CN203373630U - Prefabricated hollow reinforced concrete pavement slab - Google Patents

Prefabricated hollow reinforced concrete pavement slab Download PDF

Info

Publication number
CN203373630U
CN203373630U CN201320371155.7U CN201320371155U CN203373630U CN 203373630 U CN203373630 U CN 203373630U CN 201320371155 U CN201320371155 U CN 201320371155U CN 203373630 U CN203373630 U CN 203373630U
Authority
CN
China
Prior art keywords
prefabricated
prefabricated hollow
concrete body
steel bar
hollow steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201320371155.7U
Other languages
Chinese (zh)
Inventor
卢海陆
孙建运
刘康
宋中南
陈港
齐虎
胡衷启
翟明会
丛峻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Engineering Corp Ltd CSCEC
Original Assignee
China State Construction Engineering Corp Ltd CSCEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Engineering Corp Ltd CSCEC filed Critical China State Construction Engineering Corp Ltd CSCEC
Priority to CN201320371155.7U priority Critical patent/CN203373630U/en
Application granted granted Critical
Publication of CN203373630U publication Critical patent/CN203373630U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model provides a prefabricated hollow reinforced concrete pavement slab. The prefabricated hollow reinforced concrete pavement slab comprises a prefabricated concrete body, slab main reinforcements and screw tubes, wherein the slab main reinforcements are wrapped in the slab body; the screw tubes are embedded in the top of the prefabricated concrete body; the prefabricated concrete body is a standard cuboid block with length of 3m, width of 1m and thickness of 0.3m; through holes are uniformly formed along the length direction of the prefabricated concrete body; the slab main reinforcements are distributed at the top and bottom of the prefabricated concrete body. The prefabricated hollow reinforced concrete pavement slab has the advantages of high structural strength, convenience in transport, reusability, high efficiency in construction and the like, and can be widely applied to road rehabilitation and construction of temporary construction roads.

Description

Prefabricated hollow steel bar concrete flag
Technical field
The utility model relates to a kind of prefabricated bridge-type road slab.
Background technology
At present, the road structural system of road traffic is mainly the cast-in-situ concrete pavement system, because the ordinary Portland cement setting and harden is slow, the strength developing time is long, generally needs fencing lawn 14 days to concrete strength to reach more than 80% of design strength, can open to traffic, delay the duration.In addition, after the process of being delivered for use, usually can run into due to improper use or service time length need to repair existing road surface, the repair process complexity, repair the duration longer, especially for important road, can affect greatly public's traffic.In addition, in road construction and building operations, often need to lay some interim builder's roads, these temporary roads need to remove after using function to complete, if adopt the cast-in-situ concrete pavement system, waste a large amount of manpower and materials, and produce a large amount of building wastes, environment is worked the mischief.
Given this, the utility model is emphatically to find the prefabricated road surface of a kind of standardization, can realize rapid construction and reparation, improves road construction efficiency.
The utility model content
The purpose of this utility model is to provide a kind of prefabricated hollow steel bar concrete flag, solve existing cast-in-situ concrete road slab, and long construction period is repaired difficulty, uses and finishes the rear inconvenience of removing, and easily produces the technical problem of a large amount of building wastes.
For achieving the above object, the utility model adopts following technical scheme:
A kind of prefabricated hollow steel bar concrete flag, by precast concrete body, the fiber tube that is wrapped in the plate master muscle in plate body and is embedded in the precast concrete bodies top, formed, described precast concrete body is that length is 3m, width is 1m, the cuboid calibrated bolck that thickness is 0.3m, long to for evenly offering and through hole along it, described plate master muscle is distributed in top and the bottom of precast concrete body.
Described fiber tube is at least four, is distributed in the precast concrete bodies top near corner positions.
Described fiber tube is comprised of internal thread sleeve pipe, external screw thread rod iron, rectangle anchor slab and bar dowel, described external screw thread rod iron is vertically welded in rectangle anchor slab center, described internal thread sleeve pipe and external screw thread rod iron are threaded, described bar dowel is symmetrically welded at external screw thread rod iron both sides near rectangle anchor slab marginal position, and rectangle anchor slab edge is all exposed at its two ends.
Described internal thread sleeve pipe external diameter is 4cm, and internal diameter is 2cm, is highly 8cm; The diameter of described external screw thread rod iron is 2cm, is highly 8cm; The length of described rectangle anchor slab is 15cm, and width is 10cm, and thickness is 1cm; The diameter of described bar dowel is 1cm.
The bottom of described precast concrete body is embedded with suspension ring.
The prefabricated hollow steel bar concrete flag of the utility model, compare with traditional road pavement and method for maintaining, has structural strength high, is convenient to transportation, reusable, and the advantage such as construct efficient is in particular in the following aspects:
1) convenient transportation.Although structure is built by steel concrete, the volume of each piece is little, and is standardized structural element, transports more convenient.
2) Fast Installation, easy construction.Structure top is provided with built-in fitting, makes installing and the removal of prefabricated hollow steel bar concrete flag pavement system hoisting ring very convenient, and then makes the lifting of this prefabricated hollow steel bar concrete flag pavement system very convenient.In when construction, first reinforced concrete strip foundation is lifted into to smooth road surface, the darker beam slab of steel concrete is lifted on strip foundation, after having spliced, between between piece and piece and piece and basis, without any need for being connected, can use.
3) the required plant equipment of constructing is few, and material usage is economized, and low its of energy consumption can be reused, and greatly reduces construction costs and other expense.Because filling prefabricated reinforced concrete strip foundation and the dark beam slab of prefabricated reinforced concrete, be prefabricated in the factory, at the construction field (site), only need be by grading, lifting is laid this prefabricated hollow steel bar concrete flag pavement system and is got final product, to temporary road, be finished rear recyclablely, in order to using next time, further save material usage.
4) pavement construction is few to ambient influnence.Traditional pavement construction needs more construction machinery, produces larger noise during the construction machinery operation.Simultaneously, in traditional pavement engineering construction, waste material of buildings is more, comprises water conservancy, timber, packaging material, discarded mould etc.These refuses are buried under the ground, and can cause the pollution of underground water.The utility model is prefabricated at workshop, and refuse is less and can focus on, on the almost not impact of job site environment.
5) spread i.e. use, open to traffic early.Once laying construction is complete, just open to traffic immediately after the removal suspension ring.Even can be open to traffic on construction limit, limit, be conducive to conveniently marching into the arena of construction machinery and Construction traffic, accelerating construction progress.The time that is open to traffic after construction of cement concrete road surface is greater than 16 days, and the time that is open to traffic after asphalt concrete pavement construction is greater than 3 days, and the prefabricated hollow steel bar concrete flag pavement system that the utility model adopts can spread i.e. use, and even limit paving is just used.
6) dismounting freely.Prefabricated hollow steel bar concrete flag pavement system is reusable, can lay in advance, is transported to when needed on-the-spot the laying and gets final product.Built-in fitting is housed in structure, installs, the removal suspension ring are very convenient, structure hoisting fashionable dress upper lift ring is Liftable.
7) technique is simple, and cost is lower, and prefabricated hollow steel bar concrete flag pavement system adopts ordinary reinforced concrete as preparing material, and the cost of material is low, and structure is unified standard size, Mold Making and build all very convenient.Applied widely.Prefabricated hollow steel bar concrete flag pavement system is applicable to have the various roadbeds of certain bearing capacity, can not only be used in the laying of construction with interim matter transportation road, can also be used for rushing to repair the road be damaged in earthquake.
8) by prefabricated reinforced concrete road slab and prefabricated inverted T shape strip foundation contact surface, being lined with the L-type rubber pad, submit the vibration damping and vibration isolation effect of bridge to, improve the application life of bridge.
The accompanying drawing explanation
Below in conjunction with accompanying drawing, the utility model is described in more detail.Fig. 1 is the plan view of prefabricated hollow steel bar concrete flag.
Fig. 2 is the A-A sectional view one of Fig. 1.
Fig. 3 is the A-A sectional view two of Fig. 1.
Fig. 4 is the B-B sectional view of Fig. 1.
Fig. 5 is the fiber tube detail drawing.
Fig. 6 is Fig. 5 top view.
Reference numeral: 1-precast concrete body, 1.1-through hole, 2-plate master muscle, 3-suspension ring, 4-fiber tube, 4.1-internal thread sleeve pipe, 4.2-external screw thread rod iron, 4.3-rectangle anchor slab, 4.4-bar dowel.
The specific embodiment
Embodiment is referring to shown in Fig. 1 to 4, a kind of prefabricated hollow steel bar concrete flag, by precast concrete body 1, the fiber tube 4 that is wrapped in the plate master muscle 2 in plate body and is embedded in precast concrete body 1 top, formed, described precast concrete body 1 is 3m for length, width is 1m, the cuboid calibrated bolck that thickness is 0.3m, long to for evenly offering and through hole 1.1 along it, described plate master muscle 2 is distributed in top and the bottom of precast concrete body 1.
Described fiber tube 4 is at least four, is distributed in precast concrete body 1 top near corner positions.
Described fiber tube 4 is comprised of internal thread sleeve pipe 4.1, external screw thread rod iron 4.2, rectangle anchor slab 4.3 and bar dowel 4.4, described external screw thread rod iron 4.2 is vertically welded in rectangle anchor slab 4.3 centers, described internal thread sleeve pipe 4.1 and external screw thread rod iron 4.2 are threaded, described bar dowel 4.4 is symmetrically welded at external screw thread rod iron 4.2 both sides near rectangle anchor slab 4.3 marginal positions, and rectangle anchor slab 4.3 edges are all exposed at its two ends.Described internal thread sleeve pipe 4.1 external diameters are 4cm, and internal diameter is 2cm, are highly 8cm; The diameter of described external screw thread rod iron 4.2 is 2cm, is highly 8cm; The length of described rectangle anchor slab 4.3 is 15cm, and width is 10cm, and thickness is 1cm; The diameter of described bar dowel 4.4 is 1cm, referring to Fig. 5 and Fig. 6.
The bottom of described precast concrete body 1 is embedded with suspension ring 3, and described suspension ring 3 are welded to connect with the plate master muscle 2 of bottom.Described suspension ring 3 are formed by the reinforcing bar bending or are the finished product suspension ring.
Adopt described prefabricated hollow steel bar concrete flag to carry out pavement construction method, step is as follows:
Step 1, prefabricated inverted T shape strip foundation;
Step 2, prefabricated assembled precast hollow reinforced concrete pavement plate; Prefabricated process is: colligation plate master muscle 2, and at the default fiber tube 4 of its soffit, and the plate master muscle 2 at described fiber tube 4 tops and top is welded to connect, and then build precast concrete body 1 and carry out maintenance, and surface programming suspension ring 3 thereon;
Step 3, after the sheet metal forming of prefabricated hollow steel bar rigid pavement, catch on suspension ring by crane gear, prefabricated hollow steel bar concrete flag is sling, the demoulding, then suspension ring are cut off, and prefabricated hollow steel bar concrete flag upset is made to facing up with fiber tube 4;
Step 4, remove roadbase, and will flatten by machinery;
Step 5, be transported to job site by prefabricated inverted T shape strip foundation and prefabricated hollow steel bar concrete flag;
Step 6, at the pre-buried position of inverted T shape strip foundation end face fiber tube dress suspension ring, winch to installation site by the inverted T shape strip foundation, lays down suspension ring;
Step 7, at the step place of prefabricated inverted T shape strip foundation pad L-type rubber pad;
Step 8, adopt the mode identical with lifting inverted T shape strip foundation that prefabricated hollow steel bar concrete flag is winched to installation site, and be erected at T-shaped strip foundation step place, and and the edge of a wing of T-shaped strip foundation and web holds out against between road slab and banket in both sides.And banket and jolt ramming to the place, gap that connects between plate and plate, for travelling of vehicle provides the environment of an opposed flattened.Also want earth filling tamping in plate body both sides, road surface, to improve the lateral stability of road slab.
The length of described prefabricated inverted T shape strip foundation is 4m, and flange width is 1m, and edge of a wing thickness is 0.3m, web width 0.5m, and web height 0.35m, be also standard component.

Claims (5)

1. a prefabricated hollow steel bar concrete flag, it is characterized in that: by precast concrete body (1), the fiber tube (4) that is wrapped in the plate master muscle (2) in plate body and is embedded in precast concrete body (1) top, formed, described precast concrete body (1) is 3m for length, width is 1m, the cuboid calibrated bolck that thickness is 0.3m, long to for evenly offering and through hole (1.1) along it, described plate master muscle (2) is distributed in top and the bottom of precast concrete body (1).
2. prefabricated hollow steel bar concrete flag according to claim 1, it is characterized in that: described fiber tube (4) is at least four, is distributed in precast concrete body (1) top near corner positions.
3. prefabricated hollow steel bar concrete flag according to claim 1, it is characterized in that: described fiber tube (4) is by internal thread sleeve pipe (4.1), external screw thread rod iron (4.2), rectangle anchor slab (4.3) and bar dowel (4.4) form, described external screw thread rod iron (4.2) is vertically welded in rectangle anchor slab (4.3) center, described internal thread sleeve pipe (4.1) and external screw thread rod iron (4.2) are threaded, described bar dowel (4.4) is symmetrically welded at external screw thread rod iron (4.2) both sides near rectangle anchor slab (4.3) marginal position, rectangle anchor slab (4.3) edge is all exposed at its two ends.
4. prefabricated hollow steel bar concrete flag according to claim 3, it is characterized in that: described internal thread sleeve pipe (4.1) external diameter is 4cm, and internal diameter is 2cm, is highly 8cm; The diameter of described external screw thread rod iron (4.2) is 2cm, is highly 8cm; The length of described rectangle anchor slab (4.3) is 15cm, and width is 10cm, and thickness is 1cm; The diameter of described bar dowel (4.4) is 1cm.
5. according to the described prefabricated hollow steel bar concrete flag of claim 1 or 3, it is characterized in that: the bottom of described precast concrete body (1) is embedded with suspension ring (3).
CN201320371155.7U 2013-06-26 2013-06-26 Prefabricated hollow reinforced concrete pavement slab Withdrawn - After Issue CN203373630U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320371155.7U CN203373630U (en) 2013-06-26 2013-06-26 Prefabricated hollow reinforced concrete pavement slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320371155.7U CN203373630U (en) 2013-06-26 2013-06-26 Prefabricated hollow reinforced concrete pavement slab

Publications (1)

Publication Number Publication Date
CN203373630U true CN203373630U (en) 2014-01-01

Family

ID=49836175

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320371155.7U Withdrawn - After Issue CN203373630U (en) 2013-06-26 2013-06-26 Prefabricated hollow reinforced concrete pavement slab

Country Status (1)

Country Link
CN (1) CN203373630U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103334358A (en) * 2013-06-26 2013-10-02 中国建筑股份有限公司 Fabricated precast hollow reinforced concrete pavement slab and pavement construction method
CN105839504A (en) * 2016-03-24 2016-08-10 杭州江润科技有限公司 Assembly type cement pavement construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103334358A (en) * 2013-06-26 2013-10-02 中国建筑股份有限公司 Fabricated precast hollow reinforced concrete pavement slab and pavement construction method
CN103334358B (en) * 2013-06-26 2015-10-28 中国建筑股份有限公司 Prefabricated hollow steel bar concrete flag and pavement construction method
CN105839504A (en) * 2016-03-24 2016-08-10 杭州江润科技有限公司 Assembly type cement pavement construction method
CN105839504B (en) * 2016-03-24 2018-01-16 济南长兴建设集团有限公司 Assembled cement pavement construction method

Similar Documents

Publication Publication Date Title
CN103334356B (en) The dark beam slab pavement system of bridge-type prefabricated reinforced concrete and construction method thereof
CN103334359B (en) Prefabricated reinforced concrete pavement plate and pavement construction method
CN103334361B (en) Prefabricated hollow steel bar concrete wear resistant road surface plate and pavement construction method
CN103866670B (en) Fabricated vehicle bearing pavement and construction method thereof
CN103352471B (en) Container prefabricated house assembling type steel reinforced concrete single-double-column foundation and construction method thereof
CN103343503B (en) Bridge-type prefabricated reinforced concrete trough slab wear resistant road surface structural system and construction method
CN103334360B (en) The dark beam slab wear-resistant pavement system of bridge-type prefabricated reinforced concrete and construction method thereof
CN103343547B (en) Container type prefabricated house assembling steel reinforced concrete four patten and construction method
CN203373630U (en) Prefabricated hollow reinforced concrete pavement slab
CN203768757U (en) Novel assembled vehicle bearing pavement
CN203373631U (en) Prefabricated reinforced concrete pavement slab
CN203373635U (en) Prefabricated hollow reinforced concrete wearproof pavement slab
CN103334362B (en) Prefabricated steel concrete wear resistant road surface plate and pavement construction method
CN203373624U (en) Bridge prefabricated reinforced concrete hidden beam slab wearproof pavement system
CN103850162B (en) Bridge-type combining structure pavement system and construction method thereof
CN109811613B (en) Temporary ground facility and integrated construction method thereof
CN203429528U (en) Bridge-type precast-reinforced-concrete-trough-plate wear-resistant pavement structure system
CN101929245A (en) Thin webbed girder vertical construction method
CN103334358B (en) Prefabricated hollow steel bar concrete flag and pavement construction method
CN203373629U (en) Prefabricated reinforced concrete wearproof pavement slab
CN203429655U (en) Assembly type steel reinforced concrete single-double column foundation for container prefabricated house
CN203373625U (en) Bridge prefabricated reinforced concrete hidden beam slab pavement system
CN203768753U (en) Bridge type steel plate pavement system
CN103850163B (en) Bridge-type steel plate pavement system and construction method thereof
CN203905035U (en) Novel stacking type foundation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20140101

Effective date of abandoning: 20151028

C25 Abandonment of patent right or utility model to avoid double patenting