The fume desulfurizing tower spray equipment
Technical field
The utility model relates to a kind of smoke gas treatment environmental protection equipment, is specifically related to a kind of fume desulfurizing tower spray equipment.
Background technology
Desulfurizing tower is industrial waste gas to be carried out to the equipment of desulfurization processing, and spray pipeline is one of most critical device of desulfurizing tower.Slurries are sent in spray pipeline through circulating pump, be atomized into tiny drop from nozzle ejection and evenly be scattered to surrounding, and with the abundant haptoreaction of the flue gas moved upward, thereby remove sulfur dioxide.Spray pipeline is used after a period of time and easily produces impurity (as pipe lining rubber comes off, desulfurizing agent impurity, outside rubbish etc.) and pile up, cause shower, spray nozzle clogging in desulfurizing tower, affect desulfuration efficiency, and the time maintenance difficulty of breaking down, also can't realize on-bne repair, thereby affect the stability and safety operation of whole desulphurization system.
The utility model content
For solving the above deficiency existed in prior art, the utility model provides a kind of fume desulfurizing tower spray equipment, and it can realize on-bne repair, has simple in structure, long service life, characteristics that maintenance cost is low.
For achieving the above object, the technical scheme that the utility model adopts is as follows:
A kind of fume desulfurizing tower spray equipment, comprise spray pipeline, described spray pipeline comprises house steward for delivery of slurries, be arranged at mother's pipe that the desulfurizing tower outside is communicated with house steward, many manage through tube connector and mother the arms that are communicated with respectively; Described arm is fixed on desulfurizing tower by the fixture be fixed on the desulfurizing tower outer wall, and an end of arm is equipped with nozzle and stretches into desulfurizing tower inside; On described tube connector, control valve is housed.
As to restriction of the present utility model, described fixture comprises the sleeve pipe be welded on the desulfurizing tower outer wall; The end of described sleeve pipe is fixedly connected with the first flange, and being positioned on the outer position of desulfurizing tower of described arm is fixedly connected with the second flange, and arm is connected and is fixed on sleeve pipe with the second flange by the first flange.
As another kind of the present utility model is limited, the quantity of described arm is less than or equals in eight, and these arms are in same sagittal plane spaced at equal angles around.
As to the third restriction of the present utility model, between described arm and tube connector, adopt flange to be connected.
As to the 4th kind of restriction of the present utility model, between described control valve and tube connector, adopt flange to be connected.
The utility model also has a kind of restriction, when described arm and sleeve pipe are separated, is fixed with the seal cover for Sealed casing pipe on the first flange.
Owing to having adopted technique scheme, compared with prior art, obtained technological progress is the utility model:
1. female pipe is arranged on the desulfurizing tower outside, is convenient to the preservative treatment in tower, can be completely achieved the on-bne repair of desulfurizing tower; In addition, the corresponding shower nozzle of each arm, arm adopts tube connector to be connected with female pipe, has effectively improved the pipeline terminal pressure, has improved the reliability of desulfurization, has alleviated maintenance workload;
2. after desulfurizing tower is used a period of time, if there is problems such as spray nozzle clogging, arm foulings, while needing maintenance, at first closed control valve, stop to arm feed slurries female pipe, then separate the first flange and the second flange, three-flange and the 4th flange, arm is withdrawn from from desulfurizing tower, and last fit sealing lid and the first flange and then Sealed casing pipe, carry out on-bne repair, without the stoppage in transit desulfurizing tower, thereby reach on-bne repair, purpose for ease of maintenaince.
In sum, the utlity model has simple in structure, long service life, characteristics that maintenance cost is low.。
The utility model is applicable to being applied to the following desulfurizing tower of 3.5m.
The accompanying drawing explanation
Below in conjunction with drawings and the specific embodiments, the utility model is done further to describe in detail.
The structural representation that Fig. 1 is the utility model embodiment;
The partial sectional view that Fig. 2 is Fig. 1.
Fig. 3-5 are respectively the structural representation of the first flange 5, the second flange 8 and seal cover 14 in Fig. 1.
In figure: 1, house steward; 2, female pipe; 3, arm; 4, sleeve pipe; 5, the first flange; 6, control valve; 7, nozzle; The 8~12, second~six flange; 13, tube connector; 14, seal cover; 15, desulfurizing tower outer wall.
The specific embodiment
Embodiment
A kind of fume desulfurizing tower spray equipment, structure as shown in Figure 1-2, comprises spray pipeline.
Spray pipeline comprises house steward 1 for delivery of slurries, be arranged at that mother that the desulfurizing tower outside is communicated with house steward 1 manages 2, many arms 3 of managing respectively 2 distributions of equal angles in same sagittal plane that are communicated with mother.Be fixed with fixture on desulfurizing tower outer wall 15, arm 3 is fixed on desulfurizing tower by fixture, and an end of arm 3 is connected with female pipe 2 by tube connector 13, and the other end is equipped with nozzle 7 and stretches into desulfurizing tower inside.
Fixture is the sleeve pipe 4 be welded on desulfurizing tower outer wall 15, and the end of sleeve pipe 4 is fixedly connected with the first flange 5, the round-meshed circle in position or with the polygonized structure of square hole, as shown in Figure 3 centered by it.Being positioned on the outer position of desulfurizing tower of arm 3 is fixedly connected with the second flange 8, and its size is identical with the first flange 5, centered by the round-meshed circle in position or round-meshed polygonized structure, as shown in Figure 4.Arm 3 is connected and fixed the first flange 5 and the second flange 8 and is fixed on sleeve pipe 4 by screw.
The outer end of desulfurizing tower that is positioned at of arm 3 is fixedly connected with three-flange 9, and the end be connected with arm 3 of tube connector 13 is fixedly connected with the 4th flange 10, and arm 3 and tube connector 13 are by being connected and fixed three-flange 9 with screw and the 4th flange 10 links into an integrated entity.
The 5th flange 11, the 6th flange 12 are housed on tube connector 13, control valve 6 is housed between the two-stage method orchid.
Arm 3 and sleeve pipe 4 is fixed with the seal cover 14 for Sealed casing pipe 4 after removing and separating on the first flange 5, its size is identical with the size of the first flange 5, is circle or polygonized structure, as shown in Figure 5.
The present embodiment is applicable to being applied to the following desulfurizing tower of 3.5m, and the quantity of arm 3 mostly is eight most.
In the present embodiment running, if there is problems such as nozzle 7 obstructions, arm 3 foulings, while needing maintenance, at first closed control valve 6, female pipe 2 is stopped to arm 3 feed slurries, then remove to connect the first flange 5 and the second flange 8 screw, be connected the screw of three-flange 9 and the 4th flange 10, arm 3 is withdrawn from from desulfurizing tower, finally use screw by seal cover 14 and the first flange 5 fit sealings, carry out on-bne repair, without the stoppage in transit desulfurizing tower, thereby reach on-bne repair, purpose for ease of maintenaince.