CN203500659U - Cable bridge with canopy - Google Patents

Cable bridge with canopy Download PDF

Info

Publication number
CN203500659U
CN203500659U CN201320623827.9U CN201320623827U CN203500659U CN 203500659 U CN203500659 U CN 203500659U CN 201320623827 U CN201320623827 U CN 201320623827U CN 203500659 U CN203500659 U CN 203500659U
Authority
CN
China
Prior art keywords
shaped steel
awning
square tube
testing bridge
cable testing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320623827.9U
Other languages
Chinese (zh)
Inventor
赵沭通
张跃进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINAGRATE COMPOSITES STRUCTURE (NANTONG) Ltd
Original Assignee
CHINAGRATE COMPOSITES STRUCTURE (NANTONG) Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINAGRATE COMPOSITES STRUCTURE (NANTONG) Ltd filed Critical CHINAGRATE COMPOSITES STRUCTURE (NANTONG) Ltd
Priority to CN201320623827.9U priority Critical patent/CN203500659U/en
Application granted granted Critical
Publication of CN203500659U publication Critical patent/CN203500659U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a cable bridge with a canopy. The cable bridge comprises a plurality of hollow transverse square tubes which are arranged in a front-and-back mode and are made of nonmetal materials, the two ends of each square tube are respectively connected E-shaped steel made of nonmetal materials, the two pieces of E-shaped steel on the same square tube are arranged oppositely, the cable bridge is formed by the transverse square tubes and the E-shaped steel, each piece of E-shaped steel is connected with a flat plate for the canopy through a canopy connecting piece made of nonmetal materials, the flat plates are made of nonmetal materials, the transverse square tubes and the E-shaped steel are fixedly connected through solid round bars made of nonmetal materials in an interference fit mode, and the canopy connecting pieces and the flat plates are fixedly connected through solid round bars made of nonmetal materials in an interference fit mode. The cable bridge has the advantages of being simple in structure, capable of shielding rain, suitable for field mounting and low in cost.

Description

Cable testing bridge with awning
Technical field
The utility model relates to a kind of cable testing bridge, and particularly a kind of for can antistatic, rainproof, all material be nonmetallic cable testing bridge.
Background technique
Cable testing bridge is generally applicable to the places such as the cable laying of large enterprise, major works power transformation, erecting cable, large bridge, subway and marine drilling.Existing cable testing bridge is made by bulk metal framework mostly, so not only makes overall structure heavy but also involve great expense, and is unfavorable for transportation, installs and removes and be widely used.If be applied in cable testing bridge design, can be because cable testing bridge long term exposure to be at air, easy-to-rust, there is no insulating property, existing structural formula cable testing bridge structure is comparatively complicated, by many parts, formed, and in the square tube in cable testing bridge, inner carrier is installed, preset nut or bolt, these all need to be in plant produced module, then arrive on-the-spot installation, reduce working efficiency, and a left side that need to be in cable testing bridge, right members side wall lower ends holes connecting square pipes, make like this left side in cable testing bridge, right members strength decreased, easy-rupturing, because using glue, square tube and inner carrier be connected and fixed again, because of reasons such as glue are aging, make the inner carrier square tube that easily comes off, Integral cable crane span structure is stressed lower, the form that also has a kind of cable testing bridge is to adopt square tube to be connected with C shaped steel, because of what use between its square tube and C shaped steel, be that glue is fixedly connected with mode, therefore constant intensity is determined by special glue completely, and special glue is expensive, glue can be because long term exposure is easily aging in air, so just there is very large potential safety hazard, and working life is short, poor effect.
Summary of the invention
The purpose of this utility model is in order to overcome above deficiency, provides that a kind of material is light, fire-retardant, the cable testing bridge with awning of heatproof, antistatic.
The purpose of this utility model is achieved through the following technical solutions: a kind of cable testing bridge with awning, the hollow horizontal square tube that the nonmetallic material of placing before and after comprising many are made, the two ends of every square tube are all connected with the E shaped steel that nonmetallic material are made, two E shaped steel are staggered relatively, laterally square tube and two E shaped steel form cable testing bridge, and the flat board as awning that the awning link that each E shaped steel is all made by nonmetallic material is made with nonmetallic material is connected.
Further improvement of the utility model is: between every square tube and E shaped steel, the real core pole all made by nonmetallic material between each awning link and flat board adopts interference fit to be fixedly connected with.
Further improvement of the utility model is: one end of every square tube is all fixedly connected with E shaped steel by two real core poles, and the other end of every square tube is fixedly connected with E shaped steel by a real core pole.
Further improvement of the utility model is: between each awning link and flat board, all by 4-8 real core pole, be fixedly connected with.
Further improvement of the utility model is: the distance between former and later two awning links is 500mm~1200mm, and the length of each awning link is 100~200mm.
Further improvement of the utility model is: between awning link and E shaped steel, by flat board, encircle the radian tension force and fix and be connected.
Further improvement of the utility model is: dull and stereotyped width is greater than the width of cable testing bridge.
Further improvement of the utility model is: when many horizontal square tubes are connected with E shaped steel, the real core pole that adjacent two horizontal square tubes and E shaped steel adopt is for being crisscross arranged, the left end of a square tube is fixedly connected with E shaped steel by two real core poles, right-hand member is fixedly connected with E shaped steel by a real core pole, the left end of another adjacent root square tube is fixedly connected with E shaped steel by a real core pole, and right-hand member is fixedly connected with E shaped steel by two real core poles.
The utility model compared with prior art has the following advantages: simple in structure, can be rainproof, be applicable to on-the-spot installation, cost is low etc., has that superior environmental-protecting performance, material are light, fire-retardant, heatproof, mechanical strength are high, it is corrosion-resistant to insulate, antistatic, be applicable to the advantages such as on-the-spot quick installation.
accompanying drawing explanation:
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the layout plan of the horizontal square tube in two of front and back real core pole while being connected with E shaped steel;
The horizontal square tube of number in the figure: 1-, 2-E shaped steel, 3-awning link, 4-flat board, the real core pole of 5-.
embodiment:
in order to deepen understanding of the present utility model, below in conjunction with embodiment and accompanying drawing, the utility model is described in further detail, and this embodiment only, for explaining the utility model, does not form the restriction to the utility model protection domain.
As Fig. 1 shows the utility model with a kind of embodiment of the cable testing bridge of awning, the hollow horizontal square tube 1 that the nonmetallic material of placing before and after comprising many are made, the two ends of every square tube 1 are all connected with the E shaped steel 2 that nonmetallic material are made, two E shaped steel 2 are staggered relatively, laterally square tube 1 and two E shaped steel 2 form cable testing bridge, the flat board 4 as awning that the awning link 3 that each E shaped steel 2 is all made by nonmetallic material is made with nonmetallic material is connected, between the preferred every square tube 1 of the utility model and E shaped steel 2, the real core pole 5 of all making by nonmetallic material between each awning link 3 and dull and stereotyped 4 adopts interference fit to be fixedly connected with, one end of every square tube 1 is all fixedly connected with E shaped steel 2 by two real core poles 5, the other end of every square tube 1 is fixedly connected with E shaped steel 2 by a real core pole 5, the left end that first horizontal square tube 1 is connected with E shaped steel is as shown in Figure 2 used two real plugs, right-hand member is just used a real plug.And the left end that adjacent second horizontal square tube 1 is connected with E shaped steel with it is just used a real plug, right-hand member is used two real plugs, many horizontal square tubes 1 constantly circulate like this, between each awning link 3 and dull and stereotyped 4, all by 4-8 real core pole 5, be fixedly connected with, distance between former and later two awning links 3 is 500mm~1200mm, the length of each awning link 3 is 100~200mm, between awning link 3 and E shaped steel 2, by dull and stereotyped 4, encircle the radian tension force and fix and be connected, dull and stereotyped 4 width is greater than the width of cable testing bridge.
Cable testing bridge described in the utility model all adopts nonmetallic material, comprise reinforcing material and resin base material, reinforcing material comprises simple glass silvalin and glass fibre continuous felt, in addition, except dull and stereotyped and real core pole, the fillet place, turning of other parts adopts glass fiber bulk strand zero twisted yarn, resin base material comprises unsaturated polyester resin, vinyl ester resin, phenolic resin, epoxy resin and polyurethane resin, there is superior environmental-protecting performance, material is light, fire-retardant, heatproof, mechanical strength is high, insulate corrosion-resistant, antistatic, be applicable to the advantages such as on-the-spot quick installation, be applicable to a kind of Code in Hazardous Special Locations as antistatic place etc., E shaped steel 2 is connected and adopts real core pole to be connected to employing interference fit with horizontal square tube 1, awning link 3 is connected and also adopts real core pole to be connected to employing interference fit with dull and stereotyped 4, at the scene according to the width of cable testing bridge and the dull and stereotyped required radian or the height that of encircleing, calculate dull and stereotyped needed width, then on dull and stereotyped length direction, every 500mm-1200mm, adopt the long awning link of 100mm-200mm to be connected with dull and stereotyped, awning link is connected with E shaped steel, mainly to rely on flat board to encircle the radian tension force to fix connection, Integral cable crane span structure is not used glue, and the width of awning is greater than the width of cable testing bridge, object is wet in order to prevent that cable side from drenching with rain, the all parts of cable testing bridge adopt pultrude process moulding.

Claims (8)

1. the cable testing bridge with awning, it is characterized in that: the hollow horizontal square tube (1) that the nonmetallic material of placing before and after comprising many are made, the two ends of every described square tube (1) are all connected with the E shaped steel (2) that nonmetallic material are made, two described E shaped steel (2) are staggered relatively, described horizontal square tube (1) and two described E shaped steel (2) form cable testing bridge, and the flat board (4) as awning that the awning link (3) that described in each, E shaped steel (2) is all made by nonmetallic material is made with nonmetallic material is connected.
2. according to claim 1 with the cable testing bridge of awning, it is characterized in that: the real core pole (5) of all making by nonmetallic material between awning link (3) and dull and stereotyped (4) between every described square tube (1) and described E shaped steel (2), described in each adopts interference fit to be fixedly connected with.
3. according to claim 2 with the cable testing bridge of awning, it is characterized in that: one end of every described square tube (1) is all fixedly connected with described E shaped steel (2) by two described real core poles (5), the other end of every described square tube (1) is fixedly connected with described E shaped steel (2) by a described real core pole (5).
4. according to claim 2 with the cable testing bridge of awning, it is characterized in that: described in each, between awning link (3) and dull and stereotyped (4), all by the individual real core pole (5) of 4-8, be fixedly connected with.
5. according to claim 1 with the cable testing bridge of awning, it is characterized in that: the distance described in former and later two between awning link (3) is 500mm~1200mm, described in each, the length of awning link (3) is 100~200mm.
6. according to claim 1 with the cable testing bridge of awning, it is characterized in that: between described awning link (3) and described E shaped steel (2), by described flat board (4), encircle the radian tension force and fix and be connected.
7. according to claim 1 with the cable testing bridge of awning, it is characterized in that: the width of described flat board (4) is greater than the width of described cable testing bridge.
8. according to claim 3 with the cable testing bridge of awning, it is characterized in that: when many described horizontal square tubes (1) are connected with described E shaped steel (2), the real core pole (5) that adjacent two described horizontal square tubes (1) and described E shaped steel (2) adopt is for being crisscross arranged, the left end of a described square tube (1) is fixedly connected with described E shaped steel (2) by two described real core poles (5), right-hand member is fixedly connected with described E shaped steel (2) by a described real core pole (5), the left end of another adjacent root square tube is fixedly connected with described E shaped steel (2) by a described real core pole (5), right-hand member is fixedly connected with described E shaped steel (2) by two described real core poles (5).
CN201320623827.9U 2013-10-11 2013-10-11 Cable bridge with canopy Expired - Fee Related CN203500659U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320623827.9U CN203500659U (en) 2013-10-11 2013-10-11 Cable bridge with canopy

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320623827.9U CN203500659U (en) 2013-10-11 2013-10-11 Cable bridge with canopy

Publications (1)

Publication Number Publication Date
CN203500659U true CN203500659U (en) 2014-03-26

Family

ID=50331638

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320623827.9U Expired - Fee Related CN203500659U (en) 2013-10-11 2013-10-11 Cable bridge with canopy

Country Status (1)

Country Link
CN (1) CN203500659U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104022473A (en) * 2014-06-24 2014-09-03 中格复合材料(南通)有限公司 Cable bridge capable of being rapidly mounted
CN104283168A (en) * 2014-10-31 2015-01-14 向荣集团有限公司 Efficient waterproof assembly for bus

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104022473A (en) * 2014-06-24 2014-09-03 中格复合材料(南通)有限公司 Cable bridge capable of being rapidly mounted
CN104283168A (en) * 2014-10-31 2015-01-14 向荣集团有限公司 Efficient waterproof assembly for bus

Similar Documents

Publication Publication Date Title
CA2959558C (en) Power transmission tower
CN203500659U (en) Cable bridge with canopy
CN103422699A (en) Electric transmission line tower made of composite materials
CN202432119U (en) Glass fiber reinforced plastic cable bridge
CN102966257B (en) 750kV composite material cross arm
CN103956683A (en) Crossing frame system used for 220-KV outgoing line engineering wire erection of 500-KV transformer substation
CN204118600U (en) A kind of positive triangle three core glass steel cable Simple clamp
CN203746350U (en) Pole board fixing frame of steel tube tower of circuits
CN201406865Y (en) 66KV overhead transmission line double-circuit horizontal crossing tower
CN204030438U (en) A kind of ground wire raiser of ultra-high-tension power transmission line
CN204571449U (en) A kind of EHV transmission steel tube tower cross-arm
CN204311817U (en) A kind of combined type composite material shaft tower
CN202674539U (en) Vertical diameter-changing height-adjusting device universally used for ocean platform bridge frames
CN203188885U (en) Portable insulated ladder
CN203813320U (en) Tool for live exchange of 220 kV narrow base tower strain insulator string
CN204571450U (en) A kind of EHV transmission steel tube tower cross-arm connector
CN202706635U (en) Lattice-type insulated electric transmission tower
CN202612860U (en) Ocean platform bridge frame universal dextrorotatory elbow
CN104895391A (en) External inserted cross arm connecting device for steel pipe rods
CN204385911U (en) The connector of body of wall oblique pull steel band
CN204266684U (en) Power equipment alarming guard
CN204517271U (en) A kind of for the special bearing tool of power transmission line steel pipe rod replacing insulator under electrified
CN202834391U (en) Combined type cable holder
CN108049693A (en) A kind of composite material electric pole of braiding structure
CN204099725U (en) A kind of power pipe optical ca ble protection pipe special fixing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140326

Termination date: 20201011

CF01 Termination of patent right due to non-payment of annual fee