CN203373772U - Foundation structure of reinforced concrete drainage pipeline under condition of soft soil foundation - Google Patents

Foundation structure of reinforced concrete drainage pipeline under condition of soft soil foundation Download PDF

Info

Publication number
CN203373772U
CN203373772U CN201320468344.6U CN201320468344U CN203373772U CN 203373772 U CN203373772 U CN 203373772U CN 201320468344 U CN201320468344 U CN 201320468344U CN 203373772 U CN203373772 U CN 203373772U
Authority
CN
China
Prior art keywords
foundation
reinforced concrete
sections
medium sand
drainage pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201320468344.6U
Other languages
Chinese (zh)
Inventor
马春亭
张慧芬
韩磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Co ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Co ltd filed Critical Shanghai Urban Construction Design Research Institute Co ltd
Priority to CN201320468344.6U priority Critical patent/CN203373772U/en
Application granted granted Critical
Publication of CN203373772U publication Critical patent/CN203373772U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Sink And Installation For Waste Water (AREA)

Abstract

The utility model discloses a foundation structure of a reinforced concrete drainage pipeline under the condition of a soft soil foundation. The foundation structure comprises a plurality of reinforced concrete strip foundation sections and medium sand filling connecting sections. The reinforced concrete strip foundation sections are arranged below the drainage pipeline, the medium sand filling connecting sections are arranged below socket-and-spigot ports or rabbets, and the socket-and-spigot ports or rabbets are arranged between pipe sections of the drainage pipeline for connection. The reinforced concrete strip foundation sections are sequentially connected in series through the medium sand filling connecting sections, and each reinforced concrete strip foundation section is of a three-layer structure, wherein the three-layer structure comprises a concrete cushion layer, a first cast-in-place layer and a second cast-in-place layer in sequence from bottom to top. According to the foundation structure of the reinforced concrete drainage pipeline under the condition of the soft soil foundation, the reinforced concrete strip foundation sections are sequentially connected in series through the medium sand filling connecting sections, shape changes caused by differential settlement can be concentrated on the medium sand filling connecting sections, rubber ring connectors matched between the pipe sections of the drainage pipeline can bear certain shape changes, and therefore the defects that that under the condition of the soft soil foundation, a foundation of the reinforced concrete pipeline breaks due to differential settlement, and consequently the drainage pipe is damaged and leaks water are effectively overcome.

Description

The foundation structure of reinforced concrete drainage pipe under soft foundation
Technical field
The utility model relates to the technical field of underground foundation structure, relates in particular to the foundation structure of reinforced concrete drainage pipe under a kind of soft foundation.
Background technology
Under weak soil (soft layers such as mud, mucky soil) ground or uneven strata condition, the reinforced concrete drainage pipe basis is general adopts continuous reinforced concrete strip foundation, and connects general bell and spigot or the tongue and groove that adopts rubber ring to connect between pipeline section.
Under regular situation, in order to guarantee body stability, reinforced concrete foundation adopts 120 ° or 180 ° of basic patterns, and pipeline and basis basically form an integral body.Reinforced concrete foundation is rigid foundation, may be due to differential settlement under Soft Soil local fracture, if fracture occurs between pipeline section, because basis and pipeline are integrated, also can cause the tubing fracture damage, cause drainage pipe to leak.
Those skilled in the art is devoted to develop the foundation structure of reinforced concrete drainage pipe under a kind of soft foundation always, overcome under soft foundation and rupture because differential settlement causes the reinforced concrete pipiline basis, and then cause the defect of drainage pipe damage, pipe leakage.
The utility model content
Because the above-mentioned deficiency of prior art, the utility model proposes the foundation structure of reinforced concrete drainage pipe under a kind of soft foundation, overcome under soft foundation and rupture because differential settlement causes the reinforced concrete pipiline basis, and then cause the defect of drainage pipe damage, pipe leakage.
For achieving the above object, the utility model provides the foundation structure of reinforced concrete drainage pipe under a kind of soft foundation, comprise that some sections are arranged on the reinforced concrete strip foundation sections of described drainage pipe below and are arranged on the bell and spigot that connects between the pipeline section of described drainage pipe or the medium sand of tongue and groove below tamps linkage section, described reinforced concrete strip foundation sections tamps linkage section by described medium sand and connects successively.
As further improvement of the utility model, described reinforced concrete strip foundation sections is three layer construction, is followed successively by from lower to upper concrete cushion, the first in-situ layer and the second in-situ layer.
As further improvement of the utility model, the length that described medium sand tamps linkage section is 150-250mm, and preferred, the length that described medium sand tamps linkage section is 200mm.
In sum, the foundation structure of reinforced concrete drainage pipe under soft foundation of the present utility model, the whole piece form that changes reinforced concrete strip foundation commonly used is sectional reinforced concrete strip foundation sections form, every section reinforced concrete strip foundation sections is as a whole, tamping linkage section by medium sand is together in series successively, the deformation caused by differential settlement just is concentrated in medium sand and tamps on linkage section, rubber ring interface between the pipeline section of cooperation drainage pipe can bear certain distortion, effectively overcome under soft foundation because differential settlement causes the fracture of reinforced concrete pipiline basis, and then cause drainage pipe to damage, the defect of pipe leakage.
Technique effect below with reference to accompanying drawing to design of the present utility model, concrete structure and generation is described further, to understand fully the purpose of this utility model, feature and effect.
The accompanying drawing explanation
The vertical section schematic diagram of the foundation structure that Fig. 1 is reinforced concrete drainage pipe under this specific embodiment soft foundation.
The schematic cross section that Fig. 2 is the foundation structure of reinforced concrete drainage pipe under this specific embodiment soft foundation.
The schematic cross section of the foundation structure of reinforced concrete drainage pipe under the soft foundation that Fig. 3 is the further specific embodiment.
The specific embodiment
The vertical section schematic diagram of the foundation structure that Fig. 1 is reinforced concrete drainage pipe under this specific embodiment soft foundation, the schematic cross section that Fig. 2 is the foundation structure of reinforced concrete drainage pipe under this specific embodiment soft foundation.As depicted in figs. 1 and 2, the present embodiment proposes the foundation structure of reinforced concrete drainage pipe under a kind of soft foundation, comprise that some sections are arranged on the reinforced concrete strip foundation sections 1 of described drainage pipe below and are arranged on the bell and spigot that connects between the pipeline section 2 of drainage pipe or the medium sand of tongue and groove below tamps linkage section 3, reinforced concrete strip foundation sections 1 tamps linkage section 3 by medium sand and connects successively.
As the further specific embodiment of the present embodiment, as shown in Figure 3, the reinforced concrete strip foundation sections of the present embodiment can also be three layer construction, is followed successively by from lower to upper concrete cushion, the first in-situ layer and the second in-situ layer.
Exemplary, perform 4 levellings of one deck (being generally 100mm) concrete cushion below design elevation at the bottom of pipeline foundation.Concrete cushion 4 has been laid rear cloth muscle and has been built the first in-situ layer 5, after the foundation construction of the first in-situ layer 5 completes, the surface of the first in-situ layer 5 is made to hair side and rinsed well, then continuing to build the second in-situ layer 6, the first in-situ layers 5 and the second in-situ layer 6 thickness all determines according to pipe diameter.The second in-situ layer 6 built after by the drainage pipe seat on the foundation structure of drainage pipe, and, after adopting the flexible rubber circle to connect joint, medium sand tamps linkage section 3 and adopts medium sands to tamp each section reinforced concrete strip foundation sections 2 connected successively.
Concrete, the length that the medium sand of the present embodiment tamps linkage section 3 is 200mm.Certainly, in other specific embodiments, the length that medium sand tamps linkage section 3 can also be other sizes such as 150mm or 250mm.
Exemplary, under soft foundation of the present utility model, the concrete applicable cases of the foundation structure of reinforced concrete drainage pipe is as follows:
The pipeline section 2 of the drainage pipe of the corresponding every joint of the present embodiment arranges one section reinforced concrete strip foundation sections 1, and medium sand is set below the bell and spigot connected between the pipeline section 2 of drainage pipe or tongue and groove tamps 3 pairs of two sections reinforced concrete strip foundation sections 1 of linkage section and dock series connection, reinforced concrete strip foundation sections 1 and medium sand tamp quantity, length and the position of linkage section 3 and can be adjusted according to the concrete condition of drainage pipe.By said structure, construct, the present embodiment has been realized being constructed the foundation structure of whole piece reinforced concrete drainage pipe, the deformation that differential settlement is caused just is concentrated in medium sand and tamps on linkage section 3, coordinate the rubber ring interface between the pipeline section 2 of drainage pipe can bear certain distortion simultaneously, effectively overcome under soft foundation and ruptured because differential settlement causes the reinforced concrete pipiline basis, and then caused the defect of drainage pipe damage, pipe leakage.
More than describe preferred embodiment of the present utility model in detail.Should be appreciated that those of ordinary skill in the art just can make many modifications and variations according to design of the present utility model without creative work.Therefore, all technician in the art comply with design of the present utility model on the basis of existing technology by the available technical scheme of logical analysis, reasoning, or a limited experiment, all should be in the determined protection domain by claims.

Claims (4)

1. the foundation structure of reinforced concrete drainage pipe under a soft foundation, it is characterized in that: comprise that some sections are arranged on the reinforced concrete strip foundation sections of described drainage pipe below and are arranged on the bell and spigot that connects between the pipeline section of described drainage pipe or the medium sand of tongue and groove below tamps linkage section, described reinforced concrete strip foundation sections tamps linkage section by described medium sand and connects successively.
2. the foundation structure of reinforced concrete drainage pipe under soft foundation as claimed in claim 1, it is characterized in that: described reinforced concrete strip foundation sections is three layer construction, is followed successively by from lower to upper concrete cushion, the first in-situ layer and the second in-situ layer.
3. the foundation structure of reinforced concrete drainage pipe under soft foundation as claimed in claim 1, it is characterized in that: the length that described medium sand tamps linkage section is 150-250mm.
4. the foundation structure of reinforced concrete drainage pipe under soft foundation as claimed in claim 1, it is characterized in that: the length that described medium sand tamps linkage section is 200mm.
CN201320468344.6U 2013-08-01 2013-08-01 Foundation structure of reinforced concrete drainage pipeline under condition of soft soil foundation Expired - Fee Related CN203373772U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320468344.6U CN203373772U (en) 2013-08-01 2013-08-01 Foundation structure of reinforced concrete drainage pipeline under condition of soft soil foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320468344.6U CN203373772U (en) 2013-08-01 2013-08-01 Foundation structure of reinforced concrete drainage pipeline under condition of soft soil foundation

Publications (1)

Publication Number Publication Date
CN203373772U true CN203373772U (en) 2014-01-01

Family

ID=49836317

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320468344.6U Expired - Fee Related CN203373772U (en) 2013-08-01 2013-08-01 Foundation structure of reinforced concrete drainage pipeline under condition of soft soil foundation

Country Status (1)

Country Link
CN (1) CN203373772U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105887912A (en) * 2016-05-05 2016-08-24 十九冶成都建设有限公司 Composite foundation structure for complex geological zone and construction method of composite foundation structure
CN106088142A (en) * 2016-07-22 2016-11-09 福建省建筑设计研究院 A kind of prefabricated assembled pipeline foundation and assembly method thereof
CN106638256A (en) * 2017-02-14 2017-05-10 上海市城市建设设计研究总院(集团)有限公司 Semi-integrated seamless bridge structure adaptive to soft foundation
CN106677073A (en) * 2017-02-14 2017-05-17 上海市城市建设设计研究总院(集团)有限公司 Construction method for semi-integral jointless bridge structure adaptive to soft soil foundation
CN107061867A (en) * 2017-04-14 2017-08-18 宣城市政建设集团有限公司 A kind of reinforced concrete drainage pipe is rested the head on pipe

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105887912A (en) * 2016-05-05 2016-08-24 十九冶成都建设有限公司 Composite foundation structure for complex geological zone and construction method of composite foundation structure
CN105887912B (en) * 2016-05-05 2018-09-25 十九冶成都建设有限公司 Composite base structure and its construction method for complex geological district
CN106088142A (en) * 2016-07-22 2016-11-09 福建省建筑设计研究院 A kind of prefabricated assembled pipeline foundation and assembly method thereof
CN106088142B (en) * 2016-07-22 2018-07-06 福建省建筑设计研究院有限公司 A kind of prefabricated assembled pipeline foundation and its assembly method
CN106638256A (en) * 2017-02-14 2017-05-10 上海市城市建设设计研究总院(集团)有限公司 Semi-integrated seamless bridge structure adaptive to soft foundation
CN106677073A (en) * 2017-02-14 2017-05-17 上海市城市建设设计研究总院(集团)有限公司 Construction method for semi-integral jointless bridge structure adaptive to soft soil foundation
CN107061867A (en) * 2017-04-14 2017-08-18 宣城市政建设集团有限公司 A kind of reinforced concrete drainage pipe is rested the head on pipe

Similar Documents

Publication Publication Date Title
CN203373772U (en) Foundation structure of reinforced concrete drainage pipeline under condition of soft soil foundation
CN102505598B (en) Method for reinforcement construction of soft soil foundation by exchange-filling with foam lightweight soil
CN108169427B (en) Tunnel water inrush physical simulation test system and method for plane stress model
WO2020248596A1 (en) Protection structure for preventing ground heave caused by tunnel grouting reinforcement and grouting method
CN104005419B (en) The box culvert structure of sinking method construction and construction method
CN103291313B (en) EPB shield tunneling excavation pressure vault support system and construction method thereof
CN101775826A (en) Construction method for laying water pipes
CN104563164B (en) A kind of ground-connecting-wall seam leak detection and grouting for water plugging method
CN201650362U (en) Maintainable tunnel drainage system
CN103256052A (en) Construction method for integral straight middle wall type double-arch tunnel
CN202787334U (en) Sealing structure of deep well casing used during tunnel construction
CN203530996U (en) Multi-well-point combined type precipitation facility
CN205688413U (en) A kind of prefabricated water intaking in power plant immersed tunnel structure
CN105274922A (en) Anti-slide tie-steel pipe pile composite structure for repairing cave-in roadbed and method
CN104963705A (en) Underground space excavating and constructing method
CN104695343A (en) Long-distance jacking construction method based on back wall pushing technology
CN104099946B (en) Inspection-pit between a kind of Novel top pipeline section
CN104215425A (en) Filled karst pipeline system and manufacturing and refilling methods thereof
CN204401485U (en) The construction structure of high roadbed draining Steel Corrugated Pipe Culvert
CN104089103B (en) Glass steel pipe lining method of circulating water pipe lined with glass steel pipe
CN105065040A (en) Top-plate-prefabricated underground space underground excavation building method
CN106958240A (en) Air-cushion type batch vacuum pipe well and apply its soft foundation Yield rainfall relation method
CN203716273U (en) Multifunctional ecological draining gutter
CN205714225U (en) A kind of railway culvert, tunnel defect wavy metal culvert pipe liner bracing means
CN211976106U (en) Pipe jacking interface structure capable of improving longitudinal rigidity

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140101