CN203462582U CN201320451760.5U CN201320451760U CN203462582U CN 203462582 U CN203462582 U CN 203462582U CN 201320451760 U CN201320451760 U CN 201320451760U CN 203462582 U CN203462582 U CN 203462582U
Authority
CN
China
Prior art keywords
strength
material members
strong
steel
equal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201320451760.5U
Other languages
Chinese (zh)
Inventor
王留成
李建洪
刘中华
邓良波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jinggong Steel Structure Group Co Ltd
Original Assignee
Zhejiang Jinggong Steel Structure Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jinggong Steel Structure Group Co Ltd filed Critical Zhejiang Jinggong Steel Structure Group Co Ltd
Priority to CN201320451760.5U priority Critical patent/CN203462582U/en
Application granted granted Critical
Publication of CN203462582U publication Critical patent/CN203462582U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model mainly discloses equal-strength connection nodes of different materials of component plates. The equal strength connection nodes comprise low-strength material components, high-strength material components, the transition sections and reinforcement plates; the components can be circular or box type components; the circular components are connected with steel castings through the transition sections to achieve the welding of internal reinforced welding joints; reinforced plates are welded on the inner wall of the box type components in advance and accordingly the equal-strength connection between the components and the steel castings can be achieved. According to the equal-strength connection nodes of the different materials of component plates, the equal-strength connection of the different thicknesses and different materials of steel can be achieved, the stress performance of the steel can be fully utilized, the safety of the structure can be ensured, the stress transmission way is clear, the structure is simple, the operation is convenient, and the efficiency is high.

Description

The strong connected node such as a kind of unlike material member sheet material
Technical field
The utility model relates to construction steel structure technical field, is specifically related to the strong connected nodes such as a kind of unlike material member sheet material.
Background technology
Along with the development of national economy, green steel building progressively increases, and the material capability of steel also progressively improves, and to high-strength steel, carries out study and use, as the Q420 high-strength steel that Beijing New Poly Building is used, the Q460 high-strength steel using in the Bird's Nest of National Stadium.Due to increasing of steel type, in a structure, according to diverse location stress performance situation, adopt the situation of different thicknesss of slab and different performance material steel also progressively to increase, to realize the economy of construction cost.Meanwhile, complicated and changeable along with form of structure, in complex node position, in order to guarantee presentation quality and the stress performance of node, the application of integrated poured cast steel node is also more and more.
Yet, because steel material performance is different, if need to realize strong connections the such as steel between the two, will inevitably be that low-intensity material steel are thick, the steel of high strength material are thin, when steel adopt melt-through weld docking, will form Weld Performance is low-intensity material, and throat depth can only be with the thin plate of high strength material, so will form weak spot at position while welding, thereby reduce the stress performance of structure, and this problem is not often designed person's ignorance, to structural safety, brings larger hidden danger.
Utility model content
The utility model obtains object and is to provide the strong connected node such as a kind of unlike material member sheet material and method thereof, by increase weld seam realize different-thickness, unlike material steel etc. strong connection, give full play to the stress performance of steel, guarantee the safety of structure.Force path in the utility model is clear and definite, simple structure, and easy to operate, efficiency is higher.
In order to achieve the above object, the utility model is achieved through the following technical solutions:
The strong connected node such as unlike material member sheet material, comprises low strong material members, high-strength material members, stiffening plate; In high-strength material members inner side, form stiffening plate, high-strength material members and stiffening plate laminating are welded on low strong material members, and the integral thickness of stiffening plate and high-strength material members is identical with low strong material members.
The steel-casting that described low strong material members is integrated poured moulding.
The utility model scheme can further be optimized:
Described stiffening plate is to pour into a mould the contract oralia of machine-shaping with low strong material members one.
On described low strong material members, weld the changeover portion that one section of height surpasses stiffening plate, high-strength material members is welded on changeover portion.
Described changeover portion is the individual member that high-strength material members is made.
The utility model scheme also can be optimized as follows:
Described stiffening plate is the independent sheet material that high-strength material members is made.
Adopt after such scheme, the utlity model has many beneficial effects:
The utility model, by the strengthening action of stiffening plate, while having made up the strong docking such as different-thickness, unlike material steel, due to the impact of material and thickness of slab, forms weak spot in docking melt-through weld position.Make component internal force by docking melt-through weld and fillet weld is transmitted jointly, guaranteed structural safety.Joint structure is succinct, does not affect outward appearance, and power transmission directly, clearly, easy to process.
Accompanying drawing explanation
Fig. 1 is the utility model preferred embodiment generalized section;
Fig. 2 is the concrete schematic diagram of the connection of the utility model preferred embodiment one;
Fig. 3 is the concrete schematic diagram of the connection of the utility model preferred embodiment two.
The specific embodiment
What the utility model mainly solved is such as steel-casting by low strong material members 1(), with high-strength material members 2(such as common iron member) connectivity problem.
Embodiment mono-: in conjunction with Fig. 1,2, in the present embodiment, low strong material members adopts pipe steel-casting 1, while docking with high-strength material members 2, in order to meet, waits strong connection, first build and add man-hour at low strong material members internal ring portion position formation one circle projection contract mouth, as stiffening plate 6.The port of stiffening plate 6 and pipe steel-casting 1 forms a breach.On this breach, place a changeover portion 4, first by butt weld 3, changeover portion 4 is connected with pipe steel-casting 1 port, then by changeover portion 4 port space, welding inner side Strengthening corner weld seam 5, realizes the connection between changeover portion 4 and stiffening plate 6.Finally adopt melt-through weld to dock with the backing plate 7 that high-strength material members 2 utilizes point to be welded in medial surface changeover portion 4.Wherein changeover portion 4 is identical with high-strength material members 2 materials.
Embodiment bis-: in conjunction with Fig. 1,3, low strong material members adopts square tube steel-casting 1 to dock with high-strength material members 2 in this embodiment, in order to meet, wait strong connection, first at high-strength material members 2 inner wall ports, pass through fillet weld 5 weld reinforcement plates 6, this stiffening plate 6 is identical with the material of high-strength material members 2, high-strength material members 2 and the total wall thickness of stiffening plate 6 are equated with square tube steel-casting 1 wall thickness, finally adopt melt-through weld to dock with the backing plate 7 that high-strength material members 2 utilizes point to be welded in medial surface square tube steel-casting 1.
Above-described embodiment is only for the inventive concept of the present utility model of explaining, but not restriction to the utility model rights protection, allly utilizes this design to carry out the change of unsubstantiality to the utility model, all should fall into protection domain of the present utility model.

Claims (6)

1. the strong connected node such as unlike material member sheet material, is characterized in that: comprise low strong material members, high-strength material members, stiffening plate; In high-strength material members inner side, form stiffening plate, high-strength material members and stiffening plate laminating are welded on low strong material members, and the integral thickness of stiffening plate and high-strength material members is identical with low strong material members.
2. the strong connected node such as a kind of unlike material member sheet material as claimed in claim 1, is characterized in that: the steel-casting that described low strong material members is integrated poured moulding.
3. the strong connected node such as a kind of unlike material member sheet material as claimed in claim 1 or 2, is characterized in that: described stiffening plate is the contract oralia with low strong material members one cast machine-shaping.
4. the strong connected node such as a kind of unlike material member sheet material as claimed in claim 3, is characterized in that: on described low strong material members, weld the changeover portion that one section of height surpasses stiffening plate, high-strength material members is welded on changeover portion.
5. the strong connected node such as a kind of unlike material member sheet material as claimed in claim 4, is characterized in that: described changeover portion is the individual member that high-strength material members is made.
6. the strong connected node such as a kind of unlike material member sheet material as claimed in claim 1, is characterized in that: described stiffening plate is the independent sheet material that high-strength material members is made.
CN201320451760.5U 2013-07-25 2013-07-25 Equal-strength connection nodes of different materials of component plates Withdrawn - After Issue CN203462582U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320451760.5U CN203462582U (en) 2013-07-25 2013-07-25 Equal-strength connection nodes of different materials of component plates

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320451760.5U CN203462582U (en) 2013-07-25 2013-07-25 Equal-strength connection nodes of different materials of component plates

Publications (1)

Publication Number Publication Date
CN203462582U true CN203462582U (en) 2014-03-05

Family

ID=50174954

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320451760.5U Withdrawn - After Issue CN203462582U (en) 2013-07-25 2013-07-25 Equal-strength connection nodes of different materials of component plates

Country Status (1)

Country Link
CN (1) CN203462582U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410226A (en) * 2013-07-25 2013-11-27 浙江精工钢结构有限公司 Equicohesive connection node and method for component plates made of different materials

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410226A (en) * 2013-07-25 2013-11-27 浙江精工钢结构有限公司 Equicohesive connection node and method for component plates made of different materials
CN105155674A (en) * 2013-07-25 2015-12-16 浙江精工钢结构集团有限公司 Equal-strength connecting joint and equal-strength connecting method for components and plates made of different materials
CN103410226B (en) * 2013-07-25 2015-12-23 浙江精工钢结构集团有限公司 Strong ties node and the methods thereof such as a kind of unlike material component sheet material
CN105155674B (en) * 2013-07-25 2017-12-01 浙江精工钢结构集团有限公司 Strong ties node and its methods such as a kind of unlike material component sheet material

Similar Documents

Publication Publication Date Title
CN204781322U (en) Steel core concrete column and outsourcing U -shaped steel -concrete composite beam connected node
CN205242773U (en) Adopt prefabricated assembled steel - concrete combination beam of cant chisei connection
CN105863074B (en) A kind of assembled wave webs beam column node connection device
CN204608999U (en) A kind of abutment node be connected with Flat steel pipe concrete column for girder steel
CN203808248U (en) Novel outer sleeve type connecting node for splicing square steel pipe column and H-shaped steel girder
CN105863075A (en) Cover plate weakening type assembly type wave web beam-column joint connection device
CN103015534A (en) Lateral connection node of concrete-filled rectangular steel tube column and steel beams
CN205976072U (en) Assembly type structure wall body and prefabricated concrete structure
CN105507426A (en) Half-through bracket haunching type compound steel pipe concrete column-steel beam joint
CN204174753U (en) A kind of board plug type node be connected with Flat steel pipe concrete column for girder steel
CN203462582U (en) Equal-strength connection nodes of different materials of component plates
CN103469902B (en) Full rigid steel pipes concrete column connected node
CN204059608U (en) A kind of sticking board type mental node be connected with Flat steel pipe concrete column for girder steel
CN103410226B (en) Strong ties node and the methods thereof such as a kind of unlike material component sheet material
CN204551759U (en) For the board plug type node that girder steel, bracing members are connected with Flat steel pipe concrete column
CN207795272U (en) Ring beam steel form is poured after a kind of portal of shield section
CN204781358U (en) Steel core concrete column and outsourcing U -shaped steel -concrete composite beam connected node
CN105484368A (en) Small angle crossing concrete-filled steel tube column internal stiffening tubular joint and making method thereof
CN207228355U (en) A kind of assembling steel plate Combined concrete wall and steel bar truss floor support plate connecting structure
CN206521768U (en) A kind of shear connector in the double-deck box hat concrete combined structure of immersed tube tunnel
CN208486165U (en) A kind of concrete circular stub and girder steel consolidate connecting structure
CN204781356U (en) Steel core concrete column and outsourcing U -shaped steel -concrete composite beam connected node
CN206844638U (en) A kind of house and its construction mould
CN205777470U (en) A kind of aluminum alloy pattern plate
CN204850066U (en) A link formula connected node structure outward that is used for girder steel and small bore steel core concrete column to be connected

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20140305

Effective date of abandoning: 20151223

AV01 Patent right actively abandoned

Granted publication date: 20140305

Effective date of abandoning: 20151223

C25 Abandonment of patent right or utility model to avoid double patenting