CN203345923U CN 201320242318 CN201320242318U CN203345923U CN 203345923 U CN203345923 U CN 203345923U CN 201320242318 CN201320242318 CN 201320242318 CN 201320242318 U CN201320242318 U CN 201320242318U CN 203345923 U CN203345923 U CN 203345923U
Authority
CN
China
Prior art keywords
support beam
fixed
arm assembly
hanging apparatus
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201320242318
Other languages
Chinese (zh)
Inventor
常治
张世海
司万强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRRC Datong Co ltd
Original Assignee
CNR Datong Electric Locomotive Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNR Datong Electric Locomotive Co Ltd filed Critical CNR Datong Electric Locomotive Co Ltd
Priority to CN 201320242318 priority Critical patent/CN203345923U/en
Application granted granted Critical
Publication of CN203345923U publication Critical patent/CN203345923U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model provides a hoisting device for a large built-in component. The hoisting device comprises a base, a supporting pillar, at least two suspension arm components, a cross beam and a hoisting plate, wherein the base is provided with a first supporting beam and a second supporting beam, the first supporting beam is vertically arranged, the second supporting beam is horizontally arranged, and one end of the first supporting beam is fixed in the middle of the second supporting beam; the supporting pillar is vertically arranged and movably fixed at the other end, far away from the second supporting beam, of the first supporting beam; the suspension arm components are horizontally arranged and symmetrically and movably fixed at two ends of the second supporting beam; the cross beam is fixed on the supporting pillar and is opposite to the suspension arm components; the hoisting plate is fixed on the cross beam, and a hoisting through hole is formed between the hoisting plate and the cross beam; and a notch with one opened side is defined by the first supporting beam, the supporting pillar, the cross beam and each suspension arm component and used for accommodating the large built-in component. The hoisting device is matched with power mechanical equipment such as a crown block and the like and can directly hoist the large built-in component into a locomotive cabinet, so that the mounting efficiency of the large built-in component is improved.

Description

Built-in large parts hanging apparatus
Technical field
The utility model relates to mechanical technique, relates in particular to a kind of built-in large parts hanging apparatus.
Background technology
Locomotive usually needs large component is installed in cabinet in producing.Such as, big-and-middle-sized voltage transformer is the important component part of HXD2 type series cab screen cabinet, and two three large-scale AC transformer are arranged in the HXD2B auxiliary converter cabinet; Two preheating transformers are arranged in the HXD2B general cabinet.During installation, voltage transformer need be installed in locomotive screen cabinet.
The lifting voltage transformer of take is example.Because big-and-middle-sized voltage transformer weight is large, volume is large, the electrical appliance screen cabinet inner space is narrow and small, and big-and-middle-sized voltage transformer need be put in locomotive screen cabinet along the opening of locomotive screen cabinet side.In actual production, can use the overhead traveling crane voltage transformer of slinging, still, due to stopping of edge on locomotive screen cabinet, voltage transformer is difficult to directly put in locomotive screen cabinet.Another kind method is to use lift car that voltage transformer is put in locomotive screen cabinet, and because lift car moves inconvenience, voltage transformer is installed difficulty, and installation effectiveness is low.Visible, there is no at present the general lifting device of built-in large parts, the inefficiency that built-in large parts are installed.
The utility model content
The utility model provides a kind of built-in large parts hanging apparatus, for coordinating with motive power machine equipment, so that built-in large parts directly are lifted in locomotive screen cabinet, improves the installation effectiveness of built-in large parts.
The utility model provides a kind of built-in large parts hanging apparatus, wherein, comprising:
Pedestal, have the first support beam and the second support beam, and described the first support beam vertically arranges, described the second support beam horizontally set, and an end of described the first support beam and the middle part of described the second support beam are fixed;
Pillar stiffener, vertically arrange and be movably fixed to the other end of described the first support beam away from described the second support beam;
The arm assembly, be at least two, is horizontally disposed with, symmetrical and be movably fixed to the two ends of described the second support beam;
Crossbeam, be fixed on described pillar stiffener, and be oppositely arranged with described arm assembly;
The lifting plate, be fixed on described crossbeam, between described lifting plate and described crossbeam, is formed with the lifting through hole;
Wherein, described the first support beam, pillar stiffener, crossbeam and each described arm assembly surround the open recess of a side, and described recess is for accommodating described built-in large parts.
Hanging apparatus as above, preferably,
Vertically offer several the first mounting holes on described the first support beam, on described pillar stiffener, correspondence offers several the second mounting holes, between described the first support beam and described pillar stiffener, by described the first mounting hole and the second mounting hole, fixes.
Hanging apparatus as above, preferably,
The two ends of described the second support beam laterally offer several the first fixed orifices, on each described arm assembly, to several the second fixed orifices should be arranged, are fixed on the two ends of described the second support beam between each described arm assembly by described the first fixed orifice and the second fixed orifice.
Hanging apparatus as above, preferably, described arm assembly comprises:
Arm,
Mount pad, comprise four flat boards that surround closed circular, and wherein a described flat board and described arm are fixed, and on the described flat board away from described arm, offers described the second fixed orifice.
Hanging apparatus as above, preferably, described arm assembly also comprises:
Floor, be fixed between arm and described mount pad.
Hanging apparatus as above, preferably,
Described the first fixed orifice and the second fixed orifice are all bolt hole.
Hanging apparatus as above, preferably,
Described the first mounting hole and the second mounting hole are all pin-and-hole.
Hanging apparatus as above, preferably,
Be provided with several grooves on described lifting plate, each described groove is communicated with described lifting through hole.
The hanging apparatus that technique scheme provides, position by the movable support post, making crossbeam and lift plate can be higher than the upper edge of locomotive screen cabinet, during lifting, crossbeam and lifting plate can not play inhibition, built-in large parts can directly be hung in locomotive screen cabinet, have improved the installation effectiveness of built-in large parts.
The accompanying drawing explanation
Fig. 1 is built-in large block construction schematic diagram to be lifted;
The hanging apparatus structural representation that Fig. 2 provides for the utility model embodiment;
Fig. 3 is arm assembly structural representation in Fig. 2.
The specific embodiment
Fig. 1 is built-in large block construction schematic diagram to be lifted, and specifically signal is voltage transformer, the hanging apparatus structural representation that Fig. 2 provides for the utility model embodiment, and Fig. 3 is arm assembly structural representation in Fig. 2.
The utility model embodiment provides a kind of built-in large parts hanging apparatus, for coordinating with motive power machine equipments such as overhead traveling cranes, so that built-in large parts 7 are lifted in locomotive screen cabinet.Built-in large parts 7 lift into the big-and-middle-sized parts in locomotive screen cabinet for any needs, such as big-and-middle-sized voltage transformer, and three AC transformer in the HXD2B auxiliary converter cabinet, the preheating transformer in the HXD2B general cabinet.Hanging apparatus comprises pedestal 1, pillar stiffener 2, arm assembly 3, crossbeam 4 and lifting plate 5.Pedestal 1, have the first support beam 11 and the second support beam 12, and described the first support beam 11 vertically arranges, described the second support beam 12 horizontally sets, and an end of described the first support beam 11 and the middle part of described the second support beam 12 are fixed.Pillar stiffener 2 vertically arranges and is movably fixed to the other end of described the first support beam 11 away from described the second support beam 12.Arm assembly 3 is at least two, is horizontally disposed with, symmetrical and be movably fixed to the two ends of described the second support beam 12.Crossbeam 4 is fixed on described pillar stiffener 2, and is oppositely arranged with described arm assembly 3.Lifting plate 5 is fixed on described crossbeam 4, is formed with lifting through hole 6 between described lifting plate 5 and described crossbeam 4.Wherein, described the first support beam 11, pillar stiffener 2, crossbeam 4 and each described arm assembly 3 surround the open recess of a side, and described recess is for accommodating described built-in large parts 7.Offer hole for hoist 71 on built-in large parts 7, hole for hoist 71 is for coordinating with arm assembly 3.
Pedestal plays skeleton function, and provides support for the installation of pillar stiffener and arm assembly.Pillar stiffener and arm assembly are all movable fixing, and the pillar stiffener vertical direction can move along the first support beam, makes hanging apparatus can adapt to the built-in large parts of differing heights, and make crossbeam and the lifting plate can be higher than the upper edge of locomotive screen cabinet.The arm assembly is horizontally disposed with, and can move along the second support beam, and the variable-width between the arm assembly makes hanging apparatus can adapt to the built-in large parts of different in width.Pillar stiffener and the mating reaction of arm assembly, hanging apparatus can adapt to the built-in large parts of differing heights, width.
The mode that pillar stiffener is movably fixed to the first support beam has a variety of, such as sliding, establishes; Adopt a plurality of positions that are fixed; Latching device perhaps is set, after pillar stiffener is moved to the correct position on the first support beam, uses latching device locking.
In like manner, the mode that the arm assembly is movably fixed to the second support beam also has multiple.
Crossbeam and each arm assembly are oppositely arranged, and make the lifting plate also be oppositely arranged with each arm assembly.While slinging, the position of movable support post on the first support beam, make crossbeam and lifting plate hight in the upper edge of locomotive screen cabinet.The overhead traveling crane lifting plate of slinging, be placed with built-in large parts on the hanging component of lifting plate below, the pulling force of the gravity of built-in large parts and overhead traveling crane lifting can keep a line substantially, thereby make built-in large parts keep horizontality, slippage does not occur, and makes that built-in large parts are follow-up can be put in locomotive screen cabinet yet.Herein, the concrete and arm each arm assembly of crossbeam is oppositely arranged.
For the pulling force of the gravity that makes better built-in large parts and overhead traveling crane lifting keeps a line, preferably, be provided with several grooves 51 on described lifting plate 5, each described groove 51 is communicated with described lifting through hole 6.Overhead traveling crane can be selected to hook different groove 51, so that the rear built-in large parts of slinging keep balance.
Arm assembly 3 at least should be two, so that built-in large parts can be placed on arm assembly 3 by pulsation-free, take in the present embodiment and arranges two as example, but be not limited to this.
The hanging apparatus that technique scheme provides, crossbeam and lifting plate can be higher than the upper edges of locomotive screen cabinet, and during lifting, crossbeam and lifting plate can not play inhibition, built-in large parts can directly be hung in locomotive screen cabinet, have improved the installation effectiveness of built-in large parts.
Below introduce movable fixing preferred implementation between the first support beam and pillar stiffener.
Vertically offer several the first mounting holes 13 on described the first support beam 11, on described pillar stiffener 2, correspondence offers several the second mounting holes 21, fixing by described the first mounting hole 13 and the second mounting hole 21 between described the first support beam 11 and described pillar stiffener 2.
The first support beam and pillar stiffener all can be the channel-section steel structure.After pillar stiffener moves to the position of requirement, between the first support beam and pillar stiffener, adopt a pair of or two pairs of the first mounting holes and the second mounting hole to fix.Change the position of pillar stiffener, first take the connection fastener between the first mounting hole and the second mounting hole apart, after pillar stiffener is moved into place, then by the first mounting hole and the second mounting hole, both are fixed.
Herein particularly, described the first mounting hole 13 and the second mounting hole 21 are all pin-and-hole.Connect fastener and be specially bearing pin.
Adopt the fixing mode easy accessibility of above-mentioned activity, and connect reliable.
Below introduce movable fixing preferred implementation between the first support beam and pillar stiffener.
The two ends of described the second support beam 12 laterally offer several the first fixed orifices (scheming not shown), to several the second fixed orifices 33 should be arranged, be fixed on the two ends of described the second support beam 12 between each described arm assembly 3 by described the first fixed orifice and the second fixed orifice 33 on each described arm assembly 3.
Each arm assembly can be fixed from different the first fixed orifices, so that the distance between two arm assemblies changes, to adapt to the built-in large parts of different in width.Should be noted that two arm assemblies preferably are symmetricly set on the both sides of support beam, so that the hanging apparatus symmetrical configuration herein.
Described arm assembly 3 preferably includes arm 31 and mount pad 32, mount pad 32 comprises four flat boards that surround closed circular, wherein a described flat board and described arm 31 are fixing, offer described the second fixed orifice 33 on the described flat board away from described arm 31.
The closed-loop that mount pad surrounds can directly be set on the second support beam, and then uses the first fixed orifice and the second fixed orifice that both are locked.
Adopt the arm assembly of above-mentioned form to fix with the second support beam better, and be convenient to change the position of arm assembly on the second support beam.
Described the first fixed orifice and the second fixed orifice 33 are all specifically bolt hole, between the first fixed orifice and the second fixed orifice 33, are bolted fasteningly, and bolt connects also is convenient to dismounting.
For increasing the rigidity of arm assembly 3, described arm assembly 3 also comprises floor 34, and floor 34 is fixed between arm 31 and described mount pad 32.
The hanging apparatus that technique scheme provides, the built-in large parts of can steadily slinging, solve on locomotive screen cabinet along stopping the problem of suspender, and can adjust flexibly position, thereby make the installation of built-in large parts safer, more efficient.
Finally it should be noted that: above each embodiment, only in order to the technical solution of the utility model to be described, is not intended to limit; Although with reference to aforementioned each embodiment, the utility model is had been described in detail, those of ordinary skill in the art is to be understood that: its technical scheme that still can put down in writing aforementioned each embodiment is modified, or some or all of technical characterictic wherein is equal to replacement; And these modifications or replacement do not make the essence of appropriate technical solution break away from the scope of each embodiment technical scheme of the utility model.

Claims (8)

1. a built-in large parts hanging apparatus, is characterized in that, comprising:
Pedestal, have the first support beam and the second support beam, and described the first support beam vertically arranges, described the second support beam horizontally set, and an end of described the first support beam and the middle part of described the second support beam are fixed;
Pillar stiffener, vertically arrange and be movably fixed to the other end of described the first support beam away from described the second support beam;
The arm assembly, be at least two, is horizontally disposed with, symmetrical and be movably fixed to the two ends of described the second support beam;
Crossbeam, be fixed on described pillar stiffener, and be oppositely arranged with described arm assembly;
The lifting plate, be fixed on described crossbeam, between described lifting plate and described crossbeam, is formed with the lifting through hole;
Wherein, described the first support beam, pillar stiffener, crossbeam and each described arm assembly surround the open recess of a side, and described recess is for accommodating described built-in large parts.
2. hanging apparatus according to claim 1, is characterized in that,
Vertically offer several the first mounting holes on described the first support beam, on described pillar stiffener, correspondence offers several the second mounting holes, between described the first support beam and described pillar stiffener, by described the first mounting hole and the second mounting hole, fixes.
3. hanging apparatus according to claim 1, is characterized in that,
The two ends of described the second support beam laterally offer several the first fixed orifices, on each described arm assembly, to several the second fixed orifices should be arranged, are fixed on the two ends of described the second support beam between each described arm assembly by described the first fixed orifice and the second fixed orifice.
4. hanging apparatus according to claim 3, is characterized in that, described arm assembly comprises:
Arm,
Mount pad, comprise four flat boards that surround closed circular, and wherein a described flat board and described arm are fixed, and on the described flat board away from described arm, offers described the second fixed orifice.
5. hanging apparatus according to claim 4, is characterized in that, described arm assembly also comprises:
Floor, be fixed between arm and described mount pad.
6. hanging apparatus according to claim 4, is characterized in that,
Described the first fixed orifice and the second fixed orifice are all bolt hole.
7. hanging apparatus according to claim 2, is characterized in that,
Described the first mounting hole and the second mounting hole are all pin-and-hole.
8. hanging apparatus according to claim 1, is characterized in that,
Be provided with several grooves on described lifting plate, each described groove is communicated with described lifting through hole.
CN 201320242318 2013-05-07 2013-05-07 Hoisting device for large built-in component Expired - Fee Related CN203345923U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201320242318 CN203345923U (en) 2013-05-07 2013-05-07 Hoisting device for large built-in component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201320242318 CN203345923U (en) 2013-05-07 2013-05-07 Hoisting device for large built-in component

Publications (1)

Publication Number Publication Date
CN203345923U true CN203345923U (en) 2013-12-18

Family

ID=49745847

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201320242318 Expired - Fee Related CN203345923U (en) 2013-05-07 2013-05-07 Hoisting device for large built-in component

Country Status (1)

Country Link
CN (1) CN203345923U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103754754A (en) * 2014-01-28 2014-04-30 常州大学 Lifter for thin-walled cylindrical workpiece
CN103879880A (en) * 2014-02-24 2014-06-25 陆玉权 Building material loading and unloading hanging fork
CN105174026A (en) * 2015-09-28 2015-12-23 山东太古飞机工程有限公司 Airplane wing detaching and installing lifting protective clamp
CN108328468A (en) * 2018-02-23 2018-07-27 上海发那科机器人有限公司 A kind of spraying track lifting device
CN108455444A (en) * 2018-04-12 2018-08-28 江苏帝蒙德轴承有限公司 A kind of back lining bearing lifting jig

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103754754A (en) * 2014-01-28 2014-04-30 常州大学 Lifter for thin-walled cylindrical workpiece
CN103754754B (en) * 2014-01-28 2016-04-06 常州大学 Thin_wall cylinder part suspender
CN103879880A (en) * 2014-02-24 2014-06-25 陆玉权 Building material loading and unloading hanging fork
CN103879880B (en) * 2014-02-24 2017-05-24 广西建工集团联合建设有限公司 Building material loading and unloading hanging fork
CN105174026A (en) * 2015-09-28 2015-12-23 山东太古飞机工程有限公司 Airplane wing detaching and installing lifting protective clamp
CN108328468A (en) * 2018-02-23 2018-07-27 上海发那科机器人有限公司 A kind of spraying track lifting device
CN108455444A (en) * 2018-04-12 2018-08-28 江苏帝蒙德轴承有限公司 A kind of back lining bearing lifting jig

Similar Documents

Publication Publication Date Title
CN203345923U (en) Hoisting device for large built-in component
CN208869154U (en) A kind of universal SVG mould group lifting appliance for installing
CN201439475U (en) Multifunctional balance hanging beam
CN202785258U (en) Hoisting device for air overturn of large-sized steel column
CN203159037U (en) Lifting appliance for dismounting transmission system part of bulldozer
CN203095387U (en) Large wind generating set cabin cover side plate hanger
CN103818840B (en) A kind of lifting part and hanging method
CN208085685U (en) Positioning device and battery replacement device
CN215854692U (en) Cubical switchboard hoisting machine of convenient operation constructs
CN208028390U (en) A kind of electric power distributing cabinet convenient for assembling lifting
CN203532624U (en) Counterweight balance system applied to vertical lifting system, container crane and bulk cargo crane
CN213059867U (en) Wind-powered electricity generation is with irregular casing counter weight frock for lifting by crane
CN204906130U (en) Motor punching device
CN204873491U (en) Self -supporting does not have crossbeam hoist system
CN210176323U (en) Simple and easy installation device of fog dispersal tower heat exchanger
CN202785394U (en) Compact-type lead-in mechanism for tower
CN203889951U (en) Turntable for construction machinery and equipment
CN209583386U (en) Prefabricated part hanging tool and Lift-on/Lift-off System
CN204490336U (en) A kind of all-hydraulic constitutional formula load carrier with multiple hold-down arm
CN208292529U (en) A kind of movable switch cubicle hanging device
CN207719623U (en) A kind of novel distribution cabinet of mounting plate easy disassembly
CN217708579U (en) Hoisting travelling crane roller carrier installation fixing device
CN211004230U (en) Special motor hoisting tool for equipment maintenance of cigarette machine
CN219217297U (en) General hoist of concrete moulded module and handling equipment
CN204490344U (en) A kind of multi-arm fluid pressure type bearing beam and driving combined hanging device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20131218

Termination date: 20190507

CF01 Termination of patent right due to non-payment of annual fee