CN203684192U - Offshore jacket production platform - Google Patents

Offshore jacket production platform Download PDF

Info

Publication number
CN203684192U
CN203684192U CN201420010829.5U CN201420010829U CN203684192U CN 203684192 U CN203684192 U CN 203684192U CN 201420010829 U CN201420010829 U CN 201420010829U CN 203684192 U CN203684192 U CN 203684192U
Authority
CN
China
Prior art keywords
jacket
production platform
platform
leg
jacket production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201420010829.5U
Other languages
Chinese (zh)
Inventor
刘伟
杨思明
夏志
沈晓鹏
巴砚
李达
黄冬云
蒋曙鸿
周晓红
朱海山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
CNOOC Research Institute Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
CNOOC Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, CNOOC Research Institute Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201420010829.5U priority Critical patent/CN203684192U/en
Application granted granted Critical
Publication of CN203684192U publication Critical patent/CN203684192U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model discloses an offshore jacket production platform. The jacket production platform is a six-legged jacket production platform or an eight-legged jacket production platform. Jacket legs of the six-legged jacket production platform are arranged into two rows and three columns. Jacket legs of the eight-legged jacket production platform are arranged into two rows and four columns. On the six-legged jacket production platform or the eight-legged jacket production platform, a well slot area is arranged in the area between the jacket legs in the every two adjacent columns, and a plurality of well slots are formed in each well slot area. The jacket production platform can meet the well drilling requirement of more than 40 (not equal to 40) well slots, and the problem that a jacket is eccentric is solved. Through the design of the jacket production platform, the area of a deck is reduced, steel is saved, and project investment cost of the platform is reduced.

Description

A kind of marine jacket production platform
Technical field
The utility model relates to a kind of marine jacket production platform.
Background technology
Along with offshore oil and gas field exploration and development is goed deep into, offshore oil platform forward maximizes, intensive, deep water future development, platform upper chunk overall weight also increases thereupon, no matter resource or ability can not meet oil-gas field development demand, the particularly integral installation of ton large module completely of large-scale crane ship (crane barge).Thereby floating tropsch technology can be realized the integral installation of ton large module and make up the inadequate problem of crane barge resource installation large module ability.
Conventional floating holder mounting platform bank is arranged in platform both wings, loads chunk barge and enters ship along jacket operating point is parallel to notch, and the floor space needing strengthens, and steel material is more, causes jacket bias.Conventional floating holder mounting platform is according to the required distance of drill ship, and every wing covers at most 20 mouthfuls of wells, causes both wings to arrange at most 40 mouthfuls of wells.Because both wings arrange that well head shifts to an earlier date pre-drilling well, floating holder begins to rehearse deck while installation need to be temporary fixed, transfers to design elevation after installing again.As shown in Figure 1, barge enters ship to notch chunk is installed along jacket operating point A, B axle are parallel.Its feature bank is arranged in that pre-drilling well is convenient to carry out in platform jacket both sides and later stage drill ship is in place, and jacket installation is waterproof casing at present, and production tree is lower than platform deck of sub-cellar, and platform arranges workover rig.The floor space that wellhead platform is installed in this floating holder to be needed strengthens, and steel material is more, causes jacket bias simultaneously, and every wing covers at most 20 mouthfuls of wells, causes both wings to arrange at most 40 mouthfuls of wells.Production period needs drill ship brill adjustment well in place again, and platform height overall (or deck floor height) is limited to drill ship climb altitude, unless mobilized larger drill ship.
Utility model content
The purpose of this utility model is to provide a kind of marine jacket production platform, 40 mouthfuls of (not containing) above well slots can be set on the utility model production platform, and be provided with platform rig, and upper chunk need to be dragged installation with floating.
The marine jacket production platform of one provided by the utility model, described jacket production platform is six leg jacket production platforms or eight leg jacket production platforms;
The jacket leg of described six leg jacket production platforms is arranged in 2 row 3 and is listed as;
The jacket leg of described eight leg jacket production platforms is arranged in 2 row 4 and is listed as;
On described six leg jacket production platforms or described eight leg jacket production platforms, the region between the jacket leg of adjacent column is provided with well slot district, and described well slot is provided with several well slots in district.
In described marine jacket production platform, described well slot district is located at the region between two row jacket legs, realizes floating and drags platform well slot to be arranged between jacket structure operating point, and the problem that solves platform bias is also saved a large amount of floor spaces.Can the undermost deck that begins to rehearse of normal arrangement, conveniently installation.
In described marine jacket production platform, it is one square that the line between adjacent 4 jacket legs forms.
In described marine jacket production platform, in described well slot district, be provided with 40 above well slots.
In described marine jacket production platform, described jacket production platform is provided with platform rig, be lowered to waterproof casing by described platform rig, cause riser pipe unbraced length to enlarge markedly because adapting to floating holder installation, need carry out part to waterproof casing self and strengthen.
The utlity model has following advantage:
1, the utility model jacket production platform can meet the drilling well demand of 40 mouthfuls of (not containing) above well slots.
2, the utility model jacket production platform has improved the problem of jacket bias;
3, the convenient deck that begins to rehearse that arranges of the design of the utility model jacket production platform;
4, floor space is saved in the design of the utility model jacket production platform, saves steel, reduces the construction investment cost of platform.
Accompanying drawing explanation
Fig. 1 is the structural representation of existing floating holder mounting platform.
Fig. 2 is the result schematic diagram of the utility model jacket production platform.
In figure, each mark is as follows: 1 jacket leg, 2 well slot districts.
The specific embodiment
Below in conjunction with accompanying drawing, the utility model is described further, but the utility model is not limited to following examples.
As shown in Figure 2, the top view of the marine jacket production platform providing for the utility model, this sea jacket production platform is eight leg jacket production platforms, and eight leg jacket legs 1 are wherein arranged in 2 row 4 and are listed as, and A is as shown in FIG. capable, B is capable, 1. row, 2. row, 3. row and 4. row.And the region between the jacket leg 1 of adjacent 1. row and 2. row is provided with well slot district 2, in this well slot district 2, be provided with 60 well slots (be greater than 40 mouthfuls of well slots, do not mark in figure).As shown in Figure 2, this well slot district 2 is located at the region between the capable and capable jacket leg of B of A, realizes floatingly dragging platform well slot to be arranged between jacket structure operating point, and the problem that solves platform bias is also saved a large amount of floor spaces.Can the undermost deck that begins to rehearse of normal arrangement, conveniently installation.
As depicted in figs. 1 and 2, floating holder barge adopts parallel conductive pipe support operating point A, B direction of principal axis to carry out chunk installation.In installation process, rely on tidal level, barge to adjust to carry the lifting of implementing upper chunk with the mode such as elevating mechanism, be aided with special coupling components simultaneously, complete chunk and jacket butt-joint operation.
In the utility model, on jacket production platform, be provided with platform rig (not shown), be lowered to waterproof casing by this platform rig, cause riser pipe unbraced length to enlarge markedly because adapting to floating holder installation, need carry out part to waterproof casing self and strengthen.
Above-mentioned marine jacket production platform, also can be six leg jacket production platforms; Also can be at 2. row conduit leg and 3. row jacket leg or 3. row jacket leg and 4. the region division well slot district between row jacket leg.

Claims (5)

1. a marine jacket production platform, is characterized in that: described jacket production platform is six leg jacket production platforms or eight leg jacket production platforms;
The jacket leg of described six leg jacket production platforms is arranged in 2 row 3 and is listed as;
The jacket leg of described eight leg jacket production platforms is arranged in 2 row 4 and is listed as;
On described six leg jacket production platforms or described eight leg jacket production platforms, the region between the jacket leg of adjacent column is provided with well slot district, and described well slot is provided with several well slots in district.
2. production platform according to claim 1, is characterized in that: described well slot district is located at the region between two row jacket legs.
3. production platform according to claim 2, is characterized in that: the line between adjacent 4 jacket legs forms one square.
4. production platform according to claim 3, is characterized in that: in described well slot district, be provided with 40 above well slots.
5. production platform according to claim 4, is characterized in that: described jacket production platform is provided with platform rig.
CN201420010829.5U 2014-01-08 2014-01-08 Offshore jacket production platform Expired - Lifetime CN203684192U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420010829.5U CN203684192U (en) 2014-01-08 2014-01-08 Offshore jacket production platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420010829.5U CN203684192U (en) 2014-01-08 2014-01-08 Offshore jacket production platform

Publications (1)

Publication Number Publication Date
CN203684192U true CN203684192U (en) 2014-07-02

Family

ID=51006115

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420010829.5U Expired - Lifetime CN203684192U (en) 2014-01-08 2014-01-08 Offshore jacket production platform

Country Status (1)

Country Link
CN (1) CN203684192U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758095A (en) * 2014-01-08 2014-04-30 中国海洋石油总公司 Offshore jacket production platform
CN104743058A (en) * 2015-03-24 2015-07-01 中国海洋石油总公司 Floating installation method for upper assembling block of tension leg platform
CN106741609A (en) * 2016-12-16 2017-05-31 中国海洋石油总公司 The chunk dynamic positioning floating support mounting technique of Large Offshore Structures

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758095A (en) * 2014-01-08 2014-04-30 中国海洋石油总公司 Offshore jacket production platform
CN104743058A (en) * 2015-03-24 2015-07-01 中国海洋石油总公司 Floating installation method for upper assembling block of tension leg platform
CN104743058B (en) * 2015-03-24 2017-03-29 中国海洋石油总公司 The method of tension leg platform (TLP) upper chunk floating support mounting
CN106741609A (en) * 2016-12-16 2017-05-31 中国海洋石油总公司 The chunk dynamic positioning floating support mounting technique of Large Offshore Structures

Similar Documents

Publication Publication Date Title
CN105041271B (en) A kind of buck exploiting ocean natural gas hydrates method and sub-sea production systems
CN103129715B (en) Conduit-rack semi-submersible type oil-extraction platform
US11401785B2 (en) Well structure for natural gas hydrate production
CN103738481B (en) Removable self-mounting type drilling processes oil storage platform
CN203684192U (en) Offshore jacket production platform
CN104818978A (en) One-well multi-control method for offshore low-permeability reservoir thick oil layer exploitation
CN2911009Y (en) One-leg three-pile simple platform suitable for developing medium-small oil fields in sea
CN105775056A (en) Bottom-supported production storage platform
CN106368197A (en) Mat type self-mounted platform with large wellheads
CN105292392A (en) Relocatable self-elevating drilling production platform and self-installing and recycling method thereof
CN104088266A (en) Standardized movable wellhead platform installed in floatover mode
CN105003232A (en) Ultra-deep marine oil and gas dry type production system, installing method of ultra-deep marine oil and gas dry type production system and evacuating method of ultra-deep marine oil and gas dry type production system
CN202389573U (en) Oil and gas field engineering development system of extreme deepwater ocean
CN104250969A (en) Piling-assisting submersible production oil storage and discharge platform penetrating upper ship body and lower ship body
CN203808035U (en) Ultra-large wellhead platform
CN102514692B (en) Ultradeep sea oil-gas field engineering development system
CN103758095A (en) Offshore jacket production platform
CN203846472U (en) Pilot production wellhead platform
CN201310089Y (en) Offshore wellhead platform supported by water-proof sleeve pipes
CN203698617U (en) Movable self-mounting-type drilling and production processing oil storage platform
CN203767043U (en) Tension leg platform
CN103879524B (en) A kind of tension leg platform (TLP)
CN103953022A (en) Supersized wellhead platform
CN104290866A (en) Split type dock construction method of self-elevating production platform and oil storing and discharging platform
CN204000813U (en) A kind of standardization that adopts floating holder method to install can be moved formula wellhead platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100010 Beijing, Chaoyangmen, North Street, No. 25, No.

Co-patentee after: CNOOC RESEARCH INSTITUTE Co.,Ltd.

Patentee after: CHINA NATIONAL OFFSHORE OIL Corp.

Address before: 100010 Beijing, Chaoyangmen, North Street, No. 25, No.

Co-patentee before: CNOOC Research Institute

Patentee before: CHINA NATIONAL OFFSHORE OIL Corp.

CX01 Expiry of patent term