CN203531496U - 倒落式双抱杆起立电杆装置 - Google Patents
倒落式双抱杆起立电杆装置 Download PDFInfo
- Publication number
- CN203531496U CN203531496U CN201320624796.9U CN201320624796U CN203531496U CN 203531496 U CN203531496 U CN 203531496U CN 201320624796 U CN201320624796 U CN 201320624796U CN 203531496 U CN203531496 U CN 203531496U
- Authority
- CN
- China
- Prior art keywords
- pole
- rope
- fixed pulley
- rod
- holding rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 15
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 abstract description 10
- 229910052742 iron Inorganic materials 0.000 abstract description 5
- 239000000463 material Substances 0.000 abstract description 5
- 238000010276 construction Methods 0.000 abstract description 2
- 238000009434 installation Methods 0.000 abstract 1
- 208000027418 Wounds and injury Diseases 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000006378 damage Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 208000014674 injury Diseases 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Abstract
本实用新型公开了一种倒落式双抱杆起立电杆装置,包括基座、绞磨机、导向滑车、小抱杆、大抱杆、牵引绳和绳索,所述绞磨机和所述导向滑车均固定在所述基座上;所述小抱杆和所述大抱杆为一端设有定滑轮的直杆;所述牵引绳一端缠绕在所述绞磨机上,另一端缠绕所述导向滑车和所述小抱杆定滑轮后与所述大抱杆定滑轮端固定连接;所述绳索穿过所述大抱杆定滑轮,两端与待起立电杆的两端固定连接;所述小抱杆和所述大抱杆的另一端支靠在所述基座上。专用于长电杆或铁塔塔材的起吊安装,对传统施工方法进行改进,操作简便,省力无风险。
Description
技术领域
本实用新型涉及电杆吊装技术领域,尤其是一种倒落式双抱杆起立电杆装置。
背景技术
过去长电杆(铁塔塔材)起吊安装在使用大型抱杆起吊时,由于大型抱杆自重较重,重心较高,使用人力起立大型抱杆至绞磨受力这段时间里,费时费力,且存在人身伤害风险。
实用新型内容
本实用新型针对现有技术的不足,提出一种倒落式双抱杆起立电杆装置,结构简单,操作简便,省力无风险。
为了实现上述实用新型目的,本实用新型提供以下技术方案:一种倒落式双抱杆起立电杆装置,包括基座、绞磨机、导向滑车、小抱杆、大抱杆、牵引绳和绳索,所述绞磨机和所述导向滑车均固定在所述基座上;所述小抱杆和所述大抱杆为一端设有定滑轮的直杆;所述牵引绳一端缠绕在所述绞磨机上,另一端缠绕所述导向滑车和所述小抱杆定滑轮后与所述大抱杆定滑轮端固定连接;所述绳索穿过所述大抱杆定滑轮,两端与待起立电杆的两端固定连接;所述小抱杆和所述大抱杆的另一端支靠在所述基座上。
进一步地,还包括风绳和制动绳,所述风绳两端分别固定在所述基座和所述待起立电杆顶部上;所述制动绳的两端分别固定在所述基座和所述待起立电杆底部上。
与现有技术相比,本实用新型具有以下优点:专用于长电杆或铁塔塔材的起吊安装,对传统施工方法进行改进,操作简便,省力无风险。
附图说明
图1为本实用新型的结构示意图。
具体实施方式
下面结合附图对本实用新型进行详细描述,本部分的描述仅是示范性和解释性,不应对本实用新型的保护范围有任何的限制作用。
如图1所示的一种倒落式双抱杆起立电杆装置,包括基座13、绞磨机1、导向滑车2、小抱杆3、大抱杆11、牵引绳6和绳索7,所述绞磨机1和所述导向滑车2均固定在所述基座13上;所述小抱杆3和所述大抱杆11为一端设有定滑轮4的直杆;所述牵引绳6一端缠绕在所述绞磨机1上,另一端缠绕所述导向滑车2和所述小抱杆定滑轮4后与所述大抱杆定滑轮端固定连接;所述绳索7穿过所述大抱杆定滑轮4,两端与待起立电杆8的两端固定连接;所述小抱杆3和所述大抱杆11的另一端支靠在所述基座13上。
为了防止被吊起的待起立电杆8的摆动,本装置还包括风绳12和制动绳9,所述风绳12两端分别固定在所述基座13和所述待起立电杆8顶部上;所述制动绳9的两端分别固定在所述基座13和所述待起立电杆8底部上。可将制动绳9缠绕动滑轮组10,达到省力作用。
本装置的简要操作过程:当绞磨机1启动后,通过导向滑车2带动小抱杆3及大抱杆11的动滑轮进行起吊。当大抱杆11起立与电杆8成70-80度时,小抱杆3失去受力。此时,大抱杆定滑轮4与小抱杆的定滑轮及导向滑车2成一条直线。
采用本装置起吊长电杆或铁塔塔材,这样人力支起小抱杆至绞磨牵引受力,再使用小抱杆起吊大抱杆至70°至80°时,小抱杆退出,再由大抱杆起吊长电杆(铁塔塔材)即可。
Claims (2)
1.一种倒落式双抱杆起立电杆装置,其特征在于:包括基座、绞磨机、导向滑车、小抱杆、大抱杆、牵引绳和绳索,所述绞磨机和所述导向滑车均固定在所述基座上;所述小抱杆和所述大抱杆为一端设有定滑轮的直杆;所述牵引绳一端缠绕在所述绞磨机上,另一端缠绕所述导向滑车和所述小抱杆定滑轮后与所述大抱杆定滑轮端固定连接;所述绳索穿过所述大抱杆定滑轮,两端与待起立电杆的两端固定连接;所述小抱杆和所述大抱杆的另一端支靠在所述基座上。
2.如权利要求1所述倒落式双抱杆起立电杆装置,其特征在于:还包括风绳和制动绳,所述风绳两端分别固定在所述基座和所述待起立电杆顶部上;所述制动绳的两端分别固定在所述基座和所述待起立电杆底部上。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320624796.9U CN203531496U (zh) | 2013-10-11 | 2013-10-11 | 倒落式双抱杆起立电杆装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320624796.9U CN203531496U (zh) | 2013-10-11 | 2013-10-11 | 倒落式双抱杆起立电杆装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203531496U true CN203531496U (zh) | 2014-04-09 |
Family
ID=50417720
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320624796.9U Expired - Lifetime CN203531496U (zh) | 2013-10-11 | 2013-10-11 | 倒落式双抱杆起立电杆装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203531496U (zh) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103982073A (zh) * | 2014-05-06 | 2014-08-13 | 国家电网公司 | 管塔拔除方法 |
CN103982074A (zh) * | 2014-05-06 | 2014-08-13 | 国家电网公司 | 分体式管塔吊装方法 |
CN105421861A (zh) * | 2015-11-13 | 2016-03-23 | 高世龙 | 一种电网电线杆架设装置及施工方法 |
CN105442932A (zh) * | 2015-11-13 | 2016-03-30 | 高世龙 | 一种电网电线杆埋设装置及施工方法 |
CN105822132A (zh) * | 2016-03-26 | 2016-08-03 | 山东华安铁塔有限公司 | 一种特高压输电铁塔的单元式组立方法 |
CN106193782A (zh) * | 2016-08-26 | 2016-12-07 | 资阳资源电力集团有限公司雁江分公司 | 坑壁竖杆稳定结构 |
CN106884565A (zh) * | 2017-04-14 | 2017-06-23 | 南京尚志电子科技有限公司 | 便携式快速升降装置 |
WO2017197731A1 (zh) * | 2016-05-20 | 2017-11-23 | 国网山东省电力公司高唐县供电公司 | 自垂直定位立杆器及其施工方法 |
CN108118950A (zh) * | 2017-12-29 | 2018-06-05 | 吕知融 | 一种标准化变电站台架双电杆架设装置 |
CN114439305A (zh) * | 2022-01-26 | 2022-05-06 | 国网先行河北能源科技有限公司 | 一种电力工程施工方法 |
-
2013
- 2013-10-11 CN CN201320624796.9U patent/CN203531496U/zh not_active Expired - Lifetime
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103982073A (zh) * | 2014-05-06 | 2014-08-13 | 国家电网公司 | 管塔拔除方法 |
CN103982074A (zh) * | 2014-05-06 | 2014-08-13 | 国家电网公司 | 分体式管塔吊装方法 |
CN103982074B (zh) * | 2014-05-06 | 2016-08-24 | 国家电网公司 | 分体式管塔吊装方法 |
CN105421861A (zh) * | 2015-11-13 | 2016-03-23 | 高世龙 | 一种电网电线杆架设装置及施工方法 |
CN105442932A (zh) * | 2015-11-13 | 2016-03-30 | 高世龙 | 一种电网电线杆埋设装置及施工方法 |
CN105822132A (zh) * | 2016-03-26 | 2016-08-03 | 山东华安铁塔有限公司 | 一种特高压输电铁塔的单元式组立方法 |
WO2017197731A1 (zh) * | 2016-05-20 | 2017-11-23 | 国网山东省电力公司高唐县供电公司 | 自垂直定位立杆器及其施工方法 |
CN106193782A (zh) * | 2016-08-26 | 2016-12-07 | 资阳资源电力集团有限公司雁江分公司 | 坑壁竖杆稳定结构 |
CN106193782B (zh) * | 2016-08-26 | 2019-02-26 | 资阳资源电力集团有限公司雁江分公司 | 坑壁竖杆稳定结构 |
CN106884565A (zh) * | 2017-04-14 | 2017-06-23 | 南京尚志电子科技有限公司 | 便携式快速升降装置 |
CN108118950A (zh) * | 2017-12-29 | 2018-06-05 | 吕知融 | 一种标准化变电站台架双电杆架设装置 |
CN114439305A (zh) * | 2022-01-26 | 2022-05-06 | 国网先行河北能源科技有限公司 | 一种电力工程施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203531496U (zh) | 倒落式双抱杆起立电杆装置 | |
CN103545751B (zh) | 架空输电线路地线光缆金具更换支架 | |
CN206502579U (zh) | 电杆起吊装置 | |
CN204778415U (zh) | 一种欧式起重机悬吊式跑车 | |
CN203998746U (zh) | 便携式吊装机 | |
CN205275101U (zh) | 便携式自动吊装机 | |
CN210313196U (zh) | 一种爬索吊运系统 | |
CN205132955U (zh) | 一种电力行业低空吊装作业用吊装架 | |
CN202829361U (zh) | 一种小型吊升机 | |
CN202444202U (zh) | 架空电缆锁定器 | |
CN202917897U (zh) | 电缆吊装水平滑车 | |
CN202175522U (zh) | 砼杆起吊装置 | |
CN201907924U (zh) | 展翅式卷筒吊装装置 | |
CN201443221U (zh) | 一种升旗具 | |
CN204433965U (zh) | 一种盘条钢丝缠绕装置 | |
CN210885082U (zh) | 一种风电法兰重型环件起吊设备装置 | |
CN203553744U (zh) | 超特高压交直流架空输电线路地线光缆金具更换装置 | |
CN201670370U (zh) | 扎捆机用万向升降架 | |
CN204265112U (zh) | 便携式接地线绕线架 | |
CN203624932U (zh) | 便捷式室内物料提升机 | |
CN202353102U (zh) | 电力线路架设上线器 | |
CN205687455U (zh) | 一种提升装置 | |
CN204310683U (zh) | 一种新型大件设备吊装工具 | |
CN204732779U (zh) | 合成绝缘子简易爬梯 | |
CN203056451U (zh) | 一种便携式架空导线位移装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term | ||
CX01 | Expiry of patent term |
Granted publication date: 20140409 |