CN203499701U - Guide positioning connecting structure for feet-lock bolt of steel frame of tunnel - Google Patents
Guide positioning connecting structure for feet-lock bolt of steel frame of tunnel Download PDFInfo
- Publication number
- CN203499701U CN203499701U CN201320616087.6U CN201320616087U CN203499701U CN 203499701 U CN203499701 U CN 203499701U CN 201320616087 U CN201320616087 U CN 201320616087U CN 203499701 U CN203499701 U CN 203499701U
- Authority
- CN
- China
- Prior art keywords
- feet
- lock bolt
- steelframe
- lock foot
- foot anchoring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 12
- 239000010959 steel Substances 0.000 title claims abstract description 12
- 238000004873 anchoring Methods 0.000 claims description 40
- 230000000694 effects Effects 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 6
- 238000000034 method Methods 0.000 abstract description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 239000010437 gem Substances 0.000 description 1
- 229910001751 gemstone Inorganic materials 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The utility model discloses a guide positioning connecting structure for a feet-lock bolt of a steel frame of a tunnel. The guide positioning connecting structure is characterized by comprising a guide tube and the feet-lock bolt, wherein the guide tube is welded to the steel frame; a drill hole is drilled in the guide tube and plays a role in guiding; the feet-lock bolt is installed through the guide tube, and the tail of the feet-lock bolt bends to form an L shape; the feet-lock bolt and the steel frame are welded into a whole. According to the guide positioning connecting structure of the feet-lock bolt, the problems that angle deviation occurs in the process of installing the feet-lock bolt and the steel frame, and the connection between the feet-lock bolt and the steel frame is not tight are solved, the installing accuracy of the feet-lock bolt is enhanced, the overall stability of the steel frame is improved, construction quality is guaranteed, and potential safety hazards are eliminated.
Description
Technical field
The utility model belongs to the construction technology of steelframe lock foot anchoring stock in constructing tunnel preliminary bracing, relates generally to steelframe lock foot anchoring stock guide-localization syndeton.
Background technology
Steel arch frame in constructing tunnel preliminary bracing generally need to be fixed with lock foot anchoring stock, to guarantee the stability of steelframe, traditional construction method is directly at steelframe side jewel hole, then install anchor pole, again anchor pole and steelframe are welded, the shortcoming of this method is, the angle of boring is difficult to meet design requirement, and the anchor pole of having installed after having holed is difficult to guarantee and steelframe fits tightly.
Utility model content
The purpose of this utility model is to provide a kind of tunnel steelframe lock foot anchoring stock guide-localization syndeton at this; The angular deviation that solution occurs when installing steelframe lock foot anchoring stock and lock foot anchoring stock are connected untight problem with steelframe, improve the precision of installing of lock foot anchoring stock, have improved the resistance to overturning of steelframe, have guaranteed construction quality, have eliminated potential safety hazard.
The utility model is to realize like this, construct a kind of tunnel steelframe lock foot anchoring stock guide-localization syndeton, it is characterized in that: comprise guide pipe and lock foot anchoring stock, described guide pipe is welded on steelframe, described guide pipe is drilled with the boring of the effect of playing guiding, by guide pipe, install the lock foot anchoring stock that described afterbody bends to L-type, and lock foot anchoring stock and steelframe are welded into an integral body.Solve the angular deviation and the lock foot anchoring stock that when installing steelframe lock foot anchoring stock, occur and be connected untight problem with steelframe, improved the precision of installing of lock foot anchoring stock, improved the resistance to overturning of steelframe, guaranteed construction quality, eliminated potential safety hazard.
According to tunnel described in the utility model steelframe lock foot anchoring stock guide-localization syndeton, it is characterized in that: described guide pipe adopts the steel pipe of external diameter 45mm, wall thickness 4mm, and guide pipe length is consistent with the width of steelframe.
According to tunnel described in the utility model steelframe lock foot anchoring stock guide-localization syndeton, it is characterized in that: described lock foot anchoring stock is ф 22HRB335 reinforcing bar, and afterbody bends to L-type.
The utility model has the advantage of: the utility model proposes a kind of lock foot anchoring stock guide-localization syndeton, solve the angular deviation and the lock foot anchoring stock that when installing steelframe lock foot anchoring stock, occur and be connected untight problem with steelframe, improved the precision of installing of lock foot anchoring stock, improved the resistance to overturning of steelframe, guarantee construction quality, eliminated potential safety hazard.
Accompanying drawing explanation
Fig. 1 is the utility model mounting structure schematic diagram
Fig. 2 is the utility model side schematic view
In figure: 1, guide pipe, 2, lock foot anchoring stock, 3, steelframe.
The specific embodiment
Below in conjunction with accompanying drawing, 1-2 is elaborated to the utility model, technical scheme in the utility model embodiment is clearly and completely described, obviously, described embodiment is only the utility model part embodiment, rather than whole embodiment.Embodiment based in the utility model, those of ordinary skills are not making the every other embodiment obtaining under creative work prerequisite, all belong to the scope of the utility model protection.
The utility model is by improving, at this, provide a kind of tunnel steelframe lock foot anchoring stock guide-localization syndeton, comprise guide pipe 1 and lock foot anchoring stock 2, described guide pipe 1 is welded on steelframe 3, described guide pipe 1 is drilled with the boring of the effect of playing guiding, by guide pipe 1, install the lock foot anchoring stock 2 that described afterbody bends to L-type, and lock foot anchoring stock 2 and steelframe 3 are welded into an integral body.
Described guide pipe 1 adopts the steel pipe of external diameter 45mm, wall thickness 4mm, and guide pipe 1 length is consistent with the width of steelframe 3.Described lock foot anchoring stock 2 is ф 22HRB335 reinforcing bar, and afterbody bends to L-type.
As shown in Figure 1, a kind of syndeton for tunnel steelframe lock foot anchoring stock guide-localization, described structure mainly comprises guide pipe 1 and lock foot anchoring stock 2; Described guide pipe 1 adopts the steel pipe of external diameter 45mm, wall thickness 4mm to be processed into, and guide pipe length is consistent with the width of steelframe; Described lock foot anchoring stock 2 one end bend to L-type; During enforcement first by guide pipe according to design lock foot anchoring stock squeeze into the side that angle is welded on steelframe, drilling rod is through guide pipe pore-forming, installs lock foot anchoring stock and is welded into integral body with steelframe after completing boring.
Above-mentioned explanation to the disclosed embodiments, makes professional and technical personnel in the field can realize or use the utility model.To the multiple modification of these embodiment, will be apparent for those skilled in the art, General Principle as defined herein can, in the situation that not departing from spirit or scope of the present utility model, realize in other embodiments.Therefore, the utility model will can not be restricted to these embodiment shown in this article, but will meet the widest scope consistent with principle disclosed herein and features of novelty.
Claims (3)
1. a tunnel steelframe lock foot anchoring stock guide-localization syndeton, it is characterized in that: comprise guide pipe (1) and lock foot anchoring stock (2), described guide pipe (1) is welded on steelframe (3), described guide pipe (1) is drilled with the boring of the effect of playing guiding, by guide pipe (1), install the lock foot anchoring stock (2) that described afterbody bends to L-type, and lock foot anchoring stock (2) and steelframe (3) are welded into an integral body.
2. tunnel steelframe lock foot anchoring stock guide-localization syndeton according to claim 1, is characterized in that: described guide pipe (1) adopts the steel pipe of external diameter 45mm, wall thickness 4mm, and guide pipe (1) length is consistent with the width of steelframe (3).
3. tunnel steelframe lock foot anchoring stock guide-localization syndeton according to claim 1, is characterized in that: described lock foot anchoring stock (2) is ф 22HRB335 reinforcing bar, and afterbody bends to L-type.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320616087.6U CN203499701U (en) | 2013-10-08 | 2013-10-08 | Guide positioning connecting structure for feet-lock bolt of steel frame of tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201320616087.6U CN203499701U (en) | 2013-10-08 | 2013-10-08 | Guide positioning connecting structure for feet-lock bolt of steel frame of tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203499701U true CN203499701U (en) | 2014-03-26 |
Family
ID=50330690
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201320616087.6U Expired - Lifetime CN203499701U (en) | 2013-10-08 | 2013-10-08 | Guide positioning connecting structure for feet-lock bolt of steel frame of tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203499701U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104234724A (en) * | 2014-09-29 | 2014-12-24 | 中铁五局(集团)有限公司 | Device for accurately positioning tunnel foot-lock anchor pipes and integrating with steel frame |
CN106677805A (en) * | 2016-12-28 | 2017-05-17 | 中铁第四勘察设计院集团有限公司 | Connecting device of tunnel steel frame and locking anchor pipe |
CN106907165A (en) * | 2017-05-03 | 2017-06-30 | 云南建投基础工程有限责任公司 | A kind of tunnel lock foot anchoring stock and supporting steelframe connecting elements |
CN106968695A (en) * | 2017-05-03 | 2017-07-21 | 云南建投基础工程有限责任公司 | A kind of prefabrication type tunnel lock foot anchoring stock and steelframe connecting elements |
CN107975382A (en) * | 2017-11-23 | 2018-05-01 | 中铁九局集团有限公司 | A kind of installation method for being used to control lock foot anchor tube precision |
CN110985011A (en) * | 2019-12-30 | 2020-04-10 | 济南城建集团有限公司 | Three-step seven-step combined excavation method for upper step of soft soil layer by adopting middle partition wall |
-
2013
- 2013-10-08 CN CN201320616087.6U patent/CN203499701U/en not_active Expired - Lifetime
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104234724A (en) * | 2014-09-29 | 2014-12-24 | 中铁五局(集团)有限公司 | Device for accurately positioning tunnel foot-lock anchor pipes and integrating with steel frame |
CN106677805A (en) * | 2016-12-28 | 2017-05-17 | 中铁第四勘察设计院集团有限公司 | Connecting device of tunnel steel frame and locking anchor pipe |
CN106677805B (en) * | 2016-12-28 | 2019-02-05 | 中铁第四勘察设计院集团有限公司 | A kind of attachment device of tunnel steelframe and lock foot anchor tube |
CN106907165A (en) * | 2017-05-03 | 2017-06-30 | 云南建投基础工程有限责任公司 | A kind of tunnel lock foot anchoring stock and supporting steelframe connecting elements |
CN106968695A (en) * | 2017-05-03 | 2017-07-21 | 云南建投基础工程有限责任公司 | A kind of prefabrication type tunnel lock foot anchoring stock and steelframe connecting elements |
CN106968695B (en) * | 2017-05-03 | 2023-10-20 | 云南建投基础工程有限责任公司 | Prefabricated tunnel lock foot stock and steelframe connecting element |
CN106907165B (en) * | 2017-05-03 | 2023-10-20 | 云南建投基础工程有限责任公司 | Connecting component for tunnel foot locking anchor rod and supporting steel frame |
CN107975382A (en) * | 2017-11-23 | 2018-05-01 | 中铁九局集团有限公司 | A kind of installation method for being used to control lock foot anchor tube precision |
CN110985011A (en) * | 2019-12-30 | 2020-04-10 | 济南城建集团有限公司 | Three-step seven-step combined excavation method for upper step of soft soil layer by adopting middle partition wall |
CN110985011B (en) * | 2019-12-30 | 2020-09-01 | 济南城建集团有限公司 | Three-step seven-step combined excavation method for upper step of soft soil layer by adopting middle partition wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203499701U (en) | Guide positioning connecting structure for feet-lock bolt of steel frame of tunnel | |
CN204691685U (en) | A kind of lock pin anchor tube drilling-hole positioning device | |
CN203021899U (en) | Quick-assembling template device for concrete ground construction | |
CN103422873B (en) | Strong-strength extendable anchor rod | |
CN202055842U (en) | Structure with connection with steel arch frame and locking anchor pipes of tunnel | |
CN103670452A (en) | Installation structure and method for accurately positioning tunnel arch wall lining buried type water-stop belt | |
CN203879523U (en) | Expansion shell anchor rod | |
CN103953121A (en) | Pre-buried sleeve for wall tie bar, and positioning method thereof | |
CN205314534U (en) | Frame post can't harm drawknot steel form structure | |
CN104929670A (en) | Wing type anchor rod | |
CN203867081U (en) | Wall steel tie bar pre-buried sleeve | |
CN204174638U (en) | Underground structure ruggedized construction | |
CN203796280U (en) | Segment joint structure high in bearing capacity | |
CN203876019U (en) | Pore-forming member manufacturing preformed hole of precast concrete component | |
CN203476355U (en) | Hollow pipe concrete support | |
CN204492851U (en) | Metro built by mining method transverse passage-way temporary support component | |
CN201258587Y (en) | Reducing pad for tubular scaffold fastener | |
CN205116154U (en) | Steel pipe concrete pile is strutted to side slope | |
CN204510688U (en) | A kind of temporary fixing structure of precast wall panel | |
CN103835731A (en) | Supporting device and method for primary supporting of expansible soil layer tunnel | |
CN204023887U (en) | A kind of tencel ground tackle | |
CN203924501U (en) | Steel bar skeleton positioning | |
CN202391122U (en) | Waterproof opposite-pull screw rod of wall body | |
CN207761678U (en) | A kind of device of the first branch steel arch-shelf shear stability of raising | |
CN204754957U (en) | Wing formula stock |
Legal Events