒连接的结构示意图; Fig. 5 is a structural schematic diagram of the connection between the steel transition tower section and the concrete bottom section tower in Example 1 of the utility model;

图6为本实用新型实施例1中钢制过渡段的结构示意图; Fig. 6 is a structural schematic diagram of a steel transition section in Example 1 of the utility model;

图7为本实用新型实施例1中制过渡塔段下法兰盘的结构示意图; Fig. 7 is the schematic structural view of the lower flange of the transition tower section in Example 1 of the utility model;

图8为本实用新型实施例1中钢制塔段、钢制过渡塔段与混凝土底段塔筒的连接结构示意图; Fig. 8 is a schematic diagram of the connection structure of the steel tower section, the steel transition tower section and the concrete bottom section tower in Example 1 of the utility model;

图9为本实用新型实施例2的塔架结构示意图; Fig. 9 is a schematic diagram of the tower structure of Embodiment 2 of the utility model;

图10为图9的半剖视图; Fig. 10 is a half-sectional view of Fig. 9;

图11为本实用新型实施例2中混凝土梁板基础的结构俯视图; Fig. 11 is a top view of the structure of the concrete beam-slab foundation in Example 2 of the utility model;

图12为本实用新型实施例2中混凝土梁板基础与混凝土底段塔筒连接的结构主视图。 Fig. 12 is a front view of the structure connecting the concrete beam-slab foundation and the concrete bottom section tower in Example 2 of the present utility model.

具体实施方式 Detailed ways

    实施例1Example 1

如图1所示,一种风力发电机塔架,由下至上依次包括混凝土梁板基础1、混凝土底段塔筒2、钢制过渡塔段3、钢制塔段4。混凝土梁板基础1与预应力混凝土底段塔筒2运用现浇混凝土分段浇筑,形成整体。 As shown in FIG. 1 , a wind power generator tower includes a concrete beam-slab foundation 1 , a concrete bottom section tower tube 2 , a steel transition tower section 3 , and a steel tower section 4 from bottom to top. The concrete beam-slab foundation 1 and the prestressed concrete bottom section tower tube 2 are poured in sections using cast-in-place concrete to form a whole.

如图2所示,混凝土底段塔筒2、钢制过渡塔段3、钢制塔段4均为空心圆筒状。 As shown in Fig. 2, the concrete bottom section tower tube 2, the steel transition tower section 3, and the steel tower section 4 are all in the shape of hollow cylinders.

如图3所示,混凝土梁板基础包括底板18、设在底板18顶面中心的圆形的环壁8、底板外边沿的纵向设置的边梁17、连接边梁17与环壁8的大梁16;环壁8中心轴线与混凝土底段塔筒2竖向中心线重合;底板18的形状为正八边形,大梁16与环壁8的外壁相切。 As shown in Figure 3, the concrete beam-slab foundation includes a base plate 18, a circular ring wall 8 arranged at the center of the top surface of the base plate 18, a side beam 17 arranged longitudinally on the outer edge of the base plate, and a girder connecting the side beam 17 and the ring wall 8 16. The central axis of the ring wall 8 coincides with the vertical center line of the concrete bottom section tower 2; the shape of the bottom plate 18 is a regular octagon, and the girder 16 is tangent to the outer wall of the ring wall 8.

如图6所示,钢制过渡塔段3的上端面安装钢制过渡塔段上法兰盘12,钢制过渡塔段3的下端面安装钢制过渡塔段下法兰盘10,如图8所示,钢制塔段下法兰盘11与钢制过渡塔段上法兰盘12通过螺栓13连接,钢制过渡塔段下法兰盘10上设有用于安装螺栓13的钢制过渡塔段下法兰盘螺纹孔25。钢制过渡塔段下法兰盘10上设有用于塔顶混凝土浇筑以及振捣的灌浆孔洞26。 As shown in Figure 6, the upper end surface of the steel transition tower section 3 is equipped with a steel transition tower section upper flange 12, and the lower end surface of the steel transition tower section 3 is installed with a steel transition tower section lower flange 10, as shown in the figure As shown in 8, the lower flange 11 of the steel tower section and the upper flange 12 of the steel transition tower section are connected by bolts 13, and the lower flange 10 of the steel transition tower section is provided with a steel transition for installing the bolt 13. The threaded hole 25 of the lower flange of the tower section. The lower flange 10 of the steel transition tower section is provided with a grouting hole 26 for concrete pouring and vibration at the top of the tower.

如图4、图5所示,设有内外两层预应力张拉部件5顺次穿过混凝土底段塔筒2和混凝土梁板基础的环壁8,环壁8的顶面为基础顶板28,且预应力张拉部件5的顶端通过锚具9锚固在钢制过渡塔段下法兰盘10而底端通过锚具27锚固在混凝土梁板基础的底板18上。通过后张法张拉预应力,张拉完毕后向混凝土底段塔筒预应力孔道19内进行灌浆处理。 As shown in Fig. 4 and Fig. 5, there are inner and outer two-layer prestressed tension parts 5 passing through the concrete bottom section tower tube 2 and the ring wall 8 of the concrete beam slab foundation in sequence, and the top surface of the ring wall 8 is the foundation roof 28 , and the top end of the prestressed tension member 5 is anchored to the lower flange 10 of the steel transition tower section through the anchor 9 and the bottom end is anchored to the bottom plate 18 of the concrete beam-slab foundation through the anchor 27 . The prestress is stretched by the post-tensioning method, and the grouting treatment is carried out in the prestress tunnel 19 of the concrete bottom section of the tower after the tension is completed.

所述预应力混凝土底段塔筒2沿环向设置内外两层竖向钢筋20、环向钢筋21以及水平向拉筋22;所述预应力混凝土底段塔筒2顶部设置钢筋网23,钢制过渡塔段下法兰盘10下表面焊接锚固钢筋24。 The prestressed concrete bottom section tower tube 2 is provided with inner and outer two layers of vertical steel bars 20, circumferential steel bars 21 and horizontal tension bars 22 along the ring; The lower surface of the lower flange 10 of the transition tower section is welded with an anchoring steel bar 24.

如图7所示,钢制过渡塔段下法兰盘10设有供预应力张拉部件5穿过的钢制过渡塔段下法兰盘预应力孔洞25,混凝土底段塔筒2设有供预应力张拉部件5穿过的混凝土底段塔筒预应力孔道19。 As shown in Figure 7, the steel transition tower section lower flange 10 is provided with the steel transition tower section lower flange prestressing hole 25 for the prestressed tension member 5 to pass through, and the concrete bottom section tower tube 2 is provided with The concrete bottom section tower tube prestressed tunnel 19 for the prestressed tension member 5 to pass through.

预应力张拉部件5为预应力钢绞线。 The prestressed tension member 5 is a prestressed steel strand.

实施例2Example 2

如图9、图10所示,一种风力发电机塔架,由下至上依次包括混凝土梁板基础1、混凝土底段塔筒2、钢制过渡塔段3、钢制塔段4。混凝土梁板基础1与预应力混凝土底段塔筒2运用现浇混凝土分段浇筑,形成整体。 As shown in Fig. 9 and Fig. 10, a wind power generator tower includes a concrete beam-slab foundation 1, a concrete bottom tower section 2, a steel transition tower section 3, and a steel tower section 4 from bottom to top. The concrete beam-slab foundation 1 and the prestressed concrete bottom section tower tube 2 are poured in sections using cast-in-place concrete to form a whole.

如图11、图12所示,混凝土梁板基础包括底板18、设在底板18顶面中心的圆形的环壁8、底板外边沿的纵向设置的边梁17、连接边梁17与环壁8的大梁16;环壁8中心轴线与混凝土底段塔筒2竖向中心线重合;底板18的形状为圆形,大梁16沿底板18径向布置。 As shown in Figures 11 and 12, the concrete beam-slab foundation includes a base plate 18, a circular ring wall 8 located at the center of the top surface of the base plate 18, a longitudinally arranged edge beam 17 on the outer edge of the base plate, and connecting edge beams 17 and the ring wall. The girder 16 of 8; the central axis of the ring wall 8 coincides with the vertical centerline of the concrete bottom section tower tube 2; the shape of the bottom plate 18 is circular, and the girder 16 is radially arranged along the bottom plate 18.

其余结构与实施例1的结构一致。  All the other structures are consistent with those of Example 1. the

Claims (10)

1. 一种风力发电机塔架,包括塔架基础和塔架基础上方的钢制塔段(4),所述钢制塔段(4)的下端面安装钢制塔段下法兰盘(11),其特征是,所述塔架基础为混凝土梁板基础(1),所述混凝土梁板基础(1)顶部设有混凝土底段塔筒(2),并在混凝土底段塔筒(2)与钢制塔段(4)之间设有钢制过渡塔段(3);所述混凝土底段塔筒(2)与混凝土梁板基础(1)通过竖向预应力锚固机构连接,而钢制塔段(4)与钢制过渡塔段(3)之间通过紧固机构连接。 1. A wind power generator tower, comprising a tower foundation and a steel tower section (4) above the tower foundation, the lower end surface of the steel tower section (4) is equipped with a steel tower section lower flange ( 11), characterized in that the tower foundation is a concrete beam-slab foundation (1), the top of the concrete beam-slab foundation (1) is provided with a concrete bottom section tower (2), and the concrete bottom section tower (2) 2) There is a steel transition tower section (3) between the steel tower section (4); the concrete bottom section tower tube (2) is connected to the concrete beam-slab foundation (1) through a vertical prestressed anchorage mechanism, The steel tower section (4) is connected with the steel transition tower section (3) through a fastening mechanism. 2.根据权利要求1所述风力发电机塔架,其特征是,所述混凝土梁板基础包括底板(18)、设在底板(18)顶面中心的圆形的环壁(8)、底板外边沿的纵向设置的边梁(17)、连接边梁(17)与环壁(8)的大梁(16),所述竖向预应力锚固机构沿纵向穿过环壁(8)而与底板(18)连接。 2. The wind power generator tower according to claim 1, characterized in that, the concrete beam-slab foundation comprises a bottom plate (18), a circular ring wall (8) arranged at the center of the top surface of the bottom plate (18), a bottom plate The side beam (17) arranged longitudinally on the outer edge, the girder (16) connecting the side beam (17) and the ring wall (8), the vertical prestressed anchor mechanism passes through the ring wall (8) longitudinally and connects with the bottom plate (18) CONNECTIONS. 3.根据权利要求2所述风力发电机塔架,其特征是,所述底板(18)的形状为正多边形;所述大梁(16)与环壁(8)的外壁相切。 3. The wind power generator tower according to claim 2, characterized in that, the shape of the bottom plate (18) is a regular polygon; and the girder (16) is tangent to the outer wall of the ring wall (8). 4.根据权利要求2所述风力发电机塔架,其特征是,所述底板(18)的形状为圆形;所述大梁(16)沿底板(18)径向布置。 4. The wind power generator tower according to claim 2, characterized in that, the shape of the bottom plate (18) is circular; and the girders (16) are radially arranged along the bottom plate (18). 5.根据权利要求2所述风力发电机塔架,其特征是,所述钢制过渡塔段(3)的上端面安装钢制过渡塔段上法兰盘(12),钢制过渡塔段(3)的下端面安装钢制过渡塔段下法兰盘(10)。 5. The wind power generator tower according to claim 2, characterized in that, the upper end surface of the steel transition tower section (3) is equipped with a steel transition tower section upper flange (12), and the steel transition tower section (3) The lower end face of the steel transition tower section is installed with a lower flange (10). 6.根据权利要求5所述风力发电机塔架,其特征是,所述竖向预应力锚固机构包括沿圆周方向均匀设置的多个预应力张拉部件(5),该预应力张拉部件(5)顺次穿过混凝土底段塔筒(2)和混凝土梁板基础的环壁(8),且预应力张拉部件(5)的顶端锚固在钢制过渡塔段下法兰盘(10)而底端锚固在混凝土梁板基础的底板(18)上。 6. The wind power generator tower according to claim 5, characterized in that, the vertical prestressed anchoring mechanism includes a plurality of prestressed tension members (5) uniformly arranged along the circumferential direction, and the prestressed tension members (5) Pass through the concrete bottom section tower tube (2) and the ring wall (8) of the concrete beam-slab foundation in sequence, and the top of the prestressed tension member (5) is anchored to the lower flange of the steel transition tower section ( 10) and the bottom end is anchored on the bottom plate (18) of the concrete beam slab foundation. 7.根据权利要求6所述风力发电机塔架,其特征是,所述钢制过渡塔段下法兰盘(10)设有供预应力张拉部件(5)穿过的钢制过渡塔段下法兰盘预应力孔洞(25),所述混凝土底段塔筒(2)设有供预应力张拉部件(5)穿过的混凝土底段塔筒预应力孔道(19)。 7. The wind power generator tower according to claim 6, characterized in that the lower flange (10) of the steel transition tower section is provided with a steel transition tower for the prestressed tension member (5) to pass through The prestressed hole (25) of the lower flange plate, and the concrete bottom tower tube (2) is provided with a concrete bottom tower tube prestressed tunnel (19) for the prestressed tension member (5) to pass through. 8.根据权利要求6所述风力发电机塔架,其特征是,所述预应力张拉部件(5)为预应力钢绞线、预应力钢筋或预应力锚栓中的一种或多种。 8. The wind power generator tower according to claim 6, characterized in that, the prestressed tension member (5) is one or more of prestressed steel strands, prestressed steel bars or prestressed anchor bolts . 9.根据权利要求1或2所述风力发电机塔架,其特征是,所述预应力混凝土底段塔筒(2)沿环向设置内外两层竖向钢筋(20)、环向钢筋(21)以及水平向拉筋(22);所述预应力混凝土底段塔筒(2)顶部设置钢筋网(23)。 9. The wind power generator tower according to claim 1 or 2, characterized in that, the prestressed concrete bottom section tower (2) is provided with two layers of inner and outer vertical steel bars (20) and ring steel bars ( 21) and horizontal tension bars (22); the top of the prestressed concrete bottom section tower (2) is provided with a reinforcement mesh (23). 10.根据权利要求5所述风力发电机塔架,其特征是,所述紧固机构为连接钢制塔段下法兰盘(11)与钢制过渡塔段上法兰盘(12)的螺栓(13)。 10. The wind power generator tower according to claim 5, characterized in that, the fastening mechanism is for connecting the lower flange (11) of the steel tower section and the upper flange (12) of the steel transition tower section Bolt (13).
CN201420204401.4U 2014-04-25 2014-04-25 Wind driven generator tower Expired - Lifetime CN203809220U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420204401.4U CN203809220U (en) 2014-04-25 2014-04-25 Wind driven generator tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420204401.4U CN203809220U (en) 2014-04-25 2014-04-25 Wind driven generator tower

Publications (1)

Publication Number Publication Date
CN203809220U true CN203809220U (en) 2014-09-03

Family

ID=51447983

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420204401.4U Expired - Lifetime CN203809220U (en) 2014-04-25 2014-04-25 Wind driven generator tower

Country Status (1)

Country Link
CN (1) CN203809220U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106516992A (en) * 2016-12-09 2017-03-22 天津五洲国际集装箱码头有限公司 Heightening structure for container crane
CN106762441A (en) * 2016-12-13 2017-05-31 北京金风科创风电设备有限公司 Transition piece and wind power tower
CN108301983A (en) * 2018-03-06 2018-07-20 中国电建集团华东勘测设计研究院有限公司 A kind of fragment prefabricated Wind turbines prestressed concrete tower cylinder
CN111287459A (en) * 2018-12-06 2020-06-16 深圳京创重工特种工程有限公司 Construction method of anchoring tower section
CN111287458A (en) * 2018-12-06 2020-06-16 深圳京创重工特种工程有限公司 Construction method of anchoring tower section
CN111520289A (en) * 2020-05-12 2020-08-11 上海电气研砼(木垒)建筑科技有限公司 Connecting node of segmented prefabricated assembled combined tower cylinder and mounting method thereof
CN114412269A (en) * 2022-02-17 2022-04-29 中国能源建设集团湖南省电力设计院有限公司 Single-cylinder type corrosion-resistant chimney and construction method
CN114439033A (en) * 2022-03-08 2022-05-06 中国石油大学(华东) Reinforced concrete self-sinking umbrella-shaped mudflat wind power foundation and installation method thereof

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106516992A (en) * 2016-12-09 2017-03-22 天津五洲国际集装箱码头有限公司 Heightening structure for container crane
CN106762441A (en) * 2016-12-13 2017-05-31 北京金风科创风电设备有限公司 Transition piece and wind power tower
CN108301983A (en) * 2018-03-06 2018-07-20 中国电建集团华东勘测设计研究院有限公司 A kind of fragment prefabricated Wind turbines prestressed concrete tower cylinder
CN111287459A (en) * 2018-12-06 2020-06-16 深圳京创重工特种工程有限公司 Construction method of anchoring tower section
CN111287458A (en) * 2018-12-06 2020-06-16 深圳京创重工特种工程有限公司 Construction method of anchoring tower section
CN111287459B (en) * 2018-12-06 2022-02-11 上海风领新能源有限公司 Construction method of anchoring tower section
CN111287458B (en) * 2018-12-06 2022-03-01 上海风领新能源有限公司 Construction method of anchoring tower section
CN111520289A (en) * 2020-05-12 2020-08-11 上海电气研砼(木垒)建筑科技有限公司 Connecting node of segmented prefabricated assembled combined tower cylinder and mounting method thereof
CN114412269A (en) * 2022-02-17 2022-04-29 中国能源建设集团湖南省电力设计院有限公司 Single-cylinder type corrosion-resistant chimney and construction method
CN114412269B (en) * 2022-02-17 2025-03-11 中国能源建设集团湖南省电力设计院有限公司 A single-tube anti-corrosion chimney and construction method
CN114439033A (en) * 2022-03-08 2022-05-06 中国石油大学(华东) Reinforced concrete self-sinking umbrella-shaped mudflat wind power foundation and installation method thereof

Similar Documents

Publication Publication Date Title
CN103899499A (en) Wind turbine generator tower
CN105113389B (en) Prefabricated steel-concrete composite structure pier column member
CN103821677B (en) Prefabricated PC RPC wind power tower
CN103867019B (en) Assembling external prestressing RPC wind power tower
CN103994034B (en) Connection device of prestress concrete and steel combination wind power generation tower
CN206917805U (en) The antifatigue combination steel construction wind tower of omnidirectional's prestressing force
CN112112767B (en) A combined structural transfer structure for steel-concrete tower of wind turbine
CN111022267A (en) A hybrid wind power tower based on segmented prestressed multi-cavity composite shell
CN111173684B (en) A lattice prestressed concrete wind power tower
CN112177857A (en) A prestressed hollow interlayer concrete-filled steel tubular lattice type hybrid tower and its production and installation method
CN203755778U (en) Assembly external pre-stress reactive powder concrete wind power tower
CN110863953B (en) Circular steel tube concrete composite wind turbine tower structure
CN110468869B (en) Reinforcing structure and method for P & H type rock anchor rod fan foundation
CN105179183A (en) Prestressed concrete wind power tower system and construction method thereof
CN209671140U (en) A Prestressed Hollow Sandwich Steel Tube Concrete Wind Power Structural System
CN112627221B (en) A prestressed hollow sandwich steel tube concrete lattice hybrid jacket
CN112412707A (en) Assembled wind turbine generator system circle cross section concrete bearing structure
CN116575784A (en) A self-resetting energy-dissipating node for wind power hybrid tower structure
CN209671141U (en) A kind of mixing tower adapter ring based on composite structure technology
CN205369295U (en) Basis precast prestressed beam slab formula wind power generation column foot plinth
CN205638802U (en) A segmented combined prefabricated concrete tower structure
CN214741844U (en) A combined structure transfer structure for steel-mixed towers of wind turbines
CN102635063A (en) Post-tensioned prestressing steel pipe high-strength concrete superposition bridge pier and construction method thereof
CN102041785B (en) Pier steel-concrete composite structure column beam
CN205638803U (en) A transition section structure connecting steel tower and prestressed concrete tower

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140903

CX01 Expiry of patent term