Drainage type steel dam transmission room Download PDF

Info

Publication number
CN203307779U
CN203307779U CN2013203513062U CN201320351306U CN203307779U CN 203307779 U CN203307779 U CN 203307779U CN 2013203513062 U CN2013203513062 U CN 2013203513062U CN 201320351306 U CN201320351306 U CN 201320351306U CN 203307779 U CN203307779 U CN 203307779U
Authority
CN
China
Prior art keywords
transmission room
drainage
steel dam
type steel
room body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2013203513062U
Other languages
Chinese (zh)
Inventor
罗希
杨祖强
张晋新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Camce Whu Design & Research Co ltd
Original Assignee
Camce Whu Design & Research Co Ltd
CHINA CAMC ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Camce Whu Design & Research Co Ltd, CHINA CAMC ENGINEERING Co Ltd filed Critical Camce Whu Design & Research Co Ltd
Priority to CN2013203513062U priority Critical patent/CN203307779U/en
Application granted granted Critical
Publication of CN203307779U publication Critical patent/CN203307779U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Barrages (AREA)

Abstract

The utility model discloses a drainage type steel dam transmission room. The drainage type steel dam transmission room comprises a transmission room body, and further comprises a hydraulic hoist, a connecting lever and a bottom shaft, the hydraulic hoist, the connecting lever and the bottom shaft are arranged in the transmission room body, the hydraulic hoist is connected with the bottom shaft through the connecting lever, one end of the bottom shaft stretches out of the transmission room body, a liquid level transmitter and a dewatering pump both arranged in the transmission room body are further included, a drainage pipe arranged on the side wall of the transmission room body is further included, one end of the drainage pipe is connected with the dewatering pump, the other end of the drainage pipe stretches out of the transmission room body, and the liquid level transmitter is connected with the dewatering pump. A gate valve and a check valve are arranged at the end, stretching out of the transmission room body, of the drainage pipe and the end, connected with the dewatering pump, of the drainage pipe in sequence. The drainage type steel dam transmission room has an automatic drainage function, the position of the pipe mouth of the drainage pipe is low, the drainage pipe can work by being submerged in water, and the water cannot flow back to the transmission room body. The drainage type steel dam transmission room is simple in structure, easy and convenient to operate and low in cost.

Description

A kind of drainage type steel dam Transmission Room
Technical field
The utility model relates to the steel dam anchor gate transmission field, more specifically relates to a kind of drainage type steel dam Transmission Room, is applicable to steel dam anchor gate and drives.
Background technology
The steel dam anchor gate Transmission Room is that the operation hydraulic test drives the workplace that end transverse axis rotates to realize the steel dam anchor gate keying, needs to drain the water away in time in the steel dam anchor gate Transmission Room.Usually the outlet of drainage is arranged on the top of Transmission Room, more than being positioned at peak level.But exist when flood during far above the crest level of Transmission Room, even higher than ten meters, now drainpipe outlet need arrange very highly, affects attractive in appearancely, causes cost to increase, and has reduced security performance, thereby has hindered the steel dam utilization in market and popularization in water.
The utility model content
The purpose of this utility model is to be the problems referred to above that exist for prior art, and a kind of drainage type steel dam Transmission Room is provided.Reasonable in design, safe and reliable, and the exit position that can obviously reduce gutter.
Above-mentioned purpose of the present utility model is achieved through the following technical solutions:
A kind of drainage type steel dam Transmission Room, comprise Transmission Room, also comprise the hydraulic hoist, connecting lever and the lower shaft that are arranged in Transmission Room, hydraulic hoist is connected with lower shaft by connecting lever, and lower shaft one end stretches out outside Transmission Room, also comprises the fluid level transmitter and the drainage pump that all are arranged in Transmission Room, also comprise the gutter that is arranged on the Transmission Room sidewall, gutter one end is connected with drainage pump, and the other end stretches out outside Transmission Room, and fluid level transmitter is connected with drainage pump.
Gutter as above stretches out Transmission Room one end and is disposed with gate valve and non retern valve to drainage pump, being connected an end.
The utility model compared with prior art, has the following advantages:
1, has automatic drainage function.After Transmission Room internal water accumulation water level arrived certain altitude, gate valve was opened automatically, and drainage pump is opened; After Transmission Room internal water accumulation water level was reduced to certain altitude, gate valve and drainage pump were closed simultaneously.
2, the gutter nozzle position is lower, can be submerged in water and work, and water does not flow backwards and enters Transmission Room.
3, simple in structure, easy and simple to handle, cost is low.
The accompanying drawing explanation
Fig. 1 is the structural representation of the first embodiment of the present utility model;
Fig. 2 is the structure chart of the dewatering installation of the first embodiment of the present utility model;
Fig. 3 is the structural representation of the second embodiment of the present utility model;
Fig. 4 is the structure chart of the dewatering installation of the second embodiment of the present utility model.
In figure: the 1-Transmission Room; The 2-dewatering installation; The 3-hydraulic hoist; The 4-lower shaft; The 5-connecting lever; The 6-drainage pump; The 7-fluid level transmitter; The 8-gutter; The 9-non retern valve; The 10-gate valve.
The specific embodiment
Below in conjunction with accompanying drawing, the technical solution of the utility model is described in further detail.
Embodiment 1:
Fig. 1 ~ Fig. 2 is the first embodiment structural representation of the present utility model, and Transmission Room 1 is as the abutment pier Transmission Room.Comprise Transmission Room 1, also comprise the hydraulic hoist 3, connecting lever 5 and the lower shaft 4 that are arranged in Transmission Room 1, hydraulic hoist 3 is connected with lower shaft 4 by connecting lever 5, lower shaft 4 one ends stretch out outside Transmission Room 1, also comprise the fluid level transmitter 7 and the drainage pump 6 that all are arranged in Transmission Room 1, also comprise the gutter 8 that is arranged on Transmission Room 1 sidewall, gutter 8 one ends are connected with drainage pump 6, the other end stretches out outside Transmission Room 1, and fluid level transmitter 7 is connected with drainage pump 6.
Dewatering installation 2 is arranged on the downstream sidewall of Transmission Room 1, and dewatering installation 2 comprises fluid level transmitter 7, drainage pump 6, gutter 8.Fluid level transmitter 7 comprises liquid level sensor and controller, and fluid level transmitter 7 sensed water level change and control the startup of drainage pump 6 and close, and drainage pump 6 utilizes gutter 8 that the inner ponding of Transmission Room is drained into outside Transmission Room.Gutter 8 passes the sidewall of Transmission Room 1.In Transmission Room 1, be provided with hydraulic hoist 3, lower shaft 4 and connecting lever 5, hydraulic hoist 3 is connected with lower shaft 4 by connecting lever 5, lower shaft 4 stretches out outside Transmission Room 1, hydraulic hoist 3 drives lower shaft 4 by connecting lever 5 and rotates centered by the axial line of lower shaft, the lower shaft 4 of rotation can drive connected steel dam rotation, thereby regulates the height of steel dam interception water.
When fluid level transmitter 7 detected in Transmission Room water level and arrives predefined drainage pump priming level, fluid level transmitter 7 was controlled drainage pumps 6 operations, and the inner ponding of Transmission Room is drained into outside Transmission Room by gutter 8; When fluid level transmitter 7 detected in Transmission Room that water level is reduced to predefined drainage pump termination of pumping water level, it is out of service that fluid level transmitter 7 is controlled drainage pumps 6.
Embodiment 2:
Fig. 3 ~ 4 are the second embodiment structural representation of the present utility model, and dewatering installation 2 is arranged on the downstream sidewall of Transmission Room 1, and dewatering installation 2 comprises fluid level transmitter 7, drainage pump 6, gutter 8, gate valve 10 and non retern valve 9.Gutter 8 stretches out Transmission Room 1 one ends and is disposed with gate valve 10 and non retern valve 9 to drainage pump 6, being connected an end.The signal controlling gate valve 10 of the SEA LEVEL VARIATION detected according to fluid level transmitter 7 opens and closes, when fluid level transmitter 7 detects in Transmission Room water level and arrives predefined drainage pump priming level, fluid level transmitter 7 is controlled gate valve 10 and is opened, simultaneously opening water discharge pump 6; When fluid level transmitter 7 detected in Transmission Room that water level is reduced to predefined drainage pump termination of pumping water level, fluid level transmitter 7 was controlled gate valves 10 and is closed, and drainage pump 6 is out of service simultaneously.Thereby realize when drainage pump does not move, stop external water to enter Transmission Room inside.The effect of non retern valve 9 is when drainage pump is out of service, due to the inner remnant water body of gutter 6, avoids this part water to flow backwards under Action of Gravity Field, prevents the drainage pump reversing.Due to gate valve 10 and non retern valve 9 being installed on gutter 6, so the water of Transmission Room outside can not enter in Transmission Room by gutter 6, so drainpipe outlet can be submerged in water.If there is no this cover control system, more than the gutter mouth of pipe will be arranged on extreme high water, exceed sometimes tens meters of Transmission Rooms, thereby need to carry out oblique pull to gutter, fix, not only affect attractive in appearancely, cost is higher, simultaneously easily be subject to the shock of foreign material in water and collapse, reduced security performance.
Specific embodiment described herein is only to the explanation for example of the utility model spirit.The utility model person of ordinary skill in the field can make various modifications or supplements or adopt similar method to substitute described specific embodiment, but can't depart from spirit of the present utility model or be more than the defined scope of appended claims.

Claims (2)

1. drainage type steel dam Transmission Room, comprise Transmission Room (1), also comprise the hydraulic hoist (3) be arranged in Transmission Room (1), connecting lever (5) and lower shaft (4), hydraulic hoist (3) is connected with lower shaft (4) by connecting lever (5), lower shaft (4) one ends stretch out outside Transmission Room (1), it is characterized in that, also comprise the fluid level transmitter (7) and the drainage pump (6) that all are arranged in Transmission Room (1), also comprise the gutter (8) that is arranged on Transmission Room (1) sidewall, gutter (8) one ends are connected with drainage pump (6), the other end stretches out outside Transmission Room (1), fluid level transmitter (7) is connected with drainage pump (6).
2. a kind of drainage type steel dam Transmission Room according to claim 1, is characterized in that, described gutter (8) stretches out Transmission Room (1) one end and is disposed with gate valve (10) and non retern valve (9) to drainage pump (6), being connected an end.
CN2013203513062U 2013-06-19 2013-06-19 Drainage type steel dam transmission room Expired - Lifetime CN203307779U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013203513062U CN203307779U (en) 2013-06-19 2013-06-19 Drainage type steel dam transmission room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013203513062U CN203307779U (en) 2013-06-19 2013-06-19 Drainage type steel dam transmission room

Publications (1)

Publication Number Publication Date
CN203307779U true CN203307779U (en) 2013-11-27

Family

ID=49613997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013203513062U Expired - Lifetime CN203307779U (en) 2013-06-19 2013-06-19 Drainage type steel dam transmission room

Country Status (1)

Country Link
CN (1) CN203307779U (en)

Similar Documents

Publication Publication Date Title
CN201288937Y (en) Self-control type centrifugal pump vacuum priming device
WO2009063501A2 (en) A pumping system for pumping liquid from a lower level to an operatively higher level
CN207776007U (en) A kind of non-negative pressure water-supply installation
CN204082565U (en) Vacuum water diversion centrifugal pump device
CN203684387U (en) Special double-water-tank integrated sewage lifting equipment for subway
CN206830145U (en) Well casing gas recovery device
CN203307779U (en) Drainage type steel dam transmission room
CN205478358U (en) Vacuum diversion equipment
CN209686541U (en) Hydrocone type self-draining arrangement
CN204239221U (en) The outer arranging device of a kind of pump house ponding
CN202012134U (en) Sewage lifting device
CN206495773U (en) A kind of hydraulic water pump
CN210240007U (en) Horizontal mixed flow pump is from inhaling pressure device that intakes
CN209441550U (en) A kind of ship emergency drainage device
CN201176674Y (en) Roof rain discharging system
CN202530430U (en) Quick gate with small built-in flap valve
CN202347636U (en) Water drainer of water collection pit of semi-underground circulating water pump room
CN201425027Y (en) Automatic water supplementing vacuum water diversion tank
CN204212218U (en) A kind of cabinet type tap water pumping plant
CN201531465U (en) Bottom valve protective device
CN204082705U (en) Filter box water circulation control system at the bottom of fish jar
CN205557765U (en) Water tank siphon destructor
CN208918846U (en) Suction pumps on one body fluid of self-priming and machine sealing flushing
CN219974833U (en) Automatic water diversion device of coal mine centrifugal pump
CN203654393U (en) Pressure water inlet pool of pump station at dam toe

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CAMCE WHU DESIGN + RESEARCH CO., LTD.

Free format text: FORMER OWNER: CHINA CAMC ENGINEERING CO., LTD..

Effective date: 20140326

Free format text: FORMER OWNER: CAMCE WHU DESIGN + RESEARCH CO., LTD.

Effective date: 20140326

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 100080 HAIDIAN, BEIJING TO: 430070 WUHAN, HUBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20140326

Address after: 430070 Wuhan East Lake Development Zone, Hubei science and Technology Park, Wuhan University

Patentee after: CAMCE WHU DESIGN & RESEARCH Co.,Ltd.

Address before: 100080 Beijing city Haidian District Danleng Street No. 3 block A

Patentee before: CHINA CAMC ENGINEERING Co.,Ltd.

Patentee before: CAMCE WHU DESIGN & RESEARCH Co.,Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20131127