CN203529217U - Double-pool garbage storage tank - Google Patents

Double-pool garbage storage tank Download PDF

Info

Publication number
CN203529217U
CN203529217U CN201320698284.7U CN201320698284U CN203529217U CN 203529217 U CN203529217 U CN 203529217U CN 201320698284 U CN201320698284 U CN 201320698284U CN 203529217 U CN203529217 U CN 203529217U
Authority
CN
China
Prior art keywords
garbage
storage tank
pool
garbage pool
garbage storage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320698284.7U
Other languages
Chinese (zh)
Inventor
潘老省
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201320698284.7U priority Critical patent/CN203529217U/en
Application granted granted Critical
Publication of CN203529217U publication Critical patent/CN203529217U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model discloses a double-pool garbage storage tank. A partition wall is arranged inside the garbage storage tank for partitioning the bottom part of the garbage storage into an A garbage pool and a B garbage pool; the middle and upper part of the front wall of the A garbage pool is provided with a discharging door, a discharging hall is arranged in front of the discharging door, the discharging hall is internally provided with a discharging platform, and the discharging platform is connected with a trestle; an incinerator charging platform is arranged above the rear wall of the B garbage pool, and the incinerator charging platform is provided with a row of feed hoppers; bridge type hoisting equipment is arranged above the A garbage pool and the B garbage pool, and the bridge type hoisting equipment is provided with grab buckets. The double-pool garbage storage tank is beneficial to garbage fermentation and dewatering, the roof of the garbage storage tank is resistant to corrosion, the sealing property is extremely good, a leachate collecting tank is simple and practical, the construction cost of the whole system is low, the running and maintenance cost is low, and the environment-friendly benefit is good.

Description

A kind of pair of pond garbage storage tank
Technical field
the utility model relates to a kind of pair of pond garbage storage tank, belongs to technology of garbage disposal field.
Background technology
at present each main building of incineration treatment of garbage factory is provided with a garbage storage tank, and object is that crude waste is deposited in to the dehydration of fermenting for 5~7 days in the garbage pool of garbage storage tank.Yet, in existing garbage storage tank, be all only provided with a garbage pool, on the front wall of garbage pool, be provided with garbage unloading door, therefore the usable height of garbage pool heap garbage can only arrive the elevation of bottom place of Dump gate, after this absolute altitude and garbage pool, between the incinerator feeder hopper erecting stage absolute altitude of wall top, there is the diff-H of approximately 14 meters, the spatial volume overwhelming majority of this diff-H cannot be used for heap garbage, in garbage pool, the volume of available effective heap garbage only accounts for approximately 65% of whole garbage pool available space, in order to meet the dumping volume of 5~7 days, the garbage pool width of conventional garbage storage tank is all arranged between 18~24 meters, add the width of incinerator feeder hopper erecting stage, storage vault roof width dimensions is between 27~33 meters, if storage vault roof adopts the words of the mixed clay structure of reinforcing bar, laid down cost will be very large, so the existing storage vault roof overwhelming majority adopts grid structure, few part adopts light section steel structure.
at least there is the problem of following several aspects in conventional garbage storage vault: the rack on (1) storage vault roof or light steel and roof color steel plate corrosion are very serious, and maintenance cost is very high; (2) the own poor sealing in storage vault roof of grid structure or light section steel structure, adds that the rear leak tightness of roof color steel plate corrosion is poorer, easily causes the excessive contaminated environment of refuse odor in storage vault; (3) garbage leachate delivery chute length is longer, and the gradient is little, oozes drop flow velocity lower, causes oozing very easily settled sludge of drop liquid delivery chute; (4) rubbish and the same pond of crude waste to be burnt after fermentation, after making to ferment, rubbish to be burnt is easily subject to soaking of crude waste moisture, causes refuse thermal value to be burnt to reduce.
Summary of the invention
the purpose of this utility model is, a kind of pair of pond garbage storage tank is provided, with solve that garbage storage tank roof is very easily corroded and poorly sealed, ooze drop liquid delivery chute very easily after settled sludge, fermentation rubbish to be burnt be subject to problem and garbage storage tank laid down cost and the high problem of maintenance cost that crude waste moisture soaks.
the technical solution of the utility model is to form like this: a kind of pair of pond garbage storage tank of the present utility model be, is provided with partition wall in garbage storage tank, and partition wall is divided into A garbage pool and B garbage pool by garbage storage tank bottom; A garbage pool front wall middle and upper part is provided with a disposing bin gate, is provided with discharging hall before Dump gate, is provided with discharging platform in discharging hall, and discharging platform is connected with trestle; After B garbage pool, wall top is provided with incinerator feeding platform, and incinerator feeding platform is provided with row's feeder hopper; The top of A garbage pool and B garbage pool is provided with overhead traveling crane equipment, and overhead traveling crane equipment is provided with grab bucket.
in aforementioned pair of pond garbage storage tank, the ceiling of described garbage storage tank is the mixed clay structure of reinforcing bar, and whole garbage storage tank is enclosed construction; Partition wall in garbage storage tank is half wall construction, and the height of partition wall is concordant with incinerator feeding platform or a little less than incinerator feeding platform; The front-back wall of described garbage storage tank ceiling below is provided with the track that connects A garbage pool and B garbage pool, and track is provided with overhead traveling crane equipment; The control cabin of overhead traveling crane equipment be located at partition wall one end directly over.
in aforementioned pair of pond garbage storage tank, the bottom surface of described A garbage pool and B garbage pool is low dip plane before rear height; The front wall along continuous straight runs of A garbage pool and B garbage pool is provided with two rows and oozes drop liquid discharge orifice, lower row is oozed the base of drop liquid discharge orifice and the bottom of A garbage pool and B garbage pool in same absolute altitude, and the base that upper row is oozed drop liquid discharge orifice is higher than 2~3 meters of the bottoms of A garbage pool and B garbage pool; Ooze drop liquid discharge orifice and be the rectangular opening of 1~1.5 meter, ooze drop liquid discharge orifice and be provided with grid.
in aforementioned pair of pond garbage storage tank, the front wall bottom outside of described A garbage pool and B garbage pool is provided with leachate collecting groove, the bottom of leachate collecting groove is Wave crest and wave trough shape, trough place is provided with the dirty hole of collection, collect in dirty hole and be provided with submersible sewage pump, the sewage regulating reservoir that the garbage leachate in by submersible sewage pump, collection dirt being cheated and mud are delivered to sewage treatment station.
in aforementioned pair of pond garbage storage tank, the right-hand member wall of described A garbage pool top is provided with grab bucket inspection platform, and grab bucket inspection platform is provided with grab bucket hole for hoist, and grab bucket hole for hoist is provided with seal cover board.
adopt the aforementioned pair of method that pond garbage storage tank carries out garbage disposal, the automobile straight that crude waste is housed was connected trestle and was opened to the discharging platform in discharging hall, poured crude waste into A garbage pool from Dump gate; Crude waste is deposited and within 2~4 days, is carried out initial fermentation dehydration in A garbage pool; Then the grab bucket by overhead traveling crane equipment is had bad luck the rubbish after initial fermentation dehydration to B garbage pool and is carried out secondary fermentation dehydration 5~7 days; Rubbish input incinerator feeder hopper after secondary fermentation being dewatered by the grab bucket of overhead traveling crane equipment again enters refuse burning system and burns.
in the method for aforementioned garbage disposal, at least configure two overhead traveling crane equipment in described garbage storage tank, two above overhead traveling crane equipment are according to waste transportation amount separate operaton or work compound, and the rubbish jointly completing in A garbage pool and B garbage pool is had bad luck operation; Or the rubbish of initial fermentation dehydration in A garbage pool is had bad luck to the garbage pool to B; Or the rubbish of secondary fermentation dehydration in B garbage pool is dropped into the feeder hopper on incinerator feeding platform.
in the method for aforementioned garbage disposal, the drop liquid that oozes that rubbish in described A garbage pool and B garbage pool produces enters leachate collecting groove and flows into the dirty hole of collection from the drop liquid discharge orifice that oozes being located at A garbage pool and B garbage pool front wall, the sewage regulating reservoir that the garbage leachate in the dirty hole of collection and mud is delivered to sewage treatment station by being located at submersible sewage pump in the dirty hole of collection.
compared with prior art, only have a garbage pool in existing garbage storage tank, the usable height of heap garbage can only arrive the elevation of bottom of Dump gate.This absolute altitude lower than garbage pool after approximately 14 meters of wall top incinerator feeder hoppers, this height space of 14 meters cannot be used for heap garbage, the effective volume of heap garbage only accounts for 65% left and right of whole garbage pool, space availability ratio is low.Because existing garbage storage tank space availability ratio is low, the heap that the width that therefore can only strengthen garbage storage tank meets garbage pool high-volume, width increase due to garbage storage tank, make binding of garbage storage tank more difficult, so existing garbage storage tank adopts rack or light section steel structure mostly, roofing corrosion is very serious, and maintenance cost is very high; The utility model is divided into two A, two garbage pool of B by partition wall by the garbage pool of garbage storage tank bottom, because not establishing garbage unloading door on B garbage pool side wall, rubbish in B garbage pool can be deposited into partition wall height always, partition wall height is basic concordant with incinerator feeding platform, greatly increase the stacking thickness of rubbish, be more conducive to fermentation and the dehydration of rubbish.Because two garbage pool can be by rubbish pile up separately to be burnt after crude waste and fermentation, after having avoided fermenting, rubbish to be burnt is subject to soaking of crude waste moisture, can improve the calorific value of rubbish to be burnt, and is conducive to energy-saving and emission-reduction.In addition, because dumping thickness increases, improved the degree of utilization of garbage storage tank, therefore can reduce the width of whole garbage storage tank, be convenient to adopt the mixed earth of reinforcing bar to construct garbage storage tank ceiling, not only can reduce laid down cost and maintenance cost, and leak tightness be fine.
Accompanying drawing explanation
fig. 1 is structural representation of the present utility model (not drawing overhead traveling crane equipment and track in figure);
fig. 2 is the floor plan schematic diagram of garbage storage tank;
fig. 3 is the A-A section-drawing of Fig. 2;
fig. 4 is the B-B section-drawing of Fig. 2;
fig. 5 is the schematic diagram that oozes drop liquid discharge orifice below leachate collecting groove.
being labeled as in accompanying drawing: 1-garbage storage tank, 2-partition wall, 3-A garbage pool, 4-B garbage pool, 5-Dump gate, 6-discharging hall, 7-discharging platform, 8-trestle, 9-incinerator feeding platform, 10-feeder hopper, 11-overhead traveling crane equipment, 12-grab bucket, 13-control cabin, 14-track, 15-oozes drop liquid discharge orifice, 16-leachate collecting groove, the dirty hole of 17-collection, the 18-inspection platform of grabbing bucket, the 19-hole for hoist of grabbing bucket, 20-submersible sewage pump.
The specific embodiment
below in conjunction with accompanying drawing, the utility model is described in further detail, but not as to any restriction of the present utility model.
the structural representation of a kind of pair of pond garbage storage tank of the present utility model as Figure 1-5, is provided with partition wall 2 in garbage storage tank 1, and partition wall 2 is divided into A garbage pool 3 and B garbage pool 4 by garbage storage tank 1 bottom; A garbage pool 3 front wall middle and upper parts are provided with a disposing bin gate 5, are provided with discharging hall 6 before Dump gate 5, are provided with discharging platform 7 in discharging hall 6, and discharging platform 7 is connected with trestle 8; The rear wall of B garbage pool 4 top is provided with incinerator feeding platform 9, and incinerator feeding platform 9 is provided with row's feeder hopper 10; The top of A garbage pool 3 and B garbage pool 4 is provided with overhead traveling crane equipment 11, and overhead traveling crane equipment 11 is provided with grab bucket 12.The ceiling of described garbage storage tank 1 is the mixed clay structure of reinforcing bar, and whole garbage storage tank 1 is enclosed construction; Partition wall 2 in garbage storage tank 1 is half wall construction, and the height of partition wall 2 is concordant with incinerator feeding platform 9 or a little less than incinerator feeding platform 9; The front-back wall of described garbage storage tank ceiling below is provided with the track 14 that connects A garbage pool 3 and B garbage pool 4, and track 14 is provided with overhead traveling crane equipment 11; The control cabin 13 of overhead traveling crane equipment 11 be located at partition wall 2 one end directly over.The bottom surface of described A garbage pool 3 and B garbage pool 4 is low dip plane before rear height; The front wall along continuous straight runs of A garbage pool 3 and B garbage pool 4 is provided with two rows and oozes drop liquid discharge orifice 15, lower row is oozed the base of drop liquid discharge orifice and the bottom of A garbage pool 3 and B garbage pool 4 in same absolute altitude, and the base that upper row is oozed drop liquid discharge orifice is higher than 2~3 meters of the bottoms of A garbage pool 3 and B garbage pool 4; Ooze drop liquid discharge orifice 15 and be the rectangular opening of 1~1.5 meter, ooze drop liquid discharge orifice 15 and be provided with grid.The front wall bottom outside of described A garbage pool 3 and B garbage pool 4 is provided with leachate collecting groove 16, the bottom of leachate collecting groove 16 is Wave crest and wave trough shape, trough place is provided with the dirty hole 17 of collection, collection is provided with submersible sewage pump 20 in dirty hole 17, the sewage regulating reservoir that the garbage leachate in the dirty hole 17 of collection and mud is delivered to sewage treatment station by submersible sewage pump.The right-hand member wall top of described A garbage pool 3 is provided with grab bucket inspection platform 18, and grab bucket inspection platform 18 is provided with grab bucket hole for hoist 19, and grab bucket hole for hoist 19 is provided with seal cover board.
the method that adopts of the present utility model pair of above-mentioned pond garbage storage tank to carry out garbage disposal is, the method can be connected the automobile straight that crude waste is housed trestle 8 and open to the discharging platform 7 in discharging hall 6, poured crude waste into A garbage pool 3 from Dump gate 5; Crude waste is deposited and within 2~4 days, is carried out initial fermentation dehydration in A garbage pool 3; Then the grab bucket 12 by overhead traveling crane equipment 11 is had bad luck the rubbish after initial fermentation dehydration to B garbage pool 4 and is carried out secondary fermentation dehydration 5~7 days; Rubbish input incinerator feeder hopper 10 after secondary fermentation being dewatered by the grab bucket 12 of overhead traveling crane equipment 11 again enters refuse burning system and burns.In described garbage storage tank 1, at least configure 11, two above overhead traveling crane equipment 11 of two overhead traveling crane equipment according to waste transportation amount separate operaton or work compound, the rubbish jointly completing in A garbage pool 3 and B garbage pool 4 is had bad luck operation; Or the rubbish of the interior initial fermentation dehydration of A garbage pool 3 is had bad luck to B garbage pool 4; Or the rubbish of the interior secondary fermentation dehydration of B garbage pool 4 is dropped into the feeder hopper 10 on incinerator feeding platform 9.The drop liquid that oozes that rubbish that described A garbage pool 3 and B garbage pool are 4 li produces enters leachate collecting groove 16 and flows into the dirty hole 17 of collection from the drop liquid discharge orifice 15 that oozes being located at A garbage pool 3 and B garbage pool 4 front walls, the sewage regulating reservoir that the garbage leachate in the dirty hole 17 of collection and mud is delivered to sewage treatment station by being located at submersible sewage pump 20 in the dirty hole 17 of collection.
Embodiment
garbage storage tank of the present utility model as Figure 1-5.In garbage storage tank 1, be provided with partition wall 2, on partition wall, be not provided with any connected holes.Partition wall is divided into two garbage storage tank bottom lengths direction to be divided into A garbage pool 3 and B garbage pool 4.The front wall of A garbage pool is provided with a disposing bin gate 5, and Dump gate outside is provided with discharging platform 7, and discharging platform is connected with trestle 8, and the automobile that rubbish is housed can reach discharging platform through trestle, and rubbish is poured in A garbage pool from Dump gate.Discharging platform 7 is provided with entity enclosure wall around, and discharging platform 7 tops are provided with ceiling, form airtight discharging hall 6.The main purpose that discharging hall is set is that rubbish pollutes surrounding environment when preventing discharging.The Hou Qiang top of B garbage pool is provided with incinerator feeding platform 9, and the installing space that 9 times side spaces of incinerator feeding platform are garbage incinerating system has occupied the certain width spaces in B garbage pool bottom.The absolute altitude of incinerator feeding platform 9 is about 21 meters.Incinerator feeding platform 9 is provided with row's feeder hopper 10, and the quantity of feeder hopper 10 determines according to the quantity of incinerator, and an incinerator correspondence arranges a feeder hopper 10.Can the rubbish input incinerator feeder hopper 10 in B garbage pool be entered to refuse burning system by overhead traveling crane equipment burns.Partition wall is half wall construction, and the height of partition wall 2 is concordant with incinerator feeding platform 9 or more lower slightly than incinerator feeding platform 9, and the running space of enough overhead traveling crane equipment 11 is left in partition wall 2 tops.Above A garbage pool and B garbage pool, the ceiling of garbage storage tank 1 below is provided with at least two overhead traveling crane equipment 11, and 11 of overhead traveling crane equipment, can be along garbage storage tank length direction way traffic on the track 14 of garbage storage tank front wall and rear wall.Overhead traveling crane equipment 11 is provided with grab bucket 12, and grab bucket can be along garbage storage tank Width way traffic.The control cabin 13 of overhead traveling crane equipment is located on the front wall of track below, and be positioned at partition wall 2 one end directly over, the ground elevation of control cabin 13 is higher than the top absolute altitude that is arranged on the feeder hopper 10 on incinerator feeding platform 9, operating personal is sitting in the dumping situation that can clearly observe two garbage pool in control cabin, also can clearly observe the running condition of overhead traveling crane equipment.The right-hand member wall top of A garbage pool is provided with grab bucket inspection platform 18, the absolute altitude of grab bucket inspection platform also equates with incinerator feeding platform, grab bucket inspection platform is provided with grab bucket hole for hoist 19, during grab bucket 12 light maintenance on overhead traveling crane equipment 11, can on grab bucket inspection platform 18, overhaul, during overhaul, can put to the inspection platform of grab bucket hole for hoist below and overhaul from grab bucket hole for hoist 19.In order to prevent that rubbish stink is from the excessive contaminated environment of grab bucket hole for hoist, grab bucket hole for hoist is provided with seal cover board, in the time of grab bucket need to being hung out to maintenance, opens seal cover board, closes at ordinary times.Grab bucket inspection platform below has approximately occupied the space of A garbage pool below length direction 7-8 rice.The bottom surface of two garbage pool is the front low dip plane of rear height; In the front wall bottom of two garbage pool, be provided with two rows and ooze drop liquid discharge orifice 15, lower row ooze the base of drop liquid discharge orifice with the bottom of two garbage pool in same absolute altitude, the base that upper row is oozed drop liquid discharge orifice is higher than bottom two garbage pool 2~3 meters; Ooze drop liquid discharge orifice and be the rectangular opening of 1~1.5 meter, ooze in drop liquid discharge orifice and be provided with grid, grid can block rubbish, prevents that rubbish from flowing out in garbage pool.Ooze drop liquid discharge orifice outside and be provided with leachate collecting groove 16, the bottom of leachate collecting groove is Wave crest and wave trough shape, trough place is provided with the dirty hole 17 of collection, and collection is provided with submersible sewage pump in dirty hole, the sewage regulating reservoir that the garbage leachate in the dirty hole of collection and mud is delivered to sewage treatment station by submersible sewage pump.
working process of the present utility model
specific works process of the present utility model is as follows:
rubbish van directly reaches the discharging platform 7 in discharging hall 6 by trestle 8 by the crude waste of collecting from refuse transfer station is transported to incineration treatment of garbage factory, from Dump gate 5, pour crude waste into A garbage pool 3, by the grab bucket 12 on overhead traveling crane equipment 11, the crude waste of unloading down is stacked by planning.Crude waste is deposited 2~4 days in A garbage pool, carries out nature extrusion dehydration and initial fermentation dehydration, makes rubbish take off most of moisture.Then by the grab bucket on overhead traveling crane equipment, again the rubbish after natural extrusion dehydration and initial fermentation dehydration is caught in B garbage pool and stacked by planning, deposit and within 5~7 days, carry out nature extrusion dehydration and secondary fermentation dehydration.Due to rubbish, in B garbage pool, stack highly highlyer, approach the height of incinerator feeding platform 9, and deposit 5~7 day time, so the garbage dewatering rate of the more conventional garbage storage tank of garbage dewatering rate after secondary fermentation dehydration is high.In this example, be equipped with two cover overhead traveling crane equipment, two cover overhead traveling crane equipment share pair of tracks.The range of operation of every cover overhead traveling crane equipment can cover whole garbage storage tank 1.Overhead traveling crane equipment and main being responsible for of grab bucket near A garbage pool one side capture the crude waste of being unloaded down by rubbish van to cut and stack by planning.By highly the highest can only the heap to concordant with Dump gate 5 bases of dumping of discharging reveal, higher rubbish and garbage leachate will diffuse out from Dump gate in A garbage pool.The rubbish of being mainly responsible for having dewatered to fermenting near overhead traveling crane equipment and the grab bucket of B garbage pool one side within the scope of B garbage pool captures cuts, prepares burden and feeds intake to incinerator feeder hopper; Rubbish in A garbage pool completes after initial fermentation dehydration, and two overhead traveling crane equipment and the work compound of grabbing bucket, jointly have bad luck the rubbish in A garbage pool to B garbage pool designated area and stack.The process that overturning at rubbish from from A garbage pool to B garbage pool is stacked, be more conducive to rubbish surface dehydration by evaporation and quality and mix well, can improve the combustion efficiency of rubbish in incinerator.
the right-hand member wall top of A garbage pool is provided with garbage grab bucket inspection platform 18, and grab bucket inspection platform 18 is provided with maintenance hole for hoist 19, and maintenance hole for hoist 19 is provided with seal cover board.The straight-through discharging platform layer of 19 times side spaces of maintenance hole for hoist.When the grab bucket of overhead traveling crane equipment is broken down while needing overhaul, the discharging platform layer that grab bucket can be hung to maintenance hole for hoist 19 belows from maintenance hole for hoist overhauls, and improves the working environment of service personnel.The control cabin 13 of overhead traveling crane equipment is located on the garbage storage tank 1 top front wall of track 14 belows, the ground elevation of control cabin 13 is higher than the top absolute altitude of described incinerator feeder hopper 10, control cabin 13 be positioned at partition wall 2 one end directly over, operating personal can clearly be observed the situation of both sides garbage pool, simultaneously when feeding intake to incinerator feeder hopper, can judge intuitively the position of overhead traveling crane equipment 11 and garbage grab bucket 12 and incinerator feeder hopper 10, so that feed intake.
in the present embodiment, the Effective width of B garbage pool is 12~15 meters, add the width of incinerator feeder hopper erecting stage, garbage storage tank roof width dimensions is between 20~24 meters, so the main bearing beam in garbage storage tank roof adopts the mixed earth unitized construction of shaped steel more easily to implement, and cost is lower, and then the also more easily enforcement of the mixed clay structure of garbage storage tank deck employing reinforcing bar, and cost is lower.Garbage storage tank roof adopts after the mixed clay structure of reinforcing bar very withstanding corrosion, and leak tightness is fine, compares the maintenance cost that can save great number with conventional grid structure or light section steel structure roof, avoids the excessive contaminated environment of refuse odor in storage vault simultaneously.
on the front wall of two garbage pool, along short transverse, be respectively equipped with two rows and ooze drop liquid discharge orifice 15, lower row is oozed the base of drop liquid discharge orifice and the bottom of A garbage pool on same absolute altitude, upper row ooze the base of drop liquid discharge orifice and the elevation of bottom of A garbage pool poor be 2~3 meters, the width that oozes drop liquid discharge orifice is 1~1.5 meter, is highly 1~1.5 meter, oozes the grid that drop liquid discharge orifice is provided with gear rubbish.Two garbage pool front wall bottom outside are provided with leachate collecting groove 16, all drop liquid that oozes that oozes the discharge of drop liquid discharge orifice all directly flows to leachate collecting groove, the bottom of leachate collecting groove is set as the several Wave crest and wave trough shapes with certain slope, trough place is provided with the dirty hole 17 of collection, collection is provided with submersible sewage pump 20 in dirty hole, and submersible sewage pump is delivered directly to the garbage leachate in leachate collecting groove and mud in the sewage regulating reservoir of the sewage treatment station outside native system.
the lowest part of the leachate collecting trench bottom in the present embodiment is the bottom surface in the dirty hole of collection, the bottom surface in the dirty hole of collection is low 3 meters at the bottom of than garbage pool pond, the highest point of leachate collecting trench bottom is peak top, peak top is low 1.5 meters at the bottom of than garbage pool pond, the effective volume of leachate collecting groove is greater than 100 cubic meters, there is certain storage and ooze drop liquid ability, add that flow in the dirty hole of collection is the taking turns to operate of submersible sewage pump of 40~80 cubes ms/h, so to ooze the work of drop liquid and mud be very reliable and stable to conveying garbage in the sewage regulating reservoir of the sewage treatment station from leachate collecting groove toward system, can guarantee to ooze drop liquid liquid level in setting range in leachate collecting groove.In addition, the gradient of leachate collecting trench bottom is greater than 10%, and slope length is less than 9 meters, is easy to be pooled in the dirty hole of collection, thereby by submersible sewage pump, is transported in the sewage regulating reservoir of the sewage treatment station outside system so ooze mud in drop liquid.Therefore, the present embodiment has saved garbage leachate collecting pit, has avoided conventional garbage leachate delivery chute problem, the problem includes: the problem of serious settled sludge.
of the present utility model pair of pond garbage storage tank is conducive to fermentation and the dehydration of rubbish, garbage storage tank roof withstanding corrosion, and leak tightness is fine, and leachate collecting groove is simple and practical, and whole system laid down cost is low, operation and maintenance expense is low, environmental benefit good.
above content is further detailed description of the utility model in conjunction with specific embodiments, can not assert that concrete enforcement of the present utility model is confined to these explanations.For the utility model person of an ordinary skill in the technical field, without departing from the concept of the premise utility, can also make some simple deduction or replace, all should be considered as belonging to protection domain of the present utility model.

Claims (5)

1. two ponds garbage storage tank, comprises garbage storage tank (1), it is characterized in that: in garbage storage tank (1), be provided with partition wall (2), partition wall (2) is divided into A garbage pool (3) and B garbage pool (4) by garbage storage tank (1) bottom; A garbage pool (3) front wall middle and upper part is provided with a disposing bin gate (5), and the front discharging hall (6) that is provided with of Dump gate (5), is provided with discharging platform (7) in discharging hall (6), and discharging platform (7) is connected with trestle (8); After B garbage pool (4), wall top is provided with incinerator feeding platform (9), and incinerator feeding platform (9) is provided with row's feeder hopper (10); The top of A garbage pool (3) and B garbage pool (4) is provided with overhead traveling crane equipment (11), and overhead traveling crane equipment (11) is provided with grab bucket (12).
2. two ponds garbage storage tank according to claim 1, is characterized in that: the ceiling of described garbage storage tank (1) is the mixed clay structure of reinforcing bar, and whole garbage storage tank (1) is enclosed construction; Partition wall (2) in garbage storage tank (1) is half wall construction, and the height of partition wall (2) is concordant with incinerator feeding platform (9) or a little less than incinerator feeding platform (9); The front-back wall of described garbage storage tank ceiling below is provided with the track (14) that connects A garbage pool (3) and B garbage pool (4), and track (14) is provided with overhead traveling crane equipment (11); The control cabin (13) of overhead traveling crane equipment (11) be located at partition wall (2) one end directly over.
3. two ponds garbage storage tank according to claim 2, is characterized in that: the bottom surface of described A garbage pool (3) and B garbage pool (4) is the front low dip plane of rear height; The front wall along continuous straight runs of A garbage pool (3) and B garbage pool (4) is provided with two rows and oozes drop liquid discharge orifice (15), lower row is oozed the base of drop liquid discharge orifice and the bottom of A garbage pool (3) and B garbage pool (4) in same absolute altitude, and the base that upper row is oozed drop liquid discharge orifice is higher than 2~3 meters of the bottoms of A garbage pool (3) and B garbage pool (4); Ooze drop liquid discharge orifice (15) and be the rectangular opening of 1~1.5 meter, ooze drop liquid discharge orifice (15) and be provided with grid.
4. two ponds garbage storage tank according to claim 3, it is characterized in that: the front wall bottom outside of described A garbage pool (3) and B garbage pool (4) is provided with leachate collecting groove (16), the bottom of leachate collecting groove (16) is Wave crest and wave trough shape, trough place is provided with the dirty hole of collection (17), in the dirty hole of collection (17), be provided with submersible sewage pump (20), by submersible sewage pump, will collect the dirty sewage regulating reservoir that (17) interior garbage leachate and mud are delivered to sewage treatment station of cheating.
5. two ponds garbage storage tank according to claim 4, it is characterized in that: the right-hand member wall top of described A garbage pool (3) is provided with grab bucket inspection platform (18), grab bucket inspection platform (18) is provided with grab bucket hole for hoist (19), and grab bucket hole for hoist (19) is provided with seal cover board.
CN201320698284.7U 2013-11-07 2013-11-07 Double-pool garbage storage tank Expired - Fee Related CN203529217U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320698284.7U CN203529217U (en) 2013-11-07 2013-11-07 Double-pool garbage storage tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320698284.7U CN203529217U (en) 2013-11-07 2013-11-07 Double-pool garbage storage tank

Publications (1)

Publication Number Publication Date
CN203529217U true CN203529217U (en) 2014-04-09

Family

ID=50415458

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320698284.7U Expired - Fee Related CN203529217U (en) 2013-11-07 2013-11-07 Double-pool garbage storage tank

Country Status (1)

Country Link
CN (1) CN203529217U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103662514A (en) * 2013-11-07 2014-03-26 潘老省 Dual-pool garbage storage library and method for disposing garbage

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103662514A (en) * 2013-11-07 2014-03-26 潘老省 Dual-pool garbage storage library and method for disposing garbage
CN103662514B (en) * 2013-11-07 2015-10-28 潘老省 The method of a kind of pair of pond garbage storage tank and garbage disposal

Similar Documents

Publication Publication Date Title
CN103662514B (en) The method of a kind of pair of pond garbage storage tank and garbage disposal
CN101250014A (en) Tower earthworm ecological filter tank system
CN202031162U (en) Porous gallery type leachate collecting device
CN204281497U (en) A kind of rural sewage courtyard type Water warfare integrated apparatus
CN209042410U (en) A kind of subregion garbage pool suitable for a variety of municipal solid wastes collaboration incineration plant
CN203529217U (en) Double-pool garbage storage tank
CN107702111A (en) Garbage burning boiler sludge mixes the device of burning
CN201598286U (en) Methane tank integrating gas production and gas storage
CN110482245A (en) Environment protection type multifunctional dry bulk cargo harbour and construction method
CN217616728U (en) Industrial solid waste rigid landfill pool
CN208382166U (en) A kind of dump pit percolate filters out device
CN201183990Y (en) Rubbish dewatering leachate system of rubbish burning power plant
CN208787177U (en) A kind of rubbish multidomain treat-ment field
CN210857472U (en) Bury formula dispersion regulation storage battery system
CN214884288U (en) Rainwater regulation and storage tank cleaned by utilizing aeration sand settling and sand pump suction and discharge of silt
CN210238633U (en) Rainwater recycling system
CN209706070U (en) A kind of multidirectional function type garbage warehouse for waste incinerator
CN209779845U (en) Integrated sewage interception and regulation tank applied to water environment comprehensive remediation
CN201626668U (en) Device for collecting sewage from garbage truck with dismountable boot
CN112443846A (en) Garbage storage warehouse
CN215593888U (en) River course shore protection structure capable of intercepting, storing and purifying initial rainwater and sewage
CN216236505U (en) Improved sewage storage pool
CN1251971C (en) Treating process of percolated liquid in city refuse landfill
CN220443240U (en) Oil-water separation tank structure of gas station
CN211845768U (en) Oil-containing sludge feeding closed stock bin

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140409

Termination date: 20151107

EXPY Termination of patent right or utility model