CN203740915U - Gantry crane boom system mounting device - Google Patents
Gantry crane boom system mounting device Download PDFInfo
- Publication number
- CN203740915U CN203740915U CN201420068695.2U CN201420068695U CN203740915U CN 203740915 U CN203740915 U CN 203740915U CN 201420068695 U CN201420068695 U CN 201420068695U CN 203740915 U CN203740915 U CN 203740915U
- Authority
- CN
- China
- Prior art keywords
- jib
- trunk beam
- boom system
- crane boom
- high pedestal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 25
- 230000001681 protective effect Effects 0.000 claims description 5
- 239000000853 adhesive Substances 0.000 claims description 2
- 230000001070 adhesive effect Effects 0.000 claims description 2
- 241000406668 Loxodonta cyclotis Species 0.000 abstract 4
- 238000009434 installation Methods 0.000 description 11
- 230000000712 assembly Effects 0.000 description 4
- 238000000429 assembly Methods 0.000 description 4
- 239000000725 suspension Substances 0.000 description 4
- 238000003466 welding Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 238000004806 packaging method and process Methods 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model relates to a gantry crane boom system mounting device. The gantry crane boom system mounting device comprises at least one tensioning lug (13) arranged nearby one end of an elephant nose beam (2) of a boom (1), at least one tensioning lug (12) arranged on the elephant nose beam (2), and a boom supporting tooling (8), wherein the boom supporting tooling (8) is used for supporting assembly of the elephant nose beam (2) and the boom (1), the top end surface of the supporting tooling is an inclined surface, and the slant angle of the inclined surface is matched with that of the bottom surface of the boom (1) when in assembly with the elephant nose beam (2).
Description
Technical field
The utility model relates to high pedestal jib crane, relates in particular to high pedestal jib crane boom system erecting device.
Background technology
Four-link door seat formula hoisting crane belongs to heavy, big machinery product, mainly concentrate on the lifting of port and pier for various goods, large-scale Four-link door seat formula hoisting crane is from hundreds of tons that weigh, and approximately 50 meters of apogee distance ground levels, are made up of twenties different parts.Wherein jib, trunk beam, large pull bar, rotating disk and the large parts of column four surround a quadrilateral structure, and between each parts, use adapter shaft and associate member connect and consolidate appropriately, can mutually move.When jib, trunk beam and large pull bar are assembled, because three parts are not fixed bodies, and in the aloft work higher than 40 meters, assembling inconvenience, packaging efficiency is low, cost is high, have potential safety hazard.
As shown in Figure 1, prior art is in the time of assembling Four-link door seat formula hoisting crane, after rotating disk and columns assemblies 4 install, hanging equalizing bar and lower link bar assembly 5 and column with hoisting crane installs, hanging jib 1 lift-off with hoisting crane is again connected with jib hinged-support adapter shaft and associate member on rotating disk, then equalizing bar is connected with jib 1 use adapter shaft and associate member with the lower link bar in lower link bar assembly 5, again luffing mechanism 6 is connected with jib 1 use adapter shaft and associate member, then hang trunk beam 2, trunk beam 2 is connected with jib 1 by adapter shaft and associate member 3, because point of connection is greater than 40 meters apart from floor level, when assembling, jib need play and not unclamp with a hoisting crane, trunk beam also needs to play with a hoisting crane, now also need, with the 3rd hoisting crane, installation personnel is winched to the enterprising line operate of jib front end table balustrade, installation personnel need be fastened seat belts, operate again, and now, jib 1 is all extremely unstable with trunk beam 2, therefore very difficult when operation.When jib 1 and trunk beam 2 install, the hoisting crane of the trunk beam that plays can not unclamp, and finally hangs large pull bar 7 first ends adapter shaft and associate member and is connected with column, and the second end is connected with trunk beam 2 with adapter shaft and associate member.In the time that large pull bar 7 is connected with trunk beam 2, due to unfixing between trunk beam 2 and jib 1, there is relative motion, so same very difficult when now large pull bar 7 is installed with trunk beam 2 use adapter shafts and associate member.
Prior art has the following disadvantages: when trunk beam 2 is installed with jib 1, be in aloft work, each personal hoisting crane and steel rope play, it is indefinite under the impact of wind-force, to rock, and need volume and the weight of the adapter shaft of installing all larger, installation personnel operating difficulties, installation difficulty is very large, thereby has reduced installation effectiveness; There is great potential safety hazard; Required hoisting crane quantity is more and work-hours is longer, adds that the installation personnel quantity of input is more and work-hours is longer, has therefore increased cost of installation.When large pull bar and trunk beam are installed, due to unfixing between jib and trunk beam, there is relative motion, therefore also can have similar shortcoming.
Utility model content
Therefore, the purpose of this utility model is: a kind of high pedestal jib crane boom system erecting device is provided, can overcomes existing high pedestal jib crane boom system fitting operation difficulty, installation difficulty is large, the defect that installation effectiveness is low.
In order to solve the problems of the technologies described above, the utility model provides a kind of high pedestal jib crane boom system erecting device, comprises at least one tension hanger that is arranged on the nearly trunk beam of jib one end; At least one the tension hanger being arranged on trunk beam; Jib supporting tool, described supporting tool is for supporting the assembling of trunk beam and jib, and the top end face of supporting tool is inclined-plane, and when gradient and jib are assembled with trunk beam, the bottom surface gradient of jib matches.
As further improvement project: the high pedestal jib crane boom system erecting device that the utility model provides, also comprises that at least three are arranged on the lifting hanger for jib lifting on jib.
As further improvement project: the high pedestal jib crane boom system erecting device that the utility model provides, described lifting hanger is four, is quadrangle and is arranged on the top of jib; Two tension hangers are set on jib; Two tension hangers are set on trunk beam.
As further improvement project: the high pedestal jib crane boom system erecting device that the utility model provides, the contact surface of described supporting tool and described jib also has protection jib and increases the protective device of adhesive ability.
As further improvement project: the high pedestal jib crane boom system erecting device that the utility model provides, described protective device is wooden unit, rubber or cardboard.
As further improvement project: the high pedestal jib crane boom system erecting device that the utility model provides, described supporting tool is fixed on the traveling gear track of high pedestal jib crane.
In the situation that not conflicting, above-mentioned improvement or preferred version can be implemented alone or in combination.
The beneficial effects of the utility model: the high pedestal jib crane boom system erecting device that the utility model provides, when trunk beam and jib assembling, height when fixing and assemble because of jib is lower, be easy to assembling, in the time that large pull bar the second end is connected with trunk beam, be hung in the tension hanger of jib or trunk beam with suspension hook and the hook of cucurbit, after cucurbit tension, the relative position of jib and trunk beam is fixed, and can change convenient by operation cucurbit, accurately trunk beam angle and dock assembling with large pull bar, thereby raising work efficiency, reduces installation difficulty.
Brief description of the drawings
Accompanying drawing is used to provide further understanding of the present utility model, forms the application's a part, and schematic description and description of the present utility model is used for explaining the utility model, does not form improper restriction of the present utility model.In the accompanying drawings:
Fig. 1 is the structural representation of high pedestal jib crane boom system;
Position view when Fig. 2 is embodiment jib and the assembling of trunk beam;
Fig. 3 is the structural representation of embodiment supporting tool;
Fig. 4 is the partial enlarged drawing of Fig. 2;
In figure: 1---jib, 2---trunk beam, 3---jib and trunk beam adapter shaft and associate member, 4---rotating disk and columns assemblies, 5---equalizing bar and lower link bar assembly, 6---luffing mechanism, 7---large pull bar, 8---large supporting tool, 9---the traveling gear track of high pedestal jib crane, 10,11---lifting hanger, 12,13---tension hanger.
Detailed description of the invention
Below in conjunction with accompanying drawing, detailed description of the invention of the present utility model is described in further detail.As shown in Figures 1 to 4, high pedestal jib crane boom system erecting device, comprise four be arranged on the lifting hanger 10, the 11(that on jib 1, lift by crane for jib 1 other two not shown), four lifting hangers, are quadrangle and are welded on the top of jib 1; Two tension hanger 13(that are welded on jib 1 nearly trunk beam 2 one end other one not shown); Two be welded on tension hanger 12(on trunk beam 2 other one not shown); Jib supporting tool 8, supporting tool 8 is for supporting the assembling of trunk beam 2 and jib 1, and the top end face of supporting tool 8 is inclined-plane, also embeds two protection wooden units on top, the gradient of supporting tool 8, while assembling with trunk beam 2 with jib 1, the bottom surface gradient of the support zone of jib 1 is consistent.
Enforcement principle of the present utility model and process are as follows:
In high pedestal jib crane boom system installation process, on jib 1, weld four lifting hanger 10,11(for jib lifting other two not shown); Two tension hanger 13(of the nearly trunk beam of jib 12 one end welding other one not shown);
On trunk beam 2 with two tension hanger 12(of upper end welding of jib point of connection other one not shown);
8 of supporting tools are welded on the traveling gear track 9 of high pedestal jib crane and are fixed, described supporting tool 8 is for supporting the assembling of trunk beam 2 and jib 1, the top end face of supporting tool is inclined-plane, embed two wooden units at the top end face of supporting tool 8, the gradient of supporting tool 8, while assembling with trunk beam 2 with jib 1, the bottom surface gradient of the support zone of jib 1 is consistent;
Described jib 1 is placed on two wooden units that described supporting tool 8 embeds, and wooden unit can prevent workpiece deformation and peeling paint; Jib 1 is strained jib 1 and supporting tool 8 with supporting tool 8 spot welding or with steel rope, jib 1 and described supporting tool 8 are fixed;
Lifting trunk beam 2; Trunk beam 2 is connected with trunk beam adapter shaft and associate member 3 by jib with described jib 1;
Use two cucurbits, the suspension hook of each cucurbit and hook are hung in the tension hanger 13 of jib 1, or in the tension hanger 12 of trunk beam 2, suspension hook and hook extension into tension hanger be replaceable, by two cucurbit tensions, jib 1 and the relative position of trunk beam 2 are fixed;
After rotating disk and columns assemblies 4 install, equalizing bar and lower link bar assembly 5 are connected with rotating disk and columns assemblies 4, four that hang on jib 1 with hoisting crane are lifted by crane hangers 10,11, jib 1 and trunk beam 2 after assembling are sling, jib 1 is connected with adapter shaft and associate member with the jib hinged-support on rotating disk;
Lower link bar is connected with jib 1 use adapter shaft and associate member;
Luffing mechanism 6 is connected with jib 1 use adapter shaft and associate member;
Lift by crane large pull bar 7, the first end of described large pull bar 7 is connected with described column with adapter shaft and associate member, the second end is connected with described trunk beam 2 with adapter shaft and associate member.
It will be appreciated by those skilled in the art that, under the enlightenment of aforementioned schemes, the replaceable one-tenth rubber of the wooden unit of protective device or cardboard etc.
The technical scheme that the utility model provides, when trunk beam 2 is assembled with jib 1, height when fixing and assemble because of jib 1 is lower, be easy to assembling, in the time that large pull bar 7 second ends are connected with trunk beam 2, be hung in the tension hanger of jib 1 or trunk beam 2 with suspension hook and the hook of cucurbit, after cucurbit tension, jib 1 and the relative position of trunk beam 2 are fixed, and can change convenient by operation cucurbit, accurately trunk beam angle, convenient and large pull bar docks assembling, thereby improves work efficiency, reduces installation difficulty.
Obviously, the utility model is not limited to above preferred implementation, also can be in the spirit of the utility model claim and specification sheets restriction, carry out conversion and the improvement of various ways, can solve same technical matters, and obtain the technique effect of expection, therefore do not repeat.Those of ordinary skill in the art can be from the disclosed content of the utility model directly or all schemes of associating, as long as within the spirit limiting in claim, also belong to protection domain of the present utility model.
Claims (6)
1. a high pedestal jib crane boom system erecting device, is characterized in that, comprises at least one tension hanger (13) that is arranged on the nearly trunk beam (2) of jib (1) one end; At least one the tension hanger (12) being arranged on trunk beam (2); Jib supporting tool (8), described supporting tool (8) is for supporting the assembling of trunk beam (2) and jib (1), and the top end face of supporting tool is inclined-plane, and when gradient and jib (1) are assembled with trunk beam (2), the bottom surface gradient of jib (1) matches.
2. high pedestal jib crane boom system erecting device according to claim 1, is characterized in that, also comprises that at least three are arranged on the upper lifting hanger (10,11) for jib (1) lifting of jib (1).
3. high pedestal jib crane boom system erecting device according to claim 2, is characterized in that, described lifting hanger (10,11) is four, is quadrangle and is arranged on the top of jib (1); Two tension hangers (13) are set on jib (1); Two tension hangers (12) are set on trunk beam (2).
4. high pedestal jib crane boom system erecting device according to claim 1, is characterized in that, described supporting tool (8) also has protection jib with the contact surface of described jib (1) and increases the protective device of adhesive ability.
5. high pedestal jib crane boom system erecting device according to claim 4, is characterized in that, described protective device is wooden unit, rubber or cardboard.
6. high pedestal jib crane boom system erecting device according to claim 1, is characterized in that, described supporting tool (8) is fixed on the traveling gear track (9) of high pedestal jib crane.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420068695.2U CN203740915U (en) | 2014-02-18 | 2014-02-18 | Gantry crane boom system mounting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420068695.2U CN203740915U (en) | 2014-02-18 | 2014-02-18 | Gantry crane boom system mounting device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203740915U true CN203740915U (en) | 2014-07-30 |
Family
ID=51340743
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420068695.2U Expired - Lifetime CN203740915U (en) | 2014-02-18 | 2014-02-18 | Gantry crane boom system mounting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203740915U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109231023A (en) * | 2018-10-29 | 2019-01-18 | 广州文冲船厂有限责任公司 | The installation method of high pedestal jib crane boom system |
CN109607231A (en) * | 2018-12-11 | 2019-04-12 | 湖南长重机器股份有限公司 | A kind of Wind-proof mechanism of bucket-wheel stacker reclaimer |
CN109623361A (en) * | 2018-11-28 | 2019-04-16 | 武汉武船重型装备工程有限责任公司 | A kind of the flexible composition system and assemble method of double leval jib floating type ship unloading machine |
-
2014
- 2014-02-18 CN CN201420068695.2U patent/CN203740915U/en not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109231023A (en) * | 2018-10-29 | 2019-01-18 | 广州文冲船厂有限责任公司 | The installation method of high pedestal jib crane boom system |
CN109623361A (en) * | 2018-11-28 | 2019-04-16 | 武汉武船重型装备工程有限责任公司 | A kind of the flexible composition system and assemble method of double leval jib floating type ship unloading machine |
CN109623361B (en) * | 2018-11-28 | 2020-04-10 | 武汉武船重型装备工程有限责任公司 | Flexible assembling method of four-connecting-rod floating ship unloader |
CN109607231A (en) * | 2018-12-11 | 2019-04-12 | 湖南长重机器股份有限公司 | A kind of Wind-proof mechanism of bucket-wheel stacker reclaimer |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202463955U (en) | Non-snubbing equipment trailer | |
CN202785258U (en) | Hoisting device for air overturn of large-sized steel column | |
CN101880006B (en) | Roll-on device and method for large fixed type rotary crane | |
CN203740915U (en) | Gantry crane boom system mounting device | |
CN202358850U (en) | Light lift-type cantilever crane | |
CN205222517U (en) | Multi -functional gantry crane | |
CN102730577B (en) | Detachable propeller strut for crane | |
CN204369434U (en) | Prefabricated non-slag rail plate air turning device | |
CN104003296B (en) | The aerial counterpart bracket of a kind of removable large diameter pipeline | |
CN207328748U (en) | A kind of quick auxiliary device for realizing transverse bulkhead lifting positioning and construction safety | |
CN202785365U (en) | Bridge-type cross-rail crane | |
CN207774678U (en) | A kind of detachable walking boom hoisting | |
CN207418152U (en) | Rolling type conveying device for solving inter-span hoisting dead angle in factory building | |
CN201372159Y (en) | Monorail trolley | |
CN105947888B (en) | A kind of quayside container crane Novel bogie anchoring device | |
CN204823869U (en) | Double girder overhead crane | |
CN203222427U (en) | Underground lifting system | |
CN205419582U (en) | Floor hoist | |
CN202609437U (en) | Pulley vehicle for conveying spherical tank safety valve | |
CN211545762U (en) | Tool for plugging vertical large-pipe-diameter pipeline blind plate | |
CN204873461U (en) | Driving hook assembly | |
CN203833467U (en) | Movable large-diameter pipeline air opening alignment bracket | |
CN203998700U (en) | Transport trolley with two hanging apparatus | |
CN103387179A (en) | Gravity center self-adaptive crawler guide wheel mounting spreader | |
CN204588497U (en) | The vertical dolly of a kind of high elevator that hoists |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of utility model: Gantry crane boom system mounting device Effective date of registration: 20180503 Granted publication date: 20140730 Pledgee: Xiangtan Jiuhua Economic Construction Investment Co.,Ltd. Pledgor: TIDFORE INTERNATIONAL ENGINEERING Co.,Ltd.|TIDFORE HEAVY INDUSTRY Co.,Ltd.|TIDFORE OCEAN ENGINEERING EQUIPMENT (TIANJIN) Co.,Ltd. Registration number: 2018430000029 |
|
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20140730 |