CN202666682U - Novel spraying device of industrial smoke gas desulfurization tower - Google Patents

Novel spraying device of industrial smoke gas desulfurization tower Download PDF

Info

Publication number
CN202666682U
CN202666682U CN 201220352642 CN201220352642U CN202666682U CN 202666682 U CN202666682 U CN 202666682U CN 201220352642 CN201220352642 CN 201220352642 CN 201220352642 U CN201220352642 U CN 201220352642U CN 202666682 U CN202666682 U CN 202666682U
Authority
CN
China
Prior art keywords
desulfurization tower
desulfurizing tower
spraying device
tower wall
branch pipes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220352642
Other languages
Chinese (zh)
Inventor
陈元芝
陈凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 201220352642 priority Critical patent/CN202666682U/en
Application granted granted Critical
Publication of CN202666682U publication Critical patent/CN202666682U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model discloses a novel spraying device of an industrial smoke gas desulfurization tower; and the novel spraying device comprises a desulfurization tower wall and a spraying pipeline, wherein the spraying pipeline comprises a parent pipe and at least six branch pipes; the parent pipe is arranged on the external side of the desulfurization tower wall; through external pipeline interfaces, the branch pipes are connected with the parent pipe by hoses; the other ends of the branch pipes are connected with a nozzle by connecting pieces; the tail ends of the branch pipes are connected with the desulfurization tower wall by sealing flanges; and connecting pipe sleeves are arranged between the branch pipes and the desulfurization tower wall. The novel spraying device of the industrial smoke gas desulfurization tower, disclosed by the utility model, has the advantages as follows: special design as well as simplicity and convenience in operation are achieved, pipeline resistance is obviously reduced, the lift of a circulating pump can be also reduced, a problem that the traditional spraying device cannot be overhauled online does not exist, and operation cost and investment cost are low.

Description

Infant industry fume desulfurizing tower spray equipment
Technical field
The utility model relates to a kind of desulfurizing industrial fume environmental protection equipment that belongs to.
Background technology
During " 12 "; sulfur dioxide will realize reducing discharging 8% the binding indicator; according to country's " 12 " environmental protection plans, realize this goal, China's SO2 emissions will be reduced to from 2267.8 ten thousand tons in 2010 2086.4 ten thousand tons in 2015.Meanwhile, the coal in China consumption figure estimates to be risen to by 3,000,000,000 tons in 2010 3,800,000,000 tons in 2015.Therefore, the sulfur dioxide emission reduction tasks is very arduous.Prior art is to adopt the Wet Flue Gas Desulfurization Technology desulfurization, the as easy as rolling off a log generation of wet desulphurization spray system owing to impurity (as pipe lining rubber come off, desulfurizing agent impurity, outside rubbish etc.) assemble the shower, the shower nozzle clogging that cause in the desulfurizing tower, affect desulfuration efficiency, and the time maintenance difficulty of breaking down, also can't realize on-bne repair, thereby affect the stability and safety operation of whole desulphurization system.
Summary of the invention
Technical problem to be solved in the utility model is the blockage problem of spray system.
For solving this technical problem, the utility model provides a kind of infant industry fume desulfurizing tower spray equipment, comprise desulfurizing tower wall and spray pipeline, described spray pipeline comprises female pipe and at least 6 arms, female pipe is arranged on the outside of desulfurizing tower wall, arm adopts flexible pipe to be connected on female pipe by the exterior line interface, and the other end of arm is connected with shower nozzle by connector.
The end of described arm and desulfurizing tower wall adopt sealing flange to be connected, and are provided with between arm and the desulfurizing tower wall to be connected pipe box.
Described arm is provided with 8.
Beneficial effect: the utility model design is unique, easy and simple to handle, and the resistance of ducting obviously reduces, and also can reduce the pump lift that circulates, and does not exist traditional spray equipment can't carry out the problem of on-bne repair, and operating cost and investment cost are low.
Description of drawings
Fig. 1 is shower monomer structure schematic diagram of the present utility model;
Fig. 2 is the female tubular construction schematic diagram of spray of the present utility model;
Fig. 3 is spray coverage rate schematic diagram of the present utility model.
Among the figure: 1 female pipe, 2 desulfurizing tower walls, 3 exterior line interfaces, 4 sealing flanges, 5 connect pipe box, 6 arms, 7 connectors, 8 shower nozzles.
The specific embodiment
The utility model is to use for reference conventional wet sulfur removal technology, innovation on this basis.
Below in conjunction with drawings and Examples the utility model is done specific descriptions.
Figure 1 shows that shower monomer structure schematic diagram of the present utility model.
The utility model comprises desulfurizing tower wall 2 and spray pipeline.
Described spray pipeline comprises female pipe 1 and at least 6 arms 6, and female pipe 1 is arranged on the outside of desulfurizing tower wall 2, and arm 6 adopts flexible pipe to be connected on female pipe 1 by exterior line interface 3, and the other end of arm 6 is connected with shower nozzle 8 by connector 7.
The spray pipeline of desulphurization system is arranged on desulfurizing tower wall 2 outsides, and tower is interior without any supporting member, is convenient to the preservative treatment in the tower, can be completely achieved the on-bne repair of desulfurizing tower.
Adopt the design of each road arm 6 corresponding shower nozzle 8, arm 6 adopts flexible pipe to be connected with female pipe 1, and Effective Raise pipeline terminal pressure no longer arranges the spray piping support in the tower, improve the reliability of desulfurization, reduces maintenance workload.
The end of described arm 6 adopts sealing flange 4 to be connected with desulfurizing tower wall 2, be provided with between arm 6 and the desulfurizing tower wall 2 and be connected pipe box 5, in the situation that shower nozzle occurs to stop up, only need take adpting flange apart and extract shower nozzle and can clear up it, need not the desulfurizing tower of stopping transport, be convenient to online dismounting maintenance.
Figure 2 shows that the female tubular construction schematic diagram of spray of the present utility model.
Described arm 6 is provided with 8.
Injection apparatus in the desulfurizing tower as described in Figure 2 is comprised of 8 spray unit, spray area coverage wide (as shown in Figure 3), reach the area coverage more than 200%, single shower nozzle water spray is very big, makes flue gas and desulfurization take off the agent adverse current and fully mixes and contact, and the reaction effect angle is good, consider anticorrosion and high temperature problem all adopts the acid-proof wear-proof temperature-resistant material to make, compact conformation, intensity is high, and the stability of a system is high.
The utility model design is unique, easy and simple to handle, and the resistance of ducting obviously reduces, and also can reduce the pump lift that circulates, and does not exist traditional spray equipment can't carry out the problem of on-bne repair, and operating cost and investment cost are low.
The above-mentioned embodiment of the utility model just illustrates, and is not only, all in the utility model scope or the change that is equal in the scope of the present utility model all surrounded by the utility model.

Claims (3)

1. infant industry fume desulfurizing tower spray equipment, comprise desulfurizing tower wall (2) and spray pipeline, it is characterized in that: described spray pipeline comprises female pipe (1) and at least 6 arms (6), female pipe (1) is arranged on the outside of desulfurizing tower wall (2), arm (6) adopts flexible pipe to be connected on female pipe (1) by exterior line interface (3), and the other end of arm (6) is connected with shower nozzle (8) by connector (7).
2. infant industry fume desulfurizing tower spray equipment according to claim 1, it is characterized in that: the end of described arm (6) and desulfurizing tower wall (2) adopt sealing flange (4) to be connected, and are provided with between arm (6) and the desulfurizing tower wall (2) to be connected pipe box (5).
3. infant industry fume desulfurizing tower spray equipment according to claim 1, it is characterized in that: described arm (6) is provided with 8.
CN 201220352642 2012-07-20 2012-07-20 Novel spraying device of industrial smoke gas desulfurization tower Expired - Fee Related CN202666682U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220352642 CN202666682U (en) 2012-07-20 2012-07-20 Novel spraying device of industrial smoke gas desulfurization tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220352642 CN202666682U (en) 2012-07-20 2012-07-20 Novel spraying device of industrial smoke gas desulfurization tower

Publications (1)

Publication Number Publication Date
CN202666682U true CN202666682U (en) 2013-01-16

Family

ID=47487618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220352642 Expired - Fee Related CN202666682U (en) 2012-07-20 2012-07-20 Novel spraying device of industrial smoke gas desulfurization tower

Country Status (1)

Country Link
CN (1) CN202666682U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107362673A (en) * 2017-07-19 2017-11-21 合肥天翔环境工程有限公司 A kind of spraying device of desulfurizing tower
EP3685906A4 (en) * 2017-09-20 2021-06-23 Mitsubishi Power, Ltd. Desulfurization device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107362673A (en) * 2017-07-19 2017-11-21 合肥天翔环境工程有限公司 A kind of spraying device of desulfurizing tower
EP3685906A4 (en) * 2017-09-20 2021-06-23 Mitsubishi Power, Ltd. Desulfurization device
US11364467B2 (en) 2017-09-20 2022-06-21 Mitsubishi Power, Ltd. Desulfurization device

Similar Documents

Publication Publication Date Title
CN202666682U (en) Novel spraying device of industrial smoke gas desulfurization tower
CN203355598U (en) Spray device of flue gas desulfurization tower
CN204469544U (en) A kind of spraying device of desulfurizing tower
CN208436648U (en) A kind of spray equipment of fume desulfurizing tower
CN202590629U (en) Selective catalytic reduction (SCR) inlet flue soot blower
CN104315528A (en) Desulfurizer body device for boiler dedusting
CN206942854U (en) Tail-gas purifier of vehicle
CN202666681U (en) Pretreatment device at inlet of flue gas desulfurization tower
CN203170205U (en) High efficient desulfurization tower
CN203710904U (en) Transverse semi-drying desulfurization device for tail flue of boiler
CN201482415U (en) Spray apparatus of coal-fired boiler desulfurizing tower
CN207371348U (en) Side-feeding type high-efficiency desulfurization spray equipment
CN204254648U (en) A kind of desulfurizing tower body device for boiler dusting
CN218795066U (en) Dry desulfurization and denitrification device for flue gas dust removal
CN205127695U (en) Dry reaction tower
CN204141604U (en) Outer circulation chimney for wet flue gas desulfurization
CN202155144U (en) Outlet elbow pipe of slurry circulating pump
CN203235362U (en) Mobile desulfurizing and dedusting device
CN205164486U (en) Novel improve wet flue gas desulfurization system mass transfer efficiency device
CN204051250U (en) Desulfation dust-extraction device
CN203437016U (en) Desulfurization absorption tower
CN216935446U (en) Circulating flue gas desulfurization and denitrification tower
CN210495813U (en) Double-tower double-circulation desulfurization device
CN203857474U (en) Coal-fired boiler catalytic combustion-supporting and SNCR (Selective Non Catalytic Reduction) combined denitration device
CN201227579Y (en) Wet-method flue gas desulfurization system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130116

Termination date: 20130720