CN202055842U - Structure with connection with steel arch frame and locking anchor pipes of tunnel - Google Patents

Structure with connection with steel arch frame and locking anchor pipes of tunnel Download PDF

Info

Publication number
CN202055842U
CN202055842U CN2011201886859U CN201120188685U CN202055842U CN 202055842 U CN202055842 U CN 202055842U CN 2011201886859 U CN2011201886859 U CN 2011201886859U CN 201120188685 U CN201120188685 U CN 201120188685U CN 202055842 U CN202055842 U CN 202055842U
Authority
CN
China
Prior art keywords
anchor tube
lock pin
pin anchor
locking anchor
bow member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201886859U
Other languages
Chinese (zh)
Inventor
李德武
贾雯
谢飞鸿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huabang Construction Investment Group Co., Ltd.
Original Assignee
Lanzhou Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lanzhou Jiaotong University filed Critical Lanzhou Jiaotong University
Priority to CN2011201886859U priority Critical patent/CN202055842U/en
Application granted granted Critical
Publication of CN202055842U publication Critical patent/CN202055842U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to a structure with connection of a steel arch frame and locking anchor pipes of a tunnel, aiming to achieve firmer connection of the steel arch frame and the locking anchor pipes and improve the ultimate bearing capacity. The structure comprises a steel arch frame (4), a locking anchor pipe (3), a locking anchor pipe (2) and a steel bar connection (1), and is characterized in that the locking anchor pipe (3) and the locking anchor pipe (2) are arranged on the two sides of the steel arch frame (4), the steel arch frame (4) is anchored deep in surrounding rocks through the locking anchor pipe (3) and the locking anchor pipe (2), the ends of the locking anchor pipe (3) and the locking anchor pipe (2) are welded on the steel bar connection (1), and the steel bar connection (1) is welded on the steel arch frame (4) and is made by bending a steel bar.

Description

A kind of tunnel steel arch frame and lock pin anchor tube connected mode
One, technical field
The utility model patent relates to a kind of tunnel steel arch frame and the connected mode of locking the pin anchor tube in the tunnel support structure.
Two, background technology
Behind the tunnel cavern excavation, the equilibrium state of original country rock is broken, peripheral rock and vault have produced plastic strain and lax, in order to stop by the over-travel of the country rock after the disturbance and distortion, must adopt rational supporting and protection structure to bear the pressure of country rock.The steel bow member is an important ingredient in the Support System in Soft Rock Tunnels preliminary bracing structure, be again the part of permanent support simultaneously, the steel bow member itself has big rigidity and stronger supporting capacity, can be before sprayed mortar reach desired strength, effectively strata pressure and restrained deformation are born in the distortion and the displacement of control country rock.
Excavation back, tunnel if the steel bow member does not have firm base support, may make the steel bow member be easy to produce and skew in new stress field forming process because the load of tunnel peripheral rock discharges.Carry out firm being connected by performing lock foot anchoring stock with the steel bow member, make lock foot anchoring stock and steel bow member be linked to be an integral body, the steel bow member is anchored in the country rock deep, limit the displacement of steel bow member to a certain extent, give full play to the rigidity and the intensity of steel bow member, so that provide bigger supporting drag, prevent that country rock from producing harmful excessive deformation to the tunnel peripheral rock.
In the soft stratum,, usually replace the effect of lock foot anchoring stock with the bigger lock pin anchor tube of diameter for increasing frictional resistance and the normal pressure between country rock and the anchor pole.The main effect of lock pin anchor tube is the displacement that limits the steel bow member as much as possible, and the rigidity and the intensity of performance steel bow member make it bear the pressure that surrouding rock deformation causes as early as possible, guarantee the stability at tunnel initial stage.
The traditional lock pin anchor tube and the connected mode of steel bow member are: will lock the termination bending of pin anchor tube or the termination directly is welded on the steel bow member.The defective of this connected mode is: when bearing certain pressure from surrounding rock, when lock pin anchor tube and steel bow member itself also do not reach the bearing capacity limit, welding position, anchor tube termination has but surpassed weld strength and has destroyed, make the steel bow member lose the constraint of lock pin anchor tube, lose its due supporting capacity prematurely.
Three, summary of the invention
The utility model patent purpose provides the connected mode of a kind of novel tunnel steel arch frame and lock pin anchor tube, strengthens being connected between lock pin anchor tube and the steel bow member, thereby effectively brings into play the supporting capacity of steel bow member, raising safety of construction and stability of structure.
The technical scheme that realizes the utility model patent and adopt is:
A kind of tunnel steel arch frame and lock pin anchor tube connected mode, comprise steel bow member (4), lock pin anchor tube (3) and lock pin anchor tube (2), rebar connector (1), it is characterized in that: lock pin anchor tube (3) and lock pin anchor tube (2) are positioned at steel bow member (4) both sides, steel bow member (4) is anchored in the country rock deep by lock pin anchor tube (3) and lock pin anchor tube (2), lock pin anchor tube (3) and lock pin anchor tube (2) end are welded in rebar connector (1), rebar connector (1) is welded in steel bow member (4), and rebar connector (1) is formed by bar bending.
The advantage of comparing and having with existing structure: adopt this novel tunnel steel arch frame and the connected mode of locking the pin anchor tube, make the connection between steel bow member and the lock pin anchor tube more firm, ultimate bearing capacity is improved.
Four, description of drawings
The structural representation of Fig. 1 this patent (elevation)
The structural representation of Fig. 2 this patent (side view)
The structural representation of Fig. 3 this patent (plan view)
Five, the specific embodiment
The utility model patent is to change the connected mode of traditional lock pin anchor tube and steel bow member (be about to lock the termination bending of pin anchor tube or the termination is directly welded in the steel bow member) into a kind of novel tunnel steel arch frame and lock pin anchor tube connected mode.With reference to Fig. 1~3, in the present embodiment, comprise steel bow member (4), lock pin anchor tube (3) and lock pin anchor tube (2), rebar connector (1), it is characterized in that: lock pin anchor tube (3) and lock pin anchor tube (2) are positioned at steel bow member (4) both sides, steel bow member (4) is anchored in the country rock deep by lock pin anchor tube (3) and lock pin anchor tube (2), lock pin anchor tube (3) and lock pin anchor tube (2) end are welded in rebar connector (1), rebar connector (1) is welded in steel bow member (4), and rebar connector (1) is formed by bar bending.
Operating principle: the lock pin anchor tube that will be positioned at the steel bow member left and right sides is welded on the rebar connector, rebar connector is welded on the steel bow member, make the lock foot anchoring stock and the steel bow member of left and right sides stressed jointly, bonding area is bigger than traditional approach, connection is firm than conventional method, and ultimate bearing capacity is improved.

Claims (1)

1. tunnel steel arch frame and lock pin anchor tube connected mode, comprise steel bow member (4), lock pin anchor tube (3), lock pin anchor tube (2), rebar connector (1), it is characterized in that: lock pin anchor tube (3) and lock pin anchor tube (2) are positioned at steel bow member (4) both sides, steel bow member (4) is anchored in the country rock deep by lock pin anchor tube (3) and lock pin anchor tube (2), lock pin anchor tube (3) and lock pin anchor tube (2) end are welded in rebar connector (1), rebar connector (1) is welded in steel bow member (4), and rebar connector (1) is formed by bar bending.
CN2011201886859U 2011-05-25 2011-05-25 Structure with connection with steel arch frame and locking anchor pipes of tunnel Expired - Lifetime CN202055842U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201886859U CN202055842U (en) 2011-05-25 2011-05-25 Structure with connection with steel arch frame and locking anchor pipes of tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201886859U CN202055842U (en) 2011-05-25 2011-05-25 Structure with connection with steel arch frame and locking anchor pipes of tunnel

Publications (1)

Publication Number Publication Date
CN202055842U true CN202055842U (en) 2011-11-30

Family

ID=45015817

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201886859U Expired - Lifetime CN202055842U (en) 2011-05-25 2011-05-25 Structure with connection with steel arch frame and locking anchor pipes of tunnel

Country Status (1)

Country Link
CN (1) CN202055842U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234724A (en) * 2014-09-29 2014-12-24 中铁五局(集团)有限公司 Device for accurately positioning tunnel foot-lock anchor pipes and integrating with steel frame
CN106640147A (en) * 2016-11-25 2017-05-10 甘肃路桥建设集团有限公司 Tunnel primary support steel arch frame lock foot fixing method
CN106703854A (en) * 2017-01-05 2017-05-24 中铁工程设计咨询集团有限公司 Supporting device used for tunnel primary supporting structure and construction method thereof
CN107191204A (en) * 2017-04-04 2017-09-22 中铁二十二局哈尔滨铁路建设集团有限责任公司 A kind of support locking method of tunnel steel arch frame lock foot anchor tube
CN107829757A (en) * 2017-12-13 2018-03-23 中铁十局集团西北工程有限公司 A kind of tunnel bracing members lock pin anchor tube positioner
CN111335924A (en) * 2020-03-30 2020-06-26 中铁隧道集团二处有限公司 Connecting structure between lock pin anchor pipe and steel frame and mounting method thereof
CN112647985A (en) * 2020-12-28 2021-04-13 中国科学院武汉岩土力学研究所 Combined supporting device of lock pin anchor pipe/anchor rod and steel arch frame and construction method

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104234724A (en) * 2014-09-29 2014-12-24 中铁五局(集团)有限公司 Device for accurately positioning tunnel foot-lock anchor pipes and integrating with steel frame
CN106640147A (en) * 2016-11-25 2017-05-10 甘肃路桥建设集团有限公司 Tunnel primary support steel arch frame lock foot fixing method
CN106703854A (en) * 2017-01-05 2017-05-24 中铁工程设计咨询集团有限公司 Supporting device used for tunnel primary supporting structure and construction method thereof
CN107191204A (en) * 2017-04-04 2017-09-22 中铁二十二局哈尔滨铁路建设集团有限责任公司 A kind of support locking method of tunnel steel arch frame lock foot anchor tube
CN107829757A (en) * 2017-12-13 2018-03-23 中铁十局集团西北工程有限公司 A kind of tunnel bracing members lock pin anchor tube positioner
CN111335924A (en) * 2020-03-30 2020-06-26 中铁隧道集团二处有限公司 Connecting structure between lock pin anchor pipe and steel frame and mounting method thereof
CN112647985A (en) * 2020-12-28 2021-04-13 中国科学院武汉岩土力学研究所 Combined supporting device of lock pin anchor pipe/anchor rod and steel arch frame and construction method

Similar Documents

Publication Publication Date Title
CN202055842U (en) Structure with connection with steel arch frame and locking anchor pipes of tunnel
CN204552783U (en) A kind of loess tunnel vertical deformation control structure
CN204646269U (en) A kind of steel arch frame lock foot anchor tube device for reinforcing soft stratum tunnel
CN104790424B (en) The hardened system on generation power foundation of wind power ring basis and reinforcement means thereof
CN103556749A (en) Hanging flexible connection of precast concrete infill wall
CN106640147B (en) Tunnel steel arch frame lock foot fixed form
CN203230191U (en) Reinforced structure for resisting progressive collapse of existing concrete structure
CN103422873B (en) Strong-strength extendable anchor rod
CN203499701U (en) Guide positioning connecting structure for feet-lock bolt of steel frame of tunnel
CN205189886U (en) Tunnel transverse passage -way changes main cave construction structures
CN107191204A (en) A kind of support locking method of tunnel steel arch frame lock foot anchor tube
CN103061779B (en) Novel mine tunnel supporting structure and construction method thereof
CN202745885U (en) Inclined type locking anchor pipe apparatus
CN201665875U (en) Light gravity-type anti-earthquake concrete retaining wall
CN203822325U (en) Steel grating steel arch frame combined support for initial stage of expansibility soil layer tunnel
CN204253061U (en) The lining cutting of mine working three-dimensional bar frame antiarch
CN202991054U (en) Novel mine tunnel supporting structure
CN103277125B (en) With the lock pin ductule that steel plate connects
CN202451188U (en) Feet locking anchor rod
CN203905044U (en) Overhead deep foundation pit crossing construction elevator beam plate type base structure
CN206942780U (en) A kind of tunnel cross mouth advance support structure
CN102996142B (en) Construction method of mine tunnel supporting structure with fixed hanging rings
CN205225282U (en) Supporting construction of longitudinal force between reinforcing bow member
CN202280467U (en) Hollow grouting anchor rod
CN210396760U (en) Assembled supporting system for diversion tunnel construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: WEST ZHONGDA CONSTRUCTION GROUP CO., LTD.

Free format text: FORMER OWNER: LANZHOU JIAOTONG UNIV.

Effective date: 20130402

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 730070 LANZHOU, GANSU PROVINCE TO: 730000 LANZHOU, GANSU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20130402

Address after: 730000, Gansu Lanzhou Chengguan District, Zhangye Road No. 87 in the vast building of the West China Construction Group Co., Ltd.

Patentee after: XI'AN ZHONGDA CONSTRUCTION GROUP CO., LTD.

Address before: 730070 Anning West Road, Anning District, Gansu, Lanzhou, China, No. 88

Patentee before: Lanzhou Jiaotong Univ.

C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 730000, Gansu Lanzhou Chengguan District, Zhangye Road No. 87 in the vast building of the West China Construction Group Co., Ltd.

Patentee after: West China Construction Group Limited by Share Ltd

Address before: 730000, Gansu Lanzhou Chengguan District, Zhangye Road No. 87 in the vast building of the West China Construction Group Co., Ltd.

Patentee before: XI'AN ZHONGDA CONSTRUCTION GROUP CO., LTD.

CP03 Change of name, title or address

Address after: 730000 No. 100 Huancheng West Road, Chengguan Town, Yuzhong County, Lanzhou City, Gansu Province

Patentee after: Huabang Construction Investment Group Co., Ltd.

Address before: 730000, Gansu Lanzhou Chengguan District, Zhangye Road No. 87 in the vast building of the West China Construction Group Co., Ltd.

Patentee before: West China Construction Group Limited by Share Ltd

CP03 Change of name, title or address
DD01 Delivery of document by public notice

Addressee: Huabang Construction Investment Group Co., Ltd.

Document name: Notification of Passing Examination on Formalities

DD01 Delivery of document by public notice
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20111130