CN203587747U - Porcelain insulator insulation testing device - Google Patents

Porcelain insulator insulation testing device Download PDF

Info

Publication number
CN203587747U
CN203587747U CN201320777445.1U CN201320777445U CN203587747U CN 203587747 U CN203587747 U CN 203587747U CN 201320777445 U CN201320777445 U CN 201320777445U CN 203587747 U CN203587747 U CN 203587747U
Authority
CN
China
Prior art keywords
vertical pole
snap ring
take
porcelain insulator
semicircular ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320777445.1U
Other languages
Chinese (zh)
Inventor
张迪
孙军鹏
郑伟
郭帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shangqiu Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Shangqiu Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shangqiu Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical Shangqiu Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority to CN201320777445.1U priority Critical patent/CN203587747U/en
Application granted granted Critical
Publication of CN203587747U publication Critical patent/CN203587747U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Insulators (AREA)

Abstract

The utility model belongs to a high voltage appliance measuring device and especially relates to a porcelain insulator insulation testing device. The device also comprises a first vertical pole which is connected with one end of a horizontal pole through a universal ball. Two sides of the horizontal pole body are provided with pulleys. The other end of the horizontal pole is connected with a second vertical pole. Upper and lower ends of the second vertical pole are respectively provided with an upper snap ring and a lower snap ring. Each of the snap rings is composed of two semicircular rings connected through a spring. One end of the semicircular ring is connected with the second vertical pole, and the inner wall at the end portion of the semicircular ring is provided with a measuring head which is connected with a megger. The outer wall of the semicircular ring is provided with a pin which is connected with one end of a thread. The thread is erected on the pulley. The other end of the thread is connected with a take-up device arranged on the first vertical pole. According to the utility model, an insulation test can be rapidly and effectively carried out on single insulators which form a porcelain insulator chain.

Description

A kind of porcelain insulator insulated test device
Technical field
The utility model belongs to high-tension electricity apparatus measurement mechanism, relates in particular to a kind of porcelain insulator insulated test device.
Background technology
Insulator chain is interconnected and is conspired to create by chapeau de fer at multi-disc insulator two ends, is the important device of isolation charging equipment, therefore regularly the insulating property of insulator chain is tested particularly important.At present, the usual method of measuring porcelain insulator insulating property is: after electrical equipment has a power failure, maintainer is by operation bucket arm vehicle hoistable platform, platform is risen to suitable height, by the scissors-type clip of megger p-wire on the chapeau de fer of monolithic porcelain insulator two ends, then, after operating bucket arm vehicle hoistable platform and making personnel apart from the certain safe distance of porcelain insulator, start the dielectric test of monolithic insulator.Then by same step by lifting bucket arm vehicle operator's console, to forming all monolithic insulator sheets of porcelain insulator string, measure successively.There is multiple potential safety hazard in operation like this, and first, scissors-type clip, when being subject to external force, particularly operating bucket arm vehicle and easily touches and come off by mistake, come off meeting accidental injury personnel and the equipment of wire clamp; Secondly, while measuring bunch of insulator, the lifting of bucket arm vehicle operating platform is frequent, controls slightly deviation, easily equipment is caused to artificial injury; Again, maintainer is contact measured examination equipment continually directly, and the residual voltage on megger forms security threat to tester.
Utility model content
The purpose of this utility model is to provide a kind of simple in structure, and design is a kind of porcelain insulator insulated test device cleverly.The utility model can fast and effeciently carry out Insulation test to forming the monolithic insulator of porcelain insulator string.
For solving the problems of the technologies described above, the technical solution adopted in the utility model is as follows:
A kind of porcelain insulator insulated test device, comprise megger, described device also comprises the first vertical pole, the first vertical pole is connected with horizontal strut one end by multi-directional ball, on the horizontal strut body of rod, both sides are provided with pulley, the horizontal strut other end is connected with the second vertical pole, the second vertical pole upper/lower terminal is respectively equipped with snap ring and lower snap ring, upper and lower snap ring is respectively the annulus being comprised of two semicircular ring that connect by spring, semicircular ring one end is connected with the second vertical pole, semicircular ring inner wall of end is provided with measuring head, and measuring head is connected with megger; Semicircular ring outer wall is provided with pin, and pin is connected with clue one end, and clue is erected on pulley, and the other end is connected with the take-up being arranged on the first vertical pole.
The semicircular ring that forms upper and lower snap ring is connected with the second vertical pole by hinge, during work, by take-up, clue is received and twined, clue is by pulley and pin, the semicircular ring that forms upper snap ring and lower snap ring is pulled open, then by multi-directional ball, regulate the position of horizontal strut, the upper snap ring of folding and lower snap ring are probeed in the full skirt between adjacent two insulators, make upper and lower snap ring block respectively chapeau de fer at monolithic insulator two ends.Then by take-up, clue is lengthened, two semicircular ring that form respectively upper and lower snap ring are combined into circular upper and lower snap ring under the pulling force of spring, on upper and lower snap ring, tightly block chapeau de fer at monolithic insulator two ends, make measuring head on upper and lower snap ring respectively at the chapeau de fer contact at insulator two ends, then staff carries out insulation measurement by megger to monolithic insulator.
Preferably, the end face of described pulley is provided with baffle plate.
The design of baffle plate, prevents that clue from tightening up with separated with pulley in the process of loosening effectively.
Preferably, the first described vertical pole is expansion link, between its extension rod and fixed bar, is provided with locking member, and take-up is arranged on the fixed bar of the first vertical pole.
The first vertical pole is expansion link, its length can regulate, then by locking member, temporarily fix this length, expansion link coordinates the rotation of multi-directional ball, staff can be in the situation that keeping bucket arm vehicle hoistable platform height not adjust, realize the contacting of monolithic insulator two ends chapeau de fer of measuring head and differing heights, improved testing efficiency.Described expansion link, fixed bar and locking member are all prior art, specifically can be referring to the stretching structure of the mop handle in prior art products.
Preferably, the second described vertical pole is expansion link, and its extension rod body of rod is connected with the semicircular ring that forms upper snap ring; Its fixed bar is connected with the semicircular ring that forms lower snap ring, and the fixed bar of the second vertical pole is connected with horizontal strut.
Insulator due to different model, the spacing of its two ends chapeau de fer is different, and the second vertical pole is designed to expansion link, can reasonably regulate the spacing of upper and lower snap ring, it is coordinated with needing the monolithic insulator two ends sub-spacing of chapeau de fer of measuring, then measure.The Telescopic shaft type design of the second vertical pole, can adopt ripe design of the prior art.
Preferably, described take-up comprises first, second connecting rod, and first connecting rod one end is fixedly connected with the first vertical pole, the first connecting rod other end is provided with take-up reel, take-up reel is connected with second connecting rod, and second connecting rod is connected with handle is vertical, and take-up reel is connected with clue.
Take-up is received while twining clue, by handle, drive second connecting rod, indirectly drive take-up reel to rotate, clue is wrapped on take-up reel, the clue other end, by pin, drives the semicircular ring that forms upper and lower snap ring, overcomes spring tension, around the second vertical pole, rotate, realize the open configuration of upper and lower snap ring; When take-up lengthens to clue, by handle, drive second connecting rod, indirectly drive and rotate backward around take-up reel, clue on take-up reel is unclamped, clue lengthens, form the semicircular ring of upper and lower snap ring under spring tension effect, around the second vertical pole backwards rotation, realize the closure state of upper and lower snap ring.
Compared with prior art, tool has the following advantages the utility model:
1) simple in structure, reasonable in design, be combined into respectively between upper and lower snap ring semicircular ring and pass through spring straining, the measuring head on its upper and lower snap ring inwall is tight respectively at the chapeau de fer contact at monolithic insulator two ends, is difficult for disengaging;
2) first, second vertical strut lengths of the present utility model can regulate, join and the horizontal strut being connected with the first vertical pole by multi-directional ball, realized the utility model under the prerequisite that keeps bucket arm vehicle hoistable platform height not adjust, the monolithic insulator of different model, differing heights has been carried out to insulating property measurement.
Accompanying drawing explanation
Fig. 1 is the utility model structure front elevational schematic;
Fig. 2 tries schematic diagram after the utility model structure;
Fig. 3 is upper snap ring closure state partial structurtes schematic diagram in the utility model;
Fig. 4 is upper snap ring open configuration partial structurtes schematic diagram in the utility model.
Embodiment
In order to make the purpose of this utility model, technical scheme and advantage clearer, below in conjunction with drawings and Examples, the utility model is further elaborated.Should be appreciated that specific embodiment described herein is only in order to explain the utility model, and be not used in restriction the utility model.
As Figure 1-4, a kind of porcelain insulator insulated test device, comprise megger 21, described device also comprises the first vertical pole, and the first vertical pole is expansion link, between its extension rod 2 and fixed bar 1, is provided with locking member 3, the fixed bar 1 of the first vertical pole is fixedly connected with first connecting rod 13 one end, first connecting rod 13 other ends are provided with take-up reel 14, and take-up reel 14 is provided with second connecting rod 15, and second connecting rod 15 is connected with handle 16 is vertical; The extension rod 2 of the first vertical pole is connected with horizontal strut 5 one end by multi-directional ball 4, on horizontal strut 5 bodies of rod, both sides are provided with pulley 6, the end face of pulley 6 is provided with baffle plate 17, horizontal strut 5 other ends are connected with the second vertical pole, the second vertical pole is expansion link, and extension rod 7 bodies of rod of the second vertical pole are hinged by hinge with the semicircular ring that forms upper snap ring 9; The fixed bar 8 of the second vertical pole is hinged by hinge with the semicircular ring that forms lower snap ring 10, two semicircular ring that form respectively upper snap ring 9 and lower snap ring 10 are connected by spring 19, semicircular ring inner wall of end is provided with measuring head 18, and measuring head 18 is connected with megger 21 by wire 20; Semicircular ring outer wall is provided with pin 11, and pin 11 is connected with clue 12 one end, and clue 12 is erected on pulley 6, and clue 12 other ends are connected with take-up reel 14.
During work, staff tests the spacing of monolithic insulator two ends chapeau de fer as required, the upper snap ring 9 on adjusting the second vertical pole and the spacing of lower snap ring 10; And then according to staff's position and the distance that need to test monolithic insulator, regulate the length of the first vertical pole, simultaneously by multi-directional ball 4, regulate horizontal strut 5 with respect to the angle of monolithic insulator.After adjusting, by handle 16, drive second connecting rod 15, indirectly drive around take-up reel 14 and rotate, clue 12 is wrapped on take-up reel 14, clue 14 other ends are by pin 11, drive and form upper snap ring 9, the semicircular ring of lower snap ring 10, overcome spring 19 pulling force, around the second vertical pole, rotate, in realization, snap ring 9, the open configuration of lower snap ring 10, the upper snap ring 9 opening and lower snap ring 10 are probeed in the full skirt between adjacent two insulators, make snap ring 9, lower snap ring 10 contacts with chapeau de fer at monolithic insulator two ends respectively, then by handle 16, drive second connecting rod 15, indirectly drive and rotate backward around take-up reel 14, clue on take-up reel 14 12 is unclamped, clue 12 lengthens, on composition, snap ring 9, the semicircular ring of lower snap ring 10 is under spring 19 pulling force effects, around the second vertical pole backwards rotation, in realization, snap ring 9, the closure state of lower snap ring 10.Upper snap ring 9, lower snap ring 10 tightly block chapeau de fer at monolithic insulator two ends, make measuring head 18 on snap ring 9, lower snap ring 10 respectively at the chapeau de fer contact at insulator two ends, then staff carries out insulation measurement by 21 pairs of monolithic insulators of megger.
As stated above, staff can be under the prerequisite that keeps bucket arm vehicle hoistable platform height not adjust, and the monolithic insulator of the differing heights on porcelain insulator string carries out insulation measurement.

Claims (5)

1. a porcelain insulator insulated test device, comprise megger, it is characterized in that: described device also comprises the first vertical pole, the first vertical pole is connected with horizontal strut one end by multi-directional ball, on the horizontal strut body of rod, both sides are provided with pulley, the horizontal strut other end is connected with the second vertical pole, on the second vertical pole, lower two ends are respectively equipped with snap ring and lower snap ring, on, lower snap ring is respectively the annulus being comprised of two semicircular ring that connect by spring, semicircular ring one end is connected with the second vertical pole, semicircular ring inner wall of end is provided with measuring head, measuring head is connected with megger, semicircular ring outer wall is provided with pin, and pin is connected with clue one end, and clue is erected on pulley, and the other end is connected with the take-up being arranged on the first vertical pole.
2. a kind of porcelain insulator insulated test device as claimed in claim 1, is characterized in that: the end face of described pulley is provided with baffle plate.
3. a kind of porcelain insulator insulated test device as claimed in claim 1, is characterized in that: the first described vertical pole is expansion link, between its extension rod and fixed bar, is provided with locking member, and take-up is arranged on the fixed bar of the first vertical pole.
4. a kind of porcelain insulator insulated test device as claimed in claim 1, is characterized in that: the second described vertical pole is expansion link, and its extension rod body of rod is connected with the semicircular ring that forms upper snap ring; Its fixed bar is connected with the semicircular ring that forms lower snap ring, and the fixed bar of the second vertical pole is connected with horizontal strut.
5. a kind of porcelain insulator insulated test device as described in claim 1 or 3, it is characterized in that: described take-up comprises first, second connecting rod, first connecting rod one end is fixedly connected with the first vertical pole, the first connecting rod other end is provided with take-up reel, take-up reel is connected with second connecting rod, second connecting rod is connected with handle is vertical, and take-up reel is connected with clue.
CN201320777445.1U 2013-12-02 2013-12-02 Porcelain insulator insulation testing device Expired - Lifetime CN203587747U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320777445.1U CN203587747U (en) 2013-12-02 2013-12-02 Porcelain insulator insulation testing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320777445.1U CN203587747U (en) 2013-12-02 2013-12-02 Porcelain insulator insulation testing device

Publications (1)

Publication Number Publication Date
CN203587747U true CN203587747U (en) 2014-05-07

Family

ID=50585647

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320777445.1U Expired - Lifetime CN203587747U (en) 2013-12-02 2013-12-02 Porcelain insulator insulation testing device

Country Status (1)

Country Link
CN (1) CN203587747U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103675620A (en) * 2013-12-02 2014-03-26 国网河南省电力公司商丘供电公司 Insulation test device for porcelain insulator
CN104022373A (en) * 2014-06-24 2014-09-03 国家电网公司 Shield ring wire clamp for ground-controlled insulator
CN105300509A (en) * 2014-05-29 2016-02-03 国网山西省电力公司电力科学研究院 Extension rod for noise detection

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103675620A (en) * 2013-12-02 2014-03-26 国网河南省电力公司商丘供电公司 Insulation test device for porcelain insulator
CN103675620B (en) * 2013-12-02 2016-05-04 国网河南省电力公司商丘供电公司 A kind of porcelain insulator insulated test device
CN105300509A (en) * 2014-05-29 2016-02-03 国网山西省电力公司电力科学研究院 Extension rod for noise detection
CN104022373A (en) * 2014-06-24 2014-09-03 国家电网公司 Shield ring wire clamp for ground-controlled insulator
CN104022373B (en) * 2014-06-24 2015-11-18 国家电网公司 Ground control insulator shading ring jointing clamp

Similar Documents

Publication Publication Date Title
CN103675620B (en) A kind of porcelain insulator insulated test device
CN203587747U (en) Porcelain insulator insulation testing device
CN203117230U (en) Telescopic overhead test wire connector
CN203350292U (en) Wiring apparatus used for breaker characteristic test
CN102073003A (en) Insulation test tool for gas-insulated metal-enclosed switchgear (GIS)
CN103176000A (en) Telescopic high altitude test wire connector
CN103336232B (en) A kind of pick-up unit
CN207181455U (en) A kind of high-tension transformer tests short jumper device
CN202975127U (en) Portable safe high-voltage electroscope
CN107425309B (en) Electrical test clamp for wiring at ground operation high place
CN205666350U (en) High voltage live connects lead wire device
CN109696610B (en) Insulation tester for additive manufacturing equipment detection
CN101572357A (en) Induction prevising grounding wire
CN203705590U (en) Floor-type special device for withstand voltage tests of safety equipment
CN104991140A (en) Simulation apparatus of electric field detection of composite insulator
CN203299234U (en) Switch test wiring rod
CN202351273U (en) Special rod for 10 kV switch cabinet arrester test
CN208043993U (en) A kind of new distribution cable road on-Line Monitor Device
CN207067247U (en) A kind of p-wire storage device for DCR of Transformer three-phase direct tester
CN206945899U (en) A kind of local discharge signal blocking device
CN205787021U (en) A kind of portable testing equipment of GIS
CN105954545B (en) A kind of Dielectric Test of Transformer termination
CN205091429U (en) Superconductive insulating material dielectric strength test platform under different elongations in liquid nitrogen environment
CN205067529U (en) A action bars for arrester is electrified to be detected
CN104020325A (en) High-voltage test shielding cover for 10kV ring main unit

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20140507

CX01 Expiry of patent term