CN203625409U - High-pressure top charging device - Google Patents

High-pressure top charging device Download PDF

Info

Publication number
CN203625409U
CN203625409U CN201320802498.4U CN201320802498U CN203625409U CN 203625409 U CN203625409 U CN 203625409U CN 201320802498 U CN201320802498 U CN 201320802498U CN 203625409 U CN203625409 U CN 203625409U
Authority
CN
China
Prior art keywords
high pressure
hopper
material flow
top charging
charging equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320802498.4U
Other languages
Chinese (zh)
Inventor
师磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beris Engineering and Research Corp
Original Assignee
Beris Engineering and Research Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beris Engineering and Research Corp filed Critical Beris Engineering and Research Corp
Priority to CN201320802498.4U priority Critical patent/CN203625409U/en
Application granted granted Critical
Publication of CN203625409U publication Critical patent/CN203625409U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

The utility model provides a high-pressure top charging device which comprises a receiving hopper for accommodating furnace burdens; a baiting valve, an upper high-pressure seal valve, a high-pressure burden tank and a material flow regulating valve are sequentially connected below the receiving hopper, the high-pressure top charging device is also provided with a feeding tube which is correspondingly connected to the bottom of the material flow regulating valve, and due to the length of the feeding tube, the lower end of the feeding tube extends to the inside of a shaft furnace. According to the high-pressure top charging device, transmission devices are reduced, and the high-pressure top charging device is easy to install, repair and maintain, thereby effectively reducing the construction investment cost and the maintenance cost.

Description

A kind of high pressure top charging equipment
Technical field
The utility model relates to a kind of ironmaking technology field, relates in particular to a kind of high pressure top charging equipment.
Background technology
In metallurgical industry field, existing loading device is clock-type loading device and feeder apparatus.Clock-type loading device weight is large, and stopping property is poor, cannot meet high pressure and produce.
But without bell equipment complexity, distribution chute is changed frequent, although operating pressure increases compared with clock-type loading device, still can not meet the demands for the shaft furnace operating mode of 0.4-0.6Mpa.
Because high pressure top charging equipment of the prior art exists above-mentioned defect, therefore those skilled in the art need a kind of new high pressure top charging equipment of research and development badly.
Summary of the invention
The technical problems to be solved in the utility model is to provide a kind of high pressure top charging equipment, reduces transmission mechanism, is easy to install, overhauls, safeguards, has effectively reduced construction investment expense and maintenance cost.
For achieving the above object, the utility model provides a kind of high pressure top charging equipment, comprises the hopper for holding furnace charge; The below of described hopper is connected with in turn: baiting valve, top high pressure seal valve, high pressure batch can and material flow gate, also have: supply pipe, it is connected to the bottom of described material flow gate accordingly, and the length of described supply pipe makes its lower end stretch into the inside of shaft furnace.
Further, be provided with material fluidic distributor in the inside of described hopper.
Further, according to the charging capacity of hopper, the quantity of described high pressure batch can is set to multiple, is arranged on to multiple high pressure batch can block forms the below of top high pressure seal valve.
Further, according to the charging capacity of hopper, the quantity of described material flow gate is set to multiple, and multiple material flow gates are connected to the below of multiple high pressure batch cans accordingly side by side.
Further, according to the charging capacity of hopper, the quantity of described supply pipe is set to multiple, and on the top of shaft furnace, section distributes equably, and multiple supply pipes are connected to the below of multiple material flow gates accordingly side by side.
Further, between each described material flow gate and supply pipe, be also provided with accordingly bottom high pressure seal valve.
Further, according to the charging capacity of hopper, the quantity of described baiting valve is set to multiple.According to the utility model, by using connected structure, reduce transmission mechanism, equipment is simple, and Maintenance and Repair are convenient, reduced construction investment and the materials consumption expense of top charging equipment simultaneously.Material is flowed through hopper by multiple baiting valves, high pressure batch can, material flow gate and supply pipe, can point single channel or multichannel enter in high pressure shaft furnace, to reduce the segregation of furnace charge.And can meet the shaft furnace working condition requirement of 0.4-0.6Mpa.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the utility model is elaborated.Wherein:
Fig. 1 is according to the structural representation of a kind of high pressure top charging equipment of the present utility model.
Embodiment
Below, by exemplary embodiment, the utility model is specifically described.But should be appreciated that element, structure and the feature in an embodiment also can be attached in other embodiment valuably in the situation that further not narrating.
In conjunction with Fig. 1, it shows a kind of high pressure top charging equipment, comprises hopper 1, for holding furnace charge; At least one baiting valve 3, is connected to the bottom of this hopper 1, for furnace charge in hopper is tending towards evenly, rationally to the cloth in following high pressure batch can, guarantees the symmetry that furnace charge distributes in high pressure batch can, reduces charging segregation; At least one high pressure batch can 5, is connected to the below of baiting valve 3 accordingly; At least one material flow gate 6, is connected to the bottom of this high pressure batch can 5 accordingly, for regulating material Flow Velocity or the material stream time of furnace charge, to guarantee all even reasonableness in cloth process.
Be worth being, at least one supply pipe 8 is connected to the bottom of described material flow gate 6 accordingly with pointing out, and distributes equably at the top of shaft furnace 9 section, and the inside of shaft furnace 9 is stretched in the lower end of described supply pipe 8.Supply pipe is uniformly distributed, to reduce the segregation of furnace charge.
Be preferably, the utility model also has material fluidic distributor 2, is arranged on the inside of this hopper 1, for making furnace charge in dropping process is evenly distributed in hopper, and furnace charge is played to shock absorption.
In order to guarantee the structural compactness of top charging equipment, the receiving opening of described baiting valve 3 is connected to the bottom port of described hopper 1 by connected structure.Meanwhile, the receiving opening of described material flow gate 6 is also connected to the bottom port of described high pressure batch can 5 by connected structure.
In order to guarantee the stopping property of equipment, between described baiting valve 3 and high pressure batch can 5, be also provided with accordingly at least one top high pressure seal valve 4, for when batch can is to sealing coal gas in stove when blanking.In like manner, in order to guarantee the stopping property of equipment, between described material flow gate 6 and supply pipe 8, be also provided with accordingly at least one bottom high pressure seal valve 7.
In the situation that opening baiting valve 3 and top high pressure seal valve 4, the furnace charge in hopper 1 enters high pressure batch can 5, after the furnace charge in hopper all enters high pressure batch can 5, closes baiting valve 3, and at this moment hopper 1 prepares to receive another batch of furnace charge.According to charging capacity, material flow through hopper can point single channel or multichannel enter in high pressure shaft furnace.
Alternatively, the quantity of described material flow gate 6 can be set to multiple.According to the charging capacity of hopper 1, the quantity of described baiting valve 3 and supply pipe 8 can be set to multiple.Meanwhile, the quantity of described top high pressure seal valve 4 and bottom high pressure seal valve 7 also can be set to multiple.Specifically, as shown in Figure 1, according to a kind of specific embodiment of the present utility model, be respectively arranged with four baiting valves 3, four top high pressure seal valves 4, four high pressure batch cans 5, four bottom high pressure seal valves 7, four supply pipes 8.
The quantity that should be appreciated that baiting valve 3, top high pressure seal valve 4, high pressure batch can 5, bottom high pressure seal valve 7 and supply pipe 8 herein can be established according to actual need of production, does not have limitation.
In sum, according to high pressure top charging equipment of the present utility model, reduce transmission mechanism, be easy to install, overhaul, safeguard, can effectively reduce the whole height of loading device, therefore make its whole top charging equipment compact construction, reduced construction investment and the materials consumption expense of top charging equipment simultaneously.
Be appreciated that the utility model is described by some embodiment, those skilled in the art know, in the situation that not departing from spirit and scope of the present utility model, can carry out various changes or equivalence replacement to these features and embodiment.In addition, under instruction of the present utility model, can modify to adapt to concrete situation and material and can not depart from spirit and scope of the present utility model these features and embodiment.Therefore, the utility model is not subject to the restriction of specific embodiment disclosed herein, and the embodiment within the scope of all the application's of falling into claim belongs to protection domain of the present utility model.

Claims (7)

1. a high pressure top charging equipment, comprises the hopper (1) for holding furnace charge; The below of described hopper (1) is connected with in turn: baiting valve (3), top high pressure seal valve (4), high pressure batch can (5), and material flow gate (6), it is characterized in that,
Also have: supply pipe (8), it is connected to the bottom of described material flow gate (6) accordingly, and the length of described supply pipe (8) makes its lower end stretch into the inside of shaft furnace (9).
2. high pressure top charging equipment as claimed in claim 1, is characterized in that, is provided with material fluidic distributor (2) in the inside of described hopper (1).
3. high pressure top charging equipment as claimed in claim 1, it is characterized in that, according to the charging capacity of hopper (1), the quantity of described high pressure batch can (5) is set to multiple, is arranged on to multiple high pressure batch cans (5) block form the below of top high pressure seal valve (4).
4. high pressure top charging equipment as claimed in claim 1, it is characterized in that, according to the charging capacity of hopper (1), the quantity of described material flow gate (6) is set to multiple, and multiple material flow gates (6) are connected to the below of multiple high pressure batch cans (5) accordingly side by side.
5. high pressure top charging equipment as claimed in claim 1, it is characterized in that, according to the charging capacity of hopper (1), the quantity of described supply pipe (8) is set to multiple, top section at shaft furnace (9) distributes equably, and multiple supply pipes (8) are connected to the below of multiple material flow gates (6) accordingly side by side.
6. high pressure top charging equipment as claimed in claim 1, is characterized in that, between each described material flow gate (6) and supply pipe (8), is also provided with accordingly bottom high pressure seal valve (7).
7. high pressure top charging equipment as claimed in claim 1, is characterized in that, according to the charging capacity of hopper (1), the quantity of described baiting valve (3) is set to multiple.
CN201320802498.4U 2013-12-09 2013-12-09 High-pressure top charging device Expired - Fee Related CN203625409U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320802498.4U CN203625409U (en) 2013-12-09 2013-12-09 High-pressure top charging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320802498.4U CN203625409U (en) 2013-12-09 2013-12-09 High-pressure top charging device

Publications (1)

Publication Number Publication Date
CN203625409U true CN203625409U (en) 2014-06-04

Family

ID=50811902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320802498.4U Expired - Fee Related CN203625409U (en) 2013-12-09 2013-12-09 High-pressure top charging device

Country Status (1)

Country Link
CN (1) CN203625409U (en)

Similar Documents

Publication Publication Date Title
CN203855164U (en) Pulverized coal pneumatic conveyor
CN101709340B (en) Single-bucket serial-bucket charging method applied to bell-free blast furnaces
CN101875988A (en) Pressure-equalizing and discharging process for J-shaped sealing water pipe type blast furnace top
CN104180662A (en) Annular sleeve shaft kiln fixing distributor
CN203625409U (en) High-pressure top charging device
CN204544388U (en) The grinding machine feeding system of band metering choke preventing function
CN201447291U (en) Hydraulic pressure basis weight self-service loading device
CN202226871U (en) Material feeding device at compact bell-less furnace top of blast furnace
CN201961727U (en) Pneumatic block clearing device for coal dropping pipe
CN105368999B (en) Blast furnace bucket Weighing system blow device and technique
WO2009144521A3 (en) Steelmaking facility comprising a direct reduction plant and an electric-arc furnace
CN207159161U (en) A kind of hydrogasification pulverized coal conveying device
CN102923974B (en) Swirl type cooling system of sleeve limekiln
CN202626216U (en) Blast furnace bell-free top charging device
CN202625394U (en) Quantitative feeding device
CN102925614A (en) Material discharge device for vertical furnace
CN103695583B (en) A kind of Electromechanical integration test device of blast furnace
CN104086100A (en) Lime kiln distributing device
CN201981216U (en) Long-distance injection device for coal powder injection of blast furnace
CN102061347B (en) In-series merging arrangement process for two blast furnace ore coke groove systems
CN106399609A (en) Process system and method for blast furnace injection sintering mine returning
CN102605121A (en) Blast furnace bell-less top charging device
CN204714120U (en) Control the material blanking tube of powder storing bin blanking airborne dust
CN202912995U (en) Blowdown device of shaft furnace
CN102134622B (en) Bell-less blast furnace distributing device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140604

Termination date: 20171209

CF01 Termination of patent right due to non-payment of annual fee