CN203394544U - Large-span mountain tunnel lagging jack with supporting legs - Google Patents

Large-span mountain tunnel lagging jack with supporting legs Download PDF

Info

Publication number
CN203394544U
CN203394544U CN201320472026.7U CN201320472026U CN203394544U CN 203394544 U CN203394544 U CN 203394544U CN 201320472026 U CN201320472026 U CN 201320472026U CN 203394544 U CN203394544 U CN 203394544U
Authority
CN
China
Prior art keywords
lagging jack
bow member
mountain tunnel
span mountain
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320472026.7U
Other languages
Chinese (zh)
Inventor
夏至
施霄飞
王楠
孙艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Zhongshe Group Co ltd
Original Assignee
JIANGSU ZHONGSHE ENGINEERING CONSULTANCY GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU ZHONGSHE ENGINEERING CONSULTANCY GROUP Co Ltd filed Critical JIANGSU ZHONGSHE ENGINEERING CONSULTANCY GROUP Co Ltd
Priority to CN201320472026.7U priority Critical patent/CN203394544U/en
Application granted granted Critical
Publication of CN203394544U publication Critical patent/CN203394544U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model relates to a large-span mountain tunnel lagging jack with supporting legs. The large-span mountain tunnel lagging jack comprises a lagging jack ring. The lagging jack ring consists of a plurality of lagging jack units which are successively connected to one another end to end. The large-span mountain tunnel lagging jack is characterized in that two sides of the lagging jack ring extend to the bottom to form the supporting legs. A supporting steel plate is arranged on the bottoms of the supporting legs. The thickness of the supporting steel plate is 2cm. The large-span mountain tunnel lagging jack with the supporting legs can bear stress and pulling force in a construction process like a profile steel lagging jack; stress conversion of the lagging jack can be realized in different construction stages; the safety on construction of a tunnel is improved; and moreover, the large-span mountain tunnel lagging jack is convenient to construct, and the integrality of the lagging jack ring is effectively guaranteed.

Description

The large span mountain tunnel bow member with spike
Technical field
The utility model relates to a kind of large span mountain tunnel bow member with spike, the bow member of especially a kind of applicable large span (Four-Lane Road) mountain tunnel.
Background technology
In recent years, along with the enhancing of national society's economic strength and the needs of Regional Economic Development, land transportation increases very swift and violent, and original railway and highway system more and more can not meet instructions for use.In order to alleviate all kinds of means of transportation overload operations, the problem demanding prompt solutions such as traffic accident, traffic jam and traffic nuisance take place frequently, since reform and opening-up, China classifies communications and transportation as one of strategic emphasis of the national economic development, design and construction large quantities of highway transportation systems.In these highway transportation systems, abandoned gradually mountain terrain sky way, but adopted a large amount of construction of tunnel to pass through the mountain ridge.
Because at present highway tunnel span is increasing, the highway tunnel with four lanes up till now from two-lane tunnel in the past, tunnel cross-section more trends towards flattening, and surrouding rock deformation is difficult to be controlled, and design and construction technology is more complicated.The shaped steel arch of the first lining cutting in tunnel plays the important and pivotal role in constructing tunnel, and it has born the pressure from surrounding rock before first lining cutting does not form, and bears follow-up pressure from surrounding rock together with forming steel reinforced concrete with first lining concrete.
Along with the flattening of tunnel cross-section, shaped steel arch is stressed becoming increasingly complex in work progress, and pulling force and pressure alternately change.Tunnel loading characteristic is stage by stage.After section has just excavated, first need the vertical upper bow member of frame, now bow member is a type frame construction, need to be located on rock mass; Then after inverted arch has excavated, frame founds inverted arch bow member, and bow member has formed closed-loop.
Summary of the invention
The purpose of this utility model is to overcome the deficiencies in the prior art, a kind of large span mountain tunnel bow member with spike is provided, take into account the stressed and pulling force of shaped steel arch in work progress, solve the stressed conversion of built under the different construction stages, the safety that improves constructing tunnel.
The technical scheme providing according to the utility model, a kind of large span mountain tunnel bow member with spike, comprises the bow member ring that the bow member unit that connected successively by a plurality of head and the tail forms, feature is: two side direction bow member rings bottoms of described bow member ring extend to form spike.
Bottom at described spike arranges supporting steel plate.
The thickness of described supporting steel plate is 2cm.
The large span mountain tunnel bow member with spike described in the utility model is taken into account the stressed and pulling force of shaped steel arch in work progress, solves the stressed conversion of built under the different construction stages, the safety that improves constructing tunnel; In addition, the utility model is constructed more for convenience, has effectively guaranteed the globality of bow member ring.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
The specific embodiment
Below in conjunction with concrete accompanying drawing, the utility model is described in further detail.
As shown in Figure 1: described in there is support angle large span mountain tunnel bow member comprise bow member unit 1, spike 2, supporting steel plate 3 etc.
As shown in Figure 1, the utility model comprises the bow member ring that the bow member unit 1 that connected successively by a plurality of head and the tail forms, and two side direction bow member rings bottoms of bow member ring extend to form spike 2, in the bottom of spike 2, supporting steel plate 3 are set, and the thickness of supporting steel plate 3 is 2cm.
The utility model can be the efficient solution stressed conversion of bow member under the different construction stages of determining.Because of the tunnel cross-section excavation initial stage, bow member is stressed larger, and vertical supporting is extremely important, and the design of spike can provide vertical supporting well.In order to facilitate the installation of inverted arch bow member, generally adopt at bow member ring both sides spare interface, by factory, this spare interface place welding spike husband, be processed to form, and adopt node bolt to connect, construction more for convenience, has also effectively guaranteed the globality of bow member ring, stressed clear and definite.

Claims (3)

1. a large span mountain tunnel bow member with spike, comprises the bow member ring that the bow member unit (1) that connected successively by a plurality of head and the tail forms, and it is characterized in that: two side direction bow member rings bottoms of described bow member ring extend to form spike (2).
2. the large span mountain tunnel bow member with spike as claimed in claim 1, is characterized in that: in the bottom of described spike (2), supporting steel plate (3) is set.
3. the large span mountain tunnel bow member with spike as claimed in claim 2, is characterized in that: the thickness of described supporting steel plate (3) is 2cm.
CN201320472026.7U 2013-08-02 2013-08-02 Large-span mountain tunnel lagging jack with supporting legs Expired - Lifetime CN203394544U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320472026.7U CN203394544U (en) 2013-08-02 2013-08-02 Large-span mountain tunnel lagging jack with supporting legs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320472026.7U CN203394544U (en) 2013-08-02 2013-08-02 Large-span mountain tunnel lagging jack with supporting legs

Publications (1)

Publication Number Publication Date
CN203394544U true CN203394544U (en) 2014-01-15

Family

ID=49906080

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320472026.7U Expired - Lifetime CN203394544U (en) 2013-08-02 2013-08-02 Large-span mountain tunnel lagging jack with supporting legs

Country Status (1)

Country Link
CN (1) CN203394544U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401617A (en) * 2016-09-12 2017-02-15 中铁十九局集团第七工程有限公司 Steel arch and joint thereof
CN108868815A (en) * 2018-08-20 2018-11-23 云南省红河州水利水电勘察设计研究院 A kind of support system excavated for tunnel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401617A (en) * 2016-09-12 2017-02-15 中铁十九局集团第七工程有限公司 Steel arch and joint thereof
CN106401617B (en) * 2016-09-12 2019-02-05 中铁十九局集团第七工程有限公司 Steel arch-shelf and its connector
CN108868815A (en) * 2018-08-20 2018-11-23 云南省红河州水利水电勘察设计研究院 A kind of support system excavated for tunnel

Similar Documents

Publication Publication Date Title
CN105134216B (en) Anti- slump structure by the engineering method lane of breaking roof 110
CN106014446B (en) A kind of reinforcement means of enhancing high ground stress soft rock stress tunnel inverted arch structural stability
CN105134214B (en) A kind of coal mining later stage secondary ventilation roadway layout and adjoining rock stability control method
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN106407553A (en) Laneway side support design method based on weak plane shear and support theories
CN203394544U (en) Large-span mountain tunnel lagging jack with supporting legs
CN103244129A (en) Construction method for three-dimensional intersection concave-convex fulcrums
CN108035743A (en) The definite method of stope drift active workings critical width
CN203035204U (en) Large-section tunnel second lining grouping formwork trolley
CN203626853U (en) Expansive rock area tunnel inverted arch reinforcement device
CN203716044U (en) Low bearing or middle bearing cable arch combined structural bridge
CN204152527U (en) The combined type preliminary bracing system of wall multiple-arch tunnel in implicit expression
CN102182469B (en) Construction method for preventing cracking of second lining of middle cavity of large span tunnel
CN204677212U (en) A kind of structure reducing tunnel lining structure internal force
CN202520011U (en) Floor shore device
CN206753038U (en) It is a kind of to wear joist steel sleeve pipe applied in aluminum dipping form
CN202672484U (en) Steel pipe single-post structure
CN104088665A (en) Steel pipe column construction process for underground excavated station
CN203067026U (en) Gob-side entry retaining filling wall structure with hollow built-in reinforcing ribs
CN101845822B (en) Method for constructing gravity-type cellular underground continuous wall
CN104405404B (en) A kind of gas in mine stay roadway method
CN103982191A (en) Reserved soil column up-down-asynchronous and left-right-synchronous excavation method
CN204385748U (en) Novel tunnel structure
CN202707093U (en) Temporary support system for tunnel construction
CN202250119U (en) Totally-enclosed U-shaped shed support frame for roadway supporting

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: JIANGSU ZHONGSHE GROUP CO., LTD.

Free format text: FORMER NAME: JIANGSU ZHONGSHE ENGINEERING CONSULTANCY GROUP CO., LTD.

CP03 Change of name, title or address

Address after: Jinxi road Binhu District 214125 Jiangsu city of Wuxi province No. 100

Patentee after: JIANGSU ZHONGSHE GROUP CO.,LTD.

Address before: 214072, 2188 West Avenue, Binhu District, Jiangsu, Wuxi, Taihu

Patentee before: JIANGSU ZHONGSHE ENGINEERING CONSULTANCY GROUP Co.,Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140115