CN203639925U - Supporting pile body with waterproof curtains around foundation pit - Google Patents
Supporting pile body with waterproof curtains around foundation pit Download PDFInfo
- Publication number
- CN203639925U CN203639925U CN201320818999.1U CN201320818999U CN203639925U CN 203639925 U CN203639925 U CN 203639925U CN 201320818999 U CN201320818999 U CN 201320818999U CN 203639925 U CN203639925 U CN 203639925U
- Authority
- CN
- China
- Prior art keywords
- cement
- stop curtain
- pile body
- foundation pit
- supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 239000002689 soil Substances 0.000 claims description 27
- 239000004567 concrete Substances 0.000 claims description 16
- 229910000831 Steel Inorganic materials 0.000 claims description 15
- 239000010959 steel Substances 0.000 claims description 15
- 238000007789 sealing Methods 0.000 claims description 8
- 238000010276 construction Methods 0.000 abstract description 18
- 239000011150 reinforced concrete Substances 0.000 abstract description 11
- 239000004568 cement Substances 0.000 abstract description 10
- 238000000034 method Methods 0.000 abstract description 2
- 238000005516 engineering process Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- 238000009825 accumulation Methods 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
The utility model discloses a supporting pile body with waterproof curtains around a foundation pit. The supporting pile body solves the technical problems that in the prior art, the construction operation face is large, and the construction costs are high. The supporting pile body comprises the foundation pit (1), the sealed cement waterproof curtains (2) are arranged on the side faces of the periphery of the foundation pit (1), reinforced concrete supporting piles (3) are arranged on the outer sides of the sealed cement waterproof curtains (2) at intervals, the reinforced concrete supporting piles (3) are meshed with the sealed cement waterproof curtains (2), and when the reinforced concrete supporting piles (3) and the sealed cement waterproof curtains (2) are meshed, the largest meshing thickness is 250 mm. The supporting pile body is simple in construction process and low in construction cost and ensures the safety of the surrounding building.
Description
Technical field
The utility model relates to a kind of soldier pile, particularly the supporting pile body of a kind of foundation ditch sealing and soldier pile interlock.
Background technology
Along with social development and the progress of urban construction, due to the growing tension of building land, impel building to develop to high-altitude.Build highrise building and generally all be unable to do without deep pit digging.Also more and more less in the old construction operation space of adjoining between inhering architecture and new proposed building, in limited operating distance, carry out pattern foundation pit supporting structure, reach the sealing of foundation ditch and guarantee the safety of foundation ditch, become difficult point and the emphasis of foundation pit supporting project.For the sealing requirement of excavation of foundation pit, the following two kinds of construction methods of the general employing of prior art.The first is carried out reinforced concrete pile supporting and cement-soil curtain water stop; It two is to utilize steel sheet pile self support characteristic to carry out pile body to improve to carry out sealing.Above-mentioned two kinds of methods have certain limitation, and the first construction technology is simple, easy to operate, cheap, but constructing operation face is large; The second applicability is wide, and safety factor is high, but construction costs is high.
Summary of the invention
The utility model provides a kind of supporting pile body of foundation ditch surrounding band water-stop curtain, solved the large and high technical problem of construction costs of constructing operation face that prior art exists.
The utility model is to solve by the following technical programs above technical problem:
A kind of supporting pile body of foundation ditch surrounding band water-stop curtain, comprise foundation ditch, be provided with the cement-soil water-stop curtain of sealing in the surrounding side of foundation ditch, compartment of terrain, outside at cement-soil water-stop curtain is provided with steel concrete soldier pile, steel concrete soldier pile and cement-soil water-stop curtain are interlocked, and the maximum interlock thickness that steel concrete soldier pile and cement-soil water-stop curtain are interlocked is 250 millimeters.
Be provided with and pass through beam on the top of steel concrete soldier pile.
The pile body that a kind of sealing that the utility model provides is combined with supporting, is particularly suitable for the construction operation difficult problem for the working space of inadequate 1.75 meters of next-door neighbour surrounding building operating space; Construction technology is simple, and construction costs is low, has ensured the safety of surrounding building.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the structural representation in cross section of the present utility model.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is elaborated:
A kind of supporting pile body of foundation ditch surrounding band water-stop curtain, comprise foundation ditch 1, be provided with the cement-soil water-stop curtain 2 of sealing in the surrounding side of foundation ditch 1, compartment of terrain, outside at cement-soil water-stop curtain 2 is provided with steel concrete soldier pile 3, steel concrete soldier pile 3 is interlocked with cement-soil water-stop curtain 2, and steel concrete soldier pile 3 is 250 millimeters with the maximum interlock thickness 4 that cement-soil water-stop curtain 2 is interlocked.
Be provided with and pass through beam 5 on the top of steel concrete soldier pile 3.
The utility model has changed the usual practice of former construction, cement-soil water-stop curtain and reinforced concrete pile supporting position have been carried out to evolution, and carry out anti-stake mechanics check computation, and supporting scheme checking computations and demonstration, check the technical data of cement-soil water-stop curtain and reinforced concrete pile, and the relation of definite foundation ditch sideline and cement-soil water-stop curtain and the position of cement-soil water-stop curtain and reinforced concrete pile.Carry out the construction of cement-soil water-stop curtain, to cement-soil water-stop curtain unwrapping wire, draw control point, stake position outward at cement-soil water-stop curtain, utilize cement-soil water-stop curtain control point to draw control point, reinforced concrete pile stake position, reduce the accumulation of error, guarantee cement-soil water-stop curtain construction axis and structural drawings axial line distance, error is controlled at carries out operation in 10 millimeters; When cement-soil water-stop curtain starts to construct, the test cube in the same condition that utilizes cement-soil water-stop curtain self material to make by professional is differentiated the cement-soil water-stop curtain initial setting time, utilize the actual test cube in the same condition of job site and laboratory provide cement-soil water-stop curtain material just, the report of final setting time, control activity duration of reinforced concrete pile.In reinforced concrete pile operation, strictly control the size of interlock between cement-soil water-stop curtain and reinforced concrete pile, carry out steel concrete pile driving construction.
The utility model is to carry out anti-pile driving construction in 6 hours that have constructed to cement initial set by cement water-stop curtain, utilize cement water-stop curtain self material to carry out mud off, in cement water-stop curtain, adopt the boring of percussive drill retaining wall, reinforcing cage is winched in boring with crane, and carry out concrete building by conduit, in shortening water-stop curtain, the setting time interval of cement and anti-pile concrete, finally makes the stake of steel concrete poured support and the complete interlock of cement water-stop curtain stake.
Claims (2)
1. the supporting pile body of a foundation ditch surrounding band water-stop curtain, comprise foundation ditch (1), it is characterized in that, be provided with the cement-soil water-stop curtain (2) of sealing in the surrounding side of foundation ditch (1), be provided with steel concrete soldier pile (3) in the compartment of terrain, outside of cement-soil water-stop curtain (2), steel concrete soldier pile (3) is interlocked with cement-soil water-stop curtain (2), and steel concrete soldier pile (3) is 250 millimeters with the maximum interlock thickness (4) that cement-soil water-stop curtain (2) is interlocked.
2. the supporting pile body of a kind of foundation ditch surrounding band water-stop curtain according to claim 1, is characterized in that, is provided with and passes through beam (5) on the top of steel concrete soldier pile (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320818999.1U CN203639925U (en) | 2013-12-13 | 2013-12-13 | Supporting pile body with waterproof curtains around foundation pit |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320818999.1U CN203639925U (en) | 2013-12-13 | 2013-12-13 | Supporting pile body with waterproof curtains around foundation pit |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203639925U true CN203639925U (en) | 2014-06-11 |
Family
ID=50871183
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320818999.1U Expired - Lifetime CN203639925U (en) | 2013-12-13 | 2013-12-13 | Supporting pile body with waterproof curtains around foundation pit |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203639925U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109403336A (en) * | 2018-09-28 | 2019-03-01 | 上海建工七建集团有限公司 | A kind of closing foundation ditch side dilapidated house protects structure and its construction method |
CN109811774A (en) * | 2018-06-14 | 2019-05-28 | 江西基良工程机械设备有限公司 | A kind of continuous barricade of deep basal pit and its construction method |
-
2013
- 2013-12-13 CN CN201320818999.1U patent/CN203639925U/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109811774A (en) * | 2018-06-14 | 2019-05-28 | 江西基良工程机械设备有限公司 | A kind of continuous barricade of deep basal pit and its construction method |
CN109403336A (en) * | 2018-09-28 | 2019-03-01 | 上海建工七建集团有限公司 | A kind of closing foundation ditch side dilapidated house protects structure and its construction method |
CN109403336B (en) * | 2018-09-28 | 2020-12-11 | 上海建工七建集团有限公司 | Dangerous house protection structure near foundation pit and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100465386C (en) | Pile-anchor foundation ditch supporting construction method | |
CN109723085B (en) | Deep foundation pit division construction rib wall support replacing structure and construction method thereof | |
CN104099943B (en) | Diaphram wall and discarded underground civil defense engineering intersection processing method | |
CN103924602B (en) | Deep Thick Soft Ground foundation ditch construction method | |
CN204418187U (en) | Subway protection region soil nail wall is in conjunction with double-row pile deep foundation ditch composite supporting construction | |
CN103938634B (en) | A kind of deep foundation pit supporting structure and construction method | |
CN102943479A (en) | System and method for controlling deformation of deep and large foundation pit through partition unloading | |
CN102116030A (en) | Combined bracing structure for foundation pit and construction method thereof | |
CN203229955U (en) | Foundation pit enclosure structure allowing supporting while excavating | |
CN102444143A (en) | Construction method for cancelling operation channel for facades of basement | |
CN205100989U (en) | Utilize oblique access structure of subway access & exit double as construction | |
CN203161244U (en) | Existing subway underground excavation running tunnel protection structure | |
CN103939115A (en) | Semi-subsurface excavation method construction shed tunnel method and structure | |
CN110055973B (en) | Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method | |
CN103147444A (en) | Foundation pit enclosure structure capable of realizing supporting while excavating and foundation pit excavating method | |
CN203639925U (en) | Supporting pile body with waterproof curtains around foundation pit | |
CN102220764B (en) | Construction method of deep foundation pit bracing system | |
CN111501771A (en) | Application method of multi-elliptical-ring combined support in deep large-sludge foundation pit engineering | |
CN102767187A (en) | Reverse construction method for pebble foundation swirling well | |
CN203530958U (en) | Thin-wall prefabricated overlapped concrete underground diaphragm wall | |
CN106088758B (en) | A kind of bilayer assembled underground granary | |
CN205382942U (en) | Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility | |
CN103527217B (en) | Small-curvature-radius shield tunnel duct piece under dense pile foundation environment and manufacturing method thereof | |
CN202370539U (en) | Front tunnel face excavated soil pre-reinforcing structure of tunnel | |
CN106088762B (en) | A kind of prefabricated assembled round underground granary of insertion slot type encased steel plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20140611 |